CALCULO DEL MONTO MAXIMO DE ADELANTO

PARA MATERIALES A OTORGAR

OBRA "MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS DEL ESTADIO MUNICIPAL DE LA CIUDAD DE PANAO, DISTRITO DE PANAO,
: PROVINCIA DE PACHITEA, REGION HUANUCO"
CONTRATISTA : CONSORCIO MONUMENTAL
PPTO BASE : S/. 7,382,784.52 FACTOR DE RELACION : 0.99996
PPTO CONTR. : S/. 7,382,505.63 FECHA PPTO: 5/26/2021

a) DEL MONTO MAXIMO POR LAS INCIDENCIAS DE LOS MATERIALES EN LAS FORMULAS POLINOMICAS

ADELANTO MAXIMO = S/. 3,418,267.99 46.30%


(solo considerando estructuras y arquitectura)

b) DEL MONTO MAXIMO POR EL 20% DEL MONTO DEL CONTRATO

ADELANTO MAXIMO = (7'382,505.63*0.20) = S/. 1,476,501.13 20.00%

c) DEL MONTO MAXIMO POR LA SUMA DE CADA INSUMO EN CADA SUB PRESUPUESTO

ADELANTO MAXIMO =
(solo considerando formula 06) S/. 2,594,470.31
S/. 2,594,470.31
S/. 207,557.62
S/. 181,612.92
SUB TOTAL S/IGV S/. 2,983,640.86
TOTAL C/IGV S/. 3,520,696.21 47.69%

DEL ANALISIS ANTES EFECTUADO SE CONCLUYE:

1.- EL ADELANTO MAXIMO A OTORGAR SERA EL MINIMO DE a, b, c, QUE CORRESPONDE AL INCISO b.

2.- EL ADELANTO MAXIMO A OTORGAR SERA S/. 1'476,501.13

3.- EL ADELANTO PARA MATERIALES SOLICITADO ES S/. 1'476.501.13

4.- EL ADELANTO PARA MATERIALES SOLICITADO ES PROCEDENTE


CALCULO DEL MONTO MAXIMO DE ADELANTO PARA
MATERIALES POR INCIDIENCIA DE LAS FORMULAS POLINOMICAS

OBRA "MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS DEL ESTADIO MUNICIPAL DE LA CIUDAD DE PANAO, DISTRITO DE PANAO, PROVINCIA DE
: PACHITEA, REGION HUANUCO"
CONTRATISTA : CONSORCIO MONUMENTAL
PPTO BASE : S/. 7,382,784.52 FACTOR DE RELACION : 0.99996
PPTO CONTR. : S/. 7,382,505.63 FECHA PPTO: 5/26/2021

ADELANTO MAX. OTORG. = COEF. INCID.*%INCID.*PPTO CONTRATADO*(Ima/Imo)

FORMULA : ESTRUCTURAS AREA GEOGRAFICA: 3 HUANUCO

K= 0.291*(Mr/Mo) + 0.103*(Cr/Co) + 0.062*(Ar/Ao) + 0.227*(Ar/Ao) + 0.091*(Mr/Mo)+ 0.096*(Dr/Do)+ 0.130*(Ir/Io)

SIM COEF. % PPTO INDICE BASE INDICE ADELAN. ADELANTO ADELANTO


BO ELEMENTO REPRESENTATIVO COD INCID. INCID. CONTRATADO Imo Ima MAX. OTORG. SOLICITADO
LO S/IGV May-21 Oct-21 S/IGV S/IGV

M MANO DE OBRA INC. LEYES SOC. 47 0.291 100.00%


C CEMENTO PORTLAND TIPO I 21 0.103 100.00% S/. 4,144,708.65 449.56 472.840 S/. 449,011.82 S/. 187,901.21
A AGREGADO GRUESO 05 0.062 100.00% S/. 4,144,708.65 445.56 460.180 S/. 265,403.86 S/. 237,628.01
A ACERO DE CONSTRUCCION LISO 02 0.227 100.00% S/. 4,144,708.65 795.07 802.180 S/. 949,262.51 S/. 374,458.15
M MADERA TERCIADA PARA ENCOFRADO 45 0.091 100.00% S/. 4,144,708.65 358.48 399.470 S/. 420,295.40 S/. 288,074.77
D DÓLAR (GENERAL PONDERADO) 30 0.096 100.00% S/. 4,144,708.65 587.46 642.270 S/. 435,015.34
I INDICE GENERAL DE PRECIOS AL CONSUM. 39 0.130 100.00%

1.000 S/. 2,518,988.94 S/. 1,088,062.13

COSTO DIRECTO S/. 2,518,988.94 S/. 1,088,062.13


GASTOS GENERALES (8.00%) S/. 201,519.12 S/. 87,044.97
UTILIDAD (7.00%) S/. 176,329.23 S/. 76,164.35
SUB TOTAL S/. 2,896,837.28 S/. 1,251,271.45
IGV (18%) S/. 521,430.71 S/. 225,228.86
TOTAL S/. 3,418,267.99 S/. 1,476,500.31
CALCULO DEL MONTO DEL ADELANTO SOLICITADO PARCIAL

"MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS DEL ESTADIO MUNICIPAL DE LA CIUDAD DE PANAO, DISTRITO DE
OBRA
PANAO, PROVINCIA DE PACHITEA, REGION HUANUCO"
:
CONTRATISTA : CONSORCIO MONUMENTAL
PPTO BASE : S/. 7,382,784.52 FACTOR DE RELACION : 0.99996
PPTO CONTR. : S/. 7,382,505.63 FECHA PPTO: 5/26/2021

ADEL. SOL. PARCIAL = METR.*P.U.*(Ima/Imo)

FORMULA 06 : TRIBUNA, AREA ADMINISTRATIVA, SS.HH. PUBLICO AREA GEOGRAFICA: 3 HUANUCO

INDICE UNIFICADO: 47 (MANO DE OBRA INC. LEYES SOCIALES)

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-21 Oct-21 PARCIAL

S/. 0.00

INDICE UNIFICADO: 21 (CEMENTO PORTLAND TIPO I)

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-21 Oct-21 PARCIAL
21 CEMENTO PORTLAND TIPO I (42.5KG) BOL 9000.00 19.85 449.56 472.84 S/. 187,901.21
S/. 187,901.21

INDICE UNIFICADO: 05 (AGREGADO GRUESO)

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-21 Oct-21 PARCIAL
04 ARENA FINA m3 318.64 50.85 445.56 460.18 S/. 16,734.27
05 PIEDRA CHANCADA DE 1/2" m3 1771.40 63.54 445.56 460.18 S/. 116,247.97
05 ARENA GRUESA m3 1157.86 59.32 445.56 460.18 S/. 70,938.04
05 PIEDRA GRANDE m3 102.32 46.61 445.56 460.18 S/. 4,925.47
38 HORMIGON (PUESTO EN OBRA) m3 548.04 50.85 445.56 460.18 S/. 28,782.26
S/. 237,628.01

INDICE UNIFICADO: 02 (ACERO DE CONSTRUCCION LISO)

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-15 Nov-15 PARCIAL
02 ALAMBRE NEGRO RECOCIDO # 16 kg 3957.23 4.50 795.07 802.66 S/. 17,977.53
02 ALAMBRE NEGRO RECOCIDO # 8 kg 1427.04 4.50 795.07 802.66 S/. 6,483.01
02 CLAVOS PARA MADERA C/C 3" kg 2590.97 4.50 795.07 802.66 S/. 11,770.66
02 ACERO CONSTRUCCION CORRUGADO kg 108073.76 3.10 795.07 802.66 S/. 338,226.95
S/. 374,458.15

INDICE UNIFICADO: 45 (MADERA TERCIADA PARA ENCOFRADO)

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-15 Nov-15 PARCIAL
43 MADERA NACIONAL P/ENCOFRADO-CARP p2 1692.40 2.35 358.48 399.47 S/. 4,431.91
45 MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 37941.70 2.35 358.48 399.47 S/. 99,358.24
45 PLANCHA FENOLICA 1.22MX2.44MX18MM pln 1500.00 110.25 358.48 399.47 S/. 184,284.62
S/. 288,074.77

INDICE UNIFICADO: 30 (DÓLAR - GENERAL PONDERADO)

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-15 Nov-15 PARCIAL

S/. 0.00

INDICE UNIFICADO: 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

INDICE BASE INDICE ADELAN. ADELANTO


IU DESCRIPCION UND METR. P.U Imo Ima SOLICITADO
May-15 Nov-15 PARCIAL

S/. 0.00
S/. 541,145.01 0.96 S/. 519,499.21 S/. 41,559.94 S/. 36,364.94
S/. 217,270.13 0.96 S/. 208,579.32 S/. 16,686.35 S/. 14,600.55
S/. 38,328.74 0.96 S/. 36,795.59
S/. 39,865.77 0.96 S/. 38,271.14
S/. 48,347.00 0.96 S/. 46,413.12
S/. 24,251.70 0.96 S/. 23,281.63
S/. 909,208.35 0.96 S/. 872,840.02
S/. 63,644.58 0.96 S/. 61,098.80
S/. 72,736.67 0.96 S/. 69,827.20
S/. 1,045,589.60 0.96 S/. 1,003,766.02
S/. 597,424.09
S/. 239,866.22