FICHA DE CONTROL DE OBRA No 01

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-
TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
INFORME : MES DE ENERO DEL 2022

DATOS GENERALES

SECTOR : 99 Gobiernos Regionales


PLIEGO : 458 458 Gobierno Regional del Departamento de Puno
UNIDAD EJECUTORA : 001 Municipalidad
FUNCION : 09 15 Transporte
PROGRAMA : 061 033 Transporte Terrestre
SUB PROGRAMA : 0174 0065 Vias Departamento
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -
ACTIVIDAD O PROYECTO : 2.030123 ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-
CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -


COMPONENTE : 2.082357 ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-
CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -


META : 00001 ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-
CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -


DESCRIPCION DE LA OBRA : ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-
CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
CODIGO SNIP : 31102 95803
UBICACIÓN PROVINCIA : Puno
DISTRITO : Capachica
LOCALIDAD : Capachica

DATOS FINANCIEROS

FUENTE(S) DE FINANCIAMIENTO : 05 RECURSOS ORDINARIOS

RUBRO (S)
:
ENTIDAD FINANCIERA : GOBIERNO REGIONAL PUNO
ENTIDAD EJECUTORA : GOBIERNO REGIONAL PUNO - GERENCIA REGIONAL DE INFRAESTRUCTURA
MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA
CONVENIO : NO CORRESPONDE
(*) Si corresponde

ADDENDA AL CONVENIO : NO CORRESPONDE


(*) Si corresponde

MUNICIPALIDAD
EXPEDIENTE TECNICO INICIAL GR PUNO (1) TOTAL

COSTO DIRECTO : S/. 22,122,753.18 0.00 22,122,753.18


GASTOS GENERALES (7%) : S/. 1,548,592.72 0.00 1,548,592.72
GASTOS SUPERVISION (4%) : S/. 884,910.13 0.00 884,910.13
GASTOS DE LIQUIDACION (0.25 %) : S/. 55,306.88 0.00 55,306.88
SEGUIMIENTO Y MONITOREO (0.35%) : S/. 77,429.64 0.00 77,429.64
ELABORAC. DEL EXP. TECNICO ( 0.95%) : S/. 210,166.16 0.00 210,166.16
TOTAL : S/. 24,899,158.71 0.00 24,899,158.71

RESOLUCION DE APROBACION DEL Gerencial General


: Regional N° 323-2013- FECHA 7/25/2013
EXPEDIENTE TECNICO
GGR-GR PUNO

(1) Considerar solo si hay aporte de otra entidad para ejecutar la obra
RESOLUCION DE APROBACION :
DOCUMENTOS A ADJUNTAR * Resolución de Aprobación
: * Fotocopia del Acta de Inicio considerado en el cuaderno de obra
: * Presupuesto Analítico Inicial

EXPEDIENTE TECNICO DE AMPLIACION PRESUPUESTAL POR DEDUCTIVOS

TOTAL PRESUPUESTO : S/. -6,391,044.04


TOTAL : S/.
DOCUMENTO (S) SUSTENTATORIO (S)
* Del Residente de Obra : ING. REYNALDO SANCCO CONDORI
* Del Supervisor de Obra : ING. HILARIO TIPULA MULLISACA

ING. Luder Jesus Dueñas Ramos como DIRECTOR REGIONAL DE TRANSPORTES DEL GR PUNO, el cual aprueba el expediente denominado
* APROBADO POR : adicional N°01 con deductivos vinculante N°01, debiendo ser lo correcto que el expediente de adicional N°01 se aprobado por el TItular de la
entidad.
: resolución Directoral Regional N°428-2014-
* Resolución de Aprobación GR.PUNO/DRTCVC FECHA 7/31/2014

DOCUMENTOS A ADJUNTAR * Documento (s) sustentatorio (s)


: * Presupuesto Analítico por Mayores Metrados
EXPEDIENTE TECNICO DE AMPLIACION PRESUPUESTAL POR MAYORES METRADOS
TOTAL PRESUPUESTO : S/. 2,328,320.90
GASTOS GENERALES : S/. 0.00
GASTOS SUPERVISION : S/. 0.00
TOTAL : S/. 2,328,320.90
DOCUMENTO (S) SUSTENTATORIO (S)
* Del Residente de Obra : ING. REYNALDO SANCCO CONDORI
* Del Supervisor de Obra : ING. HILARIO TIPULA MULLISACA
ING. Luder Jesus Dueñas Ramos como DIRECTOR REGIONAL DE TRANSPORTES DEL GR PUNO, el cual aprueba el expediente denominado
* APROBADO POR : adicional N°01 con deductivos vinculante N°01, debiendo ser lo correcto que el expediente de adicional N°01 se aprobado por el TItular de la
entidad.
: resolución Directoral Regional N°428-2014-
* Resolución de Aprobación FECHA 7/31/2014
GR.PUNO/DRTCVC
DOCUMENTOS A ADJUNTAR * Documento (s) sustentatorio (s)
: * Presupuesto Analítico por Mayores Metrados

EXPEDIENTE TECNICO DE AMPLIACION PRESUPUESTAL POR PARTIDAS NUEVAS


COSTO DIRECTO : S/. 7,669,789.60
GASTOS GENERALES : S/. 0.00
GASTOS SUPERVISION : S/. 0.00
TOTAL : S/.
DOCUMENTO (S) SUSTENTATORIO (S)
* Del Residente de Obra : ING. REYNALDO SANCCO CONDORI
* Del Supervisor de Obra : ING. HILARIO TIPULA MULLISACA

ING. Luder Jesus Dueñas Ramos como DIRECTOR REGIONAL DE TRANSPORTES DEL GR PUNO, el cual aprueba el expediente denominado
* APROBADO POR : adicional N°01 con deductivos vinculante N°01, debiendo ser lo correcto que el expediente de adicional N°01 se aprobado por el TItular de la
entidad.
: resolución Directoral Regional N°428-2014-
* Resolución de Aprobación FECHA 7/31/2014
GR.PUNO/DRTCVC
DOCUMENTOS A ADJUNTAR * Documento (s) sustentatorio (s)
: * Presupuesto Analítico por Partidas Nuevas

MODIFICACION (ES) DE PRESUPUESTO ANALITICO -------------------( NO CORRESPONDE)

DOCUMENTO (S) SUSTENTATORIO (S)


* Del Residente de Obra : 0.00
* De la Sub Gerencia de Obras y E.M. : 0.00
* Del Supervisor de Obra : 0.00
* De la Of. Reg. Supervisión y L.O. : 0.00
* Resolución de Aprobación : RGGR Nº FECHA
DOCUMENTOS A ADJUNTAR * Documento (s) sustentatorio (s)
: * Presupuesto Analítico Modificado

PLAZOS DE EJECUCION DE OBRA :

SEGÚN EXPEDIENTE TECNICO INICIAL


FECHA DE INICIO : 14 DE OCTUBRE DEL 2013
FECHA DE TERMINO PREVISTA : 10 DE JUNIO DEL 2014 NO CUMPLIDO
PLAZO DE EJECUCION (DIAS) : 240 DIAS CALENDARIO

RESOLUCION DE APROBACION : Gerencial General Regional N° 323-2013-GGR-GR PUNO FECHA 7/25/2013


DOCUMENTOS A ADJUNTAR * Resolución de Aprobación
: * Fotocopia del Acta de Inicio considerado en el cuaderno de obra

AMPLIACION (ES) DE PLAZO -------------------( NO CORRESPONDE)


FECHA DE 1RA AMPLIACION : DESDE: 6/11/2014 HASTA: 30/09/2014 NO CUMPLIDO
DIAS DE AMPLIACION : 112 DIAS CALENDARIOS
FECHA DE 2DA AMPLIACION : DESDE: 11/9/2015 HASTA: 9/30/2016
DIAS DE AMPLIACION :
DOCUMENTO (S) SUSTENTATORIO (S)
* Del Residente de Obra :
* De la Sub Gerencia de Obras y E.M. :
* Del Supervisor de Obra :
* De la Of. Reg. Supervisión y L.O. :
:
* Resolución de Aprobación resolución Directoral Regional FECHA 7/31/2014
N°428-2014-GR.PUNO/DRTCVC
DOCUMENTOS A ADJUNTAR : * Documento (s) sustentatorio (s)

PARALIZACION (ES) DE OBRA -------------------( NO CORRESPONDE)


FECHA DE 1RA PARALIZACION : DESDE: 9/8/2014 HASTA: 11/8/2015
DIAS DE PARALIZACION : 426 DIAS CALENDARIOS
FECHA DE 2DA PARALIZACION : DESDE: HASTA:
DIAS DE PARALIZACION :

DOCUMENTO (S) SUSTENTATORIO (S)

* Del Residente de Obra : CUADERNO DE OBRA

* De la Sub Gerencia de Obras y E.M. :


* Del Supervisor de Obra :
* De la Of. Reg. Supervisión y L.O. :
* Resolución de Aprobación : RGGR Nº FECHA
DOCUMENTOS A ADJUNTAR : * Documento (s) sustentatorio (s)
FECHA REAL DE CONCLUSION DE OBRA : 31/09/16

AVANCE DE OBRA AL MES DE MARZO 2016

VALORIZACION TOTAL DE OBRA SEGÚN (Presupuesto Base+Mayores Metrado+ partidas nuevas)

AVANCE FISICO PRESUPUESTO COSTO ANTERIOR ACTUAL ACUM. SALDO


TOTAL

FISICO EN S/. : 24,899,158.71 11,418,515.99 152,126.83 11,570,642.82 13,328,515.89


FISICO EN % : 100% 45.86% 0.61% 46.47% 53.53%

PRESUPUESTO COSTO PRESUPUESTO EJECUTADO PRESUPUESTO PRESUPUESTO


AVANCE FINANCIERO C.T. SALDO
TOTAL ANTERIOR EJECUTADO ACTUAL ACUMULADO

FINANCIERO EN S/. : 24,899,158.71 15,518,944.68 312,242.92 15,831,187.60 9,067,971.11


FINANCIERO TOTAL EN % : 100% 62.33% 1.25% 63.58% 36.42%
DOCUMENTOS A ADJUNTAR : * Valorización Mensual de obra con VºBº del supervisor de obra.
* Reporte de Ejecución Presupuestaria Mensual
* Panel Fotográfico impreso y en archivo

VALORIZACION SEGÚN PRESUPUESTO BASE

PRESUPUESTO COSTO
AVANCE FISICO ANTERIOR ACTUAL ACUM. SALDO
TOTAL

FISICO EN S/. : 24,899,158.71 5,440,360.19 129,969.05 5,570,329.24 19,328,829.47


FISICO EN % : 21.85% 0.52% 22.37% 77.63%

VALORIZACION POR MAYORES METRADOS


PRESUPUESTO COSTO
AVANCE FISICO ANTERIOR ACTUAL ACUM. SALDO
TOTAL

FISICO EN S/. : 2,368,986.05 22,157.78 2,391,143.83


FISICO EN % : 9.51% 0.09% 9.60%
DOCUMENTOS A ADJUNTAR : * Documento (s) sustentatorio (s)
* Presupuesto Analítico por Mayores Metrados

VALORIZACION POR PARTIDAS NUEVAS


PRESUPUESTO COSTO
AVANCE FISICO C.D. ANTERIOR ACTUAL ACUM. SALDO
DIRECTO
FISICO EN S/. : 3,609,169.75 0.00 3,609,169.75
FISICO EN % : 14.50% 0.00% 14.50%
DOCUMENTOS A ADJUNTAR : * Documento (s) sustentatorio (s)
* Presupuesto Analítico por Partidas Nuevas

CONSOLIDADO GENERAL DE VALORIZACIONES


VALORIZACION ACTUAL ( PRESUPUESTO BASE + MAYORES MESTRADOS + PARTIDAS NUEVAS)

GASTOS GASTOS DE GASTOS DE SEGUIMIENTO GASTOS DE


C.D. EXP. TECNICO
VALORIZACIONES GENERALES SUPERVICIO LIQUIDACION Y MONITOREO EXP. TECNICO TOTAL %
APROBADO
(7.00%) N (4.00%) (0.25%) (0.35%) (0.95%)

NUEVO PPTO DE OBRA (R.D.R.Nº 428-2014-GR PUNO/DRTCVC) 22,122,753.18 1,548,592.72 884,910.13 55,306.88 77,429.64 210,166.16 24,899,158.71

VALORIZACION ANTERIOR (PPTO BASE ) 4,833,727.40 338,360.92 193,349.10 12,084.32 16,918.05 45,920.41 5,440,360.19 21.85%

VALORIZACION ANTERIOR (MAYORES METRADOS) 2,104,829.90 147,338.09 84,193.20 5,262.07 7,366.91 19,995.88 2,368,986.05 9.51% 45.86%

VALORIZACION ANTERIOR (PARTIDAS NUEVAS) 3,609,169.75 0.00 0.00 0.00 0.00 0.00 3,609,169.75 14.50%

VALORIZACION ACTUAL (PPTO BASE) 115,476.72 8,083.37 4,619.07 288.69 404.17 1,097.03 129,969.05 0.52%

VALORIZACION ACTUAL (MAYORES METRADOS) 19,687.06 1,378.09 787.48 49.22 68.90 187.03 22,157.78 0.09% 0.61%

VALORIZACION ACTUAL (PARTIDAS NUEVAS) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%

VALORIZACION ACUMULADA 10,682,890.83 495,160.47 282,948.84 17,684.30 24,758.02 67,200.35 11,570,642.82 46.47%

SALDO 11,439,862.35 1,053,432.25 601,961.29 37,622.58 52,671.62 142,965.81 13,328,515.89 53.53%

CUADRO COMPARATIVO DE AVANCES

ITEM DESCRIPCION EJECUTADO 2013 -2014 INF. TOTAL


CORTE
nov-15 dic-15 ene-16 feb-16 mar-16 abr-16 may-16 jun-16 jul-16 ago-16 sep-16

Mensual 14,604,949.24 73,215.05 365,544.25 - 302,722.96 172,513.18 312,242.92 15,831,187.60


FINANCIERO
AVANCE

% MENSUAL 58.66% 0.29% 1.47% 0.00% 1.22% 0.69% 1.25% 63.58%


001
Acumulado 14,604,949.24 14,678,164.29 15,043,708.54 15,043,708.54 15,346,431.50 15,518,944.68 15,831,187.60 15,831,187.60
% ACUMULADO 58.66% 58.95% 60.42% 60.42% 61.63% 62.33% 63.58% 63.58%
PROGRAMADO

Mensual 10,692,156.75 289,993.91 446,451.41 555,452.37 983,113.40 562,382.94 557,452.37 995,113.40 1,541,300.56 1,564,637.94 3,554,591.45 3,156,512.20 24,899,158.71
AVANCE
FISICO

% MENSUAL 42.94% 1.16% 1.79% 2.23% 3.95% 2.26% 2.24% 4.00% 6.19% 6.28% 14.28% 12.68% 100%
002
Acumulado 10,692,156.75 10,982,150.66 11,428,602.06 11,984,054.43 12,967,167.84 13,529,550.78 14,087,003.15 15,082,116.55 16,623,417.11 18,188,055.05 21,742,646.50 24,899,158.71 24,899,158.71
% ACUMULADO 42.94% 44.11% 45.90% 48.13% 52.08% 54.34% 56.58% 60.57% 66.76% 73.05% 87.32% 100.00% 100.0%

Mensual 10,692,156.75 179,993.91 264,328.56 96,608.25 78,908.47 106,520.05 152,126.83 11,570,642.82


EJECUTADO
AVANCE
FISICO

% MENSUAL 42.94% 0.72% 1.06% 0.39% 0.32% 0.43% 0.61% 46.47%


003
Acumulado 10,692,156.75 10,872,150.66 11,136,479.22 11,233,087.47 11,311,995.94 11,418,515.99 11,570,642.82 11,570,642.82
% ACUMULADO 42.94% 43.66% 44.73% 45.11% 45.43% 45.86% 46.47% 46.47%

CONTROL CURVA "S "


OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL CIRCUITO TURÍSTICO LAGO SAGRADO DE LOS INCAS – DISTRITOS CAPACHICA, CHUCUITO, PLATERIA, ACORA, ILAVE”
TRAMO I CAPACHICA - LLACHON

PRESUPUESTO: S/. 24,899,158.71

GRAFICO DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO ACUMULADO
Progra mado Fis ico E jecutado Financ ie ro Ejecuta do

120%
CONTROL CURVA "S "
OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL CIRCUITO TURÍSTICO LAGO SAGRADO DE LOS INCAS – DISTRITOS CAPACHICA, CHUCUITO, PLATERIA, ACORA, ILAVE”
TRAMO I CAPACHICA - LLACHON

PRESUPUESTO: S/. 24,899,158.71

GRAFICO DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO ACUMULADO
Progra mado Fis ico E jecutado Financ ie ro Ejecuta do

120%

110%
AVANCE MENSUAL ACUMULADO (%)

100%
100.00%
90%
87.32%
80%
73.05%
70%
60.42% 60.42% 66.76%
61.63% 62.33% 63.58%
60% 58.66% 58.95% 60.57%
56.58%
50% 52.08% 54.34% 46.47%
45.11% 45.43% 45.86%
48.13%
42.94% 45.90%
40% 42.94% 44.11% 44.73%
43.66%
30%

20%

10%

0% 00.00%
0.00%
Inicio informe de noviembre diciembre enero 2016 febrero marzo abril 2016 mayo 2016 junio 2016 Julio 2016 agosto setiembre
corte 2015 2015 2016 2016 2016 2016
PLAZO DE EJECUCION (MESES)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


Periodo Programado Fisico Ejecutado Financiero Ejecutado
N° de Mes del Monto % Ejecución % Monto Porcentaje % Monto Porcentaje %
Informe Informe S/. Programada Acumulado S/. de Ejecución Acumulado S/. de Ejecución Acumulado
0 Inicio 0.00 0.00% 0.00% 0 0.00% 0.00% 0
1 informe de corte 10,692,156.75 42.94% 42.94% 10,692,156.75 42.94% 42.94% 14,604,949.24 58.66% 58.66%
2 noviembre 2015 289,993.91 1.16% 44.11% 179,993.91 0.72% 43.66% 73,215.05 0.29% 58.95%
3 diciembre 2015 446,451.41 1.79% 45.90% 264,328.56 1.06% 44.73% 365,544.25 1.47% 60.42%
4 enero 2016 555,452.37 2.23% 48.13% 96,608.25 0.39% 45.11% 0.00 0.00% 60.42%
5 febrero 2016 983,113.40 3.95% 52.08% 78,908.47 0.32% 45.43% 302,722.96 1.22% 61.63%
6 marzo 2016 562,382.94 2.26% 54.34% 106,520.05 0.43% 45.86% 172,513.18 0.69% 62.33%
7 abril 2016 557, 452.37 2.24% 56.58% 152,126.83 0.61% 46.47% 312,242.92 1.25% 63.58%
8 mayo 2016 995,113.40 4.00% 60.57%
9 junio 2016 1,541,300.56 6.19% 66.76%
10 Julio 2016 1,564,637. 94 6.28% 73.05%
11 agosto 2016 3,554,591.45 14.28% 87. 32%
12 setiembre 2016 3,156,512.20 12.68% 100.00%

To tal a la Fecha 24,899,158.71 100.00% 11,570,642.82 46.47% 15,831,187.60 63.58%

DESCRIPCION DEL PROYECTO

El proyecto: “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL CIRCUITO TURISTICO LAGO SAGRADO DE LOS INCAS - DISTRITOS CAPACHICA, CHUCUITO, PLATERIA, ACORA, ILAVE TRAMO I
CAPACHICA – LLACHON”, contempla el mejoramiento de la vía a nivel de carpeta asfáltica en una longitud de L=13.76 Km, interconectando centros poblados y comunidades que se encuentran
dentro del itinerario del Tramo Capachica Llachon ademas se ejecutara trabajos de obras de arte , drenaje y señalizacion vial

OBJETIVOS DEL PROYECTO

El objetivo general es la elaboración del Expediente Técnico definitivo: “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL CIRCUITO TURISTICO LAGO SAGRADO DE LOS INCAS - DISTRITOS
CAPACHICA, CHUCUITO, PLATERIA, ACORA, ILAVE TRAMO I CAPACHICA – LLACHON”, es de mejorar la calidad de vida para la población de la jurisdicción de la vía, tramo Capachica - Llachon,
mediante el mejoramiento a nivel de pavimento flexible, en una longitud de 13.760 km, con un ancho de vía 6.60 m, ancho de bermas de 0.90 m por cada lado, implementando obras de arte y
drenaje, señalización de acuerdo a lo considerando los estudios básicos de ingeniería.

PROBLEMAS Y/O DIFICULTADES PRESENTADOS DURANTE EL PROCESO DE EJECUCION DE OBRA

Se tiene las siguentes dificultades en obra:


 hasta la fecha no se cuenta con los bienes y servicios solicitado por esta residencia en su debido momento.
 En este mes hay constantes presipitaciones pluviales la cual dificulta el avance fisico de la obra.
 No se cuenta con maquina pesada como son motoniveladora, cargador frontal y excavadara .
 No hasta la fecha no se
aprueba la modificacion del presupuesto analitico.

ACCIONES TOMADAS PARA LA SOLUCION DE PROBLEMAS Y/O DIFICULTADES PRESENTADOS DURANTE EL PROCESO DE EJECUCION DE OBRA

Debido a los problemas presentados en obra, se tomaron las siguientes acciones:


- Se hace las coordinaciones respectivas, el Residente de Obra y el cordinador de la obra .
- Se hace seguimiento en Gobierno Regional en las oficinas encargadas de abastecer materiales, y la asignacion presupuestal para continuar con lo programado.

DATOS PERSONALES DE LOS EJECUTORES DE OBRA


SUPERVISOR DE OBRA ANTERIORES
NOMBRES Y APELLIDOS : ING. HILARIO TIPULA MULLISACA
PROFESION : INGENIERO CIVIL
C.I.P. : 71177
DOCUMENTO DE DESIGNACION :

NOMBRES Y APELLIDOS : ING. JUAN HUARACHI BORDA


PROFESION : INGENIERO CIVIL
C.I.P. : 85113
DOCUMENTO DE DESIGNACION :

NOMBRES Y APELLIDOS : ING. ING. VICTOR HUGO CHAVEZ PEREA


PROFESION : INGENIERO CIVIL
C.I.P. : 78845
DOCUMENTO DE DESIGNACION :

RESIDENTE DE OBRA ANTERIORES


NOMBRES Y APELLIDOS : ING. RITA ADUVIRI MAMANI
PROFESION : INGENIERO CIVIL
C.I.P. : 86774
DOCUMENTO DE DESIGNACION :

NOMBRES Y APELLIDOS : ING. REYNALDO SONCO CONDORI


PROFESION : INGENIERO CIVIL
C.I.P. : 95533
DOCUMENTO DE DESIGNACION :

NOMBRES Y APELLIDOS : ING. MARTIN RAUL BENAVENTE ARIAS


PROFESION : INGENIERO CIVIL
C.I.P. : 78036
DOCUMENTO DE DESIGNACION :

NOMBRES Y APELLIDOS ING. NICOMEDES QUISPE MOZO


PROFESION : INGENIERO CIVIL
C.I.P. : 81000
DOCUMENTO DE DESIGNACION :

SUPERVISOR DE OBRA, RESIDENTE DE OBRA ASISTENTE ADMINISTRATIVO DE OBRA ACTUALES


SUPERVISOR DE OBRA
NOMBRES Y APELLIDOS : ING. ALFREDO ALARCON ATAHUACHI
PROFESION : INGENIERO CIVIL
C.I.P. : 81732
DOCUMENTO DE DESIGNACION :

RESIDENTE DE OBRA
NOMBRES Y APELLIDOS : ING. PERCY BAYLON CCARI APAZA
PROFESION : INGENIERO CIVIL
C.I.P. : 92354
DOCUMENTO DE DESIGNACION :

ASISTENTE ADMINISTRATIVO
NOMBRES Y APELLIDOS : Sr. STALIN MONTES MENDOZA
PROFESION : NO ESPESIFICA
DOCUMENTO DE DESIGNACION :

: En el caso que no sea de aplicación a la obra, considerar como "NO CORRESPONDE"


Esta ficha de control debe ser firmado por el Residente y Supervisor de Obra
OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHU
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
LUGAR DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIM
SUPERVISOR
INICIO DE PLAZO CO 29/10/21
PLAZO 353
FIN DE PLAZO CONT 31/08/23
PERIODO DE TRABAJ PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023
PLAZO TRANSCURRIDO A LA FECHA DE VALORIZACION DE LA OBRA: 55 días calendarios

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUIN


DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CH

Nº Valorización Monto Ejecutado Avance Físico


VAL. ANTERIOR S/.8,801,589.12 61.25% 0.43%
VAL. ACTUAL S/.23,845.90 0.17% 3.64%
VAL. ACUMULADO S/.8,825,435.02 61.42% 8.28%
SALDO S/.5,544,460.71 38.58%
COSTO TOTAL(*) S/.14,369,895.73 100.00% 5´179,774.57
DEDUCTIVO VINC 01 S/.5,179,774.57
DEDUCTIVO 01 S/.860,747.38
NUEVO MONTO
S/.13,509,148.35
DE OBRA

anterior Nº Valorización Monto Ejecutado Avance Físico


VAL. ANTERIOR S/.794,808.88 4.07% 2.17%
VAL. ACTUAL S/.1,618,323.01 8.28% 0.00%
VAL. ACUMULADO S/.2,413,131.89 12.34% 32.56%
SALDO S/.17,136,538.41 87.66%
COSTO TOTAL S/.19,549,670.30 100.00%

PROGRAMADO REAL
OBRA SITUACION
ACUM (%) ACUM.(%)

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-


TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS
DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I 61.25% 61.25% atrasada
GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

CONTROL DE VALORIZACIONES
Nº MES OBRA
1 Oct-21 83,154.66
2 Nov-21 711,654.22
3 Dec-21 1,618,323.01
4 Jan-22 768,795.55
5 Feb-22 404,754.76
6 May-22 924,392.59
7 Jun-22 839,820.07
8 Jul-22 425,055.59
9 Aug-22 413,433.05
10 Sep-22 175,711.16
11 Oct-22 607,820.18
12 Nov-22 1,477,552.06
13 Dec-22 351,122.32
14 Aug-23 23,845.90
ACUMULADO ACTUAL 8,825,435.12
NUEVO MONTO SIN CUNETAS 14,369,895.72
SALDO 5,544,460.60 5544460.69

Nº Mes Monto Facturado c/IGV


* Adelanto efectivo S/.1,436,989.57
** Adelanto Materiales S/.1,266,136.38
Octubre 2021 "valorización Nº 01" S/.74,839.20
Noviembre 2021 "valorización Nº 02" S/.640,488.80
Diciembre 2021 "valorización Nº 03" S/.1,456,490.71
Enero 2022 "valorización Nº 04" S/.691,916.00
Febrero "valorización Nº 05" S/.364,279.29
Mayo "valorización Nº 06" S/.831,953.31
Junio "valorización Nº 07" S/.707,774.50
Julio "valorización Nº 08" S/.736,249.27
Agosto "valorización Nº 09" S/.369,178.95
Septiembre "valorización Nº 10"
Octubre "valorización Nº 11"
Noviembre "valorización Nº 12"

TOTAL PAGADO: 6,720,915.22160

TOTAL RETENIDO: 1,855,380.75

*EN CADA FACTURA SE VIENE RALIZANDO LA RETENIENDO DEL 10%

RELACION DE MAQUINARIA
N° DESCRIPCION CANT.

1 EXCAVADORA DE ORUGA 3 UNIDADES

2 CARGADOR FRONTAL 2 UNIDADES


3 MOTONIVELADORA 2 UNIDADES
4 RODILLOS VIBRATORIO 3 UNIDADES
5 TRACTOR DE ORUGA 1 UNIDADES
6 MINICARGADOR-CAT-236 1 UNIDADES
7 AUTOHORMIGONERA-CARMIX 1 UNIDADES
8 COMPRENSORA-SULLAR 1 UNIDADES
9 CAMION CISTERNA 4500 GLN-IVECO 1 UNIDADES
9 RETROEXCAVADORA 1 UNIDADES
10 CAMIONETAS 4X4 4 UNIDADES
11 VOLQUETE DE 15 M3 13 UNIDADES
12 COMPRENSORA DE AIRE 2 UNIDADES
13 MARTILLOS 2 UNIDADES
14 ESTACION TOTAL 1 UNIDADES
15 NIVEL TOPOGRAFICO 2 UNIDADES

SUB TOTAL

REAJUSTES
AMORTIZACION
DIRECTO
AMORTIZACION
MATERIALES

TOTAL

IGV
MONTO A
FACTURAR

VALORIZACION 12
VALORIZACION 04
LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMAR

NSTRUCTOR PARASOL S.A.C.


DE RESPONSABILIDAD LIMITADA

A: 55 días calendarios 0
0
0
ANGUIA-RODEOPAMPA-GUINEAMAYO,
0
RODEOPAMPA - ANGUIA - CHUGUR"
0
0
0
0

49.00%
-8,825,435.04000000
0.09

Pendiente c/IGV Fecha de Pago


PAGADA
PAGADA
PAGADA
PAGADA
PAGADA 19764.88
PAGADA
PAGADA
PAGADA
PAGADA
PAGADA
PAGADA

S/.150,192.90 PENDIENTE

S/.176,491.09 PENDIENTE

S/.19,764.88 PENDIENTE

DESCRIPCION MONTO
MONTO INICIAL DEL
S/.19,549,670.30 100.00%
CONTRATO
DEDUCTIVO S/.5,179,774.57 100.00%

DEDUCTIVO 01 S/.860,747.38 200.00%

NUEVO MONTO DE
S/.13,509,148.35
OBRA
VALORIZACION 12 VALORIZACION 04
Nov-22 Nov-22

VALORIZACION 11 CON REAJUSTES SIN REAJUSTES CON REAJUSTES SIN REAJUSTES

20,208.39 20,208.39 359,448.40 359,448.40

0.00 0.00 59,247.03 0.00

(2,020.84) (2,020.84) 0.00 0.00

(1,437.65) (1,437.65) 0.00 0.00

16,749.90 16,749.90 418,695.43 359,448.40

3,014.98 3,014.98 75,365.18 64,700.71

S/.176,491.09 19,764.88 19,764.88 494,060.61 424,149.11


CONTRACTUAL ADICIONAL DE OBRA

19,764.88
424,149.11
443,913.99 noviembre
GUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
FICHA TÉCNICA
TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR

VALORIZACION DE OBRA N° 14
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023

OBRA : CONTRATO N° 02-2021-MDA/A


MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR
´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
´CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA

CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL
S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD
SUPERVISOR: : LIMITADA

CONTRATO : N° 02-2021-MDA/A

FIRMA CONTRATO : 14 de Octubre del 2021

FINANCIAMIENTO : contratación Directa N°01-2021-MDA/ABAST

PPTO CONTRACTUAL VIGENTE (CON IGV) : S/. 14,369,895.72

ADICIONAL DE OBRA N°02 : S/. 5,153,176.58 (C/IGV)

INICIO DE OBRA : 29 de octubre de 2021

PLAZO INICIAL DE EJECUCION : 210 días calendarios

SUSPENSIONES DE PLAZO

INICIO SUSPENSION DE PLAZO N°01 : 13 de enero de 2022

FIN DE SUSPENSION DE PLAZO N°01 : 31 de enero de 2022

INICIO SUSPENSION DE PLAZO N°02 : 10 de febrero de 2022

FIN DE SUSPENSION DE PLAZO N°02 : 1 de mayo de 2022

AMPLIACIONES DE PLAZO

AMPLIACION DE PLAZO N°01 APROBADA : 21 D.C. RESOLUCION DE ALCALDIA N° 127-2022-MDA/A


POR

AMPLIACION DE PLAZO N°02 APROBADA : 33 D.C. RESOLUCION DE ALCALDIA N° 166-2022-MDA/A


POR

AMPLIACION DE PLAZO PARCIAL N°02 : 18 D.C. RESOLUCION DE ALCALDIA N° 175-2022-MDA/A


APROBADA POR

AMPLIACION DE PLAZO N°06 APROBADA : 07 D.C. RESOLUCION DE GERENCIA N° 002-2022-G/MDA


POR

AMPLIACION DE PLAZO PARCIAL N°04 : 12 D.C. RESOLUCION DE GERENCIA N° 009-2022-G/MDA


APROBADA POR

AMPLIACION DE PLAZO N°07 APROBADA : 12 D.C. RESOLUCION DE GERENCIA N° 022-2022-G/MDA


POR
FICHA TÉCNICA
TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR

VALORIZACION DE OBRA N° 14
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023

AMPLIACION DE PLAZO PARCIAL N°05 : 07 D.C. RESOLUCION DE GERENCIA N° 032-2022-G/MDA


APROBADA POR

AMPLIACION DE PLAZO N°08 APROBADA : 11 D.C. RESOLUCION DE GERENCIA N° 039-2022-G/MDA


POR

AMPLIACION DE PLAZO N°09 APROBADA : 9 D.C. RESOLUCION DE ALCALDIA N° 001-2023-MDA/A (02/01/2023)


POR

AMPLIACION DE PLAZO N°10 APROBADA : 13 D.C. RESOLUCION DE ALCALDIA N° 015-2023-MDA/A (13/01/2023)


POR

AMPLIACION DE PLAZO N°11 APROBADA : 07 D.C. EN TRAMITE


POR

NUEVA FECHA DE CULMINACION DE OBRA : 14 de diciembre de 2022

RESIDENTE : ING. OTTO LUCIANO ASTOCAZA RAMOS


CIP RESIDENTE : 45855
SUPERVISOR: : ING. UBALDO ABAD PESANTES GUZMÁN
CIP SUPERVISOR : 111403
RESUMEN DE VALORIZACION N° 014
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023
August-2023
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-
OBRA : GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO -
RODEOPAMPA - ANGUIA - CHUGUR"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR :
MONTO CONTRACTUAL : S/. 14,369,895.72
ADELANTO DIRECTO (S/ IGV) : S/. 1,217,787.77
ADELANTO MATERIALES (S/ IGV) : S/. 1,072,996.93
INICIO DE PLAZO CONTRACTUAL : 10/29/2021
FIN DE PLAZO CONTRACTUAL : 8/31/2023

MONTO VALORIZACION SALDO POR


CONCEPTO CONTRATO
ANTERIOR ACTUAL ACUMULADO VALORIZAR
S/(IGV)

A. MONTO VALORIZADO
MONTO VALORIZADO 12,177,877.73 7,458,973.83 20,208.39 7,479,182.22 4,698,695.51
TOTAL 12,177,877.73 7,458,973.83 20,208.39 7,479,182.22 4,698,695.51

AVANCE FISICO DE OBRA 61.25% 0.17% 61.42% 38.58%

B. MONTO POR REAJUSTE


MONTO POR REAJUSTE 1,272,552.95 0.00 1,272,552.95
TOTAL 1,272,552.95 0.00 1,272,552.95

C. DEDUCCION QUE NO CORRESPONDE POR ADEL. DIRECTO


DEDUCCION QUE NO CORRESPONDE POR ADEL. DIRECTO 0.00 0.00 0.00
TOTAL 0.00 0.00 0.00

D. DEDUCCION QUE NO CORRESPONDE POR ADEL. DE MATERIALES


DEDUCCION QUE NO CORRESPONDE POR ADEL. DE MATERIALES 0.00 0.00 0.00
TOTAL 0.00 0.00 0.00

E. AMORTIZACION DEL ADELANTO EN EFECTIVO


AMORTIZACION DEL ADELANTO EN EFECTIVO 1,217,787.77 (788,398.83) (2,020.84) (790,419.67)
TOTAL 1,217,787.77 (788,398.83) (2,020.84) (790,419.67)

F. AMORTIZACION DEL ADELANTO DE MATERIALES


AMORTIZACION DEL ADELANTO DE MATERIALES 1,072,996.93 (241,505.26) (1,437.65) 242,942.91
TOTAL 1,072,996.93 (241,505.26) (1,437.65) 242,942.91

VALORIZACION NETA (A+B+C+D+E+F) 7,701,622.69 16,749.90 8,204,258.41

PENALIDADES Y DESCUENTOS
G. PENALIDADES
MULTA POR ATRASO DE OBRA 0.00 0.00 0.00
INDENMIZACION POR ATRASO 0.00 0.00 0.00
TOTAL 0.00 0.00 0.00

F. RETENCIONES
FONDO DE GARANTIA 0.00 0.00 0.00
TOTAL 0.00 0.00 0.00

TOTAL DE DESCUENTOS (G) 0.00 0.00 0.00

MONTO A PAGAR AL CONTRATISTA

MONTO LIQUIDO A PAGAR S/. 16,749.90


IGV (18%) 18.00% 2,192,017.99 S/. 3,014.98
MONTO A FACTURAR S/. 19,764.88
14,369,895.72
SON:VEINTICUATRO MIL CIENTO CINCUENTA Y DOS CON 52/100 SOLES
VALORIZACIONES TRAMITADAS - CONTRATO PRINCIPAL
VALORIZACION DE OBRA N° 14
OBRA : MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMA
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR :

Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 May-22


Nº DESCRIPCION TOTAL
VAL 1 VAL 2 VAL 3 VAL 4 VAL 5 VAL 6

1.00 MONTO VALORIZADO EN EL MES (A) - - - - - - -


1.01 VALORIZACION - - - - - - -

2.00 MONTO POR REAJUSTE (B) 6,342.30 62,722.07 148,117.70 63,849.12 38,760.41 139,442.27 459,233.87
2.01 REAJUSTE DE VALORIZACION 6,342.30 62,722.07 148,117.70 63,849.12 38,760.41 139,442.27 459,233.87

3.00 DEDUCCION QUE NO CORRESPONDE POR ADEL. DIRECTO (C) - - - - - - -


3.01 DEDUCCION DEL ADELANTO EN EFECTIVO - - - - - - -

4.00 DEDUCCION QUE NO CORRESPONDE POR ADEL. DE MATERIALES (D) - - - - - - -


4.01 DEDUCCION DEL ADELANTO DE MATERIALES - - - - - - -

5.00 AMORTIZACION DEL ADELANTO EN EFECTIVO (E) -7,047.00 -60,309.68 -137,146.02 -65,152.16 -34,301.25 -78,338.35 -382,294.46
3.01 AMORTIZACION DEL ADELANTO EN EFECTIVO -7,047.00 -60,309.68 -137,146.02 -65,152.16 -34,301.25 -78,338.35 -382,294.46

6.00 AMORTIZACION DEL ADELANTO DE MATERIALES (F) - - - - - #N/A #N/A


6.01 AMORTIZACION DEL ADELANTO DE MATERIALES - - - - - #N/A #N/A

SUB - TOTAL (A+B+C+D+E+F) -704.70 2,412.39 10,971.68 -1,303.04 4,459.16 #N/A #N/A
IGV 18.00% -126.85 434.23 1,974.90 -234.55 802.65 #N/A #N/A
TOTAL -831.55 2,846.62 12,946.58 -1,537.59 5,261.81 #N/A #N/A

17 de 51
VALORIZACION DE OBRA N° 14
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023

OBRA : MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA INICIO DE PLAZO CONTRACTUAL : 29/10/21
LUGAR : DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA AMPLIACION DE PLAZO PARCIAL N°02 APR : 18 D.C.
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C. NUEVO MONTO DE CONTRATO OBRA (S/IGV : S/. 12,177,877.73
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR : NUEVO MONTO DE CONTRATO OBRA (C/IGV : S/. 14,369,895.72

PRECIO TOTAL ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR
ITEM DESCRIPCION UND CANT
S/. S/. CANT S/. % CANT S/. % CANT S/. % CANT S/. %
01.00.00 OBRAS PRELIMINARES 183,415.41 113,963.69 62.13% - 0.00% 113,963.69 62.13% 66,457.80 36.23%
01.01.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 132,915.60 132,915.60 0.50 66,457.80 50.00% - - 0.00% 0.50 66,457.80 50.00% 0.50 66,457.80 50.00%
01.02.00 TRAZO, REPLANTEO Y CONTROL TOPOGRAFICO KM 22.60 1,555.59 35,156.33 22.60 35,156.33 100.00% - 0.00% 22.60 35,156.33 100.00% - - 0.00%
01.03.00 LIMPIEZA GENERAL - ROCE Y DESBROCE HA 1.35 3,114.25 4,204.24 1.35 4,204.24 100.00% - 0.00% 1.35 4,204.24 100.00% - - 0.00%
01.04.00 CARTEL DE OBRA DE 3.60 X 2.40 M und 2.00 832.18 1,664.36 2.00 1,664.36 100.00% - 0.00% 2.00 1,664.36 100.00% - - 0.00%
01.05.00 CAMPAMENTO PROVISIONAL DE OBRA m2 92.42 77.99 7,207.84 64.69 5,045.17 70.00% - 0.00% 64.69 5,045.17 70.00% 27.73 2,162.66 30.00%
01.06.00 DEMOLICION m3 12.00 188.92 2,267.04 7.60 1,435.79 63.33% - 0.00% 7.60 1,435.79 63.33% 4.40 831.25 36.67%

02.00.00 MOVIMIENTO DE TIERRAS 1,625,591.02 1,419,348.75 87.31% - 0.00% 1,419,348.75 87.31% 206,242.27 12.69%
02.01.00 CORTE EN MATERIAL SUELTO m3 60,612.91 3.33 201,840.99 52,919.51 176,221.97 87.31% - 0.00% 52,919.51 176,221.97 87.31% 7,693.40 25,619.02 12.69%
02.02.00 CORTE EN ROCA SUELTA m3 55,563.73 18.56 1,031,262.83 47,992.46 890,740.06 86.37% - 0.00% 47,992.46 890,740.06 86.37% 7,571.27 140,522.77 13.63%
02.03.00 CORTE EN ROCA FIJA m3 10,474.84 29.20 305,865.33 9,544.44 278,697.65 91.12% - 0.00% 9,544.44 278,697.65 91.12% 930.40 27,167.68 8.88%
02.04.00 CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO m3 7,480.30 11.58 86,621.87 6,363.48 73,689.07 85.07% - 0.00% 6,363.48 73,689.07 85.07% 1,116.82 12,932.80 14.93%

03.00.00 PAVIMENTOS 2,815,959.81 2,255,122.90 80.08% 17,588.63 0.62% 2,272,711.52 80.71% 543,248.29 19.29%
03.01.00 SUB-BASE GRANULAR m3 23,353.75 37.52 876,232.70 18,209.28 683,212.19 77.97% 468.78 17,588.63 2.01% 18,678.06 700,800.81 79.98% 4,675.69 175,431.89 20.02%
03.02.00 BASE GRANULAR m3 21,789.79 89.02 1,939,727.11 17,657.95 1,571,910.71 81.04% - 0.00% 17,657.95 1,571,910.71 81.04% 4,131.84 367,816.40 18.96%

03.03.00 TRATAMIENTO SUPERFICIAL 3,681,464.77 979,545.26 26.61% - 0.00% 979,545.26 26.61% 2,701,919.50 73.39%
03.03.01 IMPRIMACION BITUMINOSA CON EMULSION m2 140,192.87 6.31 884,617.01 44,264.58 279,309.50 31.57% - 0.00% 44,264.58 279,309.50 31.57% 95,928.29 605,307.51 68.43%
03.03.02 TRATAMIENTO SUPERFICIAL BICAPA - 1RA CAPA m2 140,192.87 10.26 1,438,378.85 42,736.86 438,480.18 30.48% - 0.00% 42,736.86 438,480.18 30.48% 97,456.01 999,898.66 69.52%
03.03.03 TRATAMIENTO SUPERFICIAL BICAPA - 2DA CAPA m2 140,192.87 9.69 1,358,468.91 27,012.96 261,755.58 19.27% - 0.00% 27,012.96 261,755.58 19.27% 113,179.91 1,096,713.33 80.73%

04.00.00 TRANSPORTE 1,697,856.42 1,510,276.61 88.95% - 0.00% 1,510,276.61 88.95% 187,579.83 11.05%
04.01.00 TRANSPORTES DE MATERIAL PARA AFIRMADO HASTA 1 KM M3K 42,592.78 7.03 299,427.24 36,675.04 257,825.56 86.11% - - 0.00% 36,675.04 257,825.56 86.11% 5,917.74 41,601.68 13.89%
04.02.00 TRANSPORTE DE MATERIAL PARA AFIRMADO DESPUES DE 1 KM M3K 110,070.77 1.87 205,832.34 98,387.81 183,985.21 89.39% - - 0.00% 98,387.81 183,985.21 89.39% 11,682.96 21,847.13 10.61%
04.03.00 TRANSPORTES DE MATERIAL EXCEDENTE HASTA <= 1 KM M3K 133,826.08 6.31 844,442.56 120,873.86 762,714.04 90.32% - 0.00% 120,873.86 762,714.04 90.32% 12,952.22 81,728.53 9.68%
04.04.00 TRANSPORTES DE MATERIAL EXCEDENTE > 1 KM M3K 246,917.93 1.41 348,154.28 216,845.25 305,751.80 87.82% - 0.00% 216,845.25 305,751.80 87.82% 30,072.68 42,402.49 12.18%

05.00.00 OBRAS DE ARTE Y DRENAJE


05.02.00 ALCANTARILLAS 144,927.25 54,352.45 37.50% - 0.00% 54,352.45 37.50% 90,574.80 62.50%
05.02.01 LIMPIEZA DE TERRENO MANUAL m2 269.36 2.04 549.49 131.20 267.65 48.71% - 0.00% 131.20 267.65 48.71% 138.16 281.85 51.29%
05.02.02 TRAZO Y REPLANTEO m2 323.23 3.76 1,215.34 157.44 591.97 48.71% - 0.00% 157.44 591.97 48.71% 165.79 623.37 51.29%
05.02.03 EXCAVACION PARA ESTRUCTURAS C/MAQUINA m3 336.42 15.99 5,379.36 173.95 2,781.46 51.71% - 0.00% 173.95 2,781.46 51.71% 162.47 2,597.90 48.29%
05.02.04 RELLENO COMPACTADO PARA ESTRUCTURAS m3 223.46 32.73 7,313.85 32.18 1,053.25 14.40% - 0.00% 32.18 1,053.25 14.40% 191.28 6,260.59 85.60%
05.02.05 SOLADO 4" m3 8.82 434.25 3,830.09 - - 0.00% - 0.00% - - 0.00% 8.82 3,830.09 100.00%
05.02.06 CONCRETO F'C=210 KG/CM2 m3 75.24 580.17 43,651.99 - - 0.00% - 0.00% - - 0.00% 75.24 43,651.99 100.00%
05.02.07 ENCOFRADO Y DESENCOFRADO m2 431.76 54.81 23,664.77 - - 0.00% - 0.00% - - 0.00% 431.76 23,664.77 100.00%
05.02.08 EMBOQUILLADO DE PIEDRA m3 23.47 411.77 9,664.24 - - 0.00% - 0.00% - - 0.00% 23.47 9,664.24 100.00%
05.02.09 ALCANTARILLA TMC D=60" m 50.10 991.18 49,658.12 50.10 49,658.12 100.00% - 0.00% 50.10 49,658.12 100.00% - - 0.00%
05.03.00 BADENES 128,310.76 63,130.28 49.20% - 0.00% 63,130.28 49.20% 65,180.48 50.80%
05.03.01 LIMPIEZA DE TERRENO MANUAL m2 271.25 2.04 553.35 163.25 333.03 60.18% - 0.00% 163.25 333.03 60.18% 108.00 220.32 39.82%
05.03.02 TRAZO Y REPLANTEO m2 271.25 3.76 1,019.90 163.25 613.82 60.18% - 0.00% 163.25 613.82 60.18% 108.00 406.08 39.82%
05.03.03 EXCAVACION MANUAL DE ESTRUCTURA m3 166.00 46.96 7,795.36 113.83 5,345.57 68.57% - 0.00% 113.83 5,345.57 68.57% 52.17 2,449.79 31.43%
VALORIZACION DE OBRA N° 14
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023

OBRA : MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA INICIO DE PLAZO CONTRACTUAL : 29/10/21
LUGAR : DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA AMPLIACION DE PLAZO PARCIAL N°02 APR : 18 D.C.
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C. NUEVO MONTO DE CONTRATO OBRA (S/IGV : S/. 12,177,877.73
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR : NUEVO MONTO DE CONTRATO OBRA (C/IGV : S/. 14,369,895.72

PRECIO TOTAL ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR
ITEM DESCRIPCION UND CANT
S/. S/. CANT S/. % CANT S/. % CANT S/. % CANT S/. %
05.03.04 CONCRETO F'C=210 KG/CM2 m3 95.78 580.17 55,568.68 60.29 34,980.60 62.95% - 0.00% 60.29 34,980.60 62.95% 35.49 20,588.09 37.05%
05.03.05 ENCOFRADO Y DESENCOFRADO m2 107.13 54.81 5,871.80 101.73 5,575.98 94.96% - 0.00% 101.73 5,575.98 94.96% 5.40 295.82 5.04%
05.03.06 EMBOQUILLADO DE PIEDRA m3 131.54 411.77 54,164.23 39.54 16,281.28 30.06% - 0.00% 39.54 16,281.28 30.06% 92.00 37,882.94 69.94%
05.03.07 JUNTA TRANSVERSAL DE DILATACION m 82.61 40.40 3,337.44 - - 0.00% - 0.00% - - 0.00% 82.61 3,337.44 100.00%
05.04.00 MUROS DE CONTENCIÓN
05.04.01 MUROS DE CONCRETO SIMPLE
05.04.01.01 TRABAJOS PRELIMINARES 342.37 284.37 83.06% - 0.00% 284.37 83.06% 58.00 16.94%
05.04.01.01.01 TRAZO Y REPLANTEO m2 50.50 3.76 189.88 40.50 152.28 80.20% - 0.00% 40.50 152.28 80.20% 10.00 37.60 19.80%
05.04.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 74.75 2.04 152.49 64.75 132.09 86.62% - 0.00% 64.75 132.09 86.62% 10.00 20.40 13.38%
05.04.01.02 MOVIMIENTO DE TIERRAS 10,065.50 8,211.82 81.58% - 0.00% 8,211.82 81.58% 1,853.67 18.42%
05.04.01.02.01 EXCAVACION MANUAL m3 163.50 55.21 9,026.84 132.45 7,312.56 81.01% - 0.00% 132.45 7,312.56 81.01% 31.05 1,714.27 18.99%
05.04.01.02.02 NIVELACION Y APISONADO m2 50.50 3.23 163.12 40.50 130.82 80.20% - 0.00% 40.50 130.82 80.20% 10.00 32.30 19.80%
05.04.01.02.03 RELLENO CON MATERIAL PROPIO m3 81.75 10.71 875.54 71.75 768.44 87.77% - 0.00% 71.75 768.44 87.77% 10.00 107.10 12.23%
05.04.01.03 CONCRETO SIMPLE 27,963.48 23,044.28 82.41% - 0.00% 23,044.28 82.41% 4,919.20 17.59%
05.04.01.03.01 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. EN MURO DE CONT m3 62.14 282.84 17,575.68 51.88 14,673.74 83.49% - 0.00% 51.88 14,673.74 83.49% 10.26 2,901.94 16.51%
05.04.01.03.02 ENCOFRADO Y DESENCOFRADO m2 174.00 54.81 9,536.94 140.21 7,684.91 80.58% - 0.00% 140.21 7,684.91 80.58% 33.79 1,852.03 19.42%
05.04.01.03.03 CURADO DE CONCRETO m2 174.00 4.89 850.86 140.21 685.63 80.58% - 0.00% 140.21 685.63 80.58% 33.79 165.23 19.42%
05.04.01.04 OTROS 1,124.71 880.87 78.32% - 0.00% 880.87 78.32% 243.84 21.68%
05.04.01.04.01 TUBERIA PARA DRENAJE m 55.35 20.32 1,124.71 43.35 880.87 78.32% - 0.00% 43.35 880.87 78.32% 12.00 243.84 21.68%

06.00.00 SEÑALIZACIÓN 204,743.88 - 0.00% - 0.00% - 0.00% 204,743.88 100.00%


06.01.00 SEÑALES PREVENTIVAS und 159.00 615.58 97,877.22 - - 0.00% - 0.00% - - 0.00% 159.00 97,877.22 100.00%
06.02.00 POSTES DE KILOMETRAJE und 23.00 143.53 3,301.19 - - 0.00% - 0.00% - - 0.00% 23.00 3,301.19 100.00%
06.03.00 SEÑALES INFORMATIVAS und 9.00 542.87 4,885.83 - - 0.00% - 0.00% - - 0.00% 9.00 4,885.83 100.00%
06.04.00 ESTRUCTURA DE SOPORTE DE SEÑALES INFORMATIVAS und 9.00 2,404.92 21,644.28 - - 0.00% - 0.00% - - 0.00% 9.00 21,644.28 100.00%
06.05.00 MARCAS EN EL TRATAMIENTO SUPERFICIAL m2 7,253.80 10.62 77,035.36 - - 0.00% - 0.00% - - 0.00% 7,253.80 77,035.36 100.00%

07.00.00 COSTOS AMBIENTALES 13,553.86 - 0.00% - 0.00% - 0.00% 13,553.86 100.00%


07.01.00 ACONDICIONAMIENTO DE BOTADEROS m2 4,522.50 2.38 10,763.55 - - 0.00% - 0.00% - - 0.00% 4,522.50 10,763.55 100.00%
07.02.00 ACONDICIONAMIENTO DE CANTERAS m2 896.40 0.99 887.44 - - 0.00% - 0.00% - - 0.00% 896.40 887.44 100.00%
07.03.00 ACONDICIONAMIENTO DE AREAS OCUPADAS POR CAMPAMENTO m2 92.42 5.21 481.51 - - 0.00% - 0.00% - - 0.00% 92.42 481.51 100.00%
07.04.00 ACONDICIONAMIENTO DE AREA OCUPADAS POR PATIO DE MAQUINAS m2 436.00 3.26 1,421.36 - - 0.00% - 0.00% - - 0.00% 436.00 1,421.36 100.00%

08.00.00 PLAN PARA VIGILANCIA, PREVENCIÓN Y CONTROL DE COVID-19 63,851.36 63,851.36 100.00% - 0.00% 63,851.36 100.00% - 0.00%
08.01.00 PRUEBAS RAPIDAS PARA DETECTAR COVID-19 und 552.00 48.00 26,496.00 552.00 26,496.00 100.00% - 0.00% 552.00 26,496.00 100.00% - - 0.00%
08.02.00 EQUIPAMIENTO, IMPLEMENTACION E INSUMOS PARA LA PRECENCION GLB 1.00 26,755.36 26,755.36 1.00 26,755.36 100.00% - 0.00% 1.00 26,755.36 100.00% - - 0.00%
08.03.00 SEÑALIZACION Y CAPACITACION GLB 1.00 10,600.00 10,600.00 1.00 10,600.00 100.00% - 0.00% 1.00 10,600.00 100.00% - - 0.00%

COSTO DIRECTO 10,599,170.60 6,492,012.64 17,588.63 6,509,601.26 4,089,569.33


GASTOS GENERALES 7.895% 836,765.19 512,520.31 1,388.56 513,908.86 322,856.32
UTILIDAD 7.000% 741,941.94 454,440.88 1,231.20 455,672.09 286,269.85
PARCIAL 12,177,877.73 7,458,973.83 61.25% 20,208.39 0.17% 7,479,182.21 61.42% 4,698,695.50 38.58%
IGV 18.000% 2,192,017.99 1,342,615.29 3,637.51 1,346,252.80 845,765.19
TOTAL 14,369,895.73 8,801,589.12 61.25% 23,845.90 0.17% 8,825,435.01 61.42% 5,544,460.69 38.58%
RESUMEN DE METRADOS
August-23
ENTIDAD: MUNICIPALIDAD DISTRITAL DE ANGUIA
OBRA: MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR
´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, ´CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
CONTRATO: N° 02-2021-MDA/A
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR:
Metrado Acumulado Val Nº Acumulado Saldos por
Partida Descripción Und Contrato Anterior 14 Actual Valorizar
Original Metrado Metrado Metrado % Metrado %
03.00.00 PAVIMENTOS

03.01.00 SUB-BASE GRANULAR m3 23,353.75 18,209.280 468.7800 18,678.0600 79.98% 4,675.6900 20.02%
03.02.00 BASE GRANULAR m3 21,789.79 17,657.950 - 17,657.9500 81.04% 4,131.8400 18.96%

03.03.00 TRATAMIENTO SUPERFICIAL

03.03.01 IMPRIMACION BITUMINOSA CON EMULSION m2 140,192.87 44,264.580 - 44,264.5800 31.57% 95,928.2900 68.43%
03.03.02 TRATAMIENTO SUPERFICIAL BICAPA - 1RA CAPA m2 140,192.87 42,736.860 - 42,736.8600 30.48% 97,456.0100 69.52%
03.03.03 TRATAMIENTO SUPERFICIAL BICAPA - 2DA CAPA m2 140,192.87 27,012.960 - 27,012.9600 19.27% 113,179.9100 80.73%

04.00.00 TRANSPORTE

04.01.00 TRANSPORTES DE MATERIAL PARA AFIRMADO HASTA 1 KM M3K 42,592.78 36,675.045 - 36,675.0447 86.11% 5,917.7353 13.89%
04.02.00 TRANSPORTE DE MATERIAL PARA AFIRMADO DESPUES DE 1 KM M3K 110,070.77 98,387.814 - 98,387.8141 89.39% 11,682.9559 10.61%

05.04.00 MUROS DE CONTENCIÓN

05.04.01 MUROS DE CONCRETO SIMPLE

05.04.01.01 TRABAJOS PRELIMINARES

05.04.01.01.01 TRAZO Y REPLANTEO m2 50.50 40.500 - 40.5000 80.20% 10.0000 19.80%


05.04.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 74.75 64.750 - 64.7500 86.62% 10.0000 13.38%
05.04.01.02 MOVIMIENTO DE TIERRAS

05.04.01.02.01 EXCAVACION MANUAL m3 163.50 132.450 - 132.4500 81.01% 31.0500 18.99%


05.04.01.02.02 NIVELACION Y APISONADO m2 50.50 40.500 - 40.5000 80.20% 10.0000 19.80%
05.04.01.02.03 RELLENO CON MATERIAL PROPIO m3 81.75 71.750 - 71.7500 87.77% 10.0000 12.23%
05.04.01.03 CONCRETO SIMPLE

05.04.01.03.01 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. EN MURO DE CONTECION m3 62.14 51.880 - 51.8800 83.49% 10.2600 16.51%
05.04.01.03.02 ENCOFRADO Y DESENCOFRADO m2 174.00 140.210 - 140.2100 80.58% 33.7900 19.42%
05.04.01.03.03 CURADO DE CONCRETO m2 174.00 140.210 - 140.2100 80.58% 33.7900 19.42%
05.04.01.04 OTROS

05.04.01.04.01 TUBERIA PARA DRENAJE m 55.35 43.350 - 43.3500 78.32% 12.0000 21.68%

06.00.00 SEÑALIZACIÓN

06.01.00 SEÑALES PREVENTIVAS und 159.00 - - - - 159.0000 100.00%


06.02.00 POSTES DE KILOMETRAJE und 23.00 - 23.0000 100.00%
06.03.00 SEÑALES INFORMATIVAS und 9.00 - - - - 9.0000 100.00%
06.04.00 ESTRUCTURA DE SOPORTE DE SEÑALES INFORMATIVAS und 9.00 - - - - 9.0000 100.00%
06.05.00 MARCAS EN EL TRATAMIENTO SUPERFICIAL m2 7,253.80 - - - - 7,253.8000 100.00%

07.00.00 COSTOS AMBIENTALES


07.01.00 ACONDICIONAMIENTO DE BOTADEROS m2 4,522.50 - - - - 4,522.5000 100.00%
07.02.00 ACONDICIONAMIENTO DE CANTERAS m2 896.40 - - - - 896.4000 100.00%
07.03.00 ACONDICIONAMIENTO DE AREAS OCUPADAS POR CAMPAMENTO m2 92.42 - - - - 92.4200 100.00%
07.04.00 ACONDICIONAMIENTO DE AREA OCUPADAS POR PATIO DE MAQUINAS m2 436.00 - - - - 436.0000 100.00%

08.00.00 PLAN PARA VIGILANCIA, PREVENCIÓN Y CONTROL DE COVID-19


08.01.00 PRUEBAS RAPIDAS PARA DETECTAR COVID-19 und 552.00 552.000 - 552.0000 100.00% - -
08.02.00 EQUIPAMIENTO, IMPLEMENTACION E INSUMOS PARA LA PRECENCION DEL COVID-19 GLB 1.00 1.000 - 1.0000 100.00% - -
08.03.00 SEÑALIZACION Y CAPACITACION GLB 1.00 1.000 - 1.0000 100.00% - -
FORMULAS POLINOMICAS - CONTRATO PRINCIPAL
VALORIZACION DE OBRA N° 14
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS
OBRA :
DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR :

K = 0.119*(Mr / Mo) + 0.054*(DAr / CAo) + 0.169*(CAr / CAo) + 0.382*(Ar / Ao) + 0.146*(Ar / Ao)+0.130*(Ir/Io)
AREA GEOGRAFICA: 01
1 2 3 4 5 6 7 8 9 10 11 12 13 14
BASE Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Aug-23
SIMB. IU DESCRIPCION COEF. % INCID.
May-21 INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K INDICE K

M 47 MANO DE OBRA INC. LEYES 0.119 100.00% 633.53 653.54 0.123 653.54 0.123 653.54 0.123 650.44 0.122 650.44 0.122 650.44 0.122 650.44 0.122 650.44 0.122 650.44 0.122 650.44 0.122 702.10 0.132 702.10 0.132 702.10 0.132 704.78 0.132
SOCIALES

03 ACERO DE CONSTRUCCION 18.519% 767.70 798.59 794.85 810.49 831.00 811.32 908.09 948.77 946.24 985.34 898.31 894.62 913.20 890.03 806.21
CORRUGADO
DA 30 DÓLAR (GENERAL 0.054 81.481% 587.46 642.27 0.058 648.25 0.059 654.51 0.059 632.31 0.058 621.59 0.057 627.09 0.059 633.63 0.060 638.92 0.061 674.44 0.064 669.37 0.062 673.09 0.063 688.55 0.064 673.80 0.062 640.97 0.058
PONDERADO) 0.000%

05 AGREGADO GRUESO 44.970% 464.71 491.74 493.90 498.16 502.14 504.45 500.81 505.38 508.89 504.96 509.33 513.40 513.88 517.48 517.57
CA 21 0.169 55.030% 473.39 487.39 0.176 487.39 0.176 496.50 0.179 500.99 0.181 505.45 0.182 524.09 0.185 518.68 0.185 522.37 0.186 530.26 0.187 531.35 0.188 539.21 0.190 546.69 0.191 546.69 0.192 551.55 0.193
CEMENTO PORTLAND TIPO I

MAQUINARIA Y EQUIPO
I 49 IMPORTADO 0.382 100.00% 363.39 400.19 0.421 403.22 0.424 407.98 0.429 396.02 0.416 392.63 0.413 393.72 0.414 401.03 0.422 402.27 0.423 422.26 0.444 422.12 0.444 426.54 0.448 436.49 0.459 427.32 0.449 410.52 0.432

I 13 ASFALTO 0.146 100.00% 2048.63 2484.47 0.177 2627.54 0.187 2560.04 0.182 2592.52 0.185 2834.30 0.202 3618.15 0.258 3781.57 0.270 3795.50 0.270 3800.56 0.271 3664.02 0.261 3602.14 0.257 3403.58 0.243 3292.82 0.235 3043.92 0.217

I 39 INDICE GRAL DE PREC. AL 0.130 100.00% 477.31 494.23 0.135 496.00 0.135 499.88 0.136 500.07 0.136 501.62 0.137 513.96 0.140 515.93 0.141 522.07 0.142 526.99 0.144 530.50 0.144 533.27 0.145 535.12 0.146 537.89 0.146 557.98 0.152
CONSUMIDOR

COEFICIENTE DE REAJUSTE (K) 1.000 1.090 1.104 1.108 1.098 1.113 1.178 1.200 1.204 1.232 1.221 1.235 1.235 1.216 1.184

21 de 51
CALCULO DEL REAJUSTE - CONTRATO PRINCIPAL
VALORIZACION DE OBRA N° 14
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-
OBRA :
TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR :

FORMULA GENERAL: R = V * (K - 1)
DONDE:
R = REAJUSTE DEL COMPONENTE EN S/. DE LA VALORIZACION MENSUAL
V = MONTO DEL COMPONENTE EN S/. DE LA VALORIZACION MENSUAL
K = COEFICIENTE DE REAJUSTE OBTENIDO POR LA APLICACIÓN DE LA FORMULA POLINOMICA PARA EL MES EN EL QUE DEBE SER PAGADA LA VALORIZACION

VALORIZACION PROGRAM. VALORIZACION EJECUTADA FACTOR PROV. REAJUSTE PROGRAM. REAJUSTE EJECUTADO REAJUSTE AUTORIZADO
VAL. Nº PERIODO
MES ACUMULADO MES ACUMULADO PERIODO K MES ACUM. MES ACUM. MES ACUM.

1 Oct-21 70,470.05 70,470.05 70,470.05 70,470.05 Oct-21 1.09 6,342.30 6,342.30 6,342.30 6,342.30 6,342.30 6,342.30
2 Nov-21 603,096.80 673,566.85 603,096.80 673,566.85 Nov-21 1.10 62,722.07 69,064.37 62,722.07 69,064.37 62,722.07 69,064.37
3 Dec-21 1,371,460.19 2,045,027.03 1,371,460.18 2,045,027.03 Dec-21 1.11 148,117.70 217,182.07 148,117.70 217,182.07 148,117.70 217,182.07
4 Jan-22 651,521.65 2,696,548.69 651,521.65 2,696,548.68 Jan-22 1.10 63,849.12 281,031.19 63,849.12 281,031.19 63,849.12 281,031.19
5 Feb-22 343,012.51 3,039,561.19 343,012.51 3,039,561.19 Feb-22 1.11 38,760.41 319,791.60 38,760.41 319,791.60 38,760.41 319,791.60
6 May-22 783,383.55 3,822,944.75 783,383.55 3,822,944.74 May-22 1.18 139,442.27 459,233.87 139,442.27 459,233.87 139,442.27 459,233.87
7 Jun-22 711,711.93 4,534,656.68 711,711.92 4,534,656.66 Jun-22 1.20 142,342.39 601,576.26 142,342.38 601,576.25 142,342.38 601,576.25
8 Jul-22 360,216.61 4,894,873.29 360,216.60 4,894,873.26 Jul-22 1.20 73,484.19 675,060.45 73,484.19 675,060.44 73,484.19 675,060.44
9 Aug-22 350,367.01 5,245,240.30 350,366.99 5,245,240.25 Aug-22 1.23 81,285.15 756,345.60 81,285.14 756,345.58 81,285.14 756,345.58
10 Sep-22 148,907.75 5,394,148.05 148,907.76 5,394,148.01 Sep-22 1.22 32,908.61 789,254.21 32,908.61 789,254.19 32,908.61 789,254.19
11 Oct-22 515,101.85 5,909,249.90 515,101.85 5,909,249.86 Oct-22 1.23 121,048.93 910,303.14 121,048.93 910,303.12 121,048.93 910,303.12
12 Nov-22 1,252,162.76 7,161,412.66 1,252,162.76 7,161,412.62 Nov-22 1.23 294,258.25 1,204,561.39 294,258.25 1,204,561.37 294,258.25 1,204,561.37
13 Dec-22 297,561.29 7,458,973.95 297,561.29 7,458,973.91 Dec-22 1.22 64,273.24 1,268,834.63 64,273.24 1,268,834.61 64,273.24 1,268,834.61
14 Aug-23 22,347.00 7,481,320.95 20,208.39 7,479,182.30 Aug-23 1.18 4,111.85 1,272,946.48 3,718.34 1,272,552.95 3,718.34 1,272,552.95

TOTAL PRINCIPAL 7,481,320.90 7,479,182.30 1,272,552.95


*NOTA: SE ANEXA LOS INDICES UNIFICADOS DE PRECIOS, EN EL PRESENTE INFORME

22 de 51
PORCENTAJE DE AVANCE: PROGRAMADO Vs EJECUTADO
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE


CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"
ENTIDAD: PROVIAS DESCENTRALIZADO PLAZO DE EJECUCION: 210 DIAS

CONSORCIO MDJH CONFORMADO POR IBEVIAL


EJECUTA: INICIO DE OBRA: 10/29/2021
S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS
SOCIEDAD COMERCIAL DE RESPONSABILIDAD
SUPERVISA: TERMINO DE OBRA: 9/2/2022
LIMITADA
MONTO CONTRACTUAL : S/. 14,369,895.73

GRAFICO DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO ACUMULADO
110%

100%
AVANCE MENSUAL ACUMULADO (%)

100.00%
90% PROYECTADO
93.70%

80% EJECUTADO

70%

60%

50% 54.74%

40%

30% 34.52% 29.55%


27.37%
23.07%
20% 23.43%
12.34% 18.35%
10% 0.43% 16.28% 18.35%
4.07% 12.34% 16.28%
0.00
0% 4.07%
0.00
29/10/2021 0.43%29/11/2021 29/12/2021 29/01/2022 01/03/2022 01/04/2022 01/05/2022 01/06/2022 01/07/2022 01/08/2022 01/09/2022

PLAZO DE EJECUCION (MESES)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS

MONTOS (Sin/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
29-Oct-21 0.00 0.00 0.00 0.00 29-Oct-21 0.00 0.00 0.00 0.00
31-Oct-21 83,154.66 83,154.66 0.43% 0.43% 31-Oct-21 83,154.66 83,154.66 0.43% 0.43%
30-Nov-21 711,654.22 794,808.88 3.64% 4.07% 30-Nov-21 711,654.22 794,808.88 3.64% 4.07%
31-Dec-21 1,618,323.02 2,413,131.90 8.28% 12.34% 31-Dec-21 1,618,323.01 2,413,131.89 8.28% 12.34%
31-Jan-22 768,795.55 3,181,927.45 3.93% 16.28% 31-Jan-22 768,795.55 3,181,927.44 3.93% 16.28%
28-Feb-22 404,754.76 3,586,682.21 2.07% 18.35% 28-Feb-22 404,754.76 3,586,682.20 2.07% 18.35%
31-May-22 994,698.03 4,581,380.25 5.09% 23.43% 31-May-22 924,392.59 4,511,074.79 4.73% 23.07%
30-Jun-22 2,167,351.28 6,748,731.53 11.09% 34.52% 30-Jun-22 839,820.07 5,350,894.86 4.30% 27.37%
31-Jul-22 3,952,107.31 10,700,838.84 20.22% 54.74% 31-Jul-22 425,055.59 5,775,950.45 2.17% 29.55%
31-Aug-22 7,617,172.29 18,318,011.13 38.96% 93.70% 31-Aug-22 413,433.05 6,189,383.50 2.11% 31.66%
2-Sep-22 1,231,659.23 19,549,670.36 6.30% 100.00% 2-Sep-22 175,711.16 6,365,094.66 0.90% 32.56%

TOTAL 19,549,670.30 100.00% TOTAL 6,365,094.66 32.56%


PORCENTAJE DE AVANCE: PROGRAMADO Vs EJECUTADO
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023

MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO,


DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

ENTIDAD: PROVIAS DESCENTRALIZADO PLAZO DE EJECUCION: 331 DIAS

CONSORCIO MDJH CONFORMADO POR IBEVIAL


EJECUTA: INICIO DE OBRA: 10/29/2021
S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS
SOCIEDAD COMERCIAL DE RESPONSABILIDAD
SUPERVISA:
LIMITADA
MONTO CONTRACTUAL : S/. 14,369,895.73

GRAFICO DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO ACUMULADO
110%

100%
100.00%
EJECUTADO
AVANCE MENSUAL ACUMULADO (%)

90%

PROGRAMADO
80%

70%
61.25%
61.25% 61.25% 61.43%
60% 48.52% 58.81% 61.42%
58.81%
44.29% 61.42%
43.07% 61.25%
50%
48.52% 61.25% 61.25%
37.24%40.19%
40% 31.39% 44.29%
24.96% 43.07%
22.14% 37.24% 40.19%
30%
31.39%
16.79%
20%
22.14%
0.58% 16.79% 24.96%
10% 5.53%
0.00
0% 5.53%
0.00 0.58%
2 2 1/ 2 2 1
0 4 1/ 2 2 1
1 6 2/ 2 2 1
2 8 2/ 2 2 1
0 9 2/ 2 2 1
2 1 1/ 2 2 1
0 2 1/ 2 2 2
1 4 2/ 2 2 2
2 6 2/ 2 2 2
1 0 2/ 2 2 2
2 2 3/ 2 2 2
0 3 3/ 2 2 2
1 5 4/ 2 2 2
2 7 4/ 2 2 2
0 9 4/ 2 2 2
2 1 5/ 2 2 2
0 2 5/ 2 2 2
1 4 6/ 2 2 2
2 6 6/ 2 2 2
0 8 6/ 2 2 2
2 0 7/ 2 2 2
0 1 7/ 2 2 2
1 3 8/ 2 2 2
2 5 8/ 2 2 2
0 6 8/ 2 2 2
1 8 9/ 2 2 2
3 0 9/ 2 2 2
1 2 9/ 2 2 2
2 4 0/ 2 2 2
0 5 0/ 2 2 2
1 7 1/ 2 2 2
2 9 1/ 2 2 2
1 1 1/ 2 2 2
2 3 2/ 2 2 2
0 4 2/ 2 2 2
1 6 1/ 2 2 2
2 8 1/ 2 2 3
0 9 1/ 2 2 3
2 1 2/ 2 2 3
0 5 2/ 2 2 3
1 7 3/ 2 2 3
2 9 3/ 2 2 3
1 0 3/ 2 2 3
2 2 4/ 2 2 3
0 4 4/ 2 2 3
1 6 5/ 2 2 3
2 8 5/ 2 2 3
0 9 5/ 2 2 3
2 1 6/ 2 2 3
0 3 6/ 2 2 3
1 5 7/ 2 2 3
2 7 7/ 2 2 3
0 8 7/ 2 2 3
2 0 8/ 2 2 3
0 1 8/ 2 2 3
1 3 9/ 2 2 3
9/ 3
23
/0 02
/1 0
/1 0
/1 0
/1 0
/1 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/1 0
/1 0
/1 0
/1 0
/1 0
/1 0
/1 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0
/0 0

20
1 0 0/ 2
/1
29

PLAZO DE EJECUCION (MESES)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS

MONTOS (Sin/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
29-Oct-21 0.00 0.00 0.00 0.00 29-Oct-21 0.00 0.00 0.00 0.00
31-Oct-21 83,154.66 83,154.66 0.58% 0.58% 31-Oct-21 83,154.66 83,154.66 0.58% 0.58%
30-Nov-21 711,654.22 794,808.88 4.95% 5.53% 30-Nov-21 711,654.22 794,808.88 4.95% 5.53%
31-Dec-21 1,618,323.02 2,413,131.90 11.26% 16.79% 31-Dec-21 1,618,323.01 2,413,131.89 11.26% 16.79%
31-Jan-22 768,795.55 3,181,927.45 5.35% 22.14% 31-Jan-22 768,795.55 3,181,927.44 5.35% 22.14%
9-Feb-22 404,754.76 3,586,682.21 2.82% 24.96% 9-Feb-22 404,754.76 3,586,682.20 2.82% 24.96%
31-May-22 924,392.59 4,511,074.80 6.43% 31.39% 31-May-22 924,392.59 4,511,074.79 6.43% 31.39%
30-Jun-22 839,820.08 5,350,894.88 5.84% 37.24% 30-Jun-22 839,820.07 5,350,894.86 5.84% 37.24%
31-Jul-22 425,055.60 5,775,950.48 2.96% 40.19% 31-Jul-22 425,055.59 5,775,950.45 2.96% 40.19%
31-Aug-22 413,433.07 6,189,383.55 2.88% 43.07% 31-Aug-22 413,433.05 6,189,383.50 2.88% 43.07%
30-Sep-22 175,711.15 6,365,094.70 1.22% 44.29% 30-Sep-22 175,711.16 6,365,094.66 1.22% 44.29%
30-Oct-22 607,820.18 6,972,914.88 4.23% 48.52% 30-Oct-22 607,820.18 6,972,914.84 4.23% 48.52%
30-Nov-22 1,477,552.06 8,450,466.94 10.28% 58.81% 30-Nov-22 1,477,552.06 8,450,466.90 10.28% 58.81%
31-Dec-22 351,122.32 8,801,589.26 2.44% 61.25% 31-Dec-22 351,122.32 8,801,589.22 2.44% 61.25%
31-Jan-23 0.00 8,801,589.26 0.00% 61.25% 31-Jan-23 0.00 8,801,589.22 0.00% 61.25%
28-Feb-23 0.00 8,801,589.26 0.00% 61.25% 28-Feb-23 0.00 8,801,589.22 0.00% 61.25%
31-Aug-23 26,369.46 8,827,958.72 0.18% 61.43% 31-Aug-23 23,845.90 8,825,435.12 0.17% 61.42%
7-Sep-23 5,541,937.05 14,369,895.77 38.57% 100.00% 7-Sep-23 0.00 8,825,435.12 0.00% 61.42%
TOTAL 14,369,895.72 100.00% TOTAL 8,825,435.12 61.42%
AMORTIZACION DEL ADELANTO DIRECTO
VALORIZACION DE OBRA N° 14

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR


´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV) S/. 14,369,895.72 (CON IGV)
MONTO ADELANTO S/. 1,217,787.77 (SIN IGV) S/. 1,436,989.57 (CON IGV)
FECHA DE ADELANTO 28/10/21

VALORIZACION AMORTIZACION SALDO POR


N° MES
MES ACUM. MES ACUM. AMORTIZAR
1.00 Oct-21 70,470.05 70,470.05 7,047.00 7,047.00 1,210,740.77
2.00 Nov-21 603,096.80 673,566.85 60,309.68 67,356.68 1,150,431.09
3.00 Dec-21 1,371,460.18 2,045,027.03 137,146.02 204,502.70 1,013,285.07
4.00 Jan-22 651,521.65 2,696,548.68 65,152.16 269,654.86 948,132.91
5.00 Feb-22 343,012.51 3,039,561.19 34,301.25 303,956.11 913,831.66
6.00 May-22 783,383.55 3,822,944.74 78,338.35 382,294.46 835,493.31
7.00 Jun-22 711,711.92 4,534,656.66 71,171.19 453,465.65 764,322.12
8.00 Jul-22 785,231.13 5,319,887.79 78,523.11 531,988.76 685,799.01
9.00 Aug-22 350,366.99 5,670,254.78 35,036.70 567,025.46 650,762.31
10.00 Sep-22 148,907.76 5,819,162.54 14,890.78 581,916.24 635,871.53
11.00 Oct-22 515,101.85 6,334,264.39 51,510.18 633,426.42 584,361.35
12.00 Nov-22 1,252,162.76 7,586,427.15 125,216.28 758,642.70 459,145.07
13.00 Dec-22 297,561.29 7,883,988.44 29,756.13 788,398.83 429,388.94
14.00 Aug-23 20,208.39 7,904,196.83 2,020.84 790,419.67 427,368.10
TOTAL 7,904,196.83 790,419.67

SALDO POR AMORTIZAR 427,368.10


AMORTIZACION ACUMULADA 790,419.67
AMORTIZACION ACUMULADA ANTERIOR 788,398.83
AMORTIZACION PRESENTE VALORIZACION 2,020.84
DEDUCCION DE REAJUSTE QUE NO CORRESPONDE POR EL ADELANTO DIRECTO
VALORIZACION DE OBRA N° 14
OBRA : MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABA
ENTIDAD : MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA : CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR :

FORMULA GENERAL:
D = AV/C * (K/Ka - 1)

DONDE: DATOS:
D = DEDUCCION DE REAJUSTE QUE NO CORRESPONDE POR EL ADELANTO DIRECTO
Ai = MONTOS PARCIALES DEL ADELANTO DIRECTO CONCEDIDO AL CONTRATISTA FECHA OTORGAM. = 28-Oct-21
V = MONTO DE LA VALORIZACIÓN MENSUAL. Ad (SIN IGV) = S/. 1,217,787.77
K = COEFICIENTE DE REAJUSTE OBTENIDO POR LA APLICACIÓN DE LA FORMULA POLINÓMICA. C (SIN IGV) = S/. 12,177,877.73
Ci = SALDO DEL PRESUPUESTO A LA FECHA DE ENTREGA DEL ADELANTO DIRECTO
Ka = COEFICIENTE DE REAJUSTE AL MES EN QUE SE CANCELO EL ADELANTO DIRECTO.

VALORIZACION EJECUTADA AMORTIZACION FACTOR DE REAJUSTE PROVIS. MES DEL ADELANTO (*) DEDUCCION
Nº PERIODO
MES ACUMULADO (Am=V*Ad/C) PERIODO K PERIODO Ka (D=Am*(K/Ka-1))

1 Oct-21 - 70,470.05 - - Sep-21 #N/A Sep-21 #N/A -


2 Nov-21 - - - Oct-21 #N/A Oct-21 #N/A -
3 Dec-21 - - - Nov-21 #N/A Oct-21 #N/A -
4 Jan-22 - - - Dec-21 #N/A Oct-21 #N/A -
5 Feb-22 - - - Jan-22 #N/A Oct-21 #N/A -
6 Mar-22 #N/A #N/A #N/A Feb-22 #N/A Oct-21 #N/A -
7 Apr-22 #N/A #N/A #N/A Mar-22 #N/A Oct-21 #N/A -
8 May-22 - #N/A - Apr-22 #N/A Oct-21 #N/A -
9 Jun-22 - #N/A - May-22 #N/A Oct-21 #N/A -
10 Jul-22 - #N/A - Jun-22 #N/A Oct-21 #N/A -

TOTAL #N/A #N/A -

(*) Para mayo solo se conoce los IU de abr-15, Los montos Reales a Deducir se veran al final con la Liquidacion de Obra.

28 de 51
AMORTIZACION DEL ADELANTO DE MATERIALES
VALORIZACION DE OBRA N° 14
OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPA
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)
MONTO ADELANTO S/. 1,072,996.93 (SIN IGV)
FECHA DE ADELANTO

VALORIZACION AMORTIZACION SALDO POR


N° MES
MES ACUM. MES ACUM. AMORTIZAR
1.00 Oct-21 - - - - 1,072,996.93
2.00 Nov-21 - - - - 1,072,996.93
3.00 Dec-21 - - - - 1,072,996.93
4.00 Jan-22 - - - - 1,072,996.93
5.00 Feb-22 - - - - 1,072,996.93
6.00 Mar-22 #N/A #N/A #N/A #N/A #N/A
TOTAL #N/A #N/A

SALDO POR AMORTIZAR #N/A


AMORTIZACION ACUMULADA #N/A
AMORTIZACION ACUMULADA ANTERIOR #N/A
AMORTIZACION PRESENTE VALORIZACION #N/A
CALENDARIO DE AVANCE DE OBRA VALORIZADO

ACTUALIZADO A LA FECHA DE INICIO

OBRA: MEJORAMIENTO DEL CAMINO VECINAL LA PALMA- CONCHAN-LA LEGUA-TACABAMBA-CHUGUR-ANGUIA -RODEOPAMPA-GUINEAMAYO, DISTRITOS CONCHAN-TACABAMBA-ANGUIA, CHOTA- CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA- ANGUIA- CHUGUR

Entidad: MUNICIPALIDAD DISTRITAL DE ANGUIA

Lugar: CAJAMARCA - CHOTA - ANGUIA Costo al 5/17/2021

Contratista: CONSORCIO MDJH


PLAZO DE EJECUCION 210 DC
OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO
Item Descripción Und. Metrado Precio S/. Parcial S/. 29 AL 30 DE OCT 30 DIAS 31 DIAS 31 DIAS 28 DIAS 31 DIAS 30 DIAS 27 DIAS TOTAL
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %

1.00 OBRAS PRELIMINARES 183,415.41

1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 132,915.60 132,915.60 66,457.80 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 66,457.80 50.00% 132,915.60

1.02 TRAZO, REPLANTEO Y CONTROL TOPOGRAFICO KM 22.60 1,555.59 35,156.33 1,004.47 2.86% 4,017.87 11.43% 5,022.33 14.29% 5,022.33 14.29% 5,022.33 14.29% 5,022.33 14.29% 5,022.33 14.29% 5,022.33 14.29% 35,156.33

1.03 LIMPIEZA GENERAL - ROCE Y DESBROCE HA 1.35 3,114.25 4,204.24 280.28 6.67% 1,121.13 26.67% 1,401.41 33.33% 1,401.41 33.33% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,204.24

1.04 CARTEL DE OBRA DE 3.60 X 2.40 M und 2.00 832.18 1,664.36 1,664.36 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,664.36

1.05 CAMPAMENTO PROVISIONAL DE OBRA m2 92.42 77.99 7,207.84 1,441.57 20.00% 3,603.92 50.00% 2,162.35 30.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,207.84

1.06 DEMOLICION m3 12.00 188.92 2,267.04 0.00 0.00% 2,267.04 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,267.04

2.00 MOVIMIENTO DE TIERRAS 1,625,591.02

2.01 CORTE EN MATERIAL SUELTO m3 60,612.91 3.33 201,840.99 0.00 0.00% 46,423.43 23.00% 66,607.53 33.00% 88,810.04 44.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 201,840.99

2.02 CORTE EN ROCA SUELTA m3 55,563.73 18.56 1,031,262.83 0.00 0.00% 237,190.45 23.00% 340,316.73 33.00% 453,755.65 44.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,031,262.83

2.03 CORTE EN ROCA FIJA m3 10,474.84 29.20 305,865.33 0.00 0.00% 36,703.84 12.00% 122,346.13 40.00% 146,815.36 48.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 305,865.33

2.04 CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO m3 7,480.30 11.58 86,621.87 0.00 0.00% 0.00 0.00% 34,648.75 40.00% 51,973.12 60.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 86,621.87

3.00 PAVIMENTOS 6,497,424.58

3.01 SUB-BASE GRANULAR m3 23,353.75 37.52 876,232.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 289,156.79 33.00% 289,156.79 33.00% 297,919.12 34.00% 0.00 0.00% 876,232.70

3.02 BASE GRANULAR m3 21,789.79 89.02 1,939,727.11 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 640,109.95 33.00% 640,109.95 33.00% 659,507.22 34.00% 0.00 0.00% 1,939,727.11

3.03 TRATAMIENTO SUPERFICIAL 3,681,464.77

03.03.01 IMPRIMACION BITUMINOSA CON EMULSION m2 140,192.87 6.31 884,617.01 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 176,923.40 20.00% 309,615.95 35.00% 398,077.65 45.00% 884,617.01

03.03.02 TRATAMIENTO SUPERFICIAL BICAPA - 1RA CAPA m2 140,192.87 10.26 1,438,378.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 215,756.83 15.00% 431,513.66 30.00% 791,108.37 55.00% 1,438,378.85

03.03.03 TRATAMIENTO SUPERFICIAL BICAPA - 2DA CAPA m2 140,192.87 9.69 1,358,468.91 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 135,846.89 10.00% 407,540.67 30.00% 815,081.35 60.00% 1,358,468.91

4.00 TRANSPORTE 1,697,856.42

4.01 TRANSPORTES DE MATERILA PARA AFIRMADO HASTA 1 KM M3K 42,592.78 7.03 299,427.24 0.00 0.00% 0.00 0.00% 119,770.90 40.00% 119,770.90 40.00% 59,885.45 20.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 299,427.24

4.02 TRANSPORTE DE MATERIAL PARA AFIRMADO DESPUES DE 1 KM M3K 110,070.77 1.87 205,832.34 0.00 0.00% 0.00 0.00% 82,332.94 40.00% 82,332.94 40.00% 41,166.47 20.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 205,832.34
CALENDARIO DE AVANCE DE OBRA VALORIZADO

ACTUALIZADO A LA FECHA DE INICIO

OBRA: MEJORAMIENTO DEL CAMINO VECINAL LA PALMA- CONCHAN-LA LEGUA-TACABAMBA-CHUGUR-ANGUIA -RODEOPAMPA-GUINEAMAYO, DISTRITOS CONCHAN-TACABAMBA-ANGUIA, CHOTA- CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA- ANGUIA- CHUGUR

Entidad: MUNICIPALIDAD DISTRITAL DE ANGUIA

Lugar: CAJAMARCA - CHOTA - ANGUIA Costo al 5/17/2021

Contratista: CONSORCIO MDJH


PLAZO DE EJECUCION 210 DC
OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO
Item Descripción Und. Metrado Precio S/. Parcial S/. 29 AL 30 DE OCT 30 DIAS 31 DIAS 31 DIAS 28 DIAS 31 DIAS 30 DIAS 27 DIAS TOTAL
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %

4.03 TRANSPORTES DE MATERIAL EXCEDENTE HASTA <= 1 KM M3K 133,826.08 6.31 844,442.56 0.00 0.00% 84,444.26 10.00% 278,666.04 33.00% 337,777.02 40.00% 143,555.24 17.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 844,442.56

4.04 TRANSPORTES DE MATERIAL EXCEDENTE > 1 KM M3K 246,917.93 1.41 348,154.28 0.00 0.00% 34,815.43 10.00% 114,890.91 33.00% 139,261.71 40.00% 59,186.23 17.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 348,154.28

5.00 OBRAS DE ARTE Y DRENAJE 4,133,312.55

5.01 CUNETAS LATERALES 3,820,578.48

05.01.01 CONSTRUCCION DE CUNETAS REVESTIDAS m 36,355.30 105.09 3,820,578.48 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 687,704.13 18.00% 1,146,173.54 30.00% 1,146,173.54 30.00% 840,527.27 22.00% 3,820,578.48

5.02 ALCANTARILLAS 144,927.25

05.02.01 LIMPIEZA DE TERRENO MANUAL m2 269.36 2.04 549.49 0.00 0.00% 0.00 0.00% 549.49 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 549.49

05.02.02 TRAZO Y REPLANTEO m2 323.23 3.76 1,215.34 0.00 0.00% 0.00 0.00% 1,215.34 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,215.34

05.02.03 EXCAVACION PARA ESTRUCTURAS C/MAQUINA m3 336.42 15.99 5,379.36 0.00 0.00% 0.00 0.00% 5,379.36 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,379.36

05.02.04 RELLENO COMPACTADO PARA ESTRUCTURAS m3 223.46 32.73 7,313.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,313.85 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,313.85

05.02.05 SOLADO 4" m3 8.82 434.25 3,830.09 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,830.09 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,830.09

05.02.06 CONCRETO F'C=210 KG/CM2 m3 75.24 580.17 43,651.99 0.00 0.00% 0.00 0.00% 0.00 0.00% 43,651.99 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 43,651.99

05.02.07 ENCOFRADO Y DESENCOFRADO m2 431.76 54.81 23,664.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 23,664.77 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 23,664.77

05.02.08 EMBOQUILLADO DE PIEDRA m3 23.47 411.77 9,664.24 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,664.24 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,664.24

05.02.09 ALCANTARILLA TMC Ø=60" m 50.10 991.18 49,658.12 0.00 0.00% 0.00 0.00% 0.00 0.00% 49,658.12 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 49,658.12

5.03 BADENES' 128,310.76

05.03.01 LIMPIEZA DE TERRENO MANUAL b 271.25 2.04 553.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 553.35 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 553.35

05.03.02 TRAZO Y REPLANTEO m2 271.25 3.76 1,019.90 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,019.90 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,019.90

05.03.03 EXCAVACION MANUAL DE ESTRUCTURA m3 166.00 46.96 7,795.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,795.36 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,795.36

05.03.04 CONCRETO F'C=210 KG/CM2 m3 95.78 580.17 55,568.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 55,568.68 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 55,568.68

05.03.05 ENCOFRADO Y DESENCOFRADO m2 107.13 54.81 5,871.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,871.80 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,871.80

05.03.06 EMBOQUILLADO DE PIEDRA m3 131.54 411.77 54,164.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 54,164.23 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 54,164.23
CALENDARIO DE AVANCE DE OBRA VALORIZADO

ACTUALIZADO A LA FECHA DE INICIO

OBRA: MEJORAMIENTO DEL CAMINO VECINAL LA PALMA- CONCHAN-LA LEGUA-TACABAMBA-CHUGUR-ANGUIA -RODEOPAMPA-GUINEAMAYO, DISTRITOS CONCHAN-TACABAMBA-ANGUIA, CHOTA- CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA- ANGUIA- CHUGUR

Entidad: MUNICIPALIDAD DISTRITAL DE ANGUIA

Lugar: CAJAMARCA - CHOTA - ANGUIA Costo al 5/17/2021

Contratista: CONSORCIO MDJH


PLAZO DE EJECUCION 210 DC
OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO
Item Descripción Und. Metrado Precio S/. Parcial S/. 29 AL 30 DE OCT 30 DIAS 31 DIAS 31 DIAS 28 DIAS 31 DIAS 30 DIAS 27 DIAS TOTAL
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %

05.03.07 JUNTA TRANSVERSAL DE DILATACION m 82.61 40.40 3,337.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,337.44 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,337.44

5.04 MUROS DE CONTENCION 39,496.06

05.04.01 MUROS DE CONCRETO SIMPLE 39,496.06

05.04.01.01 TRABAJOS PRELIMINARES 342.37

05.04.01.01.01 TRAZO Y REPLANTEO m2 50.50 3.76 189.88 0.00 0.00% 0.00 0.00% 189.88 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 189.88

05.04.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 74.75 2.04 152.49 0.00 0.00% 0.00 0.00% 152.49 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 152.49

05.04.01.02 MOVIMIENTO DE TIERRAS 10,065.50

05.04.01.02.01 EXCAVACION MANUAL m3 163.50 55.21 9,026.84 0.00 0.00% 0.00 0.00% 9,026.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,026.84

05.04.01.02.02 NIVELACION Y APISONADO m2 50.50 3.23 163.12 0.00 0.00% 0.00 0.00% 163.12 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 163.12

05.04.01.02.03 RELLENO CON MATERIAL PROPIO m3 81.75 10.71 875.54 0.00 0.00% 0.00 0.00% 0.00 0.00% 875.54 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 875.54

05.04.01.03 CONCRETO SIMPLE 27,963.48

CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. EN MURO DE


05.04.01.03.01 m3 62.14 282.84 17,575.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,575.68 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,575.68
CONTECION

05.04.01.03.02 ENCOFRADO Y DESENCOFRADO m2 174.00 54.81 9,536.94 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,536.94 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,536.94

05.04.01.03.03 CURADO DE CONCRETO m2 174.00 4.89 850.86 0.00 0.00% 0.00 0.00% 0.00 0.00% 850.86 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 850.86

05.04.01.04 OTROS 1,124.71

05.04.01.04.01 TUBERIA PARA DRENAJE m 55.35 20.32 1,124.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,124.71 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,124.71

6.00 SEÑALIZACIÓN 204,743.88

6.01 SEÑALES PREVENTIVAS und 159.00 615.58 97,877.22 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 97,877.22 100.00% 97,877.22

6.02 POSTES DE KILOMETRAJE und 23.00 143.53 3,301.19 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,301.19 100.00% 3,301.19

6.03 SEÑALES INFORMATIVAS und 9.00 542.87 4,885.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,885.83 100.00% 4,885.83

6.04 ESTRUCTURA DE SOPORTE DE SEÑALES INFORMATIVAS und 9.00 2,404.92 21,644.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21,644.28 100.00% 21,644.28

6.05 MARCAS EN EL TRATAMIENTO SUPERFICIAL m2 7,253.80 10.62 77,035.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 77,035.36 100.00% 77,035.36
CALENDARIO DE AVANCE DE OBRA VALORIZADO

ACTUALIZADO A LA FECHA DE INICIO

OBRA: MEJORAMIENTO DEL CAMINO VECINAL LA PALMA- CONCHAN-LA LEGUA-TACABAMBA-CHUGUR-ANGUIA -RODEOPAMPA-GUINEAMAYO, DISTRITOS CONCHAN-TACABAMBA-ANGUIA, CHOTA- CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA- ANGUIA- CHUGUR

Entidad: MUNICIPALIDAD DISTRITAL DE ANGUIA

Lugar: CAJAMARCA - CHOTA - ANGUIA Costo al 5/17/2021

Contratista: CONSORCIO MDJH


PLAZO DE EJECUCION 210 DC
OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO
Item Descripción Und. Metrado Precio S/. Parcial S/. 29 AL 30 DE OCT 30 DIAS 31 DIAS 31 DIAS 28 DIAS 31 DIAS 30 DIAS 27 DIAS TOTAL
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %

7.00 COSTOS AMBIENTALES 13,553.86

7.01 ACONDICIONAMIENTO DE BOTADEROS m2 4,522.50 2.38 10,763.55 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,763.55 100.00% 10,763.55

7.02 ACONDICIONAMIENTO DE CANTERAS m2 896.40 0.99 887.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 887.44 100.00% 887.44

7.03 ACONDICIONAMIENTO DE AREAS OCUPADAS POR CAMPAMENTO m2 92.42 5.21 481.51 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 481.51 100.00% 481.51

ACONDICIONAMIENTO DE AREA OCUPADAS POR PATIO DE


7.04 m2 436.00 3.26 1,421.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,421.36 100.00% 1,421.36
MAQUINAS

8.00 PLAN PARA VIGILANCIA, PREVENCION Y CONTROL DE COVID-19 63,851.36

8.01 PRUEBAS RAPIDAS PARA DETECTAR COVID-19 und 552.00 48.00 26,496.00 757.03 2.86% 3,028.11 11.43% 3,785.14 14.29% 3,785.14 14.29% 3,785.14 14.29% 3,785.14 14.29% 3,785.14 14.29% 3,785.14 14.29% 26,496.00

EQUIPAMIENTO, IMPLEMENTACION E INSUMOS PARA LA


8.02 glb 1.00 26,755.36 26,755.36 764.44 2.86% 3,057.76 11.43% 3,822.19 14.29% 3,822.19 14.29% 3,822.19 14.29% 3,822.19 14.29% 3,822.19 14.29% 3,822.19 14.29% 26,755.36
PRECENCION DEL COVID-19

8.03 SEÑALIZACION Y CAPACITACION glb 1.00 10,600.00 10,600.00 302.86 2.86% 1,211.43 11.43% 1,514.29 14.29% 1,514.29 14.29% 1,514.29 14.29% 1,514.29 14.29% 1,514.29 14.29% 1,514.29 14.29% 10,600.00

COSTO DIRECTO 14,419,749.08 72,672.80 457,884.66 1,193,964.17 1,613,157.50 2,053,850.35 2,618,111.36 3,266,414.12 3,143,694.13 14,419,749.08
GASTOS GENERALES 7.8946289% 1,138,385.68 5,737.25 36,148.29 94,259.05 127,352.80 162,143.86 206,690.17 257,871.27 248,182.99 1,138,385.68
GASTOS FIJOS 1.8386210% 265,124.53 1,336.18 8,418.76 21,952.48 29,659.85 37,762.52 48,137.14 60,056.97 57,800.62 265,124.53
GASTOS VARIABLES 6.0560080% 873,261.15 4,401.07 27,729.53 72,306.57 97,692.95 124,381.34 158,553.03 197,814.30 190,382.37 873,261.15
UTILIDAD 7.000000% 1,009,382.44 5,087.10 32,051.93 83,577.49 112,921.02 143,769.52 183,267.80 228,648.99 220,058.60 1,009,382.44
=========== ========= ========= ========= ========= ========= ========= ========= ========= =========
SUBTOTAL 16,567,517.20 83,497.15 526,084.88 1,371,800.71 1,853,431.32 2,359,763.73 3,008,069.33 3,752,934.38 3,611,935.72 16,567,517.20
IGV 18.00% 2,982,153.10 15,029.49 94,695.28 246,924.13 333,617.64 424,757.47 541,452.48 675,528.19 650,148.43 2,982,153.10
=========== =========== =========== ========= ========= ========= ========= ========= ========= =========
TOTAL 19,549,670.30 98,526.64 620,780.16 1,618,724.84 2,187,048.96 2,784,521.20 3,549,521.81 4,428,462.57 4,262,084.15 19,549,670.30

PORCENTAJE MENSUAL DE AVANCE DE OBRA 0.50% 3.18% 8.28% 11.19% 14.24% 18.16% 22.65% 21.80%
PORCENTAJE ACUMULADO DE AVANCE DE OBRA 0.50% 3.68% 11.96% 23.15% 37.39% 55.55% 78.20% 100.00%
CALENDARIO DE AVANCE DE OBRA VALORIZADO - CAOA N°03
Obra: : MEJORAMIENTO DEL CAMINO VECINAL ENTRE LOS TRAMOS MAL PASO - HUAYRUL - JANQUE -CRUZ LOMA - LANCHIPAMPA
Entidad: : PROVIAS DESCENTRALIZADO
Lugar: : INCAHUASI - FERREÑAFE - LAMBAYEQUE Fecha: : MAY 2018
Contratista: : CONSORCIO VIAL NORTE V
PLAZO DE EJECUCION 220 DC
MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO
Parcial S/.
Item Descripción Und. Metrado (contractual) Precio S/. (Del 04/05/2018 al 31/05/2018) (Del 01/06/2018 al 30/06/2018) (Del 01/07/2018 al 31/07/2018) (Del 01/08/2018 al 31/08/2018) (Del 01/09/2018 al 30/09/2018) (Del 01/10/2018 al 30/10/2018) (Del 01/11/2018 al 30/11/2018) (Del 01/12/2018 al 31/12/2018) (Del 01/01/2019 al 31/01/2019) (Del 01/02/2019 al 04/02/2019) TOTAL
(contractual)
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %
1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 121,265.27 121,265.27 30,316.32 25.00% 24,253.05 20.00% 0.00 0.00% 6,063.26 5.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 60,632.64 50.00% 121,265.27
1.02 TOPOGRAFIA Y GEOREFERENCIACION KM 20.87 451.65 9,425.94 1,696.67 18.00% 942.59 10.00% 942.59 10.00% 3,864.64 41.00% 1,885.19 20.00% 94.26 1.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,425.94
1.03 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL GBL 1.00 11,069.95 11,069.95 285.90 2.58% 712.56 6.44% 1,497.93 13.53% 997.26 9.01% 1,316.67 11.89% 6,259.63 56.55% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,069.95
1.04 CAMPAMENTO GLB 1.00 12,311.20 12,311.20 12,311.20 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12,311.20
2 MOVIMIENTO DE TIERRAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
2.01 DESBROCE Y LIMPIEZA DE TERRENO EN ZONAS NO BOSCOSAS HA 12.52 2,996.05 37,510.55 34,509.71 92.00% 3,000.84 8.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,510.55
2.02 EXCAVACION PARA EXPLANACIONES - MATERIAL SUELTO M3 35,764.60 3.31 118,380.83 29,595.21 25.00% 11,838.08 10.00% 11,838.08 10.00% 11,838.08 10.00% 11,838.08 10.00% 11,838.08 10.00% 29,595.21 25.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 118,380.83
2.03 EXCAVACION PARA EXPLANACIONES - ROCA SUELTA M3 2,501.33 12.65 31,641.82 7,910.46 25.00% 15,820.91 50.00% 7,910.46 25.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 31,641.82
2.04 EXCAVACION PARA EXPLANACIONES - ROCA FIJA M3 9,497.30 29.60 281,120.08 0.00 0.00% 56,224.02 20.00% 224,896.06 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 281,120.08
2.05 TERRAPLENES CON MATERIAL PROPIO M3 2,237.15 4.92 11,006.78 0.00 0.00% 3,302.03 30.00% 7,704.75 70.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,006.78
2.06 PERFILADO Y COMPACTADO EN ZONA DE CORTE M2 81,634.33 1.09 88,981.42 0.00 0.00% 35,592.57 40.00% 53,388.85 60.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 88,981.42
2.07 CONFORMACION Y ACOMODO DEL DME M3 20,388.37 1.60 32,621.39 0.00 0.00% 0.00 0.00% 3,262.14 10.00% 9,786.42 30.00% 3,262.14 10.00% 3,262.14 10.00% 3,262.14 10.00% 6,524.28 20.00% 3,262.14 10.00% 0.00 0.00% 32,621.39
2.08 MEJORAMIENTO A NIVEL DE SUBRASANTE M3 468.00 18.60 8,704.80 0.00 0.00% 4,352.40 50.00% 2,611.44 30.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,740.96 20.00% 0.00 0.00% 8,704.80
3 AFIRMADO Y SUB BASE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
3.01 AFIRMADO GRANULAR M3 20,805.40 21.97 457,094.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 45,709.46 10.00% 45,709.46 10.00% 45,709.46 10.00% 45,709.46 10.00% 274,256.78 60.00% 0.00 0.00% 457,094.64
3.02 IMPRIMACION REFORZADA M2 90,552.78 5.63 509,812.15 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 254,906.08 50.00% 254,906.08 50.00% 509,812.15
4 DRENAJE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.01 ALCANTARILLAS DE ALIVIO TMC 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.01.01 TRAZO Y REPLANTEO M2 409.51 1.46 597.88 0.00 0.00% 0.00 0.00% 597.88 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 597.88
4.01.02 EXCAVACION PARA ESTRUCTURAS M3 691.58 40.44 27,967.50 0.00 0.00% 0.00 0.00% 27,967.50 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 27,967.50
4.01.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 153.80 32.77 5,040.03 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,040.03 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,040.03
4.01.04 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 41.88 55.35 2,318.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,318.06 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,318.06
4.01.05 ENCOFRADO Y DESENCOFRADO M2 1,244.51 56.50 70,314.82 0.00 0.00% 0.00 0.00% 70,314.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 70,314.82
4.01.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 231.48 458.36 106,101.17 0.00 0.00% 0.00 0.00% 53,050.59 50.00% 53,050.59 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 106,101.17
4.01.07 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 35.99 481.56 17,331.34 0.00 0.00% 0.00 0.00% 8,665.67 50.00% 8,665.67 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,331.34
4.01.08 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 4.42 389.85 1,723.14 0.00 0.00% 0.00 0.00% 861.57 50.00% 861.57 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,723.14
4.01.09 ACERO DE REFUERZO FY=4200 KG/CM2 KG 1,416.10 4.54 6,429.09 0.00 0.00% 0.00 0.00% 6,429.09 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,429.09
4.01.10 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 M M 157.14 405.21 63,674.70 0.00 0.00% 0.00 0.00% 31,837.35 50.00% 31,837.35 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 63,674.70
4.01.11 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 85.24 208.63 17,783.62 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,783.62 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,783.62
4.01.12 ELIMINACION EXCEDENTE DE EXCAVACION M3 537.78 6.98 3,753.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,753.70 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,753.70
4.02 ALCANTARILLA DE PASE TMC 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.02.01 TRAZO Y REPLANTEO M2 24.75 1.46 36.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 36.14 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 36.14
4.02.02 EXCAVACION PARA ESTRUCTURAS M3 39.22 40.44 1,586.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,586.06 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,586.06
4.02.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 7.55 32.77 247.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 247.41 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 247.41
4.02.04 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 3.03 55.35 167.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 167.71 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 167.71
4.02.05 ENCOFRADO Y DESENCOFRADO M2 80.02 56.50 4,521.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 904.23 20.00% 3,616.90 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,521.13
4.02.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 11.47 458.36 5,257.39 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,051.48 20.00% 4,205.91 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,257.39
4.02.07 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 4.23 481.56 2,037.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 407.40 20.00% 1,629.60 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,037.00
4.02.08 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 0.52 389.85 202.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 40.54 20.00% 162.18 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 202.72
4.02.09 ACERO DE REFUERZO FY=4200 KG/CM2 KG 166.60 4.54 756.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 151.27 20.00% 605.09 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 756.36
4.02.10 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 M M 9.72 405.21 3,938.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 787.73 20.00% 3,150.91 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,938.64
4.02.11 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 6.52 208.63 1,360.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 272.05 20.00% 1,088.22 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,360.27
4.02.12 ELIMINACION EXCEDENTE DE EXCAVACION M3 31.68 6.98 221.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 44.23 20.00% 176.90 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 221.13
4.03 CANALETAS DE PASE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.03.01 TRAZO Y REPLANTEO M2 794.40 1.46 1,159.82 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,159.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,159.82
4.03.02 EXCAVACION PARA ESTRUCTURAS M3 936.26 40.44 37,862.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,862.35 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,862.35
4.03.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 506.40 32.77 16,594.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,594.73 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,594.73
4.03.04 ENCOFRADO Y DESENCOFRADO M2 2,261.63 56.50 127,782.10 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 127,782.10 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 127,782.10
4.03.05 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 28.31 389.85 11,036.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,311.00 30.00% 7,725.65 70.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,036.65
4.03.06 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 401.56 481.56 193,375.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 58,012.57 30.00% 135,362.66 70.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 193,375.23
4.03.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 22,243.12 4.54 100,983.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 70,688.63 70.00% 30,295.13 30.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 100,983.76
4.03.08 ELIMINACION EXCEDENTE DE EXCAVACION M3 429.86 6.98 3,000.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,000.42 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,000.42
4.04 BADEN 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.04.01 TRAZO Y REPLANTEO M2 1,830.33 1.46 2,672.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,672.28 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,672.28
4.04.02 EXCAVACION PARA ESTRUCTURAS M3 871.18 40.44 35,230.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 35,230.52 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 35,230.52
4.04.03 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 251.63 55.35 13,927.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13,927.72 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13,927.72
4.04.04 ENCOFRADO Y DESENCOFRADO M2 386.79 56.50 21,853.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21,853.64 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21,853.64
4.04.05 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 191.84 208.63 40,023.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 40,023.58 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 40,023.58
4.04.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 427.72 458.36 196,049.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 196,049.74 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 196,049.74
4.04.07 CONCRETO CLASE E1 (F´c= 175 kg/cm2 + 30% P.M.) M3 182.09 343.40 62,529.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 62,529.71 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 62,529.71
4.04.08 JUNTAS ASFALTICAS E=1" EN BADENES M 416.20 19.25 8,011.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,011.85 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,011.85
4.05 CUNETAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.05.01 CUNETA TRIANGULAR DE TIERRA M 12,327.50 1.51 18,614.53 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,307.27 50.00% 9,307.27 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 18,614.53
4.05.03 CUNETA TRIANGULAR REVESTIDO DE MAMPOSTERIA M 7,760.60 37.39 290,168.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 58,033.77 20.00% 232,135.06 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 290,168.83
4.05.04 CUNETA RECTANGULAR REVESTIDO DE CONCRETO C/TAPA M 927.00 154.92 143,610.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,180.54 5.00% 114,888.67 80.00% 21,541.63 15.00% 0.00 0.00% 0.00 0.00% 143,610.84
4.06 SUBDREN 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.06.01 SUBDRENES M 785.00 144.57 113,487.45 0.00 0.00% 0.00 0.00% 0.00 0.00% 22,697.49 20.00% 22,697.49 20.00% 22,697.49 20.00% 11,348.75 10.00% 22,697.49 20.00% 11,348.75 10.00% 0.00 0.00% 113,487.45
5 TRANSPORTE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
5.01 TRANSPORTE DE MATERIALES GRANULARES PARA DISTANCIAS ENTRE 120 M Y 1,000 M M3-KM 21,479.10 7.08 152,072.03 0.00 0.00% 15,207.20 10.00% 15,207.20 10.00% 15,207.20 10.00% 15,207.20 10.00% 15,207.20 10.00% 15,207.20 10.00% 38,018.01 25.00% 22,810.80 15.00% 0.00 0.00% 152,072.03
5.02 TRANSPORTE DE MATERIALES GRANULARES PARA DISTANCIAS MAYORES DE 1,000 M M3-KM 289,361.77 1.94 561,361.83 0.00 0.00% 56,136.18 10.00% 56,136.18 10.00% 56,136.18 10.00% 56,136.18 10.00% 56,136.18 10.00% 56,136.18 10.00% 140,340.46 25.00% 84,204.27 15.00% 0.00 0.00% 561,361.83
5.03 TRANSPORTE DE MATERIALES EXCEDENTES PARA DISTANCIAS ENTRE 120 M Y 1,000 M M3-KM 11,501.74 7.30 83,962.70 0.00 0.00% 8,396.27 10.00% 8,396.27 10.00% 8,396.27 10.00% 8,396.27 10.00% 8,396.27 10.00% 16,792.54 20.00% 16,792.54 20.00% 8,396.27 10.00% 0.00 0.00% 83,962.70
5.04 TRANSPORTE DE MATERIALES EXCEDENTES PARA DISTANCIAS MAYORES DE 1,000 M M3-KM 6,652.68 2.01 13,371.89 0.00 0.00% 1,337.19 10.00% 1,337.19 10.00% 1,337.19 10.00% 1,337.19 10.00% 1,337.19 10.00% 2,674.38 20.00% 2,674.38 20.00% 1,337.19 10.00% 0.00 0.00% 13,371.89
6 SEÑALIZACION Y SEGURIDAD VIAL 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
6.01 SEÑALES PREVENTIVAS UND 158.00 374.82 59,221.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 59,221.56 100.00% 59,221.56
6.02 SEÑALES REGLAMENTARIAS UND 32.00 468.58 14,994.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,994.56 100.00% 14,994.56
6.03 SEÑALES INFORMATIVAS UND 8.00 1,846.01 14,768.08 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,768.08 100.00% 14,768.08
6.04 POSTES DE KILOMETRAJE UND 21.00 124.21 2,608.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,608.41 100.00% 2,608.41
7 PROTECION AMBIENTAL 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
7.01 MONITOREO DE LA CALIDAD DE AIRE PTO 2.00 504.72 1,009.44 0.00 0.00% 336.14 33.30% 0.00 0.00% 336.14 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 337.15 33.40% 0.00 0.00% 0.00 0.00% 1,009.44
7.02 MONITOREO DE CALIDAD DEL AGUA PTO 1.00 325.26 325.26 0.00 0.00% 108.31 33.30% 0.00 0.00% 108.31 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 108.64 33.40% 0.00 0.00% 0.00 0.00% 325.26
7.03 MONITOREO DE NIVELES DE RUIDO PTO 1.00 168.24 168.24 0.00 0.00% 56.02 33.30% 0.00 0.00% 56.02 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 56.19 33.40% 0.00 0.00% 0.00 0.00% 168.24
7.04 MONITOREO DE CALIDAD DE SUELOS PTO 9.00 800.00 7,200.00 0.00 0.00% 2,397.60 33.30% 0.00 0.00% 2,397.60 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,404.80 33.40% 0.00 0.00% 0.00 0.00% 7,200.00
7.05 CAPA SUPERFICIAL DEL SUELO HA 5.30 12,334.00 65,370.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13,074.04 20.00% 52,296.16 80.00% 0.00 0.00% 0.00 0.00% 65,370.20
7.06 RECUPERACION AMBIENTAL DE AREAS AFECTADAS HA 5.97 3,338.48 19,930.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,986.15 20.00% 15,944.58 80.00% 0.00 0.00% 0.00 0.00% 19,930.73
7.07 SEÑALIZACION AMBIENTAL PERMANENTE UND 2.00 3,535.87 7,071.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,414.35 20.00% 5,657.39 80.00% 0.00 0.00% 0.00 0.00% 7,071.74
COSTO DIRECTO 4,515,726.25 116,625.45 240,013.99 594,853.61 266,227.73 492,546.50 438,438.08 926,523.17 371,103.16 662,263.24 407,131.32 4,515,726.25
GASTOS GENERALES FIJOS 0.9116464932% 41,167.46 1,063.21 2,188.08 5,422.96 2,427.06 4,490.28 3,997.01 8,446.62 3,383.15 6,037.50 3,711.60 41,167.46
GASTOS GENERALES VARIABLES 14.6517517531% 661,633.00 17,087.67 35,166.25 87,156.47 39,007.03 72,166.69 64,238.86 135,751.87 54,373.11 97,033.17 59,651.87 661,633.00
UTILIDAD 4.5441474669% 205,201.26 5,299.63 10,906.59 27,031.03 12,097.78 22,382.04 19,923.27 42,102.58 16,863.47 30,094.22 18,500.65 205,201.26
=========== =========== ========= ========= ========= ========= ========= ========= ========= ========= ========= =========
SUBTOTAL 5,423,727.97 140,075.96 288,274.91 714,464.07 319,759.60 591,585.51 526,597.22 1,112,824.24 445,722.89 795,428.13 488,995.44 5,423,727.97
IGV 18.00% 976,271.03 25,213.67 51,889.48 128,603.53 57,556.73 106,485.39 94,787.50 200,308.36 80,230.12 143,177.06 88,019.18 976,271.02
=========== =========== ========= ========= ========= ========= ========= ========= ========= ========= ========= =========
TOTAL 6,399,999.00 165,289.63 340,164.39 843,067.60 377,316.33 698,070.90 621,384.72 1,313,132.60 525,953.01 938,605.19 577,014.62 6,399,998.99

PORCENTAJE MENSUAL DE AVANCE DE OBRA 2.58% 5.32% 13.17% 5.90% 10.91% 9.71% 20.52% 8.22% 14.67% 9.02% 100.00%
PORCENTAJE ACUMULADO DE AVANCE DE OBRA 2.58% 7.90% 21.07% 26.97% 37.87% 47.58% 68.10% 76.32% 90.98% 100.00%
CALENDARIO DE AVANCE DE OBRA ACTUALIZADO
Obra: : MEJORAMIENTO DEL CAMINO VECINAL ENTRE LOS TRAMOS MAL PASO - HUAYRUL - JANQUE -CRUZ LOMA - LANCHIPAMPA
Entidad: : PROVIAS DESCENTRALIZADO
Lugar: : INCAHUASI - FERREÑAFE - LAMBAYEQUE Fecha: : OCT 2018
Contratista: : CONSORCIO VIAL NORTE V
PLAZO DE EJECUCION 220 DC

MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE


Metrado Parcial S/.
Item Descripción Und. Precio S/. (Del 04/05/2018 al 31/05/2018) (Del 01/06/2018 al 30/06/2018) (Del 01/07/2018 al 31/07/2018) (Del 01/08/2018 al 31/08/2018) (Del 01/09/2018 al 30/09/2018) (Del 01/10/2018 al 30/10/2018) (Del 01/11/2018 al 30/11/2018) (Del 01/12/2018 al 09/12/2018) TOTAL
(contractual) (contractual)
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %
1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 121,265.27 121,265.27 30,316.32 25.00% 24,253.05 20.00% 0.00 0.00% 6,063.26 5.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 60,632.64 50.00% 121,265.27
1.02 TOPOGRAFIA Y GEOREFERENCIACION KM 20.87 451.65 9,425.94 1,696.67 18.00% 942.59 10.00% 942.59 10.00% 3,864.64 41.00% 1,885.19 20.00% 94.26 1.00% 0.00 0.00% 0.00 0.00% 9,425.94
1.03 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL GBL 1.00 11,069.95 11,069.95 286.01 2.58% 712.45 6.44% 1,498.05 13.53% 997.26 9.01% 1,316.70 11.89% 1,261.61 11.40% 3,284.21 29.67% 1,713.66 15.48% 11,069.95
1.04 CAMPAMENTO GLB 1.00 12,311.20 12,311.20 12,311.20 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12,311.20
2 MOVIMIENTO DE TIERRAS
2.01 DESBROCE Y LIMPIEZA DE TERRENO EN ZONAS NO BOSCOSAS HA 12.52 2,996.05 37,510.55 34,509.71 92.00% 3,000.84 8.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,510.55
2.02 EXCAVACION PARA EXPLANACIONES - MATERIAL SUELTO M3 35,764.60 3.31 118,380.83 29,595.21 25.00% 59,190.42 50.00% 29,595.21 25.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 118,380.83
2.03 EXCAVACION PARA EXPLANACIONES - ROCA SUELTA M3 2,501.33 12.65 31,641.82 7,910.46 25.00% 15,820.91 50.00% 7,910.46 25.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 31,641.82
2.04 EXCAVACION PARA EXPLANACIONES - ROCA FIJA M3 9,497.30 29.60 281,120.08 0.00 0.00% 56,224.02 20.00% 224,896.06 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 281,120.08
2.05 TERRAPLENES CON MATERIAL PROPIO M3 2,237.15 4.92 11,006.78 0.00 0.00% 3,302.03 30.00% 7,704.75 70.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,006.78
2.06 PERFILADO Y COMPACTADO EN ZONA DE CORTE M2 81,634.33 1.09 88,981.42 0.00 0.00% 35,592.57 40.00% 53,388.85 60.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 88,981.42
2.07 CONFORMACION Y ACOMODO DEL DME M3 20,388.37 1.60 32,621.39 0.00 0.00% 0.00 0.00% 3,262.14 10.00% 9,786.42 30.00% 3,262.14 10.00% 3,262.14 10.00% 3,262.14 10.00% 9,786.42 30.00% 32,621.39
2.08 MEJORAMIENTO A NIVEL DE SUBRASANTE M3 468.00 18.60 8,704.80 0.00 0.00% 7,660.22 88.00% 1,044.58 12.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,704.80
3 AFIRMADO Y SUB BASE
3.01 AFIRMADO GRANULAR M3 20,805.40 21.97 457,094.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 45,709.46 10.00% 45,709.46 10.00% 365,675.71 80.00% 0.00 0.00% 457,094.64
3.02 IMPRIMACION REFORZADA M2 90,552.78 5.63 509,812.15 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 50,981.22 10.00% 458,830.94 90.00% 509,812.15
4 DRENAJE
4.01 ALCANTARILLAS DE ALIVIO TMC
4.01.01 TRAZO Y REPLANTEO M2 409.51 1.46 597.88 0.00 0.00% 0.00 0.00% 597.88 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 597.88
4.01.02 EXCAVACION PARA ESTRUCTURAS M3 691.58 40.44 27,967.50 0.00 0.00% 0.00 0.00% 27,967.50 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 27,967.50
4.01.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 153.80 32.77 5,040.03 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,040.03 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,040.03
4.01.04 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 41.88 55.35 2,318.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,318.06 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,318.06
4.01.05 ENCOFRADO Y DESENCOFRADO M2 1,244.51 56.50 70,314.82 0.00 0.00% 0.00 0.00% 70,314.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 70,314.82
4.01.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 231.48 458.36 106,101.17 0.00 0.00% 0.00 0.00% 53,050.59 50.00% 53,050.59 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 106,101.17
4.01.07 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 35.99 481.56 17,331.34 0.00 0.00% 0.00 0.00% 8,665.67 50.00% 8,665.67 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,331.34
4.01.08 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 4.42 389.85 1,723.14 0.00 0.00% 0.00 0.00% 861.57 50.00% 861.57 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,723.14
4.01.09 ACERO DE REFUERZO FY=4200 KG/CM2 KG 1,416.10 4.54 6,429.09 0.00 0.00% 0.00 0.00% 6,429.09 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,429.09
4.01.10 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 M M 157.14 405.21 63,674.70 0.00 0.00% 0.00 0.00% 31,837.35 50.00% 31,837.35 50.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 63,674.70
4.01.11 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 85.24 208.63 17,783.62 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,783.62 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,783.62
4.01.12 ELIMINACION EXCEDENTE DE EXCAVACION M3 537.78 6.98 3,753.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,753.70 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,753.70
4.02 ALCANTARILLA DE PASE TMC 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.02.01 TRAZO Y REPLANTEO M2 24.75 1.46 36.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 36.14 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 36.14
4.02.02 EXCAVACION PARA ESTRUCTURAS M3 39.22 40.44 1,586.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,586.06 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,586.06
4.02.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 7.55 32.77 247.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 247.41 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 247.41
4.02.04 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 3.03 55.35 167.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 167.71 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 167.71
4.02.05 ENCOFRADO Y DESENCOFRADO M2 80.02 56.50 4,521.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 904.23 20.00% 3,616.90 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,521.13
4.02.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 11.47 458.36 5,257.39 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,051.48 20.00% 4,205.91 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,257.39
4.02.07 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 4.23 481.56 2,037.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 407.40 20.00% 1,629.60 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,037.00
4.02.08 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 0.52 389.85 202.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 40.54 20.00% 162.18 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 202.72
4.02.09 ACERO DE REFUERZO FY=4200 KG/CM2 KG 166.60 4.54 756.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 151.27 20.00% 605.09 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 756.36
4.02.10 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 M M 9.72 405.21 3,938.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 787.73 20.00% 3,150.91 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,938.64
4.02.11 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 6.52 208.63 1,360.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 272.05 20.00% 1,088.22 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,360.27
4.02.12 ELIMINACION EXCEDENTE DE EXCAVACION M3 31.68 6.98 221.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 44.23 20.00% 176.90 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 221.13
4.03 CANALETAS DE PASE
4.03.01 TRAZO Y REPLANTEO M2 794.40 1.46 1,159.82 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,159.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,159.82
4.03.02 EXCAVACION PARA ESTRUCTURAS M3 936.26 40.44 37,862.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,862.35 100.00% 0.00 0.00% 0.00 0.00% 37,862.35
4.03.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 506.40 32.77 16,594.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,594.73 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,594.73
4.03.04 ENCOFRADO Y DESENCOFRADO M2 2,261.63 56.50 127,782.10 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 127,782.10 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 127,782.10
4.03.05 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 28.31 389.85 11,036.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,311.00 30.00% 7,725.65 70.00% 0.00 0.00% 0.00 0.00% 11,036.65
4.03.06 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 401.56 481.56 193,375.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 58,012.57 30.00% 135,362.66 70.00% 0.00 0.00% 0.00 0.00% 193,375.23
4.03.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 22,243.12 4.54 100,983.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 70,688.63 70.00% 30,295.13 30.00% 0.00 0.00% 0.00 0.00% 100,983.76
CALENDARIO DE AVANCE DE OBRA ACTUALIZADO
Obra: : MEJORAMIENTO DEL CAMINO VECINAL ENTRE LOS TRAMOS MAL PASO - HUAYRUL - JANQUE -CRUZ LOMA - LANCHIPAMPA
Entidad: : PROVIAS DESCENTRALIZADO
Lugar: : INCAHUASI - FERREÑAFE - LAMBAYEQUE Fecha: : OCT 2018
Contratista: : CONSORCIO VIAL NORTE V
PLAZO DE EJECUCION 220 DC

MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE


Metrado Parcial S/.
Item Descripción Und. Precio S/. (Del 04/05/2018 al 31/05/2018) (Del 01/06/2018 al 30/06/2018) (Del 01/07/2018 al 31/07/2018) (Del 01/08/2018 al 31/08/2018) (Del 01/09/2018 al 30/09/2018) (Del 01/10/2018 al 30/10/2018) (Del 01/11/2018 al 30/11/2018) (Del 01/12/2018 al 09/12/2018) TOTAL
(contractual) (contractual)
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %
4.03.08 ELIMINACION EXCEDENTE DE EXCAVACION M3 429.86 6.98 3,000.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,000.42 100.00% 0.00 0.00% 0.00 0.00% 3,000.42
CALENDARIO DE AVANCE DE OBRA ACTUALIZADO
Obra: : MEJORAMIENTO DEL CAMINO VECINAL ENTRE LOS TRAMOS MAL PASO - HUAYRUL - JANQUE -CRUZ LOMA - LANCHIPAMPA
Entidad: : PROVIAS DESCENTRALIZADO
Lugar: : INCAHUASI - FERREÑAFE - LAMBAYEQUE Fecha: : OCT 2018
Contratista: : CONSORCIO VIAL NORTE V
PLAZO DE EJECUCION 220 DC

MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE


Metrado Parcial S/.
Item Descripción Und. Precio S/. (Del 04/05/2018 al 31/05/2018) (Del 01/06/2018 al 30/06/2018) (Del 01/07/2018 al 31/07/2018) (Del 01/08/2018 al 31/08/2018) (Del 01/09/2018 al 30/09/2018) (Del 01/10/2018 al 30/10/2018) (Del 01/11/2018 al 30/11/2018) (Del 01/12/2018 al 09/12/2018) TOTAL
(contractual) (contractual)
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %
4.04 BADEN
4.04.01 TRAZO Y REPLANTEO M2 1,830.33 1.46 2,672.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,672.28 100.00% 0.00 0.00% 2,672.28
4.04.02 EXCAVACION PARA ESTRUCTURAS M3 871.18 40.44 35,230.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 35,230.52 100.00% 0.00 0.00% 35,230.52
4.04.03 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 251.63 55.35 13,927.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13,927.72 100.00% 0.00 0.00% 13,927.72
4.04.04 ENCOFRADO Y DESENCOFRADO M2 386.79 56.50 21,853.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21,853.64 100.00% 0.00 0.00% 21,853.64
4.04.05 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 191.84 208.63 40,023.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 40,023.58 100.00% 0.00 0.00% 40,023.58
4.04.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 427.72 458.36 196,049.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 196,049.74 100.00% 0.00 0.00% 196,049.74
4.04.07 CONCRETO CLASE E1 (F´c= 175 kg/cm2 + 30% P.M.) M3 182.09 343.40 62,529.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 62,529.71 100.00% 0.00 0.00% 62,529.71
4.04.08 JUNTAS ASFALTICAS E=1" EN BADENES M 416.20 19.25 8,011.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,011.85 100.00% 0.00 0.00% 8,011.85
4.05 CUNETAS
4.05.01 CUNETA TRIANGULAR DE TIERRA M 12,327.50 1.51 18,614.53 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,307.27 50.00% 9,307.27 50.00% 0.00 0.00% 0.00 0.00% 18,614.53
4.05.03 CUNETA TRIANGULAR REVESTIDO DE MAMPOSTERIA M 7,760.60 37.39 290,168.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 29,016.88 10.00% 29,016.88 10.00% 232,135.06 80.00% 0.00 0.00% 290,168.83
4.05.04 CUNETA RECTANGULAR REVESTIDO DE CONCRETO C/TAPA M 927.00 154.92 143,610.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,180.54 5.00% 136,430.30 95.00% 0.00 0.00% 143,610.84
4.06 SUBDREN 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
4.06.01 SUBDRENES M 785.00 144.57 113,487.45 0.00 0.00% 0.00 0.00% 0.00 0.00% 22,697.49 20.00% 0.00 0.00% 0.00 0.00% 90,789.96 80.00% 0.00 0.00% 113,487.45
5 TRANSPORTE
TRANSPORTE DE MATERIALES GRANULARES PARA DISTANCIAS ENTRE
5.01 M3-KM 21,479.10 7.08 152,072.03 0.00 0.00% 15,207.20 10.00% 15,207.20 10.00% 45,621.61 30.00% 30,414.41 20.00% 45,621.61 30.00% 0.00 0.00% 0.00 0.00% 152,072.03
120 M Y 1,000 MDE MATERIALES GRANULARES PARA DISTANCIAS
TRANSPORTE
5.02 M3-KM 289,361.77 1.94 561,361.83 0.00 0.00% 56,136.18 10.00% 56,136.18 10.00% 168,408.55 30.00% 112,272.37 20.00% 168,408.55 30.00% 0.00 0.00% 0.00 0.00% 561,361.83
MAYORES DE 1,000
TRANSPORTE M
DE MATERIALES EXCEDENTES PARA DISTANCIAS ENTRE
5.03 M3-KM 11,501.74 7.30 83,962.70 0.00 0.00% 8,396.27 10.00% 8,396.27 10.00% 16,792.54 20.00% 8,396.27 10.00% 4,198.14 5.00% 37,783.22 45.00% 0.00 0.00% 83,962.70
120 M Y 1,000 MDE MATERIALES EXCEDENTES PARA DISTANCIAS
TRANSPORTE
5.04 M3-KM 6,652.68 2.01 13,371.89 0.00 0.00% 1,337.19 10.00% 1,337.19 10.00% 2,674.38 20.00% 1,337.19 10.00% 668.59 5.00% 6,017.35 45.00% 0.00 0.00% 13,371.89
MAYORES DE 1,000 M
6 SEÑALIZACION Y SEGURIDAD VIAL
6.01 SEÑALES PREVENTIVAS UND 158.00 374.82 59,221.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 59,221.56 100.00% 59,221.56
6.02 SEÑALES REGLAMENTARIAS UND 32.00 468.58 14,994.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,994.56 100.00% 14,994.56
6.03 SEÑALES INFORMATIVAS UND 8.00 1,846.01 14,768.08 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,768.08 100.00% 14,768.08
6.04 POSTES DE KILOMETRAJE UND 21.00 124.21 2,608.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,608.41 100.00% 2,608.41
7 PROTECION AMBIENTAL
7.01 MONITOREO DE LA CALIDAD DE AIRE PTO 2.00 504.72 1,009.44 0.00 0.00% 336.14 33.30% 0.00 0.00% 336.14 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 337.15 33.40% 1,009.44
7.02 MONITOREO DE CALIDAD DEL AGUA PTO 1.00 325.26 325.26 0.00 0.00% 108.31 33.30% 0.00 0.00% 108.31 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 108.64 33.40% 325.26
7.03 MONITOREO DE NIVELES DE RUIDO PTO 1.00 168.24 168.24 0.00 0.00% 56.02 33.30% 0.00 0.00% 56.02 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 56.19 33.40% 168.24
7.04 MONITOREO DE CALIDAD DE SUELOS PTO 9.00 800.00 7,200.00 0.00 0.00% 2,397.60 33.30% 0.00 0.00% 2,397.60 33.30% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,404.80 33.40% 7,200.00
7.05 CAPA SUPERFICIAL DEL SUELO HA 5.30 12,334.00 65,370.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13,074.04 20.00% 52,296.16 80.00% 65,370.20
7.06 RECUPERACION AMBIENTAL DE AREAS AFECTADAS HA 5.97 3,338.48 19,930.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,986.15 20.00% 15,944.58 80.00% 19,930.73
7.07 SEÑALIZACION AMBIENTAL PERMANENTE UND 2.00 3,535.87 7,071.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,414.35 20.00% 5,657.39 80.00% 7,071.74
COSTO DIRECTO 4,515,726.25 116,625.57 290,674.03 611,044.00 406,809.87 537,103.60 528,975.26 1,325,132.74 699,361.18 4,515,726.25
GASTOS GENERALES FIJOS 0.911646% 41,167.46 1,063.21 2,649.92 5,570.56 3,708.67 4,896.49 4,822.38 12,080.53 6,375.70 41,167.46
GASTOS GENERALES VARIABLES 14.651752% 661,633.00 17,087.69 42,588.84 89,528.65 59,604.77 78,695.09 77,504.14 194,155.16 102,468.66 661,633.00
UTILIDAD 4.544147% 205,201.26 5,299.64 13,208.66 27,766.74 18,486.04 24,406.78 24,037.42 60,215.99 31,780.00 205,201.26
=========== =========== ========= ========= ========= ========= ========= ========= ========= =========
SUBTOTAL 5,423,727.97 140,076.11 349,121.45 733,909.95 488,609.35 645,101.96 635,339.20 1,591,584.42 839,985.54 5,423,727.97
IGV 18.00% 976,271.03 25,213.70 62,841.86 132,103.79 87,949.68 116,118.35 114,361.06 286,485.20 151,197.40 976,271.03
=========== =========== ========= ========= ========= ========= ========= ========= ========= =========
TOTAL 6,399,999.00 165,289.81 411,963.31 866,013.74 576,559.03 761,220.31 749,700.26 1,878,069.62 991,182.94 6,399,999.00

PORCENTAJE MENSUAL DE AVANCE DE OBRA 2.58% 6.44% 13.53% 9.01% 11.89% 11.71% 29.34% 15.49% 100.00%
PORCENTAJE ACUMULADO DE AVANCE DE OBRA 2.58% 9.02% 22.55% 31.56% 43.45% 55.17% 84.51% 100.00%
PORCENTAJE DE AVANCE FINANCIERO : PROGRAMADO Vs EJECUTADO
PERIODO DE TRABAJO DEL 21/08/2023 AL 31/08/2023
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-
GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA, CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA -
ANGUIA - CHUGUR"
ENTIDAD: PROVIAS DESCENTRALIZADO PLAZO DE EJECUCION: 180 DIAS
CONSORCIO MDJH CONFORMADO POR IBEVIAL
EJECUTA: CONTADORES E INGENIEROS ASOCIADOS INICIO DE OBRA: 10/29/2021
S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SOCIEDAD COMERCIAL DE RESPONSABILIDAD
SUPERVISA: TERMINO DE OBRA: 9/2/2022
LIMITADA
MONTO CONTRACTUAL : S/. 14,369,895.73

GRAFICO DEL AVANCE FINANCIERO


PROGRAMADO VS EJECUTADO ACUMULADO

6,600,000 6,399,998.99
AVANCE MENSUAL ACUMULADO (S/.)

6,000,000

5,400,000

4,698,210.92
4,800,000

4,200,000

3,600,000 3,586,682.20
2,957,465.29
3,181,927.44
3,000,000

2,400,000 2,413,131.89
1,734,311.25
1,800,000 PROGRAMADO

1,200,000
794,808.88 ejecutado

600,000
0.00 83,154.66 674,605.93
0 0.00 165,936.73
04/05/2018 19/05/2018 03/06/2018 18/06/2018 03/07/2018 18/07/2018 02/08/2018 17/08/2018 01/09/2018 16/09/2018 01/10/2018 16/10/2018
PLAZO DE EJECUCION (MESES)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS

MONTOS (Sin/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
4-May-18 0.00 0.00 0.00 0.00 4-May-18 0.00 0.00 0.00 0.00
31-May-18 165,936.73 165,936.73 2.59% 2.59% 31-May-18 83,154.66 83,154.66 1.30% 1.30%
30-Jun-18 508,669.20 674,605.93 7.95% 10.54% 30-Jun-18 711,654.22 794,808.88 11.12% 12.42%
31-Jul-18 1,059,705.31 1,734,311.25 16.56% 27.10% 31-Jul-18 1,618,323.01 2,413,131.89 25.29% 37.71%
31-Aug-18 1,223,154.05 2,957,465.29 19.11% 46.21% 31-Aug-18 768,795.55 3,181,927.44 12.01% 49.72%
30-Sep-18 1,740,745.62 4,698,210.92 27.20% 73.41% 30-Sep-18 404,754.76 3,586,682.20 6.32% 56.04%
30-Oct-18 1,701,788.07 6,399,998.99 26.59% 100.00% 30-Oct-18
TOTAL 6,399,999.00 100.00% TOTAL 3,586,682.20 56.04%
GRAFICO DE AVANCE PROGRAMADO VS EJECUTADO
VALORIZACION DE OBRA N° 14
OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-A
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONPLAZO DE EJEC. 672.00
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR INICIO DE OBRA 29/10/21
MONTO CONTRACTUAL (S/ IGV) S/.12,177,877.73 TERMINO DE OBRA 31/08/23

EJECUTADO Programado

30.00%

25.00%

20.00%

15.00%

10.00%

5.00%

0.00%
Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22

MES 0 MES 1 MES 2 MES 3 MES 4 MES 5


DESCRIPCION
Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22
(S/.) - 70,470.05 603,096.80 1,371,460.19 651,521.65 343,012.51
PROGRAMADO MES (S/ IGV)
(%) 0.00% 0.58% 4.95% 11.26% 5.35% 2.82%
(S/.) - - - - - -
EJECUTADO MES (S/ IGV)
(%) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(S/.) - 70,470.05 673,566.85 2,045,027.03 2,696,548.69 3,039,561.19
PROGRAMADO ACUMULADO (S/ IGV)
(%) 0.00% 0.58% 5.53% 16.79% 22.14% 24.96%
(S/.) - - - - -
EJECUTADO ACUMULADO (S/ IGV)
(%) 0.00% 0.00% 0.00%
PORCENTAJE DE AVANCE: PROGRAMADO Vs EJECUTADO

0d 50d 100d 150d 200d 250d


120.00%

100.00%

PROGRAMADO

EJECUTADO

9; 78.99% 80.00%
PRIMERA VALORIZACION

SEGUNDA VALORIZACION

TERCERA VALORIZACION

CUARTA VALORIZACION

6; 57.99% 60.00%

5; 39.27%
40.00%
5; 36.50%
4; 29.79%

7; 26.13%
4; 21.41% 8; 24.61% 20.00%
3; 9.81%
2; 1.03%
3; 8.33%
1; 0.00%
2; 2.05% 0.00%
1; 0.00
MONTOS Y/O PORCENTAJES VALORIZADOS PROGRAMADOS MONTOS Y/O PORCENTAJES VALORIZADOS EJECUTADOS
NUEVOS SOLES PORCENTAJES NUEVOS SOLES PORCENTAJES
DIAS PLAZO PARCIAL ACUMULADO PARCIAL ACUMULADO PERIODO DIAS PLAZO PARCIAL ACUMULADO PARCIAL ACUMULADO
0d 0.00 0.00 0.00% 0.00% 0d 0.00 0.00 0.00 0.00
28d 165,936.73 165,936.73 2.05% 2.05% PRIMER 28d 83154.66 83154.66 1.03% 1.03%
58d 508,669.20 674,605.93 6.28% 8.33% SEGUNDO 58d 711654.22 794808.88 8.78% 9.81%
89d 1,059,705.31 1,734,311.25 13.08% 21.41% TERCER 89d 1618323.01 2413131.89 19.97% 29.79%
120d 1,223,154.05 2,957,465.29 15.10% 36.50% CUARTO 120d 768795.55 3181927.44 9.49% 39.27%
150d 1,740,745.62 4,698,210.92 21.49% 57.99% QUINTO 150d
181d 1,442,193.28 2,116,799.22 17.80% 26.13% SEXTO 180d
211d 259,594.79 1,993,906.04 3.20% 24.61% SEXTO 180d
220d 1,701,788.07 6,399,998.99 21.01% 78.99% SEXTO 180d
8,101,787.06 100.00% 3,181,927.44 39.27%
CALENDARIO DE AVANCE DE OBRA VALORIZADO - INICIO DE OBRA
Obra: : MEJORAMIENTO DEL CAMINO VECINAL ENTRE LOS TRAMOS MAL PASO - HUAYRUL - JANQUE -CRUZ LOMA - LANCHIPAMPA
Entidad: : PROVIAS DESCENTRALIZADO
Lugar: : INCAHUASI - FERREÑAFE - LAMBAYEQUE Fecha: : MAY 2018
Contratista: : CONSORCIO VIAL NORTE V
PLAZO DE EJECUCION 180 DC
MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE
Item Descripción Und. Metrado Precio S/. Parcial S/. (Del 04/05/2018 al 31/05/2018) (Del 01/06/2018 al 30/06/2018) (Del 01/07/2018 al 31/07/2018) (Del 01/08/2018 al 31/08/2018) (Del 01/09/2018 al 30/09/2018) (Del 01/10/2018 al 30/10/2018) TOTAL
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %
1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 121,265.27 121,265.27 30,316.32 25.00% 24,253.05 20.00% 0.00 0.00% 6,063.26 5.00% 0.00 0.00% 60,632.64 50.00% 121,265.27
1.02 TOPOGRAFIA Y GEOREFERENCIACION KM 20.87 451.65 9,425.94 1,696.67 18.00% 1,885.19 20.00% 1,948.03 20.67% 1,948.03 20.67% 1,885.19 20.00% 62.84 0.67% 9,425.94
1.03 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL GBL 1.00 11,069.95 11,069.95 742.47 6.71% 1,292.18 11.67% 1,425.92 12.88% 1,794.84 16.21% 2,932.28 26.49% 2,882.25 26.04% 11,069.95
1.04 CAMPAMENTO GLB 1.00 12,311.20 12,311.20 12,311.20 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12,311.20
2 MOVIMIENTO DE TIERRAS
2.01 DESBROCE Y LIMPIEZA DE TERRENO EN ZONAS NO BOSCOSAS HA 12.52 2,996.05 37,510.55 34,509.71 92.00% 3,000.84 8.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,510.55
2.02 EXCAVACION PARA EXPLANACIONES - MATERIAL SUELTO M3 35,764.60 3.31 118,380.83 29,595.21 25.00% 59,190.42 50.00% 29,595.21 25.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 118,380.83
2.03 EXCAVACION PARA EXPLANACIONES - ROCA SUELTA M3 2,501.33 12.65 31,641.82 7,910.46 25.00% 15,820.91 50.00% 7,910.46 25.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 31,641.82
2.04 EXCAVACION PARA EXPLANACIONES - ROCA FIJA M3 9,497.30 29.60 281,120.08 0.00 0.00% 56,224.02 20.00% 224,896.06 80.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 281,120.08
2.05 TERRAPLENES CON MATERIAL PROPIO M3 2,237.15 4.92 11,006.78 0.00 0.00% 3,302.03 30.00% 7,704.75 70.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,006.78
2.06 PERFILADO Y COMPACTADO EN ZONA DE CORTE M2 81,634.33 1.09 88,981.42 0.00 0.00% 35,592.57 40.00% 53,388.85 60.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 88,981.42
2.07 CONFORMACION Y ACOMODO DEL DME M3 20,388.37 1.60 32,621.39 0.00 0.00% 0.00 0.00% 8,155.35 25.00% 8,155.35 25.00% 8,155.35 25.00% 8,155.35 25.00% 32,621.39
2.08 MEJORAMIENTO A NIVEL DE SUBRASANTE M3 468.00 18.60 8,704.80 0.00 0.00% 7,660.22 88.00% 1,044.58 12.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,704.80
3 AFIRMADO Y SUB BASE
3.01 AFIRMADO GRANULAR M3 20,805.40 21.97 457,094.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 163,248.09 35.71% 195,897.70 42.86% 97,948.85 21.43% 457,094.64
3.02 IMPRIMACION REFORZADA M2 90,552.78 5.63 509,812.15 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 509,812.15 100.00% 509,812.15
4 DRENAJE
4.01 ALCANTARILLAS DE ALIVIO TMC
4.01.01 TRAZO Y REPLANTEO M2 409.51 1.46 597.88 0.00 0.00% 0.00 0.00% 358.73 60.00% 239.15 40.00% 0.00 0.00% 0.00 0.00% 597.88
4.01.02 EXCAVACION PARA ESTRUCTURAS M3 691.58 40.44 27,967.50 0.00 0.00% 0.00 0.00% 16,780.50 60.00% 11,187.00 40.00% 0.00 0.00% 0.00 0.00% 27,967.50
4.01.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 153.80 32.77 5,040.03 0.00 0.00% 0.00 0.00% 3,024.02 60.00% 2,016.01 40.00% 0.00 0.00% 0.00 0.00% 5,040.03
4.01.04 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 41.88 55.35 2,318.06 0.00 0.00% 0.00 0.00% 1,390.84 60.00% 927.22 40.00% 0.00 0.00% 0.00 0.00% 2,318.06
4.01.05 ENCOFRADO Y DESENCOFRADO M2 1,244.51 56.50 70,314.82 0.00 0.00% 0.00 0.00% 42,188.89 60.00% 28,125.93 40.00% 0.00 0.00% 0.00 0.00% 70,314.82
4.01.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 231.48 458.36 106,101.17 0.00 0.00% 0.00 0.00% 63,660.70 60.00% 42,440.47 40.00% 0.00 0.00% 0.00 0.00% 106,101.17
4.01.07 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 35.99 481.56 17,331.34 0.00 0.00% 0.00 0.00% 10,398.80 60.00% 6,932.54 40.00% 0.00 0.00% 0.00 0.00% 17,331.34
4.01.08 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 4.42 389.85 1,723.14 0.00 0.00% 0.00 0.00% 1,033.88 60.00% 689.26 40.00% 0.00 0.00% 0.00 0.00% 1,723.14
4.01.09 ACERO DE REFUERZO FY=4200 KG/CM2 KG 1,416.10 4.54 6,429.09 0.00 0.00% 0.00 0.00% 3,857.45 60.00% 2,571.64 40.00% 0.00 0.00% 0.00 0.00% 6,429.09
4.01.10 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 M M 157.14 405.21 63,674.70 0.00 0.00% 0.00 0.00% 38,204.82 60.00% 25,469.88 40.00% 0.00 0.00% 0.00 0.00% 63,674.70
4.01.11 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 85.24 208.63 17,783.62 0.00 0.00% 0.00 0.00% 0.00 0.00% 17,783.62 100.00% 0.00 0.00% 0.00 0.00% 17,783.62
4.01.12 ELIMINACION EXCEDENTE DE EXCAVACION M3 537.78 6.98 3,753.70 0.00 0.00% 0.00 0.00% 2,252.22 60.00% 1,501.48 40.00% 0.00 0.00% 0.00 0.00% 3,753.70
4.02 ALCANTARILLA DE PASE TMC
4.02.01 TRAZO Y REPLANTEO M2 24.75 1.46 36.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 36.14 100.00% 0.00 0.00% 0.00 0.00% 36.14
4.02.02 EXCAVACION PARA ESTRUCTURAS M3 39.22 40.44 1,586.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,586.06 100.00% 0.00 0.00% 0.00 0.00% 1,586.06
4.02.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 7.55 32.77 247.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 247.41 100.00% 0.00 0.00% 0.00 0.00% 247.41
4.02.04 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 3.03 55.35 167.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 167.71 100.00% 0.00 0.00% 0.00 0.00% 167.71
4.02.05 ENCOFRADO Y DESENCOFRADO M2 80.02 56.50 4,521.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,521.13 100.00% 0.00 0.00% 0.00 0.00% 4,521.13
4.02.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 11.47 458.36 5,257.39 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,257.39 100.00% 0.00 0.00% 0.00 0.00% 5,257.39
4.02.07 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 4.23 481.56 2,037.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,037.00 100.00% 0.00 0.00% 0.00 0.00% 2,037.00
4.02.08 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 0.52 389.85 202.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 202.72 100.00% 0.00 0.00% 0.00 0.00% 202.72
4.02.09 ACERO DE REFUERZO FY=4200 KG/CM2 KG 166.60 4.54 756.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 756.36 100.00% 0.00 0.00% 0.00 0.00% 756.36
4.02.10 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 M M 9.72 405.21 3,938.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,938.64 100.00% 0.00 0.00% 0.00 0.00% 3,938.64
4.02.11 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 6.52 208.63 1,360.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,360.27 100.00% 0.00 0.00% 0.00 0.00% 1,360.27
4.02.12 ELIMINACION EXCEDENTE DE EXCAVACION M3 31.68 6.98 221.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 201.03 90.91% 20.10 9.09% 0.00 0.00% 221.13
4.03 CANALETAS DE PASE
4.03.01 TRAZO Y REPLANTEO M2 794.40 1.46 1,159.82 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,159.82 100.00% 0.00 0.00% 1,159.82
4.03.02 EXCAVACION PARA ESTRUCTURAS M3 936.26 40.44 37,862.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,862.35 100.00% 0.00 0.00% 37,862.35
4.03.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 506.40 32.77 16,594.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,594.73 100.00% 0.00 0.00% 16,594.73
4.03.04 ENCOFRADO Y DESENCOFRADO M2 2,261.63 56.50 127,782.10 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 127,782.10 100.00% 0.00 0.00% 127,782.10
4.03.05 CONCRETO CLASE H (F´C= 100 KG/CM2) M3 28.31 389.85 11,036.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,036.65 100.00% 0.00 0.00% 11,036.65
4.03.06 CONCRETO CLASE D (F´c= 210 kg/cm2) M3 401.56 481.56 193,375.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 193,375.23 100.00% 0.00 0.00% 193,375.23
CALENDARIO DE AVANCE DE OBRA VALORIZADO - INICIO DE OBRA
Obra: : MEJORAMIENTO DEL CAMINO VECINAL ENTRE LOS TRAMOS MAL PASO - HUAYRUL - JANQUE -CRUZ LOMA - LANCHIPAMPA
Entidad: : PROVIAS DESCENTRALIZADO
Lugar: : INCAHUASI - FERREÑAFE - LAMBAYEQUE Fecha: : MAY 2018
Contratista: : CONSORCIO VIAL NORTE V
PLAZO DE EJECUCION 180 DC
MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE
Item Descripción Und. Metrado Precio S/. Parcial S/. (Del 04/05/2018 al 31/05/2018) (Del 01/06/2018 al 30/06/2018) (Del 01/07/2018 al 31/07/2018) (Del 01/08/2018 al 31/08/2018) (Del 01/09/2018 al 30/09/2018) (Del 01/10/2018 al 30/10/2018) TOTAL
MONTO % MONTO % MONTO % MONTO % MONTO % MONTO %
4.03.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 22,243.12 4.54 100,983.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 100,983.76 100.00% 0.00 0.00% 100,983.76
4.03.08 ELIMINACION EXCEDENTE DE EXCAVACION M3 429.86 6.98 3,000.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,727.65 90.91% 272.77 9.09% 3,000.42
4.04 BADEN
4.04.01 TRAZO Y REPLANTEO M2 1,830.33 1.46 2,672.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,672.28 100.00% 2,672.28
4.04.02 EXCAVACION PARA ESTRUCTURAS M3 871.18 40.44 35,230.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 35,230.52 100.00% 35,230.52
4.04.03 RELLENO CON MATERIAL GRANULAR COMPACTADO M3 251.63 55.35 13,927.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13,927.72 100.00% 13,927.72
4.04.04 ENCOFRADO Y DESENCOFRADO M2 386.79 56.50 21,853.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21,853.64 100.00% 21,853.64
4.04.05 EMBOQUILLADO DE PIEDRA F´C= 175 KG/CM2 + PM (6" TAM. MAX.) M3 191.84 208.63 40,023.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 40,023.58 100.00% 40,023.58
4.04.06 CONCRETO CLASE E (F´c= 175 kg/cm2) M3 427.72 458.36 196,049.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 196,049.74 100.00% 196,049.74
4.04.07 CONCRETO CLASE E1 (F´c= 175 kg/cm2 + 30% P.M.) M3 182.09 343.40 62,529.71 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 62,529.71 100.00% 62,529.71
4.04.08 JUNTAS ASFALTICAS E=1" EN BADENES M 416.20 19.25 8,011.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,011.85 100.00% 8,011.85
4.05 CUNETAS
4.05.01 CUNETA TRIANGULAR DE TIERRA M 12,327.50 1.51 18,614.53 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,424.14 56.00% 8,190.39 44.00% 0.00 0.00% 18,614.53
4.05.03 CUNETA TRIANGULAR REVESTIDO DE MAMPOSTERIA M 7,760.60 37.39 290,168.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 116,067.53 40.00% 174,101.30 60.00% 0.00 0.00% 290,168.83
4.05.04 CUNETA RECTANGULAR REVESTIDO DE CONCRETO C/TAPA M 927.00 154.92 143,610.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 50,263.79 35.00% 93,347.05 65.00% 0.00 0.00% 143,610.84
4.06 SUBDREN
4.06.01 SUBDRENES M 785.00 144.57 113,487.45 0.00 0.00% 0.00 0.00% 0.00% 113,487.45 100.00% 0.00% 0.00 0.00% 113,487.45
5 TRANSPORTE
TRANSPORTE DE MATERIALES GRANULARES PARA DISTANCIAS ENTRE 120 152,072.03 0.00 0.00% 29,031.93 19.09% 42,856.66 28.18% 42,856.66 28.18% 37,326.77 24.55% 0.00 0.00% 152,072.03
5.01 M Y 1,000 M M3-KM
21,479.10 7.08
TRANSPORTE DE MATERIALES GRANULARES PARA DISTANCIAS MAYORES 561,361.83 0.00 0.00% 102,065.79 18.18% 158,201.97 28.18% 158,201.97 28.18% 142,892.10 25.45% 0.00 0.00% 561,361.83
5.02 DE 1,000 M M3-KM
289,361.77 1.94
TRANSPORTE DE MATERIALES EXCEDENTES PARA DISTANCIAS ENTRE 120 83,962.70 0.00 0.00% 14,502.65 17.27% 23,662.22 28.18% 23,662.22 28.18% 22,135.62 26.36% 0.00 0.00% 83,962.70
5.03 M Y 1,000 M M3-KM
11,501.74 7.30
TRANSPORTE DE MATERIALES EXCEDENTES PARA DISTANCIAS MAYORES 13,371.89 0.00 0.00% 2,188.13 16.36% 3,768.44 28.18% 3,768.44 28.18% 3,646.88 27.27% 0.00 0.00% 13,371.89
5.04 DE 1,000 M M3-KM
6,652.68 2.01
6 SEÑALIZACION Y SEGURIDAD VIAL
6.01 SEÑALES PREVENTIVAS UND 158.00 374.82 59,221.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 59,221.56 100.00% 59,221.56
6.02 SEÑALES REGLAMENTARIAS UND 32.00 468.58 14,994.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,994.56 100.00% 14,994.56
6.03 SEÑALES INFORMATIVAS UND 8.00 1,846.01 14,768.08 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,768.08 100.00% 14,768.08
6.04 POSTES DE KILOMETRAJE UND 21.00 124.21 2,608.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,608.41 100.00% 2,608.41
7 PROTECION AMBIENTAL
7.01 MONITOREO DE LA CALIDAD DE AIRE PTO 2.00 504.72 1,009.44 0.00 0.00% 336.14 33.30% 0.00 0.00% 336.14 33.30% 0.00 0.00% 337.15 33.40% 1,009.44
7.02 MONITOREO DE CALIDAD DEL AGUA PTO 1.00 325.26 325.26 0.00 0.00% 108.31 33.30% 0.00 0.00% 108.31 33.30% 0.00 0.00% 108.64 33.40% 325.26
7.03 MONITOREO DE NIVELES DE RUIDO PTO 1.00 168.24 168.24 0.00 0.00% 56.02 33.30% 0.00 0.00% 56.02 33.30% 0.00 0.00% 56.19 33.40% 168.24
7.04 MONITOREO DE CALIDAD DE SUELOS PTO 9.00 800.00 7,200.00 0.00 0.00% 2,397.60 33.30% 0.00 0.00% 2,397.60 33.30% 0.00 0.00% 2,404.80 33.40% 7,200.00
7.05 CAPA SUPERFICIAL DEL SUELO HA 5.30 12,334.00 65,370.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 32,685.10 50.00% 32,685.10 50.00% 65,370.20
7.06 RECUPERACION AMBIENTAL DE AREAS AFECTADAS HA 5.97 3,338.48 19,930.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 9,965.37 50.00% 9,965.37 50.00% 19,930.73
7.07 SEÑALIZACION AMBIENTAL PERMANENTE UND 2.00 3,535.87 7,071.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,535.87 50.00% 3,535.87 50.00% 7,071.74
COSTO DIRECTO 4,515,726.25 117,082.03 358,908.01 747,709.34 863,035.90 1,228,239.36 1,200,751.60 4,515,726.25
GASTOS GENERALES FIJOS 0.9116464932% 41,167.46 1,067.37 3,271.96 6,816.47 7,867.83 11,197.20 10,946.63 41,167.46
GASTOS GENERALES VARIABLES 14.6517517531% 661,633.00 17,154.57 52,586.31 109,552.52 126,449.88 179,958.58 175,931.14 661,633.00
UTILIDAD 4.5441474669% 205,201.26 5,320.38 16,309.31 33,977.02 39,217.62 55,813.01 54,563.91 205,201.25
=========== =========== ========= ========= ========= ========= ========= ===========
SUBTOTAL 5,423,727.97 140,624.35 431,075.59 898,055.35 1,036,571.23 1,475,208.15 1,442,193.28 5,423,727.96
IGV 18.00% 976,271.03 25,312.38 77,593.61 161,649.96 186,582.82 265,537.47 259,594.79 976,271.03
=========== =========== ========= ========= ========= ========= ========= ===========
TOTAL 6,399,999.00 165,936.73 508,669.20 1,059,705.31 1,223,154.05 1,740,745.62 1,701,788.07 6,399,998.99

PORCENTAJE MENSUAL DE AVANCE DE OBRA 2.59% 7.95% 16.56% 19.11% 27.20% 26.59%
PORCENTAJE ACUMULADO DE AVANCE DE OBRA 2.59% 10.54% 27.10% 46.21% 73.41% 100.00%
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
OBRA
CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

ADELANTO DE MATERIALES N° 01
Fecha de Pago: May-22
Monto Otorgado: S/. 1,072,996.93 Sin IGV
Monto Otorgado: S/. 1,266,136.38 Con IGV
Índice Unif. Materiales Monto Otorgado
3 ACERO DE CONSTRUCCION CORRUGADO 3,207.73
30 DÓLAR (GENERAL PONDERADO) 177,284.44
5 AGREGADO GRUESO 327,206.93
21 CEMENTO PORTLAND TIPO I 511,821.81
13 ASFALTO 53,476.03
TOTAL S/. 1,072,996.93

AMORTIZACIÓN DEL ADELANTO DE MATERIALES N° 01


Fórmula
𝑨=𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑑𝑜 𝑥 𝐼𝑚𝑎/𝐼𝑚𝑜 A : Amortización del Adelanto de Materiales
PU : Precio Unitario del Ppto Base
𝑆𝑖𝑒𝑛𝑑𝑜 𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑑𝑜 :𝐶𝑎𝑛𝑡. 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑑𝑎 𝑑𝑒𝑙 𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑥 𝑃.𝑈 𝑥 𝐹𝑟
Fr : Factor de Relación
Ima : Índice del Material a la Fecha del Adelanto
Imo : Índice del Material a la Fecha del Ppto Base

Cantidad Material Utilizado Amortización Amortización Saldo x Amortizar


N° Fecha P.U (S/) Ima Imo
Utilizada (S/) (S/) Acumulada (S/) (S/)
ACERO DE CONSTRUCCION CORRUGADO IU 03 Mto Otorgado Sin IGV (S/): 3,207.73
1 Oct-21 - 3,207.73
2 Nov-21 - 3,207.73
3 Dec-21 - 3,207.73
4 Jan-22 - 3,207.73
5 Feb-22 - 3,207.73
6 Mar-22 - 3,207.73
7 Apr-22 - 3,207.73
8 May-22 - 3,207.73
9 Jun-22 - - 3,207.73
10 Jul-22 - 3,207.73
11 Aug-22 - 3,207.73
12 Sep-22 - 3,207.73
13 Oct-22 - 3,207.73
14 Nov-22 - 3,207.73
15 Dec-22 - 3,207.73
DÓLAR (GENERAL PONDERADO) IU 30 Mto Otorgado Sin IGV (S/): 177,284.44
1 Oct-21 - 177,284.44
2 Nov-21 - 177,284.44
3 Dec-21 - 177,284.44
4 Jan-22 - 177,284.44
5 Feb-22 - 177,284.44
6 Mar-22 - 177,284.44
7 Apr-22 - 177,284.44
8 May-22 - 177,284.44
9 Jun-22 5.00 12,167.55 60,837.75 60,837.75 116,446.69
10 Jul-22 5.00 2,423.32 12,116.60 72,954.35 104,330.09
11 Aug-22 72,954.35 104,330.09
12 Sep-22 5.00 1,251.99 6,259.95 79,214.30 98,070.14
13 Oct-22 79,214.30 98,070.14
14 Nov-22 5.00 13,660.41 68,302.05 147,516.35 29,768.09
15 Dec-22 5.00 1,588.83 7,944.15 155,460.50 21,823.94
16 Aug-23 5.00 287.53 1,437.65 156,898.15 20,386.29
AGREGADO GRUESO IU05 Mto Otorgado Sin IGV (S/): 327,206.93
5 Feb-22 - 327,206.93
6 Mar-22 - 327,206.93
7 Apr-22 - 327,206.93
8 May-22 - 327,206.93
9 Jun-22 - - 327,206.93
10 Jul-22 - 327,206.93
11 Aug-22 0.68 120.00 30.23 2,466.77 2,466.77 324,740.16
12 Sep-22 0.68 120.00 5.82 474.91 2,941.68 324,265.25
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
SUPERVISOR
MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR -ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
OBRA
CHOTA-CAJAMARCA, TRAMO I GUINEAMAYO - RODEOPAMPA - ANGUIA - CHUGUR"

ADELANTO DE MATERIALES N° 01
Fecha de Pago: May-22
Monto Otorgado: S/. 1,072,996.93 Sin IGV
Monto Otorgado: S/. 1,266,136.38 Con IGV
Índice Unif. Materiales Monto Otorgado
3 ACERO DE CONSTRUCCION CORRUGADO 3,207.73
30 DÓLAR (GENERAL PONDERADO) 177,284.44
5 AGREGADO GRUESO 327,206.93
21 CEMENTO PORTLAND TIPO I 511,821.81
13 ASFALTO 53,476.03
TOTAL S/. 1,072,996.93

AMORTIZACIÓN DEL ADELANTO DE MATERIALES N° 01


Fórmula
𝑨=𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑑𝑜 𝑥 𝐼𝑚𝑎/𝐼𝑚𝑜 A : Amortización del Adelanto de Materiales
PU : Precio Unitario del Ppto Base
𝑆𝑖𝑒𝑛𝑑𝑜 𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑑𝑜 :𝐶𝑎𝑛𝑡. 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑑𝑎 𝑑𝑒𝑙 𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑥 𝑃.𝑈 𝑥 𝐹𝑟
Fr : Factor de Relación
Ima : Índice del Material a la Fecha del Adelanto
Imo : Índice del Material a la Fecha del Ppto Base

Cantidad Material Utilizado Amortización Amortización Saldo x Amortizar


N° Fecha P.U (S/) Ima Imo
Utilizada (S/) (S/) Acumulada (S/) (S/)
13 Oct-22 0.68 120.00 11.82 964.51 3,906.19 323,300.73
14 Nov-22 0.68 120.00 12.43 1,014.05 4,920.24 322,286.68
15 Dec-22 - 4,920.24 322,286.68
CEMENTO PORTLAND TIPO I IU21 Mto Otorgado Sin IGV (S/): 511,821.81
1 Oct-21 - 511,821.81
2 Nov-21 - 511,821.81
3 Dec-21 - 511,821.81
4 Jan-22 - 511,821.81
5 Feb-22 - 511,821.81
6 Mar-22 - 511,821.81
7 Apr-22 - 511,821.81
8 May-22 - 511,821.81
9 Jun-22 1.50 24.42 1.00 36.63 36.63 511,785.18
10 Jul-22 1.64 24.42 1,760.00 70,651.36 70,687.99 441,133.82
11 Aug-22 70,687.99 441,133.82
12 Sep-22 70,687.99 441,133.82
13 Oct-22 106.38 24.42 1.00 2,597.80 73,285.79 253,921.14
14 Nov-22 149.30 24.42 1.00 3,645.91 76,931.69 250,275.23
15 Dec-22 151.91 24.42 1.00 3,709.72 80,641.41 246,565.52
ASFALTO IU 13 Mto Otorgado Sin IGV (S/): 53,476.03
1 Oct-21 - 53,476.03
2 Nov-21 - 53,476.03
3 Dec-21 - 53,476.03
4 Jan-22 - 53,476.03
5 Feb-22 - 53,476.03
6 Mar-22 - 53,476.03
7 Apr-22 - 53,476.03
8 May-22 - 53,476.03
9 Jun-22 - - 53,476.03
10 Jul-22 - 53,476.03
11 Aug-22 - 53,476.03
12 Sep-22 - 53,476.03
13 Oct-22 - 53,476.03
14 Nov-22 2.37 49.2 1.00 116.60 116.60 53,359.43
15 Dec-22 7.4494 49.2 1.00 366.51 483.11 52,992.92

SALDO POR AMORTIZAR 830,054.02


AMORTIZACIÓN ACUMULADA ACTUAL 242,942.91
AMORTIZACIÓN ACUMULADA ANTERIOR 241,505.27
AMORTIZACIÓN DEL PRESENTE MES 1,437.65
RESUMEN DE VALORIZACIONES PAGADAS
VALORIZACION DE OBRA N° 14
OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR
´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
NUEVO MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)
NUEVO MONTO CONTRATO S/. 14,369,895.72 (CON IGV)

FECHA
FACTURA CONCEPTO FECHA CONTRACTUAL ADICIONAL DE OBRA (Abono)
DE FACTURA N°02

E001‐2 ADELANTO DIRECTO 22/10/2021 1,954,967.03 28/10/2021

E001‐6 VALORIZACION NRO 01 OCTUBRE‐2021 1/12/2021 74,839.19 3/12/2021

E001‐9 VALORIZACION N° 02 ‐2021 16/12/2021 640,488.80 20/12/2021

E001‐12 VALORIZACION N° 03 DIC‐2021 I PARTE 29/12/2021 1,362,877.58 31/12/2021

E001‐13 VALORIZACION N° 03 DIC‐2021 II PARTE 29/12/2021 93,613.13 31/12/2021

E001‐17 VALORIZACION N° 05 FEBRERO‐2022 21/03/2022 364,279.29 22/03/2022

E001‐16 VALORIZACION N° 04 ENERO‐2022 10/03/2022 691,915.99 16/03/2022

ADELANTO DE MATERIALES E INSUMOS Nº


E001‐18
01
20/05/2022 1,266,136.38 25/05/2022

E001‐20 VALORIZACION N° 06 MAYO‐2022 15/06/2022 831,953.32 21/06/2022

E001‐22 VALORIZACION N° 07 JUNIO‐2022 14/07/2022 707,774.50 22/07/2022

E001‐28 VALORIZACION N° 08 JULIO‐2022 19/09/2022 736,249.27 21/09/2022

VAL.NRO 01, DE ADICIONAL DE OBRA


E001‐29
NRO.02 ,AGOSTO
23/09/2022 1,605,187.71 3/10/2022

E001‐30 VALORIZACION N° 09 AGOSTO‐2022 23/09/2022 369,178.95 24/10/2022

VAL. DE ADICIONAL DE OBRA NRO.02 ,MES


E001‐35
DE SETIEMBRE
25/10/2022 423,070.19 28/10/2022

VAL. DE ADICIONAL DE OBRA NRO.02 ,MES


E001‐37
DE SETIEMBRE
26/10/2022 211,851.40 28/10/2022

VAL. DE ADICIONAL DE OBRA NRO.02 ,MES


E001‐41
DE SETIEMBRE 22
3/11/2022 25,510.10 7/11/2022

VAL. DE ADICIONAL DE OBRA NRO.02 ,MES


E001‐57
DE SETIEMBRE 22
4/18/2023 197,690.60 7/11/2022

VAL. DE ADICIONAL DE OBRA NRO.02 ,MES


E001‐58
DE SETIEMBRE 22
6/26/2023 161,002.27 7/11/2022

VALORIZACION N° 10 SEPTIEMBRE‐2022 Septiembre 2022 147,958.90

VALORIZACION N° 11 OCTUBRE‐2022 Oct-22 176,491.09

VALORIZACION N° 12 NOVIEMBRE‐2022 Nov-22 1,243,564.09

VALORIZACION N° 13 DICIEMBRE‐2022 Dec-22 142,662.95

TOTAL S/. 10,804,950.46 S/. 2,624,312.27


RESUMEN DE VALORIZACIONES TRAMITADAS

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR


´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)
MONTO CONTRATO S/. 14,369,895.72 (CON IGV)

Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion Valorizacion
Valorizacion N°06
N°01 N°02 N°03 N°04 N°05 N°07 N°08 N°09 N°10 N°11 N°12 N°13 N°14

Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Aug-23

COSTO DIRECTO 61,334.50 524,912.96 1,193,667.79 567,060.15 298,545.30 681,827.82 619,447.51 313,519.09 304,946.36 129,603.76 448,325.44 1,089,835.77 258,986.25 17,588.63

GASTOS GENERALES 4,842.13 41,439.93 94,235.64 44,767.29 23,569.04 53,827.78 48,903.08 24,751.17 24,074.38 10,231.74 35,393.63 86,038.49 20,446.00 1,388.56

UTILIDAD 4,293.42 36,743.91 83,556.75 39,694.21 20,898.17 47,727.95 43,361.33 21,946.34 21,346.25 9,072.26 31,382.78 76,288.50 18,129.04 1,231.20

PARCIAL 70,470.05 603,096.80 1,371,460.18 651,521.65 343,012.51 783,383.55 711,711.92 360,216.60 350,366.99 148,907.76 515,101.85 1,252,162.76 297,561.29 20,208.39

IGV 12,684.61 108,557.42 246,862.83 117,273.90 61,742.25 141,009.04 128,108.15 64,838.99 63,066.06 26,803.40 92,718.33 225,389.30 53,561.03 3,637.51

TOTAL 83,154.66 711,654.22 1,618,323.01 768,795.55 404,754.76 924,392.59 839,820.07 425,055.59 413,433.05 175,711.16 607,820.18 1,477,552.06 351,122.32 23,845.90
Avance Físico
REAL 0.58% 4.95% 11.26% 5.35% 2.82% 6.43% 5.84% 2.96% 2.88% 1.22% 4.23% 10.28% 2.44% 61.25%
Avance Acumulado 0.58% 5.53% 16.79% 22.14% 24.96% 31.39% 37.24% 40.19% 43.07% 44.29% 48.52% 58.81% 61.25% 122.50%
MONTO
FACTURADO 74,839.20 640,488.80 1,456,490.71 691,916.00 364,279.29 831,953.31 707,774.50 736,249.27 369,178.95 150,192.90 176,491.09 176,491.09 377,668.46 19,764.88
AVANCE FISICO Y ECONOMICO DE LA OBRA
VALORIZACION DE OBRA N° 14

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR


´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
MONTO CONTRATO S/. 14,369,895.72 (CON IGV)
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)

1.00 VALORIZACIONES

AMORTIZACION AMORTIZACION
Avance Físico VALORIZACION MONTO
Nº MES Monto Ejecutado DEL ADELANTO EN DEL ADELANTO DE REAJUSTES IGV (18%)
REAL NETA FACTURADO
EFECTIVO MATERIALES

1.00 Oct-21 70,470.05 0.58% (7,047.00) - 6,342.30 63,423.05 11,416.15 74,839.20


2.00 Nov-21 603,096.80 4.95% (60,309.68) - 62,722.07 542,787.12 97,701.68 640,488.80
3.00 Dec-21 1,371,460.18 11.26% (137,146.02) - 148,117.70 1,234,314.16 222,176.55 1,456,490.71
4.00 Jan-22 651,521.65 5.35% (65,152.16) - 63,849.12 586,369.49 105,546.51 691,916.00
5.00 Feb-22 343,012.51 2.82% (34,301.25) - 38,760.41 308,711.26 55,568.03 364,279.29
6.00 May-22 783,383.55 6.43% (78,338.35) - 139,442.27 705,045.20 126,908.14 831,953.32
7.00 Jun-22 711,711.92 5.84% (71,171.19) (60,874.38) 142,342.38 579,666.35 104,339.94 707,774.50
8.00 Jul-22 360,216.60 2.96% (78,523.11) (82,767.96) 73,484.19 198,925.53 35,806.60 736,249.27
9.00 Aug-22 350,366.99 2.88% (35,036.70) (2,466.77) 81,285.14 312,863.52 56,315.43 369,178.95
10.00 Sep-22 148,907.76 1.22% (14,890.78) (6,734.86) 32,908.61 127,282.12 22,910.78 150,192.90
11.00 Oct-22 515,101.85 4.23% (51,510.18) (3,562.31) 121,048.93 460,029.36 82,805.28 176,491.09
12.00 Nov-22 1,252,162.76 10.28% (125,216.28) (73,078.61) 294,258.25 1,053,867.87 189,696.22 1,243,564.09
13.00 Dec-22 297,561.29 2.44% (29,756.13) (12,020.38) 64,273.24 255,784.78 46,041.26 377,668.46
14.00 Aug-23 20,208.39 0.17% (2,020.84) (1,437.65) 3,718.34 16,749.90 3,014.98 19,764.88
MONTO ACUMULADO 7,479,182.30 61.42% S/. 7,840,851.45
SALDO POR VALORIZAR 4,698,695.50 38.58%
MONTO A FACTURAR PRESENTE MES S/. 19,764.88

2.00 ADELANTOS OTORGADOS

Nº DESCRIPCION MONTO CON IGV

1.00 ADELANTO DIRECTO 1,436,989.57

2.00 ADELANTO DE MATERIALES 1,266,136.38

MONTO TOTAL S/. 2,703,125.95

2.00 RETENCION

Nº DESCRIPCION MONTO CON IGV

1.00 ADELANTO DE FIEL CUMPLIMIENTO 1,855,380.75

MONTO TOTAL S/. 1,855,380.75


DETALLE DE PROGRAMACION PARA EL MES ACTUAL A VALORIZAR
VALORIZACION DE OBRA N° 14

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR


´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)
MONTO CONTRATO S/. 14,369,895.72 (CON IGV)

METRADO MES
ITEM DESCRIPCION INICIO FIN OBSERVACION
ENERO
CONFORMACION DE TERRAPLENES CON DICIEMBRE SE VALORIZO DEL 8+020 AL 9+00 Y
02.04.00 0.00 M3 09+000 KM 13+000 KM
MATERIAL PROPIO TRAMO DEL 20+00 AL 22+00

03.00.00 PAVIMENTOS

03.01.00 SUB-BASE GRANULAR 468.78 M3 05+800 KM 07+500 KM

07+700 KM 09+000 KM

21+300 KM 22+528 KM

TRAMO EN CONSULTA 22+528 KM 22+598 KM SUPERPOSICION DE PROYECTOS 70ML

04.00.00 TRANSPORTE

TRANSPORTES DE MATERIAL PARA AFIRMADO EN DICIEMBRE SE VALORIZO DEL KM 5+800 AL


04.01.00 0.00 M3K 08+000 KM 13+000 KM
HASTA 1 KM 8+000
TRANSPORTE DE MATERIAL PARA AFIRMADO EN DICIEMBRE SE VALORIZO DEL KM 5+800 AL
04.02.00 0.00 M3K 08+000 KM 13+000 KM
DESPUES DE 1 KM 8+000

TRANSPORTES DE MATERIAL EXCEDENTE HASTA SE VALORIZARA LOS TRAMOS DE CORTE DE


04.03.00 0.00 M3K
<= 1 KM MS, RS Y RF QUE SE VALORIZO EN DICIEMBRE

SE VALORIZARA LOS TRAMOS DE CORTE DE


04.04.00 TRANSPORTES DE MATERIAL EXCEDENTE > 1 KM 0.00 M3K
MS, RS Y RF QUE SE VALORIZO EN DICIEMBRE

05.00.00 OBRAS DE ARTE Y DRENAJE

05.02.00 ALCANTARILLAS

05.02.01 LIMPIEZA DE TERRENO MANUAL 0.00 M2

05.02.02 TRAZO Y REPLANTEO 0.00 M2

05.02.03 EXCAVACION PARA ESTRUCTURAS C/MAQUINA 0.00 M3

05.02.04 RELLENO COMPACTADO PARA ESTRUCTURAS 0.00 M3 ALCANTARILLAS A EJECUTAR


KM 16+370
05.02.05 SOLADO 4" 0.00 M3 KM 18+868
KM 21+123
05.02.06 CONCRETO F'C=210 KG/CM2 0.00 M3 KM 21+587

05.02.07 ENCOFRADO Y DESENCOFRADO 0.00 M2

05.02.08 EMBOQUILLADO DE PIEDRA 0.00 M3

05.02.09 ALCANTARILLA TMC D=60" 0.00 M


DETALLE DE PROGRAMACION PARA EL MES ACTUAL A VALORIZAR
VALORIZACION DE OBRA N° 14

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR


´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)
MONTO CONTRATO S/. 14,369,895.72 (CON IGV)

METRADO MES
ITEM DESCRIPCION INICIO FIN OBSERVACION
ENERO

05.04.00 MUROS DE CONTENCIÓN

05.04.01 MUROS DE CONCRETO SIMPLE

05.04.01.01TRABAJOS PRELIMINARES

05.04.01.01TRAZO Y REPLANTEO 0.00 M2

05.04.01.01LIMPIEZA DE TERRENO MANUAL 0.00 M2


MURO DE CONTENCION
05.04.01.02MOVIMIENTO DE TIERRAS MC-01
KM 3+340
05.04.01.02EXCAVACION MANUAL 0.00 M3 LONG. 5.00M
ANCHO 2.00M
ALTURA 3.00M
05.04.01.02NIVELACION Y APISONADO 0.00 M2
MC-02
05.04.01.02RELLENO CON MATERIAL PROPIO 0.00 M3 KM 11+040
LONG 15.00M
05.04.01.03CONCRETO SIMPLE ANCHO 2.25M
ALTURA 3.50M
05.04.01.03CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. 0.00 M3

05.04.01.03ENCOFRADO Y DESENCOFRADO 0.00 M2

05.04.01.03CURADO DE CONCRETO 0.00 M2

05.04.01.04OTROS

05.04.01.04TUBERIA PARA DRENAJE 0.00 M

EVALUACION DEL AVANCE VALORIZADO RESPECTO AL PROGRAMADO

PRESUPUESTO MONTO TOTAL MONTO AVANCE ACUMULADO


X PRESUPUESTO VALORIZADO PROGRAMADO
OBRA PRINCIPAL 19,549,670.30 3,181,927.44 3,181,927.45

TOTAL (Sin IGV) 19,549,670.30 3,181,927.44 3,181,927.45


16.276% 16.276%

Situacion de Obra S/.3,181,927.44 < S/.3,181,927.45 ==> Atrasada


0.000%

Conclusion :

Como el monto de la valorizacion acumulado ejecutada es mayor que el 80% del monto de la valorizacion acumulada
programada, la obra se encuentra dentro del atraso permisible, por lo que no es necesario que el contratista presente el
calendario acelerado de avance de obra (CAAO)
EVALUACION DEL AVANCE VALORIZADO RESPECTO AL PROGRAMADO
VALORIZACION DE OBRA N° 14

OBRA MEJORAMIENTO DEL CAMINO VECINAL LA PALMA-CONCHAN-LA LEGUA-TACABAMBA-CHUGUR


´-ANGUIA-RODEOPAMPA-GUINEAMAYO, DISTRITOS DE CONCHAN-TACABAMBA-ANGUIA,
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANGUIA
CONTRATISTA CONSORCIO MDJH CONFORMADO POR IBEVIAL S.A. Y GRUPO CONSTRUCTOR PARASOL S.A.C.
SUPERVISOR CONTADORES E INGENIEROS ASOCIADOS SOCIEDAD COMERCIAL DE RESPONSABILIDAD LIMITADA
MONTO CONTRATO S/. 12,177,877.73 (SIN IGV)
MONTO CONTRATO S/. 14,369,895.72 (CON IGV)

SITUACION DE LA OBRA
MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS
PERIODO PERIODO
ACUM. (A) PARCIAL ACUM. ACUM. (A) PARCIAL ACUM. OBRA %

Oct-21 - 0.000% 0.000% Oct-21 - 0.000% 0.000% 0.000%


Oct-21 83,154.66 0.425% 0.425% Oct-21 83,154.66 0.425% 0.425% ADELANTADA 0.000%
Nov-21 794,808.88 3.640% 4.066% Nov-21 794,808.88 3.640% 4.066% ADELANTADA 0.000%
Dec-21 2,413,131.90 8.278% 12.344% Dec-21 2,413,131.89 8.278% 12.344% ATRASADA 0.000%
Jan-22 3,181,927.45 3.933% 16.276% Jan-22 3,181,927.44 3.933% 16.276% ATRASADA 0.000%
Feb-22 3,586,682.21 2.070% 18.347% Feb-22 3,586,682.20 2.070% 18.347% ATRASADA
May-22 4,581,380.25 5.088% 23.435% May-22 4,511,074.79 4.728% 23.075% ATRASADA
Jun-22 6,748,731.53 11.086% 34.521% Jun-22 5,350,894.86 4.296% 27.371% ATRASADA
Jul-22 10,700,838.84 20.216% 54.737% Jul-22 5,775,950.45 2.174% 29.545% ATRASADA

EVALUACION DEL AVANCE VALORIZADO RESPECTO AL PROGRAMADO

PRESUPUESTO MONTO TOTAL MONTO AVANCE ACUMULADO


X PRESUPUESTO VALORIZADO PROGRAMADO VERIFICACION SI REQUIERE CALENDARIO ACELERADO (ART. 205 DEL RLCE)
OBRA PRINCIPAL 19,549,670.30 3,181,927.44 3,181,927.45
a.- Monto Valorizacion Acumulado Programado S/. 3,181,927.45
c.- Monto Tope acum 80% (Numeral 13.0 Bases del proceso selección) S/. 2,545,541.96
d.- Monto Tope acum 80% (Articulo N°173 del RLCE) S/. 2,545,541.96
TOTAL (Sin IGV) 19,549,670.30 3,181,927.44 3,181,927.45 e.- Monto Valorizacion Acumulado Ejecutado S/. 3,181,927.44
16.276% 16.276%
Analizando se tiene que:
Situacion de Obra S/.3,181,927.44 < S/.3,181,927.45 ==> Atrasada
0.000% ( d ) > ( c ) => S/.3,181,927.44 > S/.2,545,541.96

Conclusion :

Como el monto de la valorizacion acumulado ejecutada es mayor que el 80% del monto de la valorizacion acumulada programada, la
obra se encuentra dentro del atraso permisible, por lo que no es necesario que el contratista presente el calendario acelerado de
avance de obra (CAAO)