CRONOGRAMA DE EJECUCION DEL PROYECTO

Id No mbre Dur ación mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7 mes 8
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S
1 MEJ ORAMIENTO Y AMPLIACION DEL S ERVICIO DE A GUA EN EL SIS TEMA DE RIEGO PHARA EN 240 días
LA LOCALIDAD DE UBINAS, DISTRITO DE UBINAS, PROVINCIA GENERA L SA NCHEZ CERRO,
REGION MOQUEGUA
2 OBRAS PROVISIONA LES Y COMPLEMENTARIAS 50 días
3 OBRAS PROVIS IONA LES 3 días
4 CAMPAMENTO CON SISTEMA D E ALBERGUES REUS ABLES (02 MODULOS PARA 70 1 día
PERSONAS)
5 CASETA DE GUARDIANIA MOVIL CON SISTEMA DE ALBERGUES REUSABLES 2 día s
6 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M 2 día s
7 TRABAJ OS PRELIMINARES Y COMPLEMENTA RIOS 47 días
8 MOVILIZ ACION Y DESMOVILIZACION D E EQUIPO 2 día s
9 APERTURA DE CAMINOS DE ACCESO C/MAQUINA RIA 20 días
10 MEJORAMIENTO DE ACCESOS EXISTENTES C/MAQUINARIA 8 día s
11 APERTURA DE CAMINOS DE ACCESO MANUAL 25 días
12 TRASLADO DE MATERIAL EN SEMOVIENTE 1 día
13 FLETE TERRESTRE 20 días
14 BOCATOMA-DISIPA DOR- DESA RENA DOR 45 días
15 TRABAJ OS PRELIMINARES 1 día
16 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
17 MOVIMIENTO DE TIERRAS 38 días
18 CORTE SUPERFICIAL DE MAT. NO CLASIFICAD O C/MAQUINARIA 3 día s
19 EXCAVACION C/MAQUINARIA H ASTA 2.00M 14 días
20 PERF ILADO D E S UBRASANTE PARA CIMENTACION 3 día s
21 RELLENO COMPACTADO CON MA TERIAL PROPIO 4 día s
22 ELIMINACION MATERIAL EXCED ENTE H ASTA 30.00 MT (A MANO USANDO CARRETILLA) 14 días
23 ENROCADO DE PROTECCION DE CAUCE 1 día
24 OBRAS DE CONCRETO SIMPLE 6 días
25 SOLAD O DE CONCRETO fy =100 kg/cm2 3 día s
26 CONCRETO FC=140 KG/CM2 +50% P.G. 2 día s
27 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 1 día
28 OBRAS DE CONCRETO ARMADO 22 días
29 ZAPATAS 13 días
30 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 5 día s
31 ACERO FY 4200 Kg/cm2 8 día s
32 MURO DE CONTENCION 14 días
33 CONCRETO F'C= 210 KG/CM2. EN MUROS C/ADITIVO IMPERMEABILIZANTE 3 día s
34 ENCOFRADO Y DESENCOFRAD O CARAVISTA 8 día s
35 ACERO FY 4200 Kg/cm2 5 día s
36 BARRAJE Y CAMARA AMOTIGUADORA 6 días
37 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 2 día s
38 ENCOFRADO Y DESENCOFRAD O CARAVISTA 2 día s
39 ACERO FY 4200 Kg/cm2 2 día s
40 DES ARENADOR Y CANAL DE LIMPIA 7 días
41 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 3 día s
42 ENCOFRADO Y DESENCOFRAD O CARAVISTA 4 día s
43 ACERO FY 4200 Kg/cm2 2 día s
44 REVOQUES Y ENLUCIDOS 2 días
45 SOLAQUEADO DE OBRAS DE ARTE 2 día s
46 CURADO DE CONCRETO CON ADITIVO ANTISOL 2 día s
47 VARIOS 2 días
48 WATER STOP DE PVC DE 8" PROVISION Y COLOCACION 1 día
49 SELLO DE JUNTA S FLEXIBLES EPOXICAS 1 día
50 REJILLA EN LA VENTANA DE CAPTACION (.2*1.15 M) 1 día
51 COMPUERTAS TIPO ARMCO O SIMILAR 1.00x0.70 M CON SISTEMA D E IZAJ E 1 día
52 COMPUERTAS TIPO ARMCO O SIMILAR 0.70x0.65 M CON SISTEMA D E IZAJ E 1 día
53 COMPUERTAS TIPO ARMCO O SIMILAR 0.40x0.65 M CON SISTEMA D E IZAJ E 1 día
54 TUBOS PVC 3" PA RA VENTILA CION 1 día
55 DES ARENADOR 27 días
56 TRABAJ OS PRELIMINARES 2 días
57 LIMPIEZA Y DESBROCE DE ARBUSTOS 1 día
58 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
59 MOVIMIENTO DE TIERRAS 23 días
60 EXCAVACION Z ANJ AS EN ROCA SUELTA 9 día s
61 REFINE Y NIVELACION CAJA DE CANAL EN TERRENO ROCA S UELTA 1 día
62 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 2 día s
63 ELIMINACION MATERIAL EXCED ENTE H ASTA 30.00 MT (A MANO USANDO CARRETILLA) 14 días
64 OBRAS DE CONCRETO SIMPLE 4 días
65 SOLAD O DE CONCRETO fy =100 kg/cm2 1 día
66 CONCRETO FC=140 KG/CM2 +30% P.M. 1 día
67 CONCRETO SIMPLE FC=175 KG/CM2 + 30% P.M. 1 día
68 ENCOFRADO Y DESENCOF RAD O CARAVISTA 2 día s
69 OBRAS DE CONCRETO ARMADO 11 días
70 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 2 día s
71 ENCOFRADO Y DESENCOF RAD O CARAVISTA 6 día s
72 ACERO FY 4200 Kg /cm2 5 día s
73 REVOQUES Y ENLUCIDOS 2 días
74 SOLAQUEADO DE OBRAS DE ARTE 2 día s
75 CURADO DE CONCRETO CON ADITIVO ANTISOL 1 día
76 CA RPINTERIA METALICA 1 día
77 COMPUERTAS TIPO ARMCO O SIMILAR 0.40x0.65 M CON SISTEMA D E IZAJ E 1 día
78 VARIOS 1 día
79 JUNTAS WATER STOP DE 6" PROVISION Y COLOCACION 1 día
80 SELLO DE JUNTA S FLEXIBLES EPOXICAS 1 día
81 CA NAL PHARA Y OBRAS DE ARTE 185 días
82 CA NAL DE CONCRETO SIMPLE 132 días
83 TRABAJ OS PRELIMINARES 28 días
84 LIMPIEZA Y DESBROCE DE ARBUSTOS 24 días
85 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR 3 día s
86 CONTROL TOPOGRA FIA DURA NTE LA OBRA 4 día s
87 MOVIMIENTO DE TIERRAS 65 días
88 EXCA VACION CAJ A CANAL EN MATERIAL PIROCLASTICO 38 días
89 EXCA VACION ZANJ AS EN ROCA SUELTA 24 días
90 REFINE Y NIVELACION CAJA DE CANAL EN TERRENO ROCA S UELTA 13 días
91 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 18 días
92 ELIMINACION MATERIAL EXCED ENTE HASTA 30.00 MT (A MANO USANDO 27 días
CARRETILLA)
93 OBRAS DE CONCRETO SIMPLE 35 días
94 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 21 días
95 ENCOFRADO Y DESENCOFRAD O CARAVISTA EN CANALES 24 días
96 REVOQUES Y ENLUCIDOS 16 días
97 SOLAQUEADO DE OBRAS DE CANAL 16 días
98 CURADO DE CONCRETO CON ADITIVO ANTISOL 5 día s
99 OTROS 132 días
100 JUNTAS ASFALTICAS EN JUNTA DE DILATA CIÓN MUROS 14 días
101 JUNTAS DE CONSTRUCCION CON TEKNOPORT 14 días
102 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) 12 días
103 CA NAL DE CONDUCCION CON TUBERIA 134 días
104 TRABAJ OS PRELIMINARES 21 días
105 LIMPIEZA Y DESBROCE DE ARBUSTOS 15 días
106 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR 4 día s
107 CONTROL TOPOGRA FIA DURA NTE LA OBRA 6 día s
108 MOVIMIENTO DE TIERRAS 119 días
109 EXCA VACION ZANJ AS EN MA TERIAL SUELTO 59 días
110 EXCA VACION ZANJ AS EN ROCA SUELTA 13 días
111 RELLENO CON MA TERIAL PROPIO PARA CONFORMACION D E TALUDES 23 días
112 REFINE PERFILADO Y NIVELACION DE FONDO PARA TUBERIAS 20 días
113 CAMA DE APOYO PARA TUBERIAS 20 días
114 RELLENO COMPACTADO CON MATERIAL ZARANDEAD O 19 días
115 ELIMINACION MATERIAL EXCED ENTE HASTA 30.00 MT (A MANO USANDO 34 días
CARRETILLA)
116 TUBERIA Y PRUEBA HIDRAULICA 40 días
117 PROV. E INSTALACION TUBERIA P.V.C. 400 mm 10 días
118 PROV. E INSTALACION TUBERIA P.V.C. 355 mm 23 días
119 PRUEBA H ID RAULICA DE TUBERIA PERF ILAD A 5 día s
120 CA NOAS 55 días
121 TRABAJ OS PRELIMINARES 2 días
122 TRAZO Y REPLANTEO DE ESTRUCTURAS 1 día
123 LIMPIEZA Y DESBROCE DE ARBUSTOS 2 día s
124 MOVIMIENTO DE TIERRAS 21 días
125 EXCA VACION PARA ESTRUCTURAS 18 días
126 ELIMINACION MATERIAL EXCED ENTE HASTA 30.00 MT (A MANO USANDO 11 días
CARRETILLA)
127 OBRAS DE CONCRETO SIMPLE 20 días
128 SOLAD O DE CONCRETO f y=100 kg/cm2 1 día
129 CONCRETO F'C=140 KG/CM2 5 día s
130 ENCOFRADO Y DESENCOFRAD O CARAVISTA 19 días
131 ENROCADO DE PROTECCION DE CAUCE 1 día
132 OBRAS DE CONCRETO ARMADO 15 días
133 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 3 día s
134 ENCOFRADO Y DESENCOFRAD O CARAVISTA 10 días
135 ACERO FY 4200 Kg/cm2 4 día s
136 REVOQUES Y ENLUCIDOS 14 días
137 SOLAQUEADO DE OBRAS DE ARTE 14 días
138 CURADO DE CONCRETO CON ADITIVO ANTISOL 4 día s
139 CA JAS DE INS PECCION 23 días
140 TRABAJ OS PRELIMINARES 1 día
141 TRAZO Y REPLANTEO DE ESTRUCTURAS 1 día
142 MOVIMIENTO DE TIERRAS 21 días
143 EXCA VACION PARA ESTRUCTURAS 9 día s
144 REFINE Y NIVELACION D E F ONDOS DE CAJA 1 día
145 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 2 día s
146 OBRAS DE CONCRETO SIMPLE 1 día
147 SOLAD O DE CONCRETO f y=100 kg/cm2 1 día
148 OBRAS DE CONCRETO ARMADO 10 días
149 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 1 día
150 ENCOFRADO Y DESENCOFRAD O CARAVISTA 8 día s
151 ACERO FY 4200 Kg/cm2 2 día s
152 REVOQUES Y ENLUCIDOS 2 días
153 SOLAQUEADO DE OBRAS DE ARTE 2 día s
154 CURADO DE CONCRETO CON ADITIVO ANTISOL 1 día
155 TOMAS LATERALES 35 días
156 TRABAJ OS PRELIMINARES 1 día
157 LIMPIEZA Y DESBROCE DE ARBUSTOS 1 día
158 TRAZO Y REPLANTEO DE ESTRUCTURAS 1 día
159 MOVIMIENTO DE TIERRAS 30 días
160 EXCA VACION PARA ESTRUCTURAS 16 días
161 REFINE Y NIVELACION D E F ONDOS DE CAJA 3 día s
162 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 4 día s
163 ELIMINACION MATERIAL EXCED ENTE HASTA 30.00 MT (A MANO USANDO 2 día s
CARRETILLA)
164 OBRAS DE CONCRETO ARMADO 12 días
165 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 2 día s
166 ENCOFRADO Y DESENCOFRAD O CARAVISTA 10 días
167 ACERO FY 4200 Kg/cm2 6 día s
168 CA RPINTERIA METALICA 8 días
169 COMPUERTA METALICA TIPO TARJETA 0.40x0.40 M 8 día s
170 REVOQUES Y ENLUCIDOS 6 días
171 SOLAQUEADO DE OBRAS DE ARTE 6 día s
172 CURADO DE CONCRETO CON ADITIVO ANTISOL 4 día s
173 CA JAS DE CAMBIO DE DIRECCION 52 días
174 TRABAJ OS PRELIMINARES 1 día
175 TRAZO Y REPLANTEO DE ESTRUCTURAS 1 día
176 MOVIMIENTO DE TIERRAS 50 días
177 EXCA VACION PARA ESTRUCTURAS 18 días
178 REFINE Y NIVELACION D E F ONDOS DE CAJA 7 día s
179 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 11 días
180 OBRAS DE CONCRETO SIMPLE 2 días
181 SOLAD O DE CONCRETO f y=100 kg/cm2 2 día s
182 OBRAS DE CONCRETO ARMADO 29 días
183 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 9 día s
184 ENCOFRADO Y DESENCOFRAD O CARAVISTA 15 días
185 ACERO FY 4200 Kg/cm2 14 días
186 REVOQUES Y ENLUCIDOS 7 días
187 SOLAQUEADO DE OBRAS DE ARTE 7 día s
188 CURADO DE CONCRETO CON ADITIVO ANTISOL 6 día s
189 CA MARA DE IMPACTO TIPO I 44 días
190 TRABAJ OS PRELIMINARES 1 día
191 TRAZO Y REPLANTEO DE ESTRUCTURAS 1 día
192 MOVIMIENTO DE TIERRAS 41 días
193 EXCA VACION PARA ESTRUCTURAS 18 días
194 REFINE Y NIVELACION D E F ONDOS DE CAJA 4 día s
195 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 6 día s
196 OBRAS DE CONCRETO SIMPLE 1 día
197 SOLAD O DE CONCRETO f y=100 kg/cm2 1 día
198 OBRAS DE CONCRETO ARMADO 22 días
199 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 6 día s
200 ENCOFRADO Y DESENCOFRAD O CARAVISTA 19 días
201 ACERO FY 4200 Kg/cm2 7 día s
202 REVOQUES Y ENLUCIDOS 6 días
203 SOLAQUEADO DE OBRAS DE ARTE 6 día s
204 CURADO DE CONCRETO CON ADITIVO ANTISOL 4 día s
205 CA MARA DE IMPACTO TIPO II 36 días
206 TRABAJ OS PRELIMINARES 1 día
207 TRAZO Y REPLANTEO DE ESTRUCTURAS 1 día
208 MOVIMIENTO DE TIERRAS 33 días
209 EXCA VACION PARA ESTRUCTURAS 17 días
210 REFINE Y NIVELACION D E F ONDOS DE CAJA 2 día s
211 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 5 día s
212 OBRAS DE CONCRETO SIMPLE 1 día
213 SOLAD O DE CONCRETO f y=100 kg/cm2 1 día
214 OBRAS DE CONCRETO ARMADO 15 días
215 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 6 día s
216 ENCOFRADO Y DESENCOFRAD O CARAVISTA 12 días
217 ACERO FY 4200 Kg/cm2 6 día s
218 REVOQUES Y ENLUCIDOS 4 días
219 SOLAQUEADO DE OBRAS DE ARTE 4 día s
220 CURADO DE CONCRETO CON ADITIVO ANTISOL 3 día s
221 ALIVIA DEROS 67 días
222 TRABAJ OS PRELIMINARES 4 días
223 LIMPIEZA Y DESBROCE DE ARBUSTOS 4 día s
224 TRAZO Y REPLANTEO DE ESTRUCTURAS 2 día s
225 MOVIMIENTO DE TIERRAS 52 días

Tarea Divisió n Hito Atraso Resu men Resumen del p royecto Tarea cr ítica resumida División crítica resumida Tar eas ext ernas Hito externo Tarea inactiva Hit o inactivo Resu men inactivo Tar ea man ual Sólo du ració n Informe de resumen man ual Resum en manual Sólo el comienzo Só lo fin Fecha límite Tareas críticas División crít ica Línea base Pro greso
CRONOGRAMA DE EJECUCION DEL PROYECTO
Id No mbre Dur ación mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7 mes 8
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S
226 EXCA VACION PARA ESTRUCTURAS 29 días
227 REFINE Y NIVELACION D E F ONDOS DE CAJA 12 días
228 RELLENO COMPACTADO PARA ESTRUCTURAS CON MA TERIAL PROPIO 13 días
229 ELIMINACION MATERIAL EXCED ENTE HASTA 30.00 MT (A MANO USANDO 17 días
CARRETILLA)
230 OBRAS DE CONCRETO SIMPLE 1 día
231 SOLAD O DE CONCRETO f y=100 kg/cm2 1 día
232 OBRAS DE CONCRETO ARMADO 22 días
233 CA NAL RAPIDA 17 días
234 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 4 día s
235 ENCOFRADO Y DES ENCOFRA DO CA RAVISTA 13 días
236 POZA DIS IPADORA 15 días
237 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 8 día s
238 ENCOFRADO Y DES ENCOFRA DO CA RAVISTA 13 días
239 REVOQUES Y ENLUCIDOS 8 días
240 SOLAQUEADO DE OBRAS DE ARTE 8 día s
241 CURADO DE CONCRETO CON ADITIVO ANTISOL 3 día s
242 VARIOS 7 días
243 JUNTAS WATER STOP DE 6" PROVIS ION Y COLOCACION 7 día s
244 SELLO DE JUNTAS FLEXIBLES EPOXICAS 3 día s
245 ACUEDUCTOS 53 días
246 OBRAS PROVIS IONA LES 1 día
247 LIMPIEZA Y DESBROCE DE ARBUSTOS 1 día
248 TRABAJ OS PRELIMINARES 1 día
249 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
250 MOVIMIENTO DE TIERRAS 43 días
251 EXCAVACION PARA ESTRUCTURAS 30 días
252 RELLENO GENERAL COMPACTADO CON MATERIAL PROPIO 1 día
253 OBRAS DE CONCRETO SIMPLE 4 días
254 CONCRETO SIMPLE FC=175 KG/CM2 + 30% P.M. 2 día s
255 ENCOFRADO Y DESENCOF RAD O CARAVISTA 3 día s
256 REVOQUES Y ENLUCIDOS 1 día
257 TARRAJEO DE MUROS 1 día
258 TUBERIA Y A CCESORIOS 4 días
259 SUMINIS TRO E INSTALACION TUBERIA HD PE Ø=400mm 2 día s
260 SOLDA DURA P/TERMOFUSION TUBERIA HDPE Ø 400 mm (Tubos de 12 M) 2 día s
261 ESTRUCTURA DE ACUEDUCTO 14 días
262 PERF IL METALICO, INCLUYE SUMINIS TRO Y COLOCACION KM 2+610 4 día s
263 PERF IL METALICO, INCLUYE SUMINIS TRO Y COLOCACION KM 5+910 4 día s
264 PERF IL METALICO, INCLUYE SUMINIS TRO Y COLOCACION KM 7+100 4 día s
265 ACCESORIOS VARIOS PARA ACUEDUCTO 4 día s
266 ABRAZ ADERA PREFABRICAD O PARA ANCLAJE DE TUBERIA EN PUENTE 14 días
267 BRIDA DE ACERO PARA SOLDAR Y EMPERNAR DE 16"(400MM) 3 día s
268 NEOPRENO 2 día s
269 PINTURA 4 días
270 PINTURA ESMALTE USO NAVAL EN ELEMENTOS METALICOS, COLOR NARANJA 4 día s
271 SIFON INVERTIDO Y ACUEDUCTO INFIERNILLO 52 días
272 TRABAJ OS PRELIMINARES 5 días
273 LIMPIEZA DE TERRENO MANUAL 5 día s
274 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
275 MOVIMIENTO DE TIERRAS 34 días
276 EXCAVACION PARA ESTRUCTURAS 26 días
277 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 6 día s
278 ELIMINACION MATERIAL EXCED ENTE H ASTA 30.00 MT (A MANO USANDO CARRETILLA) 2 día s
279 OBRAS DE CONCRETO SIMPLE 3 días
280 SOLAD O DE CONCRETO fy =100 kg/cm2 1 día
281 CONCRETO FC=140 KG/CM2 +25% P.M. CAMARA D E ANCLAJE 2 día s
282 OBRAS DE CONCRETO ARMADO 8 días
283 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 1 día
284 ENCOFRADO Y DESENCOF RAD O CARAVISTA 4 día s
285 ACERO FY 4200 Kg /cm2 3 día s
286 REVOQUES Y ENLUCIDOS 2 días
287 TARRAJEO DE COLUMNAS-S UPERFICIE 2 día s
288 VESTIDURA DE ARISTAS DE COLUMNAS 2 día s
289 SISTEMA DE ANCLAJE 8 días
290 TENDIDO DE CABLE DE ACERO TIPO BOA D=5/8" 3 día s
291 INSTALACION DE PENDOLA S DE ACERO LISO D=1/2" 3 día s
292 CAMARA DE ANCLAJE PRINCIPAL 1 día
293 ACCESORIOS VARIOS 1 día
294 PINTURA ESMALTE EN COLUMNAS 1 día
295 TUBERIA Y A CCESORIOS 12 días
296 SUMINIS TRO E INSTALACION TUBERIA HD PE Ø=200mm 12 días
297 SOLDA DURA P/TERMOFUSION TUBERIA HDPE Ø 200 mm (Tubos de 12 M) 7 día s
298 VARIOS 7 días
299 ABRAZ ADERAS EN DADOS DE ANCLAJE 7 día s
300 BRIDA DE ACERO PARA SOLDAR Y EMPERNAR DE 8"(200MM) 1 día
301 MEJORAMIENTO RES ERVORIO CURA BAYA 19 días
302 TRABAJ OS PRELIMINARES 6 días
303 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
304 DEMOLICION ESTRUCTURA DE CONCRETO 1 día
305 PICADO DE PISO INTERIOR DE RESERVORIO E= 2" 3 día s
306 ELIMINACION MATERIAL EXCED ENTE H ASTA 30.00 MT (A MANO USANDO CARRETILLA) 2 día s
307 RETIRO DE VALVULAS D ETERIORAD A 1 día
308 MOVIMIENTO DE TIERRAS 12 días
309 EXCAVACION PARA ESTRUCTURAS 1 día
310 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 1 día
311 OBRAS DE CONCRETO SIMPLE 3 días
312 SOLAD O DE CONCRETO fy =100 kg/cm2 1 día
313 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 1 día
314 ENCOFRADO Y DESENCOF RAD O CARAVISTA 1 día
315 OBRAS DE CONCRETO ARMADO 8 días
316 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 1 día
317 CONCRETO F'C= 210 KG/CM2 C/A DITIVO IMPERMEABILIZ ANTE 1 día
318 ENCOFRADO Y DESENCOF RAD O CARAVISTA 2 día s
319 ACERO FY 4200 Kg /cm2 4 día s
320 REVOQUES Y ENLUCIDOS 10 días
321 SOLAQUEADO DE OBRAS DE ARTE 1 día
322 CURADO DE CONCRETO CON ADITIVO ANTISOL 1 día
323 SISTEMA EPOXICO PARA PEGAR CONCRETO NUEVO A ANTIGUO 1 día
324 CA RPINTERIA METALICA 1 día
325 COMPUERTA METALICA TIPO TARJETA 0.40x0.40 M 1 día
326 REGLA GRADUAD A DE BRONCE 1 día
327 INSTALACIONES SANITARIAS 1 día
328 VALVULA COMPUERTA D E F IERRO FUND ID O BB DE 8" 1 día
329 TUBERIA DE PVC CLASE A-10 DE 8"(200MM)+ELEM. UNION+2%DESPER 1 día
330 CODO DE PVC PARA AGUA D E 8" 1 día
331 REJILLA METALICA CIRCULAR 1 día
332 CANASTILLA DE 8" 1 día
333 OTROS 2 días
334 PINTADO CON A NTICORROS IVO EPOXICO EN CARAS INTERIORES 2 día s
335 JUNTAS CON SELLO EPOXICO 1 día
336 RESERVORIO TA SSATA 36 días
337 TRABAJ OS PRELIMINARES 1 día
338 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
339 MOVIMIENTO DE TIERRAS 23 días
340 EXCAVACION MAS IVA 2 día s
341 EXCAVACION PARA ESTRUCTURAS 5 día s
342 EXCAVACION CAJ A CANAL EN MATERIAL PIROCLASTICO 2 día s
343 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 2 día s
344 OBRAS DE CONCRETO SIMPLE 6 días
345 SOLAD O DE CONCRETO fy =100 kg/cm2 2 día s
346 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 1 día
347 ENCOFRADO Y DESENCOF RAD O CARAVISTA 3 día s
348 OBRAS DE CONCRETO ARMADO 12 días
349 CONCRETO F'C= 210 KG/CM2 C/A DITIVO IMPERMEABILIZ ANTE 2 día s
350 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 1 día
351 ENCOFRADO Y DESENCOF RAD O CARAVISTA 4 día s
352 ACERO FY 4200 Kg /cm2 5 día s
353 REVOQUES 3 días
354 SOLAQUEADO DE OBRAS DE ARTE 3 día s
355 CURADO DE CONCRETO CON ADITIVO ANTISOL 2 día s
356 CA RPINTERIA METALICA 12 días
357 SUMINIS TRO E INSTALACION RESERVORIO TIPO ARMCO D E 1500 M3 10 días
358 COMPUERTA METALICA TIPO TARJETA 0.40x0.40 M 1 día
359 REGLA GRADUAD A DE BRONCE 1 día
360 INSTALACIONES SANITARIAS 9 días
361 VALVULA COMPUERTA D E F IERRO FUND ID O BB DE 8" 1 día
362 TUBERIA DE PVC CLASE A-10 DE 8"(200MM)+ELEM. UNION+2%DESPER 1 día
363 CODO DE PVC PARA AGUA D E 8" 1 día
364 REJILLA METALICA CIRCULAR 1 día
365 CANASTILLA DE 8" 1 día
366 OTROS 2 días
367 WATER STOP DE P.V.C. DE 9". PROVISION Y COLOCADO DE JUNTA EN MUROS 2 día s
368 JUNTAS CON SELLO EPOXICO 2 día s
369 JUNTAS ASFALTICAS 1 día
370 RESERVORIO JANACCHIMPA 34 días
371 TRABAJ OS PRELIMINARES 1 día
372 TRAZO Y REPLA NTEO DE ESTRUCTURAS 1 día
373 MOVIMIENTO DE TIERRAS 22 días
374 EXCAVACION MAS IVA 3 día s
375 EXCAVACION PARA ESTRUCTURAS 6 día s
376 EXCAVACION CAJ A DE CANAL 2 día s
377 RELLENO CON MATERIAL PROPIO 4 día s
378 OBRAS DE CONCRETO SIMPLE 5 días
379 SOLAD O DE CONCRETO fy =100 kg/cm2 2 día s
380 CONCRETO FC=175 KG/CM2 INC/ADITIVO INCORPORADOR DE AIRE 1 día
381 ENCOFRADO Y DESENCOF RAD O CARAVISTA 2 día s
382 OBRAS DE CONCRETO ARMADO 13 días
383 CONCRETO F'C= 210 KG/CM2 C/A DITIVO IMPERMEABILIZ ANTE 2 día s
384 CONCRETO F'C= 210 KG/CM2 INC/ADITIVOS 1 día
385 ENCOFRADO Y DESENCOF RAD O CARAVISTA 4 día s
386 ACERO FY 4200 Kg /cm2 6 día s
387 REVOQUES 2 días
388 SOLAQUEADO DE OBRAS DE ARTE 2 día s
389 CURADO DE CONCRETO CON ADITIVO ANTISOL 2 día s
390 CA RPINTERIA METALICA 9 días
391 SUMINIS TRO E INSTALACION RESERVORIO TIPO ARMCO D E 800 M3 7 día s
392 COMPUERTA METALICA TIPO TARJETA 0.40x0.40 M 1 día
393 REGLA GRADUAD A DE BRONCE 1 día
394 INSTALACIONES SANITARIAS 2 días
395 VALVULA COMPUERTA D E F IERRO FUND ID O BB DE 8" 1 día
396 TUBERIA DE PVC CLASE A-10 DE 8"(200MM)+ELEM. UNION+2%DESPER 1 día
397 CODO DE PVC PARA AGUA D E 8" 1 día
398 REJILLA METALICA CIRCULAR 1 día
399 CANASTILLA DE 8" 1 día
400 OTROS 3 días
401 WATER STOP DE P.V.C. DE 9". PROVISION Y COLOCADO DE JUNTA 1 día
402 JUNTAS CON SELLO EPOXICO 1 día
403 JUNTAS ASFALTICAS 1 día
404 DISEÑO DE MEZCLAS D E CONCRETO 1 día
405 PLAN DE MANEJO AMBIENTAL 202 días
406 PROGRAMA DE MEDIDAS PREVENTIVAS Y CORRECTIVA S 31 días
407 ELIMINACION DE RESIDUOS DE COMBUSTIBLE, LUBRICANTES Y OTROS 15 días
408 ACCIONES PREVENTIVAS , MITIGACION O CORRECCION 15 días
409 PROGRAMA DE S EGUIMIENTO Y MONITOREO AMBIENTA L 3 días
410 MONITOREO DE LA CALIDAD DEL AGUA 3 día s
411 MONITOREO DE LA CALIDAD DEL AIRE 3 día s
412 MONITOREO DE LOS NIVELES DE RUIDO 3 día s
413 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL 1 día
414 CAPACITACIÓN EN EDUCACION Y CONCIENTIZ ACION AMBIENTAL 1 día
415 PROGRAMA DE CONTINGENCIA 1 día
416 PLAN DE CONTINGENCIA 1 día
417 PROGRAMA DE ABA NDONO DE OBRA 1 día
418 RESTAURACION DE AREAS 1 día
419 PROGRAMA DE S EÑA LIZA CION AMBIENTAL 1 día
420 PROGRAMA DE IMPLEMENTACION Y COLOCACION DE LETREROS 1 día
421 PROGRAMA DE MANEJO ARQUEOLOGICO 1 día
422 PLAN DE MONITOREO ARQUEOLOGICO 1 día
423 PLAN DE SEGURIDAD Y SA LUD EN OBRA 2 días
424 ENTRENAMIENTO DE RECURSOS HUMANOS 1 día
425 ANALISIS DE RIES GOS Y PROCEDIMIENTO DE TRABAJ OS 1 día
426 SEÑALIZ ACION TEMPORAL DE ADVERTENCIA Y SEGURIDAD 1 día
427 ELEMENTOS D E PREVENCION 1 día
428 ELEMENTOS D E PROTECCION INDIVIDUAL 1 día
429 EXAMENES MED ICOS PREOCUPACIONALES ANTES, DURANTE Y DESPUES DE LA OBRA 1 día
430 IMPLEMENTACION DE REGIS TROS Y DOCUMENTA CION DE SISTEMA DE GESTION DE LA 1 día
SEGURIDAD Y SALUD EN EL TRABAJO
431 RECURSOS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO 1 día

Tarea Divisió n Hito Atraso Resu men Resumen del p royecto Tarea cr ítica resumida División crítica resumida Tar eas ext ernas Hito externo Tarea inactiva Hit o inactivo Resu men inactivo Tar ea man ual Sólo du ració n Informe de resumen man ual Resum en manual Sólo el comienzo Só lo fin Fecha límite Tareas críticas División crít ica Línea base Pro greso