CERCHA 1 6 unid
largos totales
elementos l parcial n° eementos n cerchas l total c 100 * 50 l 40 *3
Diagonales 1.15 4 6 27.6 - 27.6
tirante 9 1 6 54 54 -
vertical 2L 0.45 4 6 10.8 - 10.8
Diagonales 1.22 4 6 29.28 - 29.28
Diagonales 1.64 4 6 39.36 - 39.36
Diagonales 4.7 2 6 56.4 56.4 -
total(m] 110.4 107.04
total tiras 19 18
kg/mt 3.54 1.77
total kg 403.56 191.16
TOTAL KG 594.72
5% despuntes 29.736
TOTAL KG 624.456
CERCHA 2 4 unid
largos totales
elementos l parcial n° eementos n cerchas l total c 100 * 50 l 40 *3
diagonales 4.7 1 4 18.8 18.8 -
diagonales 2.61 1 4 10.44 10.44 -
vertical canal 0.75 1 4 3 3 -
tirante 6.5 1 4 26 26 -
vertical 2L 0.45 2 4 3.6 - 3.6
diagonales 1.15 2 4 9.2 - 9.2
diagonales 1.22 4 4 19.52 - 19.52
diagonales 1.64 4 4 26.24 - 26.24
total(m] 58.24 58.56
total tiras 10 10
kg/mt 3.54 1.77
total kg 212.4 106.2
TOTAL KG 318.6
5% despuntes 15.93
TOTAL KG 334.53
m kg/m kg tiras
arrostriamiento L50/3 40 2.24 94.08 7
cumbrera 100/50/3 11 6.6 79.2 2
total kg 173.28
5% despuntes 8.664
TOTAL KG 181.944
Resumen Cubicacion
kg
cercha c1 624.456
cercha c2 334.53
otros perfiles 181.944
total para 1 casa 1140.93
total para 20 casas 22818.6
casa 91 m2
mano de obra
soldador 0.1505 hd $158,334.00 $2,167,776.13
ayudante 0.0752 hd $71,047.00 $486,357.92
subtotal mano de obra $2,654,134.05
Lista de materiales