Está en la página 1de 5

m3 de Hojas totales

AVANCE DE OBRA 20,504.60


(Capas) Fecha 30 de agosto de 2023

TABLAROCAS Avance ponderado

CONTRATISTA Carvid-Acabados Rodriguez


8,166.29
m2 de muro
ensamble lijero
y total de
Tablaroca
32.44%
% de m2 de
CTGS
Planta Baja construcción de
muro terminado
0.00%
D= 32.44%
NIVEL POSTES FIBRA HOJAS PASTA PINTURA AVANCE GENERAL
15.73% 19.52% 46.33% 11.85% 6.57%

Nombre del % del TOTAL Total (M2)


Avance Avance
Total (M2) Avance (M2) Avance (%) Total (M2) Avance (M2) Avance (%) Total (M2) Avance (M2) Avance (%) Total (M2) Avance (M2) Avance (%) PONDERADO (%)
DEL TOTAL ACUMULADO
nivel (M2) (%) (%) (%)

1 PB DH1 36.00% 2,940.0 2,557.8 87% 2,940.0 2,557.8 87% 9,413.0 2,146.8 23% 2,940.0 2,557.8 87% 2,940.0 0.0 0% 52.00% 18.72% 18.72%
1 PB DH2 31.05% 2,536.0 2,206.3 87% 2,536.0 2,206.3 87% 8,401.3 0.0 0% 2,536.0 2,206.3 87% 2,536.0 0.0 0% 41.00% 12.73% 31.45%
1 PB DH3 32.94% 2,690.3 189.2 7% 2,690.3 189.2 7% 2,690.3 0.0 0% 2,690.3 189.2 7% 2,690.3 0.0 0% 3.00% 0.99% 32.44%
0.00% 32.44%
100.00% 8,166.3 8,166.3 20,504.6 8,166.3 8,166.3 32.44%

La información del documento es estrictamente confidencial, destinada exclusivamente para fines específicos que lo originan, su utilización con fines distintos será responsabilidad civil y/o penal de quien lo haga. 22:31:58
Planta Baja
Totales Avance
Tipo de N Area de Area de Area de Area de
Data Area
Muro hojas Hojas Postes Fibra Hojas
DH1 PR_MD_01 2,157.66 4 8,630.65 1,877.16 1,877.16 2,146.81
DH1 PR_ML_01 557.77 1 557.77 485.26 485.26
DH1 PR_ML_03 224.55 1 224.55 195.36 195.36
2,939.98 9,412.97 2,557.78 2,557.78 2,146.81

DH2 PR_MD_01 1,955.11 4 7,820.43 1,700.95 1,700.95


DH2 PR_ML_01 356.21 1 356.21 309.90 309.90
DH2 PR_ML_03 224.65 1 224.65 195.45 195.45
2,535.97 8,401.29 2,206.29 2,206.29 0.00

DH3 PR_MD_01 1,891.55 4 1,891.55 189.16 189.16


DH3 PR_ML_01 574.14 1 574.14
DH3 PR_ML_03 224.65 1 224.65
2,690.34 2,690.34 189.16 189.16 0.00

TOTAL 8,166.29 20,504.60 4,953.23 4,953.23 2,146.81


Avance %
Area de Area
Area Hojas
Pasta Pintura
1,877.16 87.00%
485.26 87.00%
195.36 87.00%
2,557.78 0.00 2.61

1,700.95 87.00%
309.90 87.00%
195.45 87.00%
2,206.29 0.00 2.61

189.16 10.00%
0.00%
0.00%
189.16 0.00 0.10

4,953.23 0.00 5.32


AVANCE DE OBRA 1,816.65 m2 de muro Fecha 30 de agosto de 2023

MUROS CELUCRETO Avance ponderado

CONTRATISTA Carvid-Sistemas Integrales


y total de
Tablaroca
27.36%
% de m2 de
CTGS
Planta Baja construcción de
muro terminado
0.00%
D= 27.36%
NIVEL CELUCRETO CADENAS CASTILLOS AVANCE GENERAL
60.00% 16.00% 24.00%

Avance Avance DEL TOTAL ACUMULADO


Nombre del nivel % del TOTAL Total (M2)
(M2) (%)
Total (M2) Avance (M2) Avance (%) Total (M2) Avance (M2) Avance (%) PONDERADO (%)
(%) (%)

1 Cto Cilindros DH1 14.69% 242.9 237.2 98% 42.7 37.1 87% 8.1 7.0 87% 93.00% 13.66% 13.66%
2 Cto Cilindros DH2 14.73% 243.6 237.2 97% 42.3 36.8 87% 7.8 6.8 87% 93.00% 13.70% 27.36%
3 Cto Cilindros DH3 14.73% 243.6 0.0 0% 42.4 0.0 0% 7.8 0.0 0% 0.00% 0.00% 27.36%
3 Edif apoyo 1 25.16% 416.1 0.0 0% 212.0 0.0 0% 300.8 0.0 0% 0.00% 0.00% 27.36%
3 Edif apoyo 2 30.70% 507.7 0.0 0% 0.0 0.0 0% 150.2 0.0 0% 0.00% 0.00% 27.36%
27.36%
100.00% 1,653.9 339.3 474.6 27.36%

La información del documento es estrictamente confidencial, destinada exclusivamente para fines específicos que lo originan, su utilización con fines distintos será responsabilidad civil y/o penal de quien lo haga. 22:31:58
AVANCE DE OBRA 21,000.00 m3 de concreto total
El total no incluye el 1/5 del claro construido para T2
Fecha 12 de mayo de 2007

ESTRUCTURA
30.22%
T1
Avance ponderado y
44,315.76 m de construcción TOTAL
2
100.00% total de estructura
CONTRATISTA IMPULSA
38,675.94 m2 de TORRE 87.27%
Amsterdam
% de m2 de
TORRE 1 5,639.82 m2 de BASAMENTO 12.73%
construcción
contruidos
30.01%
D= 0.21%
NIVEL COLUMNAS MUROS LOSAS AVANCE GENERAL
15.17% 23.16% 61.66%
PONDERADO
Nombre del % del
TOTAL (pza)
AVANCE AVANCE
TOTAL (m)
AVANCE
AVANCE (%)
TOTAL (podio + PUENTES (+) 1/5 DEL BASAMENTO TORRE AVANCE TOTAL AVANCE
DEL NIVEL
DEL TOTAL ACUMULADO
nivel TOTAL (pza) (%) (m) torre) (m2) (m2) CLARO (m2) (m2) (m2) (m2) (%)
(%)
(%) (%)

B06
1 B05 7.23% 23 23 100% 382.98 382.98 100% 3,204.81 129.34 1,852.29 1,352.52 3,204.81 100% 100.00% 7.23% 7.23%
2 B04 4.05% 32 32 100% 293.73 293.73 100% 1,793.90 114.21 719.89 1,074.01 1,793.90 100% 100.00% 4.05% 11.28%
3 B03 5.62% 51 51 100% 314.08 311.28 99% 2,489.56 106.08 1,252.38 1,237.18 2,407.84 97% 98.00% 5.51% 16.79%
4 B02 4.53% 70 70 100% 232.93 232.93 100% 2,005.59 105.15 806.64 1,198.95 2,005.59 100% 100.00% 4.53% 21.31%
5 B01 4.73% 85 85 100% 240.43 222.31 92% 2,096.66 91.35 872.45 1,224.21 2,096.66 100% 98.00% 4.64% 25.95%
6 L00 0.78% 68 67.00 99% 93.20 93.20 100% 346.74 48.43 96.24 250.50 346.74 100% 99.77% 0.78% 26.73%
7 L01 2.19% 68 20.00 29% 92.19 92.19 100% 971.36 25.04 39.93 931.43 971.36 100% 89.28% 1.96% 28.68%
8 L02 2.65% 65 20.00 31% 92.03 92.03 100% 1,174.03 1,174.03 470.85 40% 52.56% 1.39% 30.08%
9 L03 2.22% 71 10.00 14% 89.59 16.68 19% 982.60 982.60 - 0% 6.45% 0.14% 30.22%
10 L04 2.22% 71 0% 89.59 982.60 982.60 - 0% 0.00% 30.22%
11 L05 2.22% 71 0% 89.59 982.60 982.60 - 0% 0.00% 30.22%
12 L06 2.22% 71 0% 89.59 982.60 982.60 - 0% 0.00% 30.22%
13 L07 1.98% 71 0% 89.59 876.68 876.68 - 0% 0.00% 30.22%
14 L08 2.25% 72 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
15 L09 2.25% 71 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
16 L10 2.25% 70 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
17 L11 2.25% 71 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
18 L12 2.25% 71 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
19 L13 1.98% 69 0% 90.06 876.68 876.68 - 0% 0.00% 30.22%
20 L14 2.25% 72 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
21 L15 2.25% 70 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
22 L16 2.25% 70 0% 90.06 997.86 997.86 - 0% 0.00% 30.22%
23 L17 3.06% 71 0% 90.06 1,356.20 1,356.20 - 0% 0.00% 30.22%
24 L18 2.53% 71 0% 90.06 1,121.02 1,121.02 - 0% 0.00% 30.22%
25 L19 2.28% 70 0% 90.06 1,010.47 1,010.47 - 0% 0.00% 30.22%
26 L20 3.06% 73 0% 90.06 1,357.06 1,357.06 - 0% 0.00% 30.22%
27 L21 2.46% 81 0% 90.06 1,088.89 1,088.89 - 0% 0.00% 30.22%
28 L22 2.46% 81 0% 90.06 1,088.89 1,088.89 - 0% 0.00% 30.22%
29 L23 2.46% 81 0% 90.06 1,088.89 1,088.89 - 0% 0.00% 30.22%
30 L24 2.46% 81 0% 90.06 1,088.89 1,088.89 - 0% 0.00% 30.22%
31 L25 2.21% 80 0% 90.06 977.31 977.31 - 0% 0.00% 30.22%
32 L26 2.46% 83 0% 90.06 1,088.89 1,088.89 - 0% 0.00% 30.22%
33 L27 2.46% 81 0% 90.06 1,088.89 1,088.89 - 0% 0.00% 30.22%
34 L28 2.33% 81 0% 90.06 1,031.39 1,031.39 - 0% 0.00% 30.22%
35 L29 2.45% 75 0% 90.06 1,086.09 1,086.09 - 0% 0.00% 30.22%
36 L30 1.83% 71 0% 90.06 809.39 809.39 - 0% 0.00% 30.22%
37 L31 0.38% 16 0% 153.13 169.21 169.21 - 0% 0.00% 30.22%
38 L32 1.44% 636.36 636.36 - 0% 0.00% 30.22%
39 L33 1.08% 478.63 478.63 - 0% 0.00% 30.22%
40 L34 0.00% 30.22%
100.00% 2,549.00 4,414.03 44,315.76 619.60 5,639.82 38,675.94 13,297.75 30.22%
Total Puentes 1/5 Basamento Torre Avance