Documentos de Académico
Documentos de Profesional
Documentos de Cultura
02 Cro. de Adq. de Materiales
02 Cro. de Adq. de Materiales
DE ADQUISICION DE MATERIALES
PROYECTO: "MEJORAMIENTO DEL SISTEMA DE RIEGO DEL CANAL ABASMAYO EN LA PARTE ALTA DEL CASERÍO NILLAS DE COMBAYO, C.P DE COMBAYO DEL DISTRITO DE ENCAÑADA ‐ PROVINCIA DE CAJAMARCA"
FECHA: OCTUBRE 2022
PRESUPUESTO MES 01 MES 02 MES 03
PRECIO
DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL
OPERARIO hh 24.22 1,639.55 39,709.94 257.13 6,227.69 281.79 6,824.99 1,100.63 26,657.26
OFICIAL hh 19.13 667.87 12,776.34 32.06 613.31 122.16 2,336.91 513.65 9,826.12
PEON hh 17.29 7,510.70 129,860.04 852.74 14,743.87 514.54 8,896.43 6,143.42 106,219.73
OPERADOR DE EQUIPO PESADO hh 25.26 43.33 1,094.41 0.00 0.00 43.33 1,094.41
OPERADOR DE EQUIPO LIVIANO hh 25.04 221.59 5,548.57 0.00 20.66 517.28 200.93 5,031.29
ELABORACIÓN DEL PLAN DE TRABAJO PARA VIGILANCIA, PREVENCIÓN Y CONTROL COVID-19 GLB 5,000.00 1.00 5,000.00 1 5,000.00 0.00 0.00
EVALUACIÓN DE DESCARTE Y PRUEBAS DE SALUD AL PERSONAL PREVENCIÓN Y CONTROL COVID-19 GLB 430.00 27.00 11,610.00 27 11,610.00 0.00 0.00
DESINFECCIÓN INICIAL DE CAMPAMENTO, ALMACÉN, VESTUARIO, COMEDOR Y SS.HH. GLB 1,968.00 6.00 11,808.00 6 11,808.00 0.00 0.00
SEÑALIZACIÓN EXTERIOR CON PANELES TIPO BANNER GLB 38.75 30.00 1,162.50 30 1,162.50 0.00 0.00
SEÑALIZACIÓN INTERIOR CON SEÑALES TIPO STICKER GLB 6.35 60.00 381.00 60 381.00 0.00 0.00
CAPACITACIÓN EN SEGURIDAD Y SALUD P/EJECUCIÓN DE TRABAJOS EN COVID-19 GLB 111.84 12.00 1,342.08 12 1,342.08 0.00 0.00
EQUIPOS DE PROTECCIÓN PERSONAL EN OBRA - COVID19, PERSONAL TÉCNICO. GLB 290.00 12.00 3,480.00 12 3,480.00 0.00 0.00
EQUIPOS DE PROTECCIÓN PERSONAL EN OBRA - COVID19, PERSONAL ADMINISTRATIVO. GLB 108.00 6.00 648.00 6 648.00 0.00 0.00
EQUIPOS DE PROTECCIÓN PERSONAL EN OBRA - COVID19, PERSONAL SALUD. GLB 479.00 3.00 1,437.00 3 1,437.00 0.00 0.00
EQUIPOS DE PROTECCIÓN PERSONAL EN OBRA - COVID19, PERSONAL LIMPIEZA Y DESINFECCIÓN. GLB 310.45 6.00 1,862.70 6 1,862.70 0.00 0.00
EQUIPOS DE PROTECCIÓN PERSONAL EN OBRA - COVID19, PERSONAL OBRERO. GLB 150.00 69.00 10,350.00 69 10,350.00 0.00 0.00
CAPACITACION DE ADMINISTRACION DE OPERACION Y MANTENIMIENTO GLB 2,500.00 1.00 2,500.00 1 2,500.00 0.00 0.00
CLAVOS PARA CALAMINA kg 9.84 2.59 25.49 2.59 25.49 0.00 0.00
CLAVOS PARA MADERA C/C 2 1/2" kg 9.84 56.87 559.65 0.5 4.92 30.63 301.44 25.74 253.28
ALAMBRE NEGRO N° 16 kg 6.56 233.01 1,528.52 0.00 123.93 812.95 109.08 715.56
ALAMBRE NEGRO N° 8 kg 6.56 112.96 741.03 0.00 61.46 403.19 51.50 337.84
PERNOS HEXAGONALES DE 5/8" INC. TUERCA und 3.50 15.00 52.50 15 52.50 0.00 0.00
BARRENO DE 5" x 1/8" und 381.66 1.56 596.23 1.49 568.67 0.00 0.07 27.56
ACERO DE REFUERZO FY=4200 GRADO 60 kg 5.26 4,155.27 21,856.72 0.00 2210.16 11,625.44 1,945.11 10,231.28
ARENA FINA DE CERRO m3 60.00 20.51 1,230.46 0.00 0.30 17.86 20.21 1,212.60
AFIRMADO m3 40.00 85.75 3,430.00 8.05 322.00 0.00 77.70 3,108.00
HORMIGON DE RIO m3 80.00 218.72 17,497.70 0.25 20.00 9.06 724.90 209.41 16,752.80
PIEDRA CHANCADA DE 1/2" m3 150.00 50.34 7,550.81 0.00 22.03 3,304.31 28.31 4,246.50
PIEDRA MEDIANA DE 4" m3 80.00 8.59 687.06 0.00 0.00 8.59 687.06
PIEDRA GRANDE MIN.10" m3 60.00 52.87 3,172.39 0.00 3.26 195.79 49.61 2,976.60
PIEDRA GRANDE 8" m3 60.00 0.20 11.88 0.00 0.00 0.20 11.88
ARENA GRUESA DE RIO m3 150.00 44.45 6,667.79 0.00 19.18 2,877.29 25.27 3,790.50
PIEDRA MEDIANA 2" a 3" m3 80.00 120.39 9,630.82 0.00 0.00 120.39 9,630.82
ASFALTO RC-250 gln 23.50 87.83 2,063.93 0.00 0.00 87.83 2,063.93
CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.94 1,607.27 38,478.10 1 23.94 384.20 9,197.80 1,222.07 29,256.36
COMBUSTIBLE gln 13.96 198.02 2,764.35 0.00 0.00 198.02 2,764.35
YESO DE 10 Kg BOL 8.00 35.60 284.78 2.05 16.40 4.86 38.86 28.69 229.52
GASOLINA 84 gln 15.68 0.07 1.10 0.00 0.00 0.07 1.10
PEGAMENTO PARA PVC gln 137.76 0.16 21.72 0.00 0.00 0.16 21.72
LEÑA TER 7.50 307.23 2,304.20 0.00 0.00 307.23 2,304.20
FLETE TERRESTRE GLB 26,619.21 1.00 26,619.21 1 26,619.21 0.00 0.00
MOVILIZACION DESMOVILIZACION DE EQUIPOS GLB 5,083.80 1.00 5,083.80 1 5,083.80 0.00 0.00
FLETE EN ZONA RURAL GLB 16,125.85 1.00 16,125.85 1 16,125.85 0.00 0.00
EQUIPOS DE PROTECCIÓN INDIVIDUAL GLB 10,725.84 1.00 10,725.84 1 10,725.84 0.00 0.00
MÓDULO PREFABRICADO PARA TÓPICO DE ENFERMERÍA EN OBRA - COVID-19 GLB 1,550.00 3.00 4,650.00 3 4,650.00 0.00 0.00
IMPLEMENTACIÓN DE TÓPICO DE ENFERMERÍA EN OBRA - COVID-19 GLB 2,510.00 3.00 7,530.00 3 7,530.00 0.00 0.00
ENFERMERO CONTROL COVID-19 GLB 3,500.00 3.00 10,500.00 3 10,500.00 0.00 0.00
MITIGACION DE IMPACTO AMBIENTAL GLB 2,500.00 1.00 2,500.00 0.00 0.00 1.00 2,500.00
RESTAURACION DE AREAS AFECTADAS EN ZONAS DE DESLIZAMIENTOS GLB 5,500.00 1.00 5,500.00 0.00 0.00 1.00 5,500.00
AGUA m3 5.00 20.44 102.19 0.00 9.24 46.19 11.20 56.00
GIGANTOGRAFIA m2 16.00 8.64 138.24 8.64 138.24 0.00 0.00
ESTACA DE MADERA DE EUCALIPTO p2 1.20 67.18 80.61 1.64 1.97 9.41 11.29 56.13 67.36
MADERA EUCALIPTO ( HABILITADA) p2 5.70 157.50 897.75 157.5 897.75 0.00 0.00
MADERA EUCALIPTO PARA ENCOFRADO p2 5.70 1,777.97 10,134.40 0.00 965.97 5,506.00 812.00 4,628.40
TRIPLAY DE 1.20m x 2.40m x 8mm und 54.04 12.25 661.99 12.25 661.99 0.00 0.00
TECKNOPORT DE 1" m2 14.35 1.85 26.54 0.00 0.00 1.85 26.54
TECKNOPORT DE 2" m2 47.56 95.62 4,547.83 0.00 0.00 95.62 4,547.83
ADITIVO IMPERMEABILIZANTE gln 22.96 21.37 490.66 0.00 0.95 21.82 20.42 468.84
ESMALTE gln 8.20 0.67 5.49 0.41 3.36 0.05 0.41 0.21 1.72
COMPUERTA METÁLICA TIPO ARMCO 1.20x0.50 x 3/16 und 600.00 1.00 600.00 0.00 0.00 1.00 600.00
COMPUERTA METÁLICA TIPO ARMCO 0.80x0.80 x 3/16 und 800.00 1.00 800.00 0.00 0.00 1.00 800.00
COMPUERTAS METÁLICAS E=1/4" und 205.00 31.00 6,355.00 0.00 1.00 205.00 30.00 6,150.00
TUBERIA PVC SAP C-10, Ø2'' m 38.46 7.46 286.72 0.00 7.46 286.72 0.00
TUBERIA PVC SAP C-10, Ø4'' m 53.21 27.59 1,468.28 0.00 0.00 27.59 1,468.28
CALAMINA GALVANIZADA 1.83 m. x 0.83 m. x 0.25 mm. und 33.21 26.25 871.76 26.25 871.76 0.00 0.00
WINCHA DE 50m. und 38.00 10.08 382.91 0.25 9.50 1.41 53.45 8.42 319.96
HERRAMIENTAS MANUALES %MO 5,706.20 1,809.82 687.63 3,208.74
CARGADOR FRONTAL hm 270.00 12.60 3,402.43 0.00 0.00 12.60 3,402.43
CAMION VOLQUETE DE 15 m3 hm 250.00 12.60 3,150.40 0.00 0.00 12.60 3,150.40
MEZCLADORA DE CONCRETO DE 9 - 11 P3 hm 18.75 222.56 4,173.08 0.00 21.36 400.58 201.20 3,772.50
RETROEXCAVADORA hm 271.18 13.40 3,634.52 0.00 0.00 13.40 3,634.52
EXCAVADORA SOBRE ORUGAS 115 HP hm 275.14 4.73 1,300.04 0.00 0.00 4.73 1,300.04
ESTACION TOTAL día 120.00 5.04 604.70 0.16 19.20 0.61 73.10 4.27 512.40
COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 16.39 3.30 54.08 1.29 21.14 0.00 2.01 32.93
COMPACTADOR VIBR. TIPO PLANCHA 7 HP hm 22.15 0.09 1.95 0.00 0.00 0.09 1.95
VIBRADOR DE CONCRETO 4 HP 1.35" hm 13.87 48.68 675.15 0.00 16.45 228.12 32.23 447.03
MARTILLO NEUMÁTICO DE 29 kg hm 5.90 198.50 1,171.17 198.27 1,169.79 0.00 0.23 1.38
COMPRESORA NEUMATICA 250 - 330 PCM - 87 HP hm 30.75 10.07 309.66 9.91 304.73 0.00 0.16 4.93
COSTO TOTAL: 502,996.26 S/.161,344.03 S/.55,595.79 S/.286,056.44
GASTOS GENERALES: 13.71% S/.22,119.85 S/.7,622.04 S/.39,217.61
UTILIDAD: 5% S/.8,067.20 S/.2,779.79 S/.14,302.82