FICHA TÉCNICA

OBRA: MEJORAMIENTO DE TROCHA CARROZABLE PAMPA HERMOSA INAHUAYA -PROVINCIA DE UCAYALI - CUI: 2078436

COD. CUI: 2078436

1.00 DEL PROCESO DE ELABORACION DEL EXPEDIENTE TECNICO

1.20 DE LA CONSULTORIA Elaborado por la entidad

1.2.1 RESOL. BASES -


1.2.2 PRES. BASE S/.
1.2.3 TIPO DE PROCESO
1.2.4 ACTA DE ADJUD.
1.2.5 PROYECTISTA
1.2.6 PRE. CONTRA. S/.

PRO.
ITEM POSTORES PRO. TECNICA ORDEN DE
ECONOMICA
PUNTAJE PUNTAJE CALIFICACIÓN

1.30 DEL EXPEDIENTE TECNICO

1.3.1 RESOL.EXP. TEC. RESOLUCION GERENCIAL REGIONAL N° 005-2017-GRL-GRI


1.3.2 PRE. BASE S/. 35,994,100.60 (Incluido el IGV)
1.3.3 FECHA BASE EXP. 01/12/2017
1.3.4 FINANCIAMIENTO RECURSOS ORDINARIOS
1.3.5 PROYECTISTA -

2.00 DEL PROCESO DE SELECCIÓN DE LA CONTRATISTA

2.10 DE LA CONTRATISTA

2.1.1 RESOL. BASES


2.1.2 TIPO DE PROCESO LP N° 002-2017-GRL-GRI
2.1.3 MODALIDAD ADMINISTRACIÓN INDIRECTA - POR CONTRATA
2.1.4 PRE. BASE S/. 35,994,100.60 (Incluido el IGV)
2.1.5 FECHA BASE EXP. 01/12/2017
2.1.6 ACTA DE ADJUD. SN con fecha 5/7/2017
2.1.7 CONTRATISTA Consorcio Vial Pampa Hermosa
2.1.8 PRE. CONTRAT. S/. 30,503,475.08 (Sin IGV)
2.1.9 PLAZO EJEC. 570 días Calendario
2.1.10 BUENA PRO 5/7/2017
2.1.11 RESIDENTE Ing. Walter Arturo Morales Pilco

PRO.
PRO. TECNICA ORDEN DE
ITEM POSTORES ECONOMICA
PUNTAJE PUNTAJE CALIFICACIÓN
01 Consorcio Vial Pampa Hermosa 100.00 100.00 100.00

2.20 DEL CONTRATO

2.2.1 FIEL CUMPLIM. S/. 3,050,347.51 Fecha: 02-Abr-21 Vigencia: 02-Oct-21


Entidad Financiera POSITIVA
Observacion VENCIDO
N° 1832602

2.2.2 CONTRATISTA Consorcio Vial Pampa Hermosa


2.2.3 FIRMA DE CONTRA. 21 de Julio del 2017

3.00 DEL PROCESO DE EJECUCION DE OBRA

3.1 INICIO DE OBRA

3.1.1 MEMO. INSPECTOR/


3.1.1 MEMO. COORDINADOR ING. Gary Joe Angulo Soria Carta N° 016-2023-GRL-GGR-GRI-SGRSyCO
3.1.2 SUPERVISOR Angel Dino Diaz Colqui
3.1.3 ACTA DE TERRENO 04 de agosto de 2017
3.1.4 PLAZO DE EJEC. 570 días Calendario
3.1.5 FECHA DE INICIO 05 de agosto del 2017
FECHA DE TERMINO
3.1.6
CONTRACTUAL
FECHA DE TERMINO
3.1.7
VIGENTE
3.2 DE LAS VALORIZACIONES

3.2.1 MONTO OBRA 30,503,475.08 (Sin IGV) ENTIDAD


FIEL CUMPLIM. S/. 3,050,347.51 Fecha: 02-Abr-21 Vigencia: 02-Oct-21 POSITIVA
FIEL CUMPLIM. S/. Fecha: Vigencia:

ADICIONAL Nº 01
3.2.2 ADEL. DIRECTO 3,050,347.51 Fecha: 02-Abr-21 Vigencia: 02-Oct-21 VENCIDO
FIEL CUMPLIM. S/. 698,737.97 Fecha: 17/07/2021 Vigencia: 17/01/2022 1832603-08
FIEL CUMPLIM. S/. Fecha: Vigencia:

3.2.4 ADEL. MATERIALES Fecha: Vigencia:


3.2.5 FIEL CUMPLIM. S/. 482,102.23 Fecha: 04-Jul-21 Vigencia: 04-Ene-21 30019688-06 VENCIDO
3.2.5 FIEL CUMPLIM. S/. 1.676,053.19 Fecha: 23-11-2017 Vigencia: VENCIDO
1,374,294.32 Fecha: 01-Dic-17 VENCIDO

CUADRO DE VALORIZACIONES CONTRACTUALES

INVERSIÓN DEDUCCIONES RETENCIÓN MONTO A


D. REAJ. NO
VAL. MES M. VALORIZADO REAJUSTE ADEL. DIREC. ADEL. MATER. FONDO GAR. PAGAR S/.
CORRES.

01 Ago-17 22,986.16 2,298.62 20,687.54


02 Nov-17 1,935,158.45 193,515.85 1,741,642.60
03 Dic-17 905,673.72 90,567.37 798,724.17 16,382.18
04 Ene-18 18,062.61 1,806.26 16,256.35
05 Feb-18 530,661.19 53,066.12 107,633.28 369,961.79
06 Mar-18 11,325.12 1,132.51 9,948.07 244.54
07 Jun-18 196,503.61 19,650.36 39,856.55 136,996.70
08 Jul-18 381,612.70 38,161.27 97,204.90 246,246.53
09 Ago-18 797,138.43 79,713.84 399,048.58 318,376.01
0.00
10 Set-18 912,460.66 91,246.07 456,779.03 364,435.56
11 Oct-18 1,032,971.29 103,297.13 494,093.96 435,580.20
12 Nov-18 531,535.78 53,153.58 98,425.73 379,956.47
13 Dic-18 24,672.74 2,467.27 15,780.24 6,425.23
14 May-19 180,944.23 18,094.42 35,907.72 126,942.09
15 Jun-19 1,133,731.76 113,373.18 130,984.89 889,373.69
16 Jul-19 597,186.47 59,718.65 81,252.62 456,215.20
17 Ago-19 2,497,839.35 249,783.94 326,296.44 1,921,758.97
18 Set-19 2,384,164.37 238,416.44 303,128.61 1,842,619.32
19 Oct-19 621,327.20 62,132.72 86,870.27 472,324.21
20 Nov-19 71,758.92 7,175.89 0.00 64,583.03
21 Dic-19 2,216,002.59 221,600.26 254,560.42 1,739,841.91
22 Ago-20 1,331,464.88 133,146.49 405,984.35 792,334.04
23 Set-20 1,285,843.62 128,584.36 568,819.40 588,439.86
24 Oct-20 882,586.02 88,258.60 330,012.58 464,314.84
25 Nov-20 372,085.59 37,208.56 168,750.15 166,126.88
26 Dic-20 2,640,397.92 264,039.79 408,530.85 1,967,827.28
27 May-21 9,587.15 958.71 1,248.47 7,379.97
28 Jul-21 2,658,391.12 697,779.26 480,853.76 1,479,758.10
29 Ago-21 1,629,246.96
30 Set-21 49,637.35
31 Oct-21 13,093.87
32 Nov-21 10,370.59
33 Nov-22 -4,499,317.44

TOTAL ACUMULADO 23,387,104.98 0.00 3,050,347.52 6,100,695.04

CUADRO DE VALORIZACIONES DEL ADICIONAL

INVERSIÓN DEDUCCIONES RETENCIÓN MONTO A


D. REAJ. NO
VAL. MES REAJUSTE ADEL. DIREC. ADEL. MATER. FONDO GAR. PAGAR S/.
CORRES.

0.00 0.00 0.00 0.00 0.00 0.00

CUADRO COMPARATIVO PROGRAMADO VS VALORIZADO CONTRACTUAL

VALORIZACIONES PROGRAMADAS VALORIZACIUONES REALES


N° MES % DE
ACUMULADO % DE
MONT PROG ACUMULADO PROGRAMADO EJECUCION % ACUMULADO MONT. VAL. % ACUMULADO
PROGRAMADO EJECUCION
PRORAMADA

01 Ago-17 22,986.17 22,986.17 0.08% 0.08% 22,986.17 22,986.17 0.08% 0.08%


02 Nov-17 1,935,158.45 1,958,144.62 6.34% 6.42% 1,935,158.45 1,958,144.62 6.34% 6.42%
03 Dic-17 905,673.72 2,863,818.34 2.97% 9.39% 905,673.72 2,863,818.34 2.97% 9.39%
04 Ene-18 18,062.60 2,881,880.94 0.06% 9.45% 18,062.60 2,881,880.94 0.06% 9.45%
05 Feb-18 530,661.18 3,412,542.12 1.74% 11.19% 530,661.18 3,412,542.12 1.74% 11.19%
06 Mar-18 11,325.12 3,423,867.24 0.04% 11.22% 11,325.12 3,423,867.24 0.04% 11.22%
07 Jun-18 196,503.61 3,620,370.85 0.64% 11.87% 196,503.61 3,620,370.85 0.64% 11.87%
08 Jul-18 381,612.70 4,001,983.55 1.25% 13.12% 381,612.70 4,001,983.55 1.25% 13.12%
09 Ago-18 797,138.44 4,799,121.99 2.61% 15.73% 797,138.44 4,799,121.99 2.61% 15.73%
10 Set-18 912,460.66 5,711,582.65 2.99% 18.72% 912,460.66 5,711,582.65 2.99% 18.72%
11 Oct-18 1,032,971.29 6,744,553.94 3.39% 22.11% 1,032,971.29 6,744,553.94 3.39% 22.11%
12 Nov-18 531,536.51 7,276,090.45 1.74% 23.85% 531,536.51 7,276,090.45 1.74% 23.85%
13 Dic-18 24,672.74 7,300,763.19 0.08% 23.93% 24,672.74 7,300,763.19 0.08% 23.93%
14 May-19 180,944.22 7,481,707.41 0.59% 24.53% 180,944.22 7,481,707.41 0.59% 24.53%
15 Jun-19 1,133,731.75 8,615,439.16 3.72% 28.24% 1,133,731.75 8,615,439.16 3.72% 28.24%
16 Jul-19 597,186.47 9,212,625.63 1.96% 30.20% 597,186.47 9,212,625.63 1.96% 30.20%
17 Ago-19 2,497,839.35 11,710,464.98 8.19% 38.39% 2,497,839.35 11,710,464.98 8.19% 38.39%
18 Set-19 2,384,165.58 14,094,630.56 7.82% 46.21% 2,384,165.58 14,094,630.56 7.82% 46.21%
19 Oct-19 621,328.05 14,715,958.61 2.04% 48.24% 621,328.05 14,715,958.61 2.04% 48.24%
20 Nov-19 71,758.92 14,787,717.53 0.24% 48.48% 71,758.92 14,787,717.53 0.24% 48.48%
21 Dic-19 2,216,002.59 17,003,720.12 7.26% 55.74% 2,216,002.59 17,003,720.12 7.26% 55.74%
22 Ago-20 1,331,464.88 18,335,185.00 4.36% 60.11% 1,331,464.88 18,335,185.00 4.36% 60.11%
23 Set-20 1,248,680.54 19,583,865.54 4.09% 64.20% 1,248,680.54 19,583,865.54 4.09% 64.20%
24 Oct-20 808,763.16 20,392,628.70 2.65% 66.85% 808,763.16 20,392,628.70 2.65% 66.85%
25 Nov-20 503,707.20 20,896,335.90 1.65% 68.50% 503,707.20 20,896,335.90 1.65% 68.50%
26 Dic-20 2,517,052.52 23,413,388.42 8.25% 76.76% 2,517,052.52 23,413,388.42 8.25% 76.76%
27 May-21 9,587.15 23,422,975.57 0.03% 76.79% 9,587.15 23,422,975.57 0.03% 76.79%
28 Jul-21 2,658,391.13 26,081,366.70 8.72% 85.50% 2,658,391.12 26,081,366.69 8.72% 85.50%
29 Ago-21 1,629,246.96 27,710,613.66 5.34% 90.84% 1,629,246.96 27,710,613.65 5.34% 90.84%
30 Set-21 49,637.34 27,760,251.00 0.16% 91.01% 49,637.35 27,760,251.00 0.16% 91.01%
31 Oct-21 8,185.42 27,768,436.42 0.03% 91.03% 10,370.59 27,770,621.59 0.03% 91.04%
32 Nov-21 31,665.46 27,800,101.88 0.10% 91.14% -4,499,317.44 23,271,304.15 -14.75% 76.29%
33 Dic-21 779,765.18 28,579,867.06 2.56% 93.69%
34 Ene-23 1,923,607.46 30,503,474.52 6.31% 100.00%

30,503,474.52 11.79% 23,271,304.16 76.29%

3.3 DE LOS ADICIONALES, DEDUCTIVOS, AMPLIACIONES

3.3.1 ADICIONALES

Nº CAUSAL DE ADICIONAL Nº DE RESOL. FECHA SOLICITAD.S/. APROBAD. S/. %

01 R.G.G.R N° 058-2021-GGR 18-Feb-21 185,450.63 0.61% Adicional N° 03


02 R.G.G.R N° 057-2021-GRL-GGR 18-Feb-21 1,541,159.28 5.05% Adicional N° 04
03 R.G.G.R N° 260-2021-GRL-GGR 05-Jul-21 631,399.68 2.07% Adicional N° 05
04 R.G.G.R N° 335-2021-GRL-GGR 14-Set-21 846,193.57 2.77% Adicional N° 06
05 R.G.G.R N° 350-2021-GRL-GGR 23-Set-21 1,347,810.21 4.42% Adicional N° 07

0.00 4,552,013.37 14.92%

3.3.2 DEDUCCIONES

Nº CAUSAL DE DEDUCCIÓN Nº DE RESOL. FECHA SOLICITAD.S/. APROBAD. S/. %

0.00 0.00 0.00%

3.3.3 AMPLIACIONES PROCEDENTES

3.3.3.1 FECHA DE TERMINO REAL

Nº CAUSAL DE AMPLIACIÓN Nº DE RESOL. FECHA Nº DÍAS APROB. TERM. SOLICIT. TERM. APRO. OBS.

precipitacion pluviales(lluvias) el dia 25, impidiendo que se


1 R.G.R. N°039-2018-GRL-GRI 28/3/2018 01 Ampliacion de Plazo N° 05
realice los trabajos desde el 26 de febrero 2018

Lluvia ,suaves, torrenciales lo que genero que el terreno no


2 R.G.R. N°144-2018-GRL-GRI 21/8/2018 02 Ampliacion de Plazo N° 11
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que el terreno no


3 R.G.R. N°155-2018-GRL-GRI 08/11/2018 02 Ampliacion de Plazo N° 12
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que el terreno no


4 R.G.R. N°156-2018-GRL-GRI 09/11/2018 01 Ampliacion de Plazo N° 13
se encontro en condiciones apropiadas para el trabajo

5 Por deuda de tres valorizaciones (julio, agosto y setiembre) R.G.R. N°272-2018-GRL-GRI 26/12/2018 04 Ampliacion de Plazo N° 18

Lluvia ,suaves, torrenciales lo que genero que le terreno se


6 R.G.R. N°001-2019-GRL-GRI 01/10/2019 01 Ampliacion de Plazo N° 20
sature con la humedad

Lluvia torrenciales generano efectos negativos en el suelo la


7 R.G.R. N°055-2019-GRL-GRI 18/6/2019 04 Ampliacion de Plazo N° 21
saturacion del terreno

Lluvia torrenciales generano efectos negativos en el suelo la


8 R.G.R. N°058-2019-GRL-GRI 28/6/2019 04 Ampliacion de Plazo N° 22
saturacion del terreno

Efecto de vicios ocultos en la cimentacion del puente


9 R.G.R. N°098-2019-GRL-GRI 28/8/2019 45 Ampliacion de Plazo N° 25
CACHIYACU

Lluvia ,suaves, torrenciales lo que genero que le terreno no


10 R.G.R. N°112-2019-GRL-GRI 10/07/2019 33 Ampliacion de Plazo N° 26
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que le terreno no


11 R.G.R. N°140-2019-GRL-GRI 12/11/2019 33 Ampliacion de Plazo N° 27
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que le terreno no


12 R.G.R. N°0164-2019-GRL-GRI 12/10/2019 03 Ampliacion de Plazo N° 29
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que le terreno no


13 R.G.R. N°0162-2019-GRL-GRI 12/10/2019 02 Ampliacion de Plazo N° 30
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que le terreno no


14 R.G.R. N°0163-2019-GRL-GRI 12/10/2019 02 Ampliacion de Plazo N° 31
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que el terreno no


15 R.G.R. N°0172-2019-GRL-GRI 23/12/2019 6 Ampliacion de Plazo N° 32
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que el terreno no


16 R.G.R. N°004-2021-GRL-GRI 13/01/2020 3 Ampliacion de Plazo N° 33
se encontro en condiciones apropiadas para el trabajo

Lluvia ,suaves, torrenciales lo que genero que el terreno no


17 R.G.R. N°133-2021-GRL-GRI 17/06/2021 56 Ampliacion de Plazo N° 44
se encontro en condiciones apropiadas para el trabajo

La causal se debe a que no tienen resolucion de aprobacion


18 de los adicionales N° 06 y 07 , esto genera un a ampliacion R.G.R. N°278-2021-GRL-GRI 29/10/2021 90 Ampliacion de Plazo N° 46
de plazo.

292

4.00 DE LA LIQUIDACION DE LA OBRA

4.01

5.00 OBSERVACIONES

La obra se encuentra suspendida desde el 16 de noviembre 2022


La amplicion de plazon N° 47 se encuentra en tramite