TRACK DTM SAC

PLANEAMIENTO SEMANAL TAJEOS 10/10/04 AL 16/10/04

PROGRAM PIES
PROG/ A EJECUTADO NUMERO PROG/ PROG/ F.C. TOTAL- KG.
NIVEL LABOR LEY Nro TAL TM/TAL CART/TAL Nro. BARR.
MES RESTANT AL 04/09/04 BALANC/DIA GDIA SEM. KG/TM CART. EXPLOS.
E PERF.
3250 TJ-440 SPLIT 400 272 127.64 12 6 84 1.75 263 0.32 7 1838 147 1378 2
3250 TJ-540 SPLIT 500 343 156.78 11 6 80 1.75 250 0.32 7 1752 140 1314 2
3250 TJ-600 SPLIT 500 322 177.89 11 5 75 1.75 235 0.32 7 1644 132 1233 2
3250 TJ-660 SPLIT 350 233 116.58 8 4 54 1.75 170 0.32 7 1191 95 894 1
TOTAL 1750 1171 578.89 0.00 42 21 294 1.75 918 28 6425 514 4819 6
Nro.
BROCAS

6
5
5
4
19
EVALUACION DE TAJEOS AL 09 OCTUBRE - 2004

PROG. A LA
NIVEL LABOR PROG/MES FECHA
EJECUTADO
% LOGROS
KG. EXPL. F.C. KG/TM PIES PERF. Nro. BARREN
AL 04/09/04 ROTURA (100%)
09/10/04
3250 TJ-440 SPLIT 400 120 127.64 106% 211.07 1.65 1675 2
3250 TJ-540 SPLIT 500 150 156.78 105% 294.70 1.88 2058 3
3250 TJ-600 SPLIT 500 150 177.89 119% 323.08 1.82 2335 3
3250 TJ-660 SPLIT 350 105 116.58 111% 232.16 1.99 1530 2
TOTAL 1750 525 578.89 110.26% 1061.01 1.83 7598 9
Nro. BROCAS

8
10
12
8
38