PRESUPUESTO DESAGREGADO

PROYECTO: "AMPLIACION DEL SERVICIO DE AGUA POTABLE URBANO Y AMPLIACION DEL SERVICIO DE ALCANTARILLADO EL BARRIO LOS EUCALIPTOS EN EL DISTRITO DE CONCEPCION, PROVINCIA
CONCEPCION, DEPARTAMENTO JUNIN"
SUBPRESUPUESTO: AGUA POTABLE Y ALCANTARILLADO CALLE NUEVA TAMBO ALAPA
CLIENTE: MUNICIPALIDAD PROVINCIAL DE CONCEPCION
UBICACION: PLAZA PRINCIPAL - CONCEPCION - CONCEPCION - JUNIN
FECHA BASE: 2023-06-01
MONEDA: SOLES

Item Partida Unidad Metrado PU Mano de Obra Materiales Equipos Sub Contratos Sub Partidas Parcial
1 OBRAS PRELIMINARES 361.80 578.70 135.32 2,025.00 0.00 3,100.82
1.1 CASETA P/GUARDIANIA Y/O DEPOSITO GLB 1.00 525.00 0.00 0.00 0.00 525.00 0.00 525.00
1.2 CARTEL DE IDENTIFICACION DE OBRA DE 2.40 M X 3.60 M UND 1.00 694.79 172.56 518.78 3.45 0.00 0.00 694.79
1.3 TRAZO Y REPLANTEO INICIAL KM 0.66 577.32 189.24 59.92 131.87 0.00 0.00 381.03
1.4 FLETE EN OBRA GLB 1.00 1,500.00 0.00 0.00 0.00 1,500.00 0.00 1,500.00
2 SEGURIDAD SALUD Y MEDIO AMBIENTE 41.03 1,363.85 0.00 900.00 0.00 2,304.88
2.1 IMPLEMENTACION DE EPP UND 15.00 76.00 0.00 1,140.00 0.00 0.00 0.00 1,140.00
2.2 CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD DE OBRA ML 164.11 0.70 41.03 73.85 0.00 0.00 0.00 114.88
2.3 GESTION DE SEGURIDAD SALUD Y MEDIO AMBIENTE GLB 1.00 1,050.00 0.00 150.00 0.00 900.00 0.00 1,050.00
3 AGUA POTABLE 3,461.19 9,066.69 1,958.53 377.16 0.00 14,863.54
3.1 RED DE DISTRIBUCION 2,407.95 5,772.34 1,077.57 0.00 0.00 9,257.84
3.1.1 MOVIMIENTO DE TIERRAS PARA RED 1,717.33 913.65 1,019.32 0.00 0.00 3,650.28
3.1.1.1 EXCAVACION C/MAQUINA DE ZANJA EN TERRENO NORMAL ML 194.17 6.56 314.56 0.00 959.20 0.00 0.00 1,273.76
3.1.1.2 NIVELACION, REFINE Y COMPACTACION, PISÓN MANUAL M2 77.67 5.31 354.18 19.42 38.84 0.00 0.00 412.43
3.1.1.3 RELLENO COMPACTADO, MAT. PROPIO PISÓN MANUAL M3 62.13 16.69 979.79 37.28 19.88 0.00 0.00 1,036.95
3.1.1.4 CAMA DE APOYO PARA TUBERIA MAT. ZARANDEADO M3 15.53 59.70 68.80 856.95 1.40 0.00 0.00 927.14
3.1.2 SUMINISTRO E INSTALACION DE TUBERIA 227.18 4,158.47 7.77 0.00 0.00 4,393.41
3.1.2.1 SUMINISTRO E INSTALACION TUBERIA PVC 63 MM C10 ML 194.17 22.31 227.18 4,096.99 7.77 0.00 0.00 4,331.93
3.1.2.2 ACCESORIOS PARA RED DE DISTRIBUCION GBL 1.00 61.48 0.00 61.48 0.00 0.00 0.00 61.48
3.1.3 VALVULA DE CONTROL 300.34 535.18 0.00 0.00 0.00 835.52
3.1.3.1 SUM VALVULA COMPUERTA Y ACCES Ø 2" P/VALVULA DE CONTROL UND 1.00 177.10 0.00 177.10 0.00 0.00 0.00 177.10
3.1.3.2 INSTALACION DE VALVULA COMPUERTA 2" UND 1.00 658.42 300.34 358.08 0.00 0.00 0.00 658.42
3.1.4 PRUEBA HIDRAULICA 163.10 165.04 50.48 0.00 0.00 378.63
3.1.4.1 PRUEBA HIDRAULICA ML 194.17 1.95 163.10 165.04 50.48 0.00 0.00 378.63
3.2 CONEXION DOMICILIARIA 1,053.24 3,294.35 880.96 377.16 0.00 5,605.70
3.2.1 MOVIMIENTO DE TIERRAS PARA CONEXION 396.00 169.43 198.64 0.00 0.00 764.06
3.2.1.1 EXCAVACION C/MAQUINA DE ZANJA EN TERRENO NORMAL ML 36.00 6.56 58.32 0.00 177.84 0.00 0.00 236.16
3.2.1.2 NIVELACION, REFINE Y COMPACTACION, PISÓN MANUAL M2 14.40 5.31 65.66 3.60 7.20 0.00 0.00 76.46
PRESUPUESTO DESAGREGADO
PROYECTO: "AMPLIACION DEL SERVICIO DE AGUA POTABLE URBANO Y AMPLIACION DEL SERVICIO DE ALCANTARILLADO EL BARRIO LOS EUCALIPTOS EN EL DISTRITO DE CONCEPCION, PROVINCIA
CONCEPCION, DEPARTAMENTO JUNIN"
SUBPRESUPUESTO: AGUA POTABLE Y ALCANTARILLADO CALLE NUEVA TAMBO ALAPA
CLIENTE: MUNICIPALIDAD PROVINCIAL DE CONCEPCION
UBICACION: PLAZA PRINCIPAL - CONCEPCION - CONCEPCION - JUNIN
FECHA BASE: 2023-06-01
MONEDA: SOLES

Item Partida Unidad Metrado PU Mano de Obra Materiales Equipos Sub Contratos Sub Partidas Parcial
3.2.1.3 RELLENO COMPACTADO, MAT. PROPIO PISÓN MANUAL M3 11.52 23.07 246.53 6.91 12.33 0.00 0.00 265.77
3.2.1.4 CAMA DE APOYO PARA TUBERIA MAT. ZARANDEADO M3 2.88 64.47 25.49 158.92 1.27 0.00 0.00 185.67
3.2.2 SUMINISTRO E INSTALACION CONEXION DOM 657.24 3,124.92 682.32 377.16 0.00 4,841.64
3.2.2.1 SUMINISTRO E INST. CONEXION AGUA 15mm, INCL. LOSA 1X1X0.1 UND 12.00 294.88 657.24 1,821.84 682.32 377.16 0.00 3,538.56
3.2.2.2 MICROMEDICION UND 12.00 108.59 0.00 1,303.08 0.00 0.00 0.00 1,303.08
4 ALCANTARILLADO SANITARIO 28,194.28 34,108.21 6,957.34 3,395.12 0.00 72,654.93
4.1 REDES DE ALCANTARILLADO 26,222.20 31,360.57 6,690.46 2,850.20 0.00 67,123.41
4.1.1 MOVIMIENTO DE TIERRAS 8,920.14 2,112.80 4,265.69 0.00 0.00 15,298.62
4.1.1.1 EXCAVACION C/MAQUINA DE ZANJA EN TERRENO NORMAL C/RETRO 58 ML 185.69 7.88 360.24 0.00 1,103.00 0.00 0.00 1,463.24
4.1.1.2 EXCAVACION MANUAL DE ZANJAS H=1.40M MATERIAL SUELTO ML 180.56 18.15 3,181.47 0.00 95.70 0.00 0.00 3,277.16
4.1.1.3 REFINE Y NIVELACION T. NORMAL P/TUB. DN 160mm P/TODA PROFUND ML 366.25 6.27 2,007.05 91.56 197.78 0.00 0.00 2,296.39
4.1.1.4 RELLENO COMP. ZANJA (PULSO) P/TUB. - T. NORMAL DN 160mm HASTA ML 366.25 16.11 3,047.20 0.00 2,853.09 0.00 0.00 5,900.29
4.1.1.5 CAMA DE APOYO PARA TUBERIA MAT. ZARANDEADO M3 36.63 64.47 324.18 2,021.24 16.12 0.00 0.00 2,361.54
4.1.2 SUMINISTRO E INSTALACION DE TUBERIA 2,263.49 16,100.38 43.95 0.00 0.00 18,407.82
4.1.2.1 TUBERIA PVC - U UF NTP ISO 4435 SERIE 25 DN 200mm, INCL. ANILLO + ML 366.25 41.15 0.00 15,071.19 0.00 0.00 0.00 15,071.19
4.1.2.2 INSTALACION DE TUBERIA DE PVC P/DESAGUE DN 160mm ML 366.26 9.11 2,263.49 1,029.19 43.95 0.00 0.00 3,336.63
4.1.3 BUZONES 12,874.51 12,102.75 2,018.06 1,905.20 0.00 28,900.52
4.1.3.1 TRANSPORTE A ZONA S/AC. MAT. P/CONSTR. BUZON T-N, H PROM. 1.50 UND 11.00 58.22 621.72 0.00 18.70 0.00 0.00 640.42
4.1.3.2 BUZON TIPO I TERRENO NORMAL E.D. C/CARG. + VOLQ. DE 1.51 M A 1.7 UND 11.00 2,569.10 12,252.79 12,102.75 1,999.36 1,905.20 0.00 28,260.10
4.1.4 VARIOS 2,164.06 1,044.64 362.76 945.00 0.00 4,516.45
4.1.4.1 DADO DE CONCRETO DE EMPALME A BUZON UND 21.00 101.09 1,337.91 758.31 26.67 0.00 0.00 2,122.89
4.1.4.2 EMPALME DE TUBERIA A BUZON EXISTENTE UND 1.00 110.97 105.69 0.00 5.28 0.00 0.00 110.97
4.1.4.3 CORTE Y REPOSICION DE PISTA DE ASFALTO E=0.10 CM ML 8.00 97.81 370.40 220.40 191.68 0.00 0.00 782.48
4.1.4.4 AUTORIZACION DE CORTE Y REPOSICION DE PISTA GBL 1.00 750.00 0.00 0.00 0.00 750.00 0.00 750.00
4.1.4.5 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) UND 3.00 25.34 16.77 0.00 29.25 30.00 0.00 76.02
4.1.4.6 PRUEBA DE COMPACTACION DE SUELOS (PROCTOR MODIFIC. DENSIDAD UND 3.00 55.00 0.00 0.00 0.00 165.00 0.00 165.00
4.1.4.7 PRUEBA HIDRAULICA RED COLECTORA ML 366.25 1.39 333.29 65.93 109.88 0.00 0.00 509.09
4.2 CONEXIONES DOMICILIARIAS DE DESAGUE 1,972.08 2,747.64 266.88 544.92 0.00 5,531.52
PRESUPUESTO DESAGREGADO
PROYECTO: "AMPLIACION DEL SERVICIO DE AGUA POTABLE URBANO Y AMPLIACION DEL SERVICIO DE ALCANTARILLADO EL BARRIO LOS EUCALIPTOS EN EL DISTRITO DE CONCEPCION, PROVINCIA
CONCEPCION, DEPARTAMENTO JUNIN"
SUBPRESUPUESTO: AGUA POTABLE Y ALCANTARILLADO CALLE NUEVA TAMBO ALAPA
CLIENTE: MUNICIPALIDAD PROVINCIAL DE CONCEPCION
UBICACION: PLAZA PRINCIPAL - CONCEPCION - CONCEPCION - JUNIN
FECHA BASE: 2023-06-01
MONEDA: SOLES

Item Partida Unidad Metrado PU Mano de Obra Materiales Equipos Sub Contratos Sub Partidas Parcial
4.2.1 MOVIMIENTO DE TIERRAS 1,171.20 163.20 104.64 0.00 0.00 1,439.04
4.2.1.1 EXCAVACION DE ZANJA (PULSO), TERRENO NORMAL, DN 160mm, H=1.2 ML 48.00 20.12 947.04 0.00 18.72 0.00 0.00 965.76
4.2.1.2 REFINE Y NIVELACION T. SEMIROCOSO P/TUB. DN 160mm P/TODA PRO ML 48.00 3.20 150.72 0.00 2.88 0.00 0.00 153.60
4.2.1.3 RELLENO COMP. ZANJA (MAQ) P/TUB. -T. NORMAL DN 160mm HASTA 1 ML 48.00 6.66 73.44 163.20 83.04 0.00 0.00 319.68
4.2.2 SUMINISTRO E INSTALACION DE TUBERIA 800.88 2,584.44 162.24 544.92 0.00 4,092.48
4.2.2.1 SUMINISTRO DE CAJA DE CONCRETO SIMPLE Y TAPA CONCRETO ARMADO UND 12.00 57.95 0.00 695.40 0.00 0.00 0.00 695.40
4.2.2.2 INST. DE CAJA + TAPA DE REGISTRO 0.30MX0.60M, P/TODO TERRENO, IN UND 12.00 98.23 590.16 0.00 151.20 437.40 0.00 1,178.76
4.2.2.3 TUBERIA PVC - U UF NTP ISO 4435 SERIE 25 DN 160mm, INCL. ANILLO + ML 48.00 27.61 0.00 1,325.28 0.00 0.00 0.00 1,325.28
4.2.2.4 SUMINISTRO DE ELEMENTO DE EMPOTRAMIENTO DE TUBERIA U-PVC U UND 12.00 26.58 0.00 318.96 0.00 0.00 0.00 318.96
4.2.2.5 INSTALACION DE ELEMENTO DE EMPOTRAMIENTO DE TUBERIA PVC-U UND 12.00 34.48 165.60 244.80 3.36 0.00 0.00 413.76
4.2.2.6 INSTALACION DE TUBERIA DE PVC P/DESAGUE DN 160mm INCL. PRUEBA ML 48.00 3.34 45.12 0.00 7.68 107.52 0.00 160.32
COSTO DIRECTO 92,924.17
GASTOS GENERALES 12.9095% 11,996.05
UTILIDAD 3.5% 3,252.35
SUB TOTAL 108,172.57
IGV 18% 19,471.06
TOTAL PRESUPUESTO 127,643.63

SON: CIENTO VEINTISIETE MIL SEISCIENTOS CUARENTA Y TRES CON 63/100 SOLES