Documentos de Académico
Documentos de Profesional
Documentos de Cultura
0 OBRA GRUESA
1 MOVIMIENTO DE TIERRA Y DESPEJE DE TERRENO
1.1 EXCAVACIÓN PARA FUNDACIONES Y ALCANTARILLADO M3
2 FUNDACIONES
2.1 EMPLANTILLADO M3
2.2 CIMIENTO M3
2.3 SOBRECIMIENTO M3
2.3.1 MOLDAJE DE SOBRECIMIENTO M2
2.3.2 ENFIERRADURA DE SOBRECIMIENTO KG
2.3.3 H° DE SOBRECIMIENTO M3
3 RADIER
3.1 CAMA DE RIPIO COMPACTADA DE 10 CM MINIMO M3
3.2 H° DE RADIER DE 8 CM M3
4 ALBAÑILERIA 1ER PISO
4.1 ENFIERRADURA KG
4.2 MUROS ESTRUCTURALES M2
4.3 MUROS NO ESTRUCTURALES M2
5 ALBAÑILERIA 2DO PISO
5.1 ENFIERRADURA KG
5.2 MUROS ESTRUCTURALES M2
5.3 MUROS NO ESTRUCTURALES M2
6 LOSA 2DO PISO
6.1 MOLDAJE DE LOSA M2
6.2 ENFIERRADURA DE LOSA KG
6.3 H° DE LOSA M3
7 PILARES 1ER PISO
7.1 ENFIERRADURA DE PILARES KG
7.2 H° DE PILARES KG
8 PILARES 2ER PISO
8.1 ENFIERRADURA DE PILARES KG
8.2 H° DE PILARES KG
9 VIGAS
9.1 VIGA 1ER PISO KG
9.2 VIGA 2DO PISO KG
10 CADENAS
10.1 CADENAS 1ER PISO KG
10.2 CADENAS 2DO PISO KG
11 TABIQUERIA 1ER PISO
11.1 ZONA SECA - VOLCOMETAL 6.1 M2
11.2 ZONA HUMEDA - VOLCOMETAL M2
12 TABIQUERIA 2ER PISO
12.1 ZONA SECA - VOLCOMETAL 6.1 M2
12.1 ZONA HUMEDA - VOLCOMETAL M2
13 CUBIERTA
13.1 TEJA TIPO CHILENA DE H° M2
14 TABIQUES DE MADERA
14.1 Ravestimiento de tabique en zona seca M2
14.2 Revestimiento de tabique en zona humeda M2
15 TRATAMIENTO DE JUNTAS
15.1 Yeso M2
16 PINTURAS REVESTIMIENTO
16.1 Pintura exterior M2
16.2 Pintura de cielo (Baño y Cocina) M2
16.3 Pintura cielo (Zona Seca) M2
16.4 Papel mural color madera M2
16.5 Papel nilo blanco M2
16.6 latex en muros de albañileria M2
17 REVESTIMIENTO EXTERIOR
17.1 Estuco M2
18 MOLDURAS
18.1 Cornizas ML
18.2 Guarda polvos ML
19 AISLACIÓN
19.1 Aislación termica en cielo M2
19.2 Muros de hormigon perimetrales (POLIGYP) M2
20 VANOS
20.1 Puertas UNIDAD
20.2 Ventanas UNIDAD
21 CIELO
21.1 Cielo falso M2
22 PAVIMENTOS
22.1 Piso flotante M2
22.2 Alfombra M2
22.3 Ceramica zona humeda M2
22.4 Ceramica zona seca M2
23 REVESTIMIENTO DE ESCALERA
23.1 Porcelanato M2
EXCAVACIÓN PARA FUNDACIONES Y ALCANTARILLADO
EJES Largo Ancho Alto
1 3.03 0.4 0.6
2 4.05 0.4 0.6
3 0.46 0.4 0.6
4 7.74 0.4 0.6
B 5.3 0.4 0.6
D 0.98 0.4 0.6
E 2 0.4 0.6
F 3.33 0.4 0.6
G-B 2.58 0.4 0.6
Volumen
30 % Esponjamiento
Total M3
FUNDACIONES
EMPLANTILLADO
EJES Largo Ancho Alto
1 3.03 0.4 0.1
2 4.05 0.4 0.1
3 0.46 0.4 0.1
4 7.74 0.4 0.1
B 5.3 0.4 0.1
D 0.98 0.4 0.1
E 2 0.4 0.1
F 3.33 0.4 0.1
G 2.58 0.4 0.1
Volumen
5 % PERDIDA
Total M3
CIMIENTO
EJES Largo Ancho Alto
1 3.03 0.4 0.5
2 4.05 0.4 0.5
3 0.46 0.4 0.5
4 7.74 0.4 0.5
B 5.3 0.4 0.5
D 0.98 0.4 0.5
E 2 0.4 0.5
F 3.33 0.4 0.5
G 2.58 0.4 0.5
Volumen
5 % PERDIDA
Total M3
SOBRECIMIENTO
EJES Largo Ancho Alto
1 3.03 0.14 0.3
2 4.05 0.14 0.3
3 0.46 0.14 0.3
4 7.74 0.14 0.3
B 5.3 0.14 0.3
D 0.98 0.14 0.3
E 2 0.14 0.3
F 3.33 0.14 0.3
G 2.58 0.14 0.3
Volumen
5 % PERDIDA
Total M3
MOLDAJE DE SOBRECIMIENTO
EJES ml Ancho total m2
Exterior 1-3 3.47 0.14 0.5
Interior 1-3 3.19 0.14 0.4
exterior 3-4 2.72 0.14 0.4
interior 3-4 2.44 0.14 0.3
exterior 2-4 5.44 0.14 0.8
interior 2-4 5.16 0.14 0.7
exterior D 1.03 0.14 0.1
interior D 0.75 0.14 0.1
Exterior E 1.83 0.14 0.3
Interior E 1.83 0.14 0.3
Exterior B-C 3.05 0.14 0.4
Interior B-C 2.91 0.14 0.4
Exterior D-F 3.2 0.14 0.4
Interior D-F 3.06 0.14 0.4
Exterior G-F 0.46 0.14 0.1
Interior G-F 0.46 0.14 0.1
Exterior G-B 7.91 0.14 1.1
Interior G-B 7.63 0.14 1.1
Volumen 7.92
5 % PERDIDA 7.97
Total M3 15.88
RADIER
CAMA DE RIPIO COMPACTADA DE 10 CM MINIMO
EJE LARGO ANCHO ALTO
A 3.66 2.75 0.1
B 3.2 3.33 0.1
C 4.25 5.47 0.1
H 0.23 0.21 0.1
TOTAL
5% PERDIDA
VOLUMEN
RADIER
HORMIGÓN DE RADIER
EJE LARGO ANCHO ALTO
A 3.66 2.75 0.08
B 3.2 3.33 0.08
C 4.25 5.47 0.08
H 0.23 0.21 0.08
TOTAL
5% PERDIDA
VOLUMEN
ALBAÑILERIA
MURO PISO N° 1
EJES Largo ALTO DESCUENTO VANO M2
1 3.03 2.13 0
2 4.05 2.13 0
3 0.46 2.13 0
4 7.74 2.13 2.66
B 5.3 2.13 1.56
D 0.98 2.13 0
E 2 2.13 0
F 3.33 2.13 4.1
G 2.58 2.13 3.6
Volumen
5 % PERDIDA
Total M3
MURO PISO N° 2
EJES Largo ALTO DESCUENTO VANO M2
1 4.4 2.12 1.26
2 2.9 2.12 0
3 0.46 2.12 0
4 7.74 2.12 2.15
B 5.3 2.12 2.31
D 0.98 2.12 0
E 2 2.12 0
F 3.33 2.12 2.27
G 2.58 2.12 1.82
Volumen
5 % PERDIDA
Total M3
TENSORES
ELEVACION EJE 1 / 1ER Y 2DO PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 37.7 0.395 14.89
SUB TOTAL 14.89
5% PERDIDA 0.7445
TOTAL KG 15.6345
TENSORES
ELEVACION EJE 2 / 1ER Y 2DO PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 32.75 0.395 12.94
SUB TOTAL 12.94
5% PERDIDA 0.65
TOTAL KG 13.58
TENSORES
ELEVACION EJE 3 / 1ER Y 2DO PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 6.49 0.395 2.56
SUB TOTAL 2.56
5% PERDIDA 0.13
TOTAL KG 2.69
TENSORES
ELEVACION EJE 2 / 1ER Y 2DO PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 46.5 0.395 18.37
SUB TOTAL 18.37
5% PERDIDA 0.92
TOTAL KG 19.29
TENSORES
ELEVACION EJE B / 1ER Y 2DI PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 29.4 0.395 11.61
SUB TOTAL 11.61
5% PERDIDA 0.58
TOTAL KG 12.19
TENSORES
ELEVACION EJE D / 1ER Y 2DO PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 6.7 0.395 2.65
SUB TOTAL 2.65
5% PERDIDA 0.13
TOTAL KG 2.78
TENSORES
ELEVACION EJE E / 1ER Y 2DO PISO
DIAMTERO LARGO PESO NOMINAL KG TOTAL
8 6.4 0.395 2.53
SUB TOTAL 2.53
5% PERDIDA 0.13
TOTAL KG 2.65
TABIQUERIA
PRIMER PISO
LARGO ALTO M2
0.95 2.3 2.19
3.53 2.3 8.12
1.88 2.3 4.32
1.75 2.3 4.03
TOTAL 14.63
5% PERDIDA 0.73
TOTAL M2 15.36
CUBIERTA
Largo Ancho Total parcial
5.95 3.33 19.81
6.4 4.13 26.43
6.85 2.88 19.73
3.67 0.61 2.24
Total m2 68.21
DO
M3
0.73
0.97
0.11
1.86
1.27
0.24
0.48
0.80
0.62 TOTAL OBRA GRUESA 1602.09
7.07
2.12
9.19
M3
0.12
0.16
0.02
0.31
0.21
0.04
0.08
0.13
0.10
1.18
0.06
1.24
M3
0.61
0.81
0.09
1.55
1.06
0.20
0.40
0.67
0.52
5.89
0.29
6.19
M3
0.13
0.17
0.02
0.33
0.22
0.04
0.08
0.14
0.11
1.24
0.06
1.30
7.63
TOTAL EJE CANTIDAD ML TOTAL PESO NOMINALKG
3.83 4 15.32 0.617 9.45
4.85 4 19.4 0.617 11.97
1.26 4 5.04 0.617 3.11
8.54 4 34.16 0.617 21.08
6.10 4 24.4 0.617 15.05
1.78 4 7.12 0.617 4.39
2.80 4 11.2 0.617 6.91
4.13 4 16.52 0.617 10.19
3.38 4 13.52 0.617 8.34
SUBTOTAL EN 90.50
10 % PERDIDA 9.05
KG TOTALES 99.6
m3
0.8
0.9
1.9
0.004
3.5
0.2
3.7
M2
6.45
8.63
0.98
13.83
9.73
2.09
4.26
2.99
1.90
50.85
2.54
53.39
M2
5.26
5.02
2.58
7.71
5.11
3.10
4.12
3.18
2.88
38.96
1.95
40.91
M3
0.20
0.13
0.02
0.35
0.24
0.04
0.09
0.15
0.12
1.33
0.07
1.40
M3
2.91
1.95
0.39
5.05
3.49
0.72
1.38
2.23
1.75
19.87
0.99
20.86
PRIMER PISO
PERSO NOMINAL 1 TOTAL KG
0.617 12.83
0.617 9.13
0.617 3.11
0.617 21.08
0.617 15.05
0.617 4.39
0.617 6.91
0.617 10.19
0.617 8.34
Volumen 91.04
5 % PERDIDA 4.55
Total M3 95.60
RIMER PISO
PERSO NOMINAL M TOTAL KG
0.222 4.53
0.222 5.72
0.222 1.54
0.222 10.02
0.222 7.18
0.222 2.14
0.222 3.33
0.222 4.88
0.222 4.01
Volumen 43.35
5 % PERDIDA 2.17
Total M3 45.51
M3
0.24
0.16
0.03
0.03
0.03
0.42
0.29
0.03
0.05
0.11
0.18
0.14
1.72
0.09
1.81
M3
3.51
2.34
0.55
0.55
0.44
6.12
4.21
0.55
0.84
1.64
2.68
2.09
25.52
1.28
26.80
M3
3.55
2.38
0.59
0.59
0.48
6.15
4.25
0.88
0.94
2.71
2.13
24.66
1.23
25.90
M2
13.64
14.99
15.37
1.35
44.00
2.20
46.20
M2
13.64
14.99
15.37
1.35
44.00
2.20
46.20
SA 2 PISO
Total ml F Peso Ø 10mm Total
201.76 0.617 124.49
208.03 0.617 128.36
232.41 0.617 143.40
28.03 0.617 17.30
48.13 0.617 118.79
Subtotal 532.33
Perdida 5% 26.62
Total M2 558.95
72.88
3.64
Total m2 76.52
ITEM PARTIDAS
0 OBRA GRUESA
1 MOVIMIENTO DE TIERRA Y DESPEJE DE TERREN
1.1 EXCAVACIÓN PARA FUNDACIONES Y ALCANTARILLADO
2 FUNDACIONES
2.1 EMPLANTILLADO
2.2 CIMIENTO
2.3 SOBRECIMIENTO
2.3.1 MOLDAJE DE SOBRECIMIENTO
2.3.2 ENFIERRADURA DE SOBRECIMIENTO
2.3.3 H° DE SOBRECIMIENTO
3 RADIER
3.1 CAMA DE RIPIO COMPACTADA DE 10 CM MINIMO
3.2 H° DE RADIER DE 8 CM
4 ALBAÑILERIA 1ER PISO
4.1 ENFIERRADURA
4.2 MUROS ESTRUCTURALES
4.3 MUROS NO ESTRUCTURALES
5 ALBAÑILERIA 2DO PISO
5.1 ENFIERRADURA
5.2 MUROS ESTRUCTURALES
5.3 MUROS NO ESTRUCTURALES
6 LOSA 2DO PISO
6.1 MOLDAJE DE LOSA
6.2 ENFIERRADURA DE LOSA
6.3 H° DE LOSA
7 PILARES 1ER PISO
7.1 ENFIERRADURA DE PILARES
7.2 H° DE PILARES
8 PILARES 2ER PISO
8.1 ENFIERRADURA DE PILARES
8.2 H° DE PILARES
9 VIGAS
9.1 VIGA 1ER PISO
9.2 VIGA 2DO PISO
10 CADENAS
10.1 CADENAS 1ER PISO
10.2 CADENAS 2DO PISO
11 TABIQUERIA 1ER PISO
11.1 ZONA SECA - VOLCOMETAL 6.1
11.2 ZONA HUMEDA - VOLCOMETAL
12 TABIQUERIA 2ER PISO
12.1 ZONA SECA - VOLCOMETAL 6.1
12.1 ZONA HUMEDA - VOLCOMETAL
13 CUBIERTA
13.1 TEJA TIPO CHILENA DE H°
14 TABIQUES DE MADERA
14.1 Ravestimiento de tabique en zona seca
14.2 Revestimiento de tabique en zona humeda
15 TRATAMIENTO DE JUNTAS
15.1 Yeso
16 PINTURAS REVESTIMIENTO
16.1 Pintura exterior
16.2 Pintura de cielo (Baño y Cocina)
16.3 Pintura cielo (Zona Seca)
16.4 Papel mural color madera
16.5 Papel nilo blanco
16.6 latex en muros de albañileria
17 REVESTIMIENTO EXTERIOR
17.1 Estuco
18 MOLDURAS
18.1 Cornizas
18.2 Guarda polvos
19 AISLACIÓN
19.1 Aislación termica en cielo
19.2 Muros de hormigon perimetrales (POLIGYP)
20 VANOS
20.1 Puertas
20.2 Ventanas
21 CIELO
21.1 Cielo falso
22 PAVIMENTOS
22.1 Piso flotante
22.2 Alfombra
22.3 Ceramica zona humeda
22.4 Ceramica zona seca
23 REVESTIMIENTO DE ESCALERA
23.1 Porcelanato
UNIDAD TOTAL CUBICACION
GRUESA
Y DESPEJE DE TERRENO
M3 9.19
CIONES
M3 1.24
M3 6.19
M3
M2 15.88
KG 140.9
M3 1.3
M3 4.6
M3 3.7
RIA 1ER PISO
KG VER VALOR EN LA TABLA
M2 53.39
M2
IA 2DO PISO
KG VER VALOR EN LA TABLA
M2 40.91
M2
M2 46.2
KG 558.95
M3 46.2
1ER PISO
KG
KG
2ER PISO
KG
KG
GAS
KG VER VALOR EN LA TABLA
KG VER VALOR EN LA TABLA
ENAS
KG VER VALOR EN LA TABLA
KG VER VALOR EN LA TABLA
IA 1ER PISO
M2 VER VALOR EN LA TABLA
M2 VER VALOR EN LA TABLA
IA 2ER PISO
M2 VER VALOR EN LA TABLA
M2 VER VALOR EN LA TABLA
ERTA
M2 68.21
DE MADERA
M2 71.85
M2 33.85
O DE JUNTAS
M2 125.09
VESTIMIENTO
M2 51.84
M2 30.3
M2 136.27
M2 15.99
M2 67.91
M2 20.6
NTO EXTERIOR
M2 51.84
DURAS
ML 101.64
ML 87.05
ACIÓN
M2 136.27
M2 159.82
NOS
UNIDAD 7
UNIDAD 15
ELO
M2 136.27
ENTOS
M2 23.47
M2 28.79
M2 15.38
M2 23.58
O DE ESCALERA
M2 5