Está en la página 1de 4

PARTIDAS DEDUCIDAS

EXPEDIENTE TECNICO DEDUCIDAS


PARTIDA DESCRIPCIÓN
UND. METRADO PRECIO S/. PARCIAL S/. METRADO PRECIO S/. PARCIAL S/.
2 AGUA POTABLE SECTOR LUCMA
2.02 AGUA POTABLE - LUCMA
02.02.05 PASE AEREO TIPO I (L=60.00M) 05 UNIDADES
02.02.05.01 TRAZO Y REPLANTEO DE PASO AEREO m2 196.00 1.08 211.68 156.80 1.08 169.34
02.02.05.02 EXCAVACION EN TERRENO NORMAL HASTA 1.40M PROF. m3 155.52 40.47 6,293.89 124.42 40.47 5,035.12
02.02.05.03 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50m) m3 202.18 27.79 5,618.58 161.74 27.79 4,494.87
02.02.05.04 CONCRETO F'C=140KG/CM2 PARA SOLADO Y/O DADOS m3 10.72 287.45 3,081.46 8.58 287.45 2,465.17
02.02.05.05 ENCOFRADO Y DESENCOFRADO NORMAL m2 183.93 46.31 8,517.80 147.14 46.31 6,814.24
02.02.05.06 ACERO CORRUGADO fy= 4,200 kg/cm2 GRADO 60 kg 2178.65 5.92 12,897.61 1742.92 5.92 10,318.09
02.02.05.07 CONCRETO F'C=210KG/CM2 m3 78.24 381.23 29,827.44 62.59 381.23 23,861.95
02.02.05.08 TARRAJEO EN EXTERIORES m2 149.20 35.90 5,356.28 119.36 35.90 4,285.02
02.02.05.09 PINTURA DE MURO EXTERIOR C/ESMALTE SINTETICO m2 149.20 12.34 1,841.13 119.36 12.34 1,472.90
02.02.05.10 PROVISION E INSTALACION DE TUBERIA HDPE DN 2 1/2" m 338.00 12.83 4,336.54 270.40 12.83 3,469.23
02.02.05.11 PROVISION Y COLOCACION DE CABLE PRINCIPAL TIPO BOA DE D=5/8" m 457.50 7.58 3,467.85 366.00 7.58 2,774.28
02.02.05.12 PROVISION Y COLOCACION DE PENDOLAS C/TIPO BOA DE D=1/4" m 427.50 10.25 4,381.88 342.00 10.25 3,505.50
02.02.05.13 ACCESORIOS DE CONEXION DE CABLES Y ANCLAJES und 5.00 2,139.88 10,699.40 4.00 2,139.88 8,559.52
02.02.05.14 ACCESORIOS DE UNION DE TUBERIAS und 5.00 89.33 446.65 4.00 89.33 357.32

1
PARTIDAS DEDUCIDAS

EXPEDIENTE TECNICO DEDUCIDAS


PARTIDA DESCRIPCIÓN
UND. METRADO PRECIO S/. PARCIAL S/. METRADO PRECIO S/. PARCIAL S/.
3 ALCANTARILLADO SANITARIO
03.02.01 CRUCE AERERO (L=15M, 01UND)
03.02.01.01 TRABAJOS PRELIMINARES
03.02.01.01.01 LIMPIEZA MANUAL DE TERRENO NORMAL m 3.50 0.77 2.70 3.50 0.77 2.70
03.02.01.01.02 TRAZO, NIVEL Y REPLANTEO m 15.12 1.35 20.41 15.12 1.35 20.41
03.02.01.02 MOVIMIENTO DE TIERRAS
03.02.01.02.01 EXCAVACION DE ZANJA EN MATERIAL CONGLOMERADO m3 5.04 40.47 203.97 5.04 40.47 203.97
03.02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO COMPACTADO C/EQUIPO m3 3.36 27.97 93.98 3.36 27.97 93.98
03.02.06.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50m) m3 2.18 27.79 60.58 2.18 27.79 60.58
03.02.01.03 CONCRETO SIMPLE
03.02.01.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.16 46.31 377.89 8.16 46.31 377.89
03.02.01.03.02 CONCRETO F'C=175KG/CM2 m3 1.09 312.84 341.00 1.09 312.84 341.00
03.02.01.03.03 TARRAJEO EXTERIORES C:A 1:5, E=1.5CM m3 8.16 35.39 288.78 8.16 35.39 288.78
03.02.01.04 RED ALCANTARILLADO
03.02.01.04.01 ESTRUCTURA METALICA PARA CRUCE AEREO glb 1.00 1,288.11 1,288.11 1.00 1,288.11 1,288.11
03.02.01.04.02 PLATINA METALICA INCLUIDO ACCESORIOS und 4.00 195.94 783.76 4.00 195.94 783.76
03.02.01.04.03 TENDIDO DE TUBERIA PVC UF ISO 4435 200MM S-25 m 15.12 33.28 503.19 15.12 33.28 503.19
03.02.01.04.04 TENDIDO DE TUBERIA HDPE 250MM DE FORRO m 15.12 105.76 1,599.09 15.12 105.76 1,599.09
03.02.01.04.05 PRUEBA HIDRAULICA PARA TUBERIA DE DESAGUE m 15.12 3.96 59.88 15.12 3.96 59.88
03.05.01 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES (01UNIDAD)
03.05.04 POZO DE PERCOLACION(04 UND)
03.05.04.01 TRABAJOS PRELIMINARES
03.05.04.01.01 TRAZO, NIVEL Y REPLANTEO m2 47.29 1.12 52.96 47.29 1.12 52.96
03.05.04.02 MOVIMIENTO DE TIERRAS
03.05.04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 229.38 47.21 10,829.03 229.38 47.21 10,829.03
03.05.04.02.02 REFINE, NIVELACION Y COMPACTADO m2 47.29 13.89 656.86 47.29 13.89 656.86
03.05.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50m) m3 292.05 27.79 8,116.07 292.05 27.79 8,116.07
03.05.04.03 CONCRETO SIMPLE
03.05.04.03.01 SOLADO DE CONCRETO C:H (1:12) E=4" m2 47.29 27.69 1,309.46 47.29 27.69 1,309.46
03.05.04.04 CONCRETO ARMADO
03.05.04.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 171.42 52.12 8,934.41 171.42 52.12 8,934.41
03.05.04.04.02 ACERO CORRUGADO fy= 4,200 kg/cm2 GRADO 60 kg 665.55 6.21 4,133.07 665.55 6.21 4,133.07
03.05.04.04.03 CONCRETO F'C=175KG/CM2 m3 25.55 312.84 7,993.06 25.55 312.84 7,993.06
03.05.04.05 COLOCACION DE ACCESORIOS
03.05.04.05.01 ACCESORIOS PARA POZO DE PERCOLACION glb 1.00 1,000.00 1,000.00 1.00 1,000.00 1,000.00
03.05.04.06 ALBAÑILERIA
03.05.04.06.01 MURO DE LADR. EN CABEZA DE POZO PERCOLADOR m2 144.80 109.47 15,851.26 144.80 109.47 15,851.26
03.05.04.07 FILTRO DE GRAVA
03.05.04.07.01 SUMINISTRO E INSTALACION DE PIEDRA SELECCIONADA m3 40.79 74.00 3,018.46 40.79 74.00 3,018.46
03.05.04.08 COLOCACION DE TAPAS DE CONCRETO
03.05.04.08.01 COLOCACION DE TAPAS DE CONCRETO und 4.00 112.99 451.96 4.00 112.99 451.96
4 UBS CON ARRASTRE HIDRAULICO
4.01 UBS CON ARRASTRE HIDRAULICO DE LA LOCALIDAD DE COLLON (118UND)
04.01.01 OBRAS PRELIMINARES
04.01.01.01 TRAZO, NIVEL Y REPLANTEO m2 1267.17 1.32 1,672.66 676.54 1.32 893.03
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACION MANUAL EN MATERIAL SUELTO (CIMENTOS CORRIDOS) m3 302.32 40.47 12,234.89 161.41 40.47 6,532.19
04.01.02.02 EXCAVACION MANUAL P/TUBERIA EN MATERIAL SUELTO 0.50X0.80M m 1652.00 3.54 5,848.08 882.00 3.54 3,122.28

2
PARTIDAS DEDUCIDAS

EXPEDIENTE TECNICO DEDUCIDAS


PARTIDA DESCRIPCIÓN
UND. METRADO PRECIO S/. PARCIAL S/. METRADO PRECIO S/. PARCIAL S/.
04.01.02.03 EXCAVACION MANUAL EN MATERIAL SUELTO (BIODIGESTOR) m3 321.08 40.47 12,994.11 171.42 40.47 6,937.53
04.01.02.04 EXCAVACION MANUAL EN MATERIAL SUELTO (POZO PERCOLADOR) m3 375.55 40.47 15,198.51 200.51 40.47 8,114.46
04.01.02.05 REFINE, NIVELACION Y COMPACTACION m2 880.52 3.47 3,055.40 470.11 3.47 1,631.28
04.01.02.06 RELLENO Y COMPACTADO CON EQUIPO C/MATERIAL PROPIO m3 63.54 30.51 1,938.61 33.92 30.51 1,035.02
04.01.02.07 RELLENO CON MATERIAL PROPIO DE ZANJA C/EQUIPO m 1652.00 13.43 22,186.36 882.00 13.43 11,845.26
04.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50m) m3 1216.03 27.79 33,793.47 649.24 27.79 18,042.28
04.01.03 CASETA
04.01.03.01 OBRAS DE CONCRETO SIMPLE
04.01.03.01.01 FALSO PISO e=4" m2 321.43 35.62 11,449.34 171.61 35.62 6,112.78
04.01.03.01.02 PISO DE CONCRETO PULIDO 2" m2 321.43 18.32 5,888.60 171.61 18.32 3,143.91
04.01.03.01.03 CIMIENTO CORRIDO 1:10 + 30%PM m3 259.84 163.98 42,608.56 138.73 163.98 22,748.64
04.01.03.01.04 SOBRECIMIENTO + MEZCLA C:H=1:8 + 25%PM m3 31.27 180.17 5,633.92 16.70 180.17 3,007.94
04.01.03.01.05 ENCOFRADO Y DESENCOFRADO NORMAL m2 417.02 46.31 19,312.20 222.65 46.31 10,310.75
04.01.03.01.06 CONCRETO F'C=140KG/CM2 PARA ZARDINELES DE DUCHA m3 3.30 262.42 865.99 1.76 262.42 462.35
04.01.03.01.07 ENCOFRADO Y DESENCOFRADO NORMAL PARA SARDINEL DE DUCHA m2 66.08 53.10 3,508.85 35.28 53.10 1,873.37
04.01.03.01.08 VEREDA DE CONCRETO F'C=175 kg/cm2 DE E=4" INC. ENCOFRADO EN CAJA DE REGISTRO m2 303.26 64.76 19,639.12 161.91 64.76 10,485.29
04.01.03.02 ALBAÑILERIA
04.01.03.02.01 MURO ASENTADO CARAVISTA LADRILLO KK18H DE 0.90X0.13X0.24M C:A 1:4, E=1.5CM m2 1775.78 66.37 117,858.52 948.09 66.37 62,924.46
04.01.03.03 REVOQUES ENLUCIDOS Y MOLDURAS
04.01.03.03.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2.0CM m2 1854.81 36.96 68,553.78 990.28 36.96 36,600.75
04.01.03.04 ZOCALOS Y CONTRAZOCALOS
04.01.03.04.01 CONTRAZOCALO DE CEMENTO S/COLOREAR H:30CM m 907.42 9.50 8,620.49 484.47 9.50 4,602.47
04.01.03.05 CONCRETO ARMADO
04.01.03.05.01 CONCRETO F'C=175KG/CM2 m3 27.21 332.40 9,044.60 14.53 332.40 4,828.90
04.01.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 50.59 46.31 2,342.82 27.01 46.31 1,250.83
04.01.03.05.03 ACERO CORRUGADO fy= 4,200 kg/cm2 kg 2598.87 6.21 16,138.98 1387.53 6.21 8,616.58
04.01.03.06 CUBIERTAS
04.01.03.06.01 VIGA DE MADERA DE 2"X2"X3.17MM pza 472.00 26.96 12,725.12 252.00 26.96 6,793.92
04.01.03.06.02 VIGA DE MADERA DE 3"X3"X3.14MM pza 472.00 50.60 23,883.20 252.00 50.60 12,751.20
04.01.03.06.03 COBERTURA CON FIBRAFORTE m2 1001.82 26.90 26,948.96 534.87 26.90 14,388.00
04.01.03.07 CARPINTERIA
04.01.03.07.01 PUERTA METALICA PRE FABRICADA DE 2.10X0.70M und 118.00 318.61 37,595.98 63.00 318.61 20,072.43
04.01.03.07.02 VENTANA DE MADERA TORNILLO DE 0.40X0.60M und 118.00 90.47 10,675.46 63.00 90.47 5,699.61
04.01.03.08 PINTURA
04.01.03.08.01 PINTURA DE MURO EXTERIOR C/ESMALTE SINTETICO m2 1899.15 12.34 23,435.51 1013.95 12.34 12,512.18
04.01.04 BIODIGESTOR
04.01.04.01 SUMINISTRO E INSTALACION DE BIODIGESTORES und 118.00 746.74 88,115.32 63.00 746.74 47,044.62
04.01.04.02 CAJA DE REGISTRO DE LODOS DE 0.60X0.60X0.60M und 118.00 345.07 40,718.26 63.00 345.07 21,739.41
04.01.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.52 46.31 765.04 8.82 46.31 408.45
04.01.04.04 CONCRETO F'C=175KG/CM2 m3 5.78 332.40 1,921.27 3.09 332.40 1,025.76
04.01.05 POZO DE PERCOLACION
04.01.05.01 FILTRO - GRAVA 1/2" m3 186.56 60.89 11,359.64 99.60 60.89 6,064.89
04.01.05.02 FILTRO - GRAVA 2" m3 8.50 60.89 517.57 4.54 60.89 276.33
04.01.05.03 MURO DE LADR. EN CABEZA DE POZO PERCOLADOR m2 533.82 87.47 46,693.24 285.01 87.47 24,929.44
04.01.05.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 203.00 46.31 9,400.93 108.38 46.31 5,019.14
04.01.05.05 CONCRETO F'C=175KG/CM2 EN VIGUETAS m3 73.13 332.40 24,308.41 39.04 332.40 12,978.22
04.01.05.06 SUMINISTRO DE ACCESORIO DE POZO DE PERCOLACION und 118.00 36.49 4,305.82 63.00 36.49 2,298.87
04.01.05.07 TAPA DE CONCRETO PARA POZO DE PERCOLACION und 118.00 33.45 3,947.10 63.00 33.45 2,107.35

3
PARTIDAS DEDUCIDAS

EXPEDIENTE TECNICO DEDUCIDAS


PARTIDA DESCRIPCIÓN
UND. METRADO PRECIO S/. PARCIAL S/. METRADO PRECIO S/. PARCIAL S/.
04.01.06 INSTALACIONES SANITARIAS
04.01.06.01 APARATOS Y ACCESORIOS SANITARIOS
04.01.06.01.01 INODORO TANQUE BAJO BLANCO und 118.00 144.07 17,000.26 63.00 144.07 9,076.41
04.01.06.01.02 DUCHA CROMADA 1 LLAVE INC. ACCESORIOS und 118.00 60.18 7,101.24 63.00 60.18 3,791.34
04.01.06.01.03 LAVATORIO DE PARED BLANCO + ACCESORIOS und 118.00 72.88 8,599.84 63.00 72.88 4,591.44
04.01.06.01.04 COLOCACION DE APARATOS SANITARIOS und 354.00 19.91 7,048.14 189.00 19.91 3,762.99
04.01.06.01.05 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC und 118.00 19.05 2,247.90 63.00 19.05 1,200.15
04.01.06.02 SISTEMA DE AGUA FRIA
04.01.06.02.01 SUMINISTRO E INSTALACION DE TUBERIAS PVC SAP DE 1/2" m 885.00 3.58 3,168.30 472.50 3.58 1,691.55
04.01.06.02.02 VALVULA ESFERICA DE BRONCE 1/2" und 118.00 37.59 4,435.62 63.00 37.59 2,368.17
04.01.06.02.03 SALIDA DE AGUA FRIA CON TUBERIA PVC-SAP 1/2" pto 354.00 21.02 7,441.08 189.00 21.02 3,972.78
04.01.06.03 SISTEMA DE DESAGUE
04.01.06.03.01 SALIDA DE DESAGUE EN PVC 2" und 236.00 27.81 6,563.16 126.00 27.81 3,504.06
04.01.06.03.02 SALIDA DE DESAGUE EN PVC 4" und 118.00 63.02 7,436.36 63.00 63.02 3,970.26
04.01.06.03.03 SALIDA DE VENTILACION 2" pto 118.00 28.24 3,332.32 63.00 28.24 1,779.12
04.01.06.04 REDES COLECTORAS
04.01.06.04.01 TUBERIA PVC SAL 2" m 1239.00 10.35 12,823.65 661.50 10.35 6,846.53
04.01.06.04.02 TUBERIA PVC SAL 4" m 885.00 23.22 20,549.70 472.50 23.22 10,971.45
04.01.06.04.03 REGISTRO DE 4" und 118.00 45.51 5,370.18 63.00 45.51 2,867.13
04.01.06.04.04 SUMIDERO DE BRONCE DE 2" und 236.00 23.83 5,623.88 126.00 23.83 3,002.58
04.01.06.04.05 CAJA DE REGISTRO 12"X24" und 118.00 100.37 11,843.66 63.00 100.37 6,323.31
04.01.06.05 LAVADERO DOMICILIARIO
04.01.06.05.01 LAVADERO DE CONCRETO und 118.00 370.76 43,749.68 63.00 370.76 23,357.88
TOTAL COSTO DIRECTO (CD) 4,214,853.28 724,545.61
GASTOS GENERALES (11.64%) 490,976.40 0.00
UTILIDAD (3.99%) 168,594.13 0.00
COSTO PARCIAL 4,874,423.81 724,545.61
I.G.V. (18.00%) 877,396.29 130,418.21
COSTO DE EJECUCION DE OBRA (PRESUPUESTO REFERENCIAL) 5,751,820.10 854,963.82