ITEM DESCRIPCION MES-1 MES-2 MES-3 MES-4 MES-5 MONTO
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
01 OBRAS PROVISIONALES
01.01 CAMPAMENTO PROVISIONAL DE LA OBRA S/. 3,409.24 3,409.24
P
01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M S/. 850.00 850.00
P
01.03 MOVILIZACION DE MAQUINARIAS-HERRAMIENTAS PARA LA OBRA S/. 3,150.00 3,150.00
P
02 TRABAJOS PRELIMINARES
02.01 TRAZO, NIVELACION Y REPLANTEO S/. ### 5,705.15
P
02.02 ROCE S/. 4,431.46 4,431.46
P
03 EXPLANACIONES
03.01 CORTE CON MAQUINARIA MATERIAL SUELTO S/. 29,048.16 46,477.06 46,477.06 46,477.06 29,048.16 197,527.50
P
03.02 CORTE ROCA SUELTA (PERF. Y DISP.) RENDIMIENTO=250 M3/DIA S/. 33,495.50 33,495.50 66,991.00
P
03.03 CORTE ROCA FIJA (PERF. Y DISP.) RENDIMIENTO=160 M3/DIA S/. 8,405.03 8,405.03 16,810.06
P
03.04 DESQUINCHE Y PEINADO DE TALUDES REND=440 M3/DIA S/. 6,615.00 26,460.00 19,845.00 52,920.00
P
03.05 ELIMINACION DE MATERIAL EXCEDENTE A BOTADEROS S/. 8,307.00 8,307.00 16,614.00
P
03.06 BASE GRANULAR E=0.20 M REND.=2310 M2/DIA FACT. COMPACT.= S/. 59,840.00 59,840.00 119,680.00
P
04 OBRAS DE ARTE
04.01 ALCANTARILLAS DE CONCRETO (21 UND)
04.01.01 TRAZO Y REPLANTEO S/. 148.87 148.87 148.87 446.60
P
04.01.02 EXCAVACION S/. 653.56 653.56 653.56 1,960.69
P
04.01.03 MAMPOSTERIA DE PIEDRA S/. 229.59 229.59 229.59 688.76
P
04.01.04 CONCRETO F'C=175 KG/CM2 S/. ### ### ### 8,274.57
P
04.01.05 ENCOFRADO Y DESENCOFRADO S/. 1,789.93 1,789.93 1,789.93 5,369.78
P
04.01.06 ACERO f´y=4,200 Kg/cm2 S/. 3,054.92 3,054.92 3,054.92 9,164.76
P
04.01.07 RELLENO Y COMPACTADO CON MATERIAL PROPIO S/. 157.78 157.78 157.78 473.33
DURACION
ITEM DESCRIPCION MES-1 MES-2 MES-3 MES-4 MES-5 MONTO
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
P
04.02 BADEN (01UND)
04.02.01 TRAZO Y REPLANTEO S/. 91.20 91.20
P
04.02.02 EXCAVACION S/. 218.40 218.40
P
04.02.03 ENCOFRADO Y DESENCOFRADO S/. 87.72 87.72
P
04.02.04 CONCRETO FC=210 KG/CM2 S/. 3,335.30 3,335.30
P
04.02.05 EMBOQUILLADO DE PIEDRA CANTO RODADO E= 0.20 m. 140 Kg/cm S/. 439.92 439.92
P
04.02.06 ACERO f´y=4,200 Kg/cm2 S/. 732.70 732.70
P
04.02.07 ENROCADO CON PIEDRA DE 8" S/. 654.24 654.24
P
04.02.08 JUNTA DE DILATACION S/. 248.64 248.64
P
04.03 PONTON (L= 3.00 M.)
04.03.01 TRAZO Y REPLANTEO S/. 47.08 47.08
P
04.03.02 EXCAVACION PARA ESTRUCTURAS RENDIMIENTO=25 M3/DIA S/. 84.93 84.93
P
04.03.03 CONCRETO CICLOPEO f´c= 175kg/cm2 +70% PM S/. 6,390.71 6,390.71
P
04.03.04 ENCOFRADO Y DESENCOFRADO DE MUROS S/. 1,528.84 1,528.84
P
04.03.05 CONCRETO EN LOSAS MACIZAS F'C=210 KG/CM2 S/. 869.21 869.21
P
04.03.06 CONCRETO F'C=175 KG/CM2 EN VIGA SARDINEL S/. 150.49 150.49
P
04.03.07 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZAS S/. 599.35 599.35
P
04.03.08 ENCOFRADO Y DESENCOFRADO PARA VIGAS SARDINEL S/. 138.58 138.58
P
04.03.09 ACERO ESTRUCTURAL FY=4200 KG/CM2 LOSA S/. 1,798.06 1,798.06
P
04.03.10 APOYO MOVIL S/. 1,209.42 1,209.42
P
04.03.11 BARANDA DE TUBO FºGº 3" S/. ### 1,770.72
P
04.04 CUNETAS
04.04.01 EXCAVACION DE CUNETA S/. 9,514.30 9,514.30 9,514.30 9,514.30 38,057.18
P
05 SEÑALIZACION
05.01 EXCAVACION Y COLOCACION POSTES KILOMETRICOS REND 16 H S/. 170.60 170.60
DURACION
ITEM DESCRIPCION MES-1 MES-2 MES-3 MES-4 MES-5 MONTO
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
P
05.02 POSTES KILOMETRICOS S/. 1,185.80 1,185.80
P
05.03 FABRICACION DE SEÑALES REGLAMENTARIAS RENDIMIENTO=25 S/. 713.55 713.55
P
06 FORESTACION DE TALUDES
06.01 EXCAVACION DE HOYOS PARA PLANTACION DE ARBOLES S/. ### ### ### 1,274.99 5,099.99
P
06.02 SIEMBRA DE PLANTONES INCL. TAPADO DE HOYOS Y SUMINISTR S/. 2,925.00 2,925.00 2,925.00 2,925.00 11,700.00
P
07 OBRAS COMPLEMENTARIAS
07.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESIO S/. 150.00 150.00 300.00
P
07.02 DISEÑO DE MEZCLAS DE CONCRETO LAB. S/. 700.00 700.00
P
07.03 PLACA DECORDATORIA S/. 300.00 300.00
P
08 FLETE TERRESTRE
08.01 FLETE TERRESTRE S/. 500.00 666.67 666.67 666.66 2,500.00
P
COSTO DIRECTO 60,786.84 129,640.85 164,915.53 135,026.67 105,219.65 595,589.53