NIVELAIÓN DIFERENCIAL DE IDA

PV + AL - COTAS
BN-A 1.423 2,501.423 2,500.000
PL -1 1.235 2501.708 0.950 2,500.473
PL-2 1.225 2501.102 1.831 2499.877
PL-3 1.123 2501.117 1.108 2499.994
BN-B 2.505 2498.612

SUMAS 5.006 6.394


COMPROBACIÓN ARITMÉTICA

LECT (+)= 5.006


LECT (-)= 6.394
h= -1.388 m

COTA BN-2 (LLEGADA)= 2498.612 OK


COTA BN-1 (SALIDA)= 2500.000
h= -1.388 m

NIVELACIÓN DIFERECIAL DE REGRESO


PV + AL - COTAS
BN-B 1.856 2500.468 2498.612
PL-4 1.123 2500.139 1.452 2499.016
PL-5 1.346 2499.535 1.950 2498.189
PL-6 1.925 2500.295 1.165 2498.370
BN-A 0.205 2500.090

SUMAS 6.250 4.772


COMPROBACIÓN ARITMETICA
LECT(+)= 6.250
LECT(-)= 4.772
h2= 1.478 m

COTA BN-1 (LLEGADA)= 2500.09 OK


COTA BN-2 (SALIDA)= 2498.612
h2= 1.478 m
9/1/2022
OPERACIONES
COTAS BN-A = 2500.000
+ 1.423
AL = 2,501.423
- 0.95
COTA PL-1 = 2,500.473
+ 1.235
AL = 2501.708
- 1.831
COTA PL-2 = 2499.877
+ 1.225
AL = 2501.102
- 1.108
COTA PL-3 = 2499.994
+ 1.123
AL = 2501.117
- 2.505
COTA BN-B= 2498.612
=

9/1/2022
OPERACIONES

COTA DE LLEGADA= 2500.090


COTA DE PARTIDA= 2500.000
ERROR Eh= 0.090

TOLERNACIA (T)
k=2 (1250m)= 2500 = 2.5 km
T= ±0.01√𝑘=0.01√2.5=±0.016𝑚

Eh< T ; SE ACEPTA LA NIVELACIÓN

h PROMEDIO = 2.378 + 1.478/2 = 3.117 m

COTA BN-A = 2500.000


DESNIVEL PROMEDIO = + 3.117m
COTA BN-B = 2498.612
NIVELAIÓN DIFERENCIAL DE IDA
PV + AL - COTAS
BN-2 0.253 2,295.350
PL -1 3.785 2299.135 0.355 2,298.882
PL-2 3.925 2302.807 0.475 2302.452
PL-3 3.640 2306.092 0.496 2305.617
BN-3 3.635 2309.252 2308.756

SUMAS 14.985 1.579


COMPROBACIÓN ARITMÉTICA

LECT (+)= 14.985


LECT (-)= 1.579
h= 13.406 m

COTA BN-2 (LLEGADA)= 2308.756 OK


COTA BN-1 (SALIDA)= 2295.350
h= 13.406 m

NIVELACIÓN DIFERECIAL DE REGRESO


PV + AL - COTAS
BN-3 3.035 2311.791 2308.756
PL-4 3.898 2315.472 0.217 2311.574
PL-5 3.940 2319.162 0.250 2315.222
PL-6 3.879 2322.847 0.194 2318.968
BN-2 0.691 2322.156

SUMAS 14.752 1.352


COMPROBACIÓN ARITMETICA
LECT(+)= 14.752
LECT(-)= 1.352
h2= 13.400 m

COTA BN-1 (LLEGADA)= 2322.156 OK


COTA BN-2 (SALIDA)= 2308.756
h2= 13.400 m
9/1/2022
OPERACIONES
COTAS BN-2= 2295.350
+ 3.785
AL = 2,299.135
- 0.253
COTA PL-1 = 2,298.882
+ 3.925
AL = 2302.807
- 0.355
COTA PL-2 = 2302.452
+ 3.640
AL = 2306.092
- 0.475
COTA PL-3 = 2305.617
+ 3.635
AL = 2309.252
- 0.496
COTA BN-3= 2308.756
=

9/1/2022
OPERACIONES

COTA DE LLEGADA= 2322.156


COTA DE PARTIDA= 2295.350
ERROR Eh= 26.806

TOLERNACIA (T)
k= 2295.350 = 2.295 km
T= ±0.01√𝑘=0.01√2.295=±0.015𝑚

Eh> T ; NO SE ACEPTA LA NIVELACIÓN

h PROMEDIO = 40.206 + 13.400/2 = 46.906 m

COTA BN-2 = 2295.350


DESNIVEL PROMEDIO = + 46.906m
COTA BN-3 = 2308.756
NIVELAIÓN DIFERENCIAL DE IDA
PV + AL - COTAS
BN-1 2.859 2,294.359 2,291.500
PL -1 3.945 2297.890 0.414 2,293.945
PL-2 3.786 2301.360 0.316 2297.574
BN-2 0.843 2300.517

SUMAS 10.590 1.573

COMPROBACIÓN ARITMÉTICA

LECT (+)= 10.59


LECT (-)= 1.573
h= 9.017 m

COTA BN-2 (LLEGADA)= 2300.517 OK


COTA BN-1 (SALIDA)= 2291.500
h= 9.017 m

NIVELACIÓN DIFERECIAL DE REGRESO


PV + AL - COTAS
BN-2 2304.444 0.895 2300.517
PL-3 3.927 2307.344 0.534 2303.549
PL-4 3.795 2309.690 0.159 2306.810
BN-1 2.880 2309.531

SUMAS 10.602 1.588


COMPROBACIÓN ARITMETICA
LECT(+)= 10.602
LECT(-)= 1.588
h2= 9.014 m

COTA BN-1 (LLEGADA)= 2309.531 OK


COTA BN-2 (SALIDA)= 2300.517
h2= 9.014 m
9/1/2022
OPERACIONES
COTAS BN-2= 2291.500
+ 2.859
AL = 2,294.359
- 0.414
COTA PL-1 = 2,293.945
+ 3.945
AL = 2297.890
- 0.316
COTA PL-2 = 2297.574
+ 3.789
AL = 2301.360
- 0.843
COTA BN-3= 2300.517
=

9/1/2022
OPERACIONES

COTA DE LLEGADA= 2309.531


COTA DE PARTIDA= 2291.500
ERROR Eh= 18.031

TOLERNACIA (T)
k= 2291.500 = 2.29 km
T= ±0.01√𝑘=0.01√2.29=±0.015𝑚

Eh> T ; NO SE ACEPTA LA NIVELACIÓN

h PROMEDIO = 27.045 + 9.014/2 = 31.552 m

COTA BN-1 = 2291.500


DESNIVEL PROMEDIO = + 31.552m
COTA BN-2 = 2309.531