COSTO DE EQUIPOS

REHABILITACION Y MEJORAMIENTO DE LA CARRETERA EMP. RUTA AN 111 – HUAMANIN – PROGRESO – POQUE – LLATA –
COCHAPATA (TUNEL ANLAY) – NUEVAS FLORES – QUIVILLA – TINGO CHICO Y CONSTRUCCION DEL TUNEL ANLAY.

FECHA PRESUPUESTO BASE: jun-17


TIPO DE CAMBIO S/. : 3.269

PRECIO DE ALQUILER DE EQUIPOS PARA LA OBRA (JUNIO 2017)

CAPECO COSTOS (S10) CONSTRUCTIVO OTROS PRESUPUESTO


EQUIPO UNIDAD
(S/.) PAG. (S/.) PAG. (S/.) PAG. (S/.) PROVEEDOR (S/.)

ANDAMIOS H.M. 1.50 235 1.50


ANDAMIO COLGANTE H.M. 2.50 235 2.50
BOMBA DE CONCRETO H.M. 91.35 GEOTUNEL 91.35
CAMA BAJA 18 Ton H.M. 229.41 124 229.41
CAMA BAJA 25 Ton H.M. 231.92 124 231.92
CAMION BARANDA DE 2 TON H.M. 72.30 SUST. 72.30
CAMION CISTERNA 4 X 2 (AGUA) 145 - 165 HP H.M. 152.72 57 141.24 124 141.24
CAMION DUMPER 6 X 6 H.M. 205.66 57 219.23 GEOTUNEL 205.66
CAMION GRUA DE 5 ton H.M. 120.00 120.00
CAMION IMPRIMADOR 210 HP DE 2000 GLN H.M. 162.85 57 119.33 124 119.33
CAMION MIXER 8 M3 H.M. 259.02 57 258.05 124 258.05
CAMION PLATAFORMA 19 Ton H.M. 257.64 58 231.92 124 231.92
CAMION VOLQUETE 15 m3 H.M. 239.72 58 245.13 124 239.72
CAMIONETA PICK UP 4 X 4 170 HP H.M. 94.71 57 70.72 124 70.72
CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3 H.M. 178.69 56 177.33 123 177.33
CARGADOR SOBRE LLANTAS 200-250 HP 4-4.1 yd3 H.M. 233.15 56 234.09 123 233.15
CHANCADORA PRIMARIA SECUNDARIA 46 - 70 ton/h (*) H.M. 288.94 57 297.00 124 288.94
COMPACTADOR VIBRATORIO TIPO PLANCHA 7 HP H.M. 33.79 56 30.59 123 30.59
COMPRESORA NEUMATICA 87 HP 250-330 PCM H.M. 75.47 56 76.00 123 75.47
COMPRESORA NEUMATICA 196 HP 600-690 PCM H.M. 151.86 56 153.83 123 151.86
CORTADORA DE CONCRETO H.M. 9.80 SUST. 9.80
DOSIFICADORA DE CONCRETO 45 HP 50-90 M3/HR H.M. 120.22 57 110.45 124 110.45
ELEVADOR TELESCOPICO H.M. 132.45 GEOTUNEL 132.45
EQUIPO DE GRANALLADO H.M. 35.14 235 35.14
EQUIPO DE OXICORTE H.M. 6.25 58 6.25
EQUIPO DE PINTURA AIRLESS H.M. 43.74 235 43.74
ESMERIL H.M. 1.67 58 1.67
ESTACION TOTAL H.M. 15.61 58 15.00 235 15.00
EXCAVADORA SOBRE ORUGA 115-165 HP 0.75-1.4 Y3 H.M. 227.99 56 221.04 123 221.04
FAJA TRANSPORTADORA 18"x40" MOTOR ELECTRICO 3 KW 150 TON/H (***) H.M. 7.29 57 6.78 124 6.78
GATAS DE 50 ton H.M. 15.00 15.00
GRUA HIDRAULICA AUTOPROPULSADA 127 HP 18 ton 9 m H.M. 167.31 167.31
GRUA HIDRAULICA AUTOPROPULSADA 147 HP 50 ton 33 m H.M. 193.66 193.66
GRUPO ELECTROGENO 89 HP 50 KW (***) H.M. 85.60 58 95.29 124 85.60
GRUPO ELECTROGENO 116 HP 75 KW (***) H.M. 102.16 58 112.08 124 102.16
GRUPO ELECTROGENO 140 HP 90 KW (***) H.M. 112.78 58 124.78 124 112.78
GRUPO ELECTROGENO 230 HP 150 KW (***) H.M. 129.54 58 139.44 124 129.54
GRUPO ELECTROGENO 380 HP 250 KW (***) H.M. 156.08 58 165.18 124 156.08
HIDROLAVADORA A PRESION H.M. 29.00 29.00
JUMBO DE 2 BRAZOS H.M. 456.73 GEOTUNEL 456.73
MAQUINA PARA PINTAR MARCAS EN PAVIMENTO H.M. 57.21 235 57.21
MARTILLO DE HINCADO H.M. 32.69 SUST. 32.69
MARTILLO DE IMPACTO H.M. 8.00 8.00
MARTILLO HIDRAULICO H.M. 292.31 GEOTUNEL 292.31
MARTILLO NEUMATICO DE 25-29 kg (***) H.M. 6.87 56 5.52 123 5.52
MINICARGADOR 70 HP H.M. 85.31 56 64.60 123 64.60
MEZCLADORA DE CONCRETO DE 11p3 18 HP (****) H.M. 12.36 57 11.07 124 11.07
MONTACARGA 80 HP 5 TON H.M. 89.77 58 87.10 124 87.10
MOTOBOMBA 34 HP 8" (***) H.M. 68.49 58 69.95 124 68.49
MOTOBOMBA 7-10 HP 3-4" (***) H.M. 8.25 58 6.66 124 6.66
MOTONIVELADORA DE 145-150 HP H.M. 203.98 57 205.93 124 203.98
MOTOSIERRA DE 30" H.M. 5.36 SUST. 5.36
MOTOSOLDADORA DE 225 A H.M. 23.70 235 23.70
COSTO DE EQUIPOS
REHABILITACION Y MEJORAMIENTO DE LA CARRETERA EMP. RUTA AN 111 – HUAMANIN – PROGRESO – POQUE – LLATA –
COCHAPATA (TUNEL ANLAY) – NUEVAS FLORES – QUIVILLA – TINGO CHICO Y CONSTRUCCION DEL TUNEL ANLAY.

FECHA PRESUPUESTO BASE: jun-17


TIPO DE CAMBIO S/. : 3.269

PRECIO DE ALQUILER DE EQUIPOS PARA LA OBRA (JUNIO 2017)

CAPECO COSTOS (S10) CONSTRUCTIVO OTROS PRESUPUESTO


EQUIPO UNIDAD
(S/.) PAG. (S/.) PAG. (S/.) PAG. (S/.) PROVEEDOR (S/.)

NIVEL TOPOGRAFICO H.M. 9.46 58 6.90 235 6.90


SE ASUME
PALA SCOOPTRAM 250 HP 5 M3 H.M. 233.15 CARGADOR 233.15
200-250HP
PAVIMENTADORA SOBRE ORUGAS 105 HP 10-16' H.M. 134.41 57 133.85 124 133.85
PISTOLA PARA RESINA EPOXICA H.M. 5.00 5.00
PLANTA ASFALTO EN CALIENTE 150 ton/h (*) (**) H.M. 1400.00 CONCAY 1400.00
RETROEXCAVADOR SOBRE LLANTAS 58 HP 1 yd3 H.M. 104.39 56 97.17 123 97.17
ROBOT DE LANZADO H.M. 255.77 GEOTUNEL 255.77
RODILLO LISO VIBRATORIO AUTOPROPULSADO 101-135HP 10-12 ton H.M. 149.27 56 152.94 123 149.27
RODILLO LISO VIBRATORIO MANUAL 10.8HP 0.8-1.1 ton H.M. 36.60 56 34.98 123 34.98
RODILLO NEUMATICO AUTOPROPULSADO 135 HP 9.26 ton H.M. 135.75 57 149.35 123 135.75
RODILLO TANDEM VIBRATORIO AUTOPROPULSADO 111-130HP 9-11 ton H.M. 199.46 57 199.46
SEMI-TRAYLER 35 Ton H.M. 229.41 57 230.93 124 229.41
SOLDADORA ELECTRICA TRIFASICA 400 A H.M. 13.08 235 13.08
TECLE DE 5 TON H.M. 15.00 15.00
TIRFOR DE 5 TON H.M. 7.50 7.50
TORQUIMETRO H.M. 2.00 2.00
TRACTOR DE ORUGAS DE 140-160 HP H.M. 255.43 56 260.86 123 255.43
TRACTOR DE ORUGAS DE 190-240 HP H.M. 347.11 56 352.41 123 347.11
VIBRADOR DE CONCRETO 4 HP 1.50" (***) H.M. 6.68 56 5.27 123 5.27
ZARANDA ESTATICA H.M. 10.00 10.00
ZARANDA VIBRATORIA 4" X 6" X 14" MOTOR ELECTRICO 15 HP (*) H.M. 61.08 57 53.92 124 53.92
COSTO DE EQUIPOS
REHABILITACION Y MEJORAMIENTO DE LA CARRETERA EMP. RUTA AN 111 – HUAMANIN – PROGRESO – POQUE – LLATA
– COCHAPATA (TUNEL ANLAY) – NUEVAS FLORES – QUIVILLA – TINGO CHICO Y CONSTRUCCION DEL TUNEL ANLAY.

FECHA PRESUPUESTO BASE: jun-17


TIPO DE CAMBIO S/. : 3.269

PRECIO DE ALQUILER DE EQUIPOS PARA LA OBRA (JUNIO 2017)

OPERADOR DE EQUIPO COMBUSTIBLE


(1) (2)

COSTO DE PRESUPUESTO
EQUIPO UNIDAD ELECTRO PETROLEO DIESSEL #
POSESION
MEDIANO PESADO GASOLINA
MECANICO 2

21.29 21.45 21.85 8.16 8.60 (S/.)


IU 47 IU 34 IU 53
ANDAMIOS H.M. 1.50
ANDAMIO COLGANTE H.M. 2.50
CAMA BAJA 18 Ton H.M. 21.45 8.00 68.80 139.16 229.41
CAMA BAJA 25 Ton H.M. 21.45 8.79 75.59 134.88 231.92
CAMION BARANDA DE 2 TON H.M. 21.29 3.08 25.13 25.88 72.30
CAMION CISTERNA 4 X 2 (AGUA) 145 - 165 HP H.M. 21.45 4.50 38.70 81.09 141.24
CAMION DUMPER 6 X 6 H.M. 21.45 5.59 48.07 136.14 205.66
CAMION GRUA DE 5 ton H.M. 21.45 1.60 13.76 84.79 120.00
CAMION IMPRIMADOR 210 HP DE 2000 GLN H.M. 21.45 5.59 48.07 49.81 119.33
CAMION MIXER 8 M3 H.M. 21.45 8.79 75.59 161.01 258.05
CAMION PLATAFORMA 19 Ton H.M. 21.45 8.00 68.80 141.67 231.92
CAMION VOLQUETE 15 m3 H.M. 21.45 8.79 75.59 142.68 239.72
CAMIONETA PICK UP 4 X 4 170 HP H.M. 21.45 3.40 29.24 20.03 70.72
CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3 H.M. 21.45 4.60 39.56 116.32 177.33
CARGADOR SOBRE LLANTAS 200-250 HP 4-4.1 yd3 H.M. 21.45 6.60 56.76 154.94 233.15
CHANCADORA PRIMARIA SECUNDARIA 46 - 70 ton/h (*) H.M. 21.45 267.49 288.94
COMPACTADOR VIBRATORIO TIPO PLANCHA 7 HP H.M. 21.29 0.30 2.45 6.85 30.59
COMPRESORA NEUMATICA 87 HP 250-330 PCM H.M. 21.29 2.40 20.64 33.54 75.47
COMPRESORA NEUMATICA 196 HP 600-690 PCM H.M. 21.29 7.30 62.78 67.79 151.86
CORTADORA DE PAVIMENTO INCLUYE DISCO H.M. 0.50 4.08 5.72 9.80
DOSIFICADORA DE CONCRETO 45 HP 50-90 M3/HR H.M. 110.45
ELEVADOR TELESCOPICO H.M. 21.85 3.00 25.80 84.80 132.45
EQUIPO DE GRANALLADO H.M. 21.85 13.29 35.14
EQUIPO DE OXICORTE H.M. 6.25
EQUIPO DE PINTURA AIRLESS H.M. 21.85 21.89 43.74
ESMERIL H.M. 1.67
ESTACION TOTAL H.M. 15.00 15.00
EXCAVADORA SOBRE ORUGA 115-165 HP 0.75-1.4 Y3 H.M. 21.45 5.00 43.00 156.59 221.04
FAJA TRANSPORTADORA 18"x40" MOTOR ELECTRICO 3 KW 150 TON/H (***) H.M. 6.78 6.78
GATAS DE 50 ton H.M. 15.00
GRUA HIDRAULICA AUTOPROPULSADA 127 HP 18 ton 9 m H.M. 21.45 4.50 38.70 107.16 167.31
GRUA HIDRAULICA AUTOPROPULSADA 147 HP 50 ton 33 m H.M. 21.45 6.00 51.60 120.61 193.66
GRUPO ELECTROGENO 89 HP 50 KW (***) H.M. 6.70 57.62 27.98 85.60
GRUPO ELECTROGENO 116 HP 75 KW (***) H.M. 7.90 67.94 34.22 102.16
GRUPO ELECTROGENO 140 HP 90 KW (***) H.M. 8.70 74.82 37.96 112.78
GRUPO ELECTROGENO 230 HP 150 KW (***) H.M. 9.25 79.55 49.99 129.54
GRUPO ELECTROGENO 380 HP 250 KW (***) H.M. 10.18 87.55 68.53 156.08
HIDROLAVADORA A PRESION H.M. 29.00
JUMBO DE 2 BRAZOS H.M. 21.85 15.80 135.88 299.00 456.73
MAQUINA PARA PINTAR MARCAS EN PAVIMENTO H.M. 57.21 57.21
MARTILLO DE HINCADO H.M. 32.69 32.69
MARTILLO DE IMPACTO H.M. 8.00
MARTILLO HIDRAULICO H.M. 21.45 7.50 64.50 206.36 292.31
MARTILLO NEUMATICO DE 25-29 kg (***) H.M. 5.52 5.52
MINICARGADOR 70 HP H.M. 21.29 1.88 16.17 27.14 64.60
MEZCLADORA DE CONCRETO DE 11p3 18 HP H.M. 11.07 11.07
COSTO DE EQUIPOS
REHABILITACION Y MEJORAMIENTO DE LA CARRETERA EMP. RUTA AN 111 – HUAMANIN – PROGRESO – POQUE – LLATA
– COCHAPATA (TUNEL ANLAY) – NUEVAS FLORES – QUIVILLA – TINGO CHICO Y CONSTRUCCION DEL TUNEL ANLAY.

FECHA PRESUPUESTO BASE: jun-17


TIPO DE CAMBIO S/. : 3.269

PRECIO DE ALQUILER DE EQUIPOS PARA LA OBRA (JUNIO 2017)

OPERADOR DE EQUIPO COMBUSTIBLE


(1) (2)

COSTO DE PRESUPUESTO
EQUIPO UNIDAD ELECTRO PETROLEO DIESSEL #
POSESION
MEDIANO PESADO GASOLINA
MECANICO 2

21.29 21.45 21.85 8.16 8.60 (S/.)


IU 47 IU 34 IU 53
MONTACARGA 80 HP 5 TON H.M. 21.29 2.13 18.32 47.49 87.10
MOTOBOMBA 34 HP 8" (***) H.M. 0.46 3.96 64.53 68.49
MOTOBOMBA 7-10 HP 3-4" (***) H.M. 0.40 3.26 3.40 6.66
MOTONIVELADORA DE 145-150 HP H.M. 21.45 5.60 48.16 134.37 203.98
MOTOSIERRA DE 30" H.M. 0.50 4.30 1.06 5.36
MOTOSOLDADORA DE 225 A H.M. 1.50 12.24 11.46 23.70
NIVEL TOPOGRAFICO H.M. 6.90 6.90
PALA SCOOPTRAM 250 HP 5 M3 H.M. 21.45 6.60 56.76 154.94 233.15
PAVIMENTADORA SOBRE ORUGAS 105 HP 10-16' H.M. 21.45 2.81 24.17 88.23 133.85
PISTOLA PARA RESINA EPOXICA H.M. 5.00
PLANTA ASFALTO EN CALIENTE 150 ton/h (*) (**) H.M. 1400.00 1400.00
RETROEXCAVADOR SOBRE LLANTAS 58 HP 1 yd3 H.M. 21.45 3.00 25.80 49.92 97.17
ROBOT DE LANZADO H.M. 21.85 14.60 125.56 108.36 255.77
RODILLO LISO VIBRATORIO AUTOPROPULSADO 101-135HP 10-12 ton H.M. 21.45 3.60 30.96 96.86 149.27
RODILLO LISO VIBRATORIO MANUAL 10.8HP 0.8-1.1 ton H.M. 21.45 0.26 2.24 11.29 34.98
RODILLO NEUMATICO AUTOPROPULSADO 135 HP 9.26 ton H.M. 21.45 0.13 1.12 113.18 135.75
RODILLO TANDEM VIBRATORIO AUTOPROPULSADO 111-130HP 9-11 ton H.M. 21.45 3.46 29.76 148.25 199.46
SEMI-TRAYLER 35 Ton H.M. 229.41 229.41
SOLDADORA ELECTRICA TRIFASICA 400 A H.M. 13.08 13.08
TECLE DE 5 TON H.M. 15.00
TIRFOR DE 5 TON H.M. 7.50
TORQUIMETRO H.M. 2.00
TRACTOR DE ORUGAS DE 140-160 HP H.M. 21.45 5.10 43.86 190.12 255.43
TRACTOR DE ORUGAS DE 190-240 HP H.M. 21.45 7.70 66.22 259.44 347.11
VIBRADOR DE CONCRETO 4 HP 1.50" (***) H.M. 0.16 1.31 3.96 5.27
ZARANDA ESTATICA H.M. 10.00 10.00
ZARANDA VIBRATORIA 4" X 6" X 14" MOTOR ELECTRICO 15 HP (*) H.M. 21.45 32.47 53.92

NOTA :
(*) Las tarifas de equipos marcados con este simbolo no consideran fuente de poder que accionan dichas unidades
( ** ) La Planta de Asfalto incluye calentador de aceite, secador de áridos, fajas transportadoras y operador. No incluye los combustibles.
(***) Las tarifas de equipos marcados con este simbolo no incluyen operador
(****) Las tarifas de equipos marcados con este simbolo no incluyen combustible, lubricantes, filtros ni operador