Está en la página 1de 2

PLAZO DE EJECUCION

13 al 31 de 01 al 26 de
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial Marzo 2023 Abril 2023 26
45 Dias
19 Días Días

MANO DE OBRA
47 00006 TOPOGRAFO HH 15.33 8.75 134.14 80.00 54.14 134.14
47 00007 OPERARIO HH 583.92 8.75 5,109.30 1,600.00 3,509.30 5,109.30
47 00008 OFICIAL HH 222.06 8.13 1,805.35 1,750.00 55.35 1,805.35
47 00009 PEON HH 1,228.22 7.50 9,211.65 2,950.00 6,261.65 9,211.65
47 00112 OPERADOR DE EQUIPO LIVIANO HH 0.57 8.75 4.99 4.99 - 4.99
MATERIALES
00 07037 ALCOHOL PARA DESINFECCION und 2.00 12.00 24.00 24.00 - 24.00
00 07039 BALDE PLASTICO PARA LAVAR MANOS 8LT UND 1.00 12.00 12.00 12.00 - 12.00
00 07038 BARBIJO CJA 1.00 52.00 52.00 52.00 - 52.00
00 07053 BOTIQUIN DE OBRA IMPLEMENTADO und 1.00 120.00 120.00 120.00 - 120.00
00 07011 EXTINTOR DE POLVO QUIMICO SECO (PQS) und 1.00 200.00 200.00 200.00 - 200.00
00 07047 GUANTES DE LONA par 10.00 10.00 100.00 100.00 - 100.00
00 07040 TOALLA EM ROLLOS UND 4.00 3.00 12.00 12.00 - 12.00
00 06998 YESO DE 28 Kg bls 1.14 18.00 20.52 20.52 - 20.52
01 07046 CORTAVIENTO PARA CASCO UND 5.00 12.00 60.00 60.00 - 60.00
01 07059 GASOLINA GLN 4.01 22.00 88.22 50.00 38.22 88.22
02 00093 ALAMBRE NEGRO N°16 KG 44.07 7.50 330.53 210.00 120.53 330.53
02 07082 ANCLAJE METALICO PARA TENSORES UND 5.00 120.00 600.00 - 600.00 600.00
02 00019 CLAVOS CON CABEZA DE 3" KG 5.10 8.00 40.80 20.00 20.80 40.80
02 07069 COBERTURA CON PLANCHA DE ACERO LAC 0.60M UND 6.00 50.00 300.00 - 300.00 300.00
02 07076 GRAPAS CJA 44.95 2.25 101.14 - 101.14 101.14
02 07075 OJAL UND 49.04 2.00 98.08 - 98.08 98.08
02 07077 TEMPLADORES UND 40.81 15.00 612.15 - 612.15 612.15
02 07063 TUBO DE FIERRO CIRCULAR DE 1 X 1/2" E=2MM X 6M UND 112.40 90.00 10,116.00 - 10,116.00 10,116.00
02 07092 TUBO DE FIERRO CIRCULAR DE 2 1/2" E=2.5MM X 6M UND 49.00 175.00 8,575.00 - 8,575.00 8,575.00
02 07067 TUBO DE FIERRO CIRCULAR DE 2" E=2MM X 6M UND 30.00 120.00 3,600.00 - 3,600.00 3,600.00
02 07068 TUBO NEGRO LAC REDONDO DE 3/8"X6M E=1.8MM M 60.00 9.00 540.00 - 540.00 540.00
03 00094 ACERO KG 519.26 8.00 4,154.08 2,900.04 1,254.04 4,154.08
03 07081 CABLE DE ACERO GALVANIZADO DE 3/8" UND 98.00 5.00 490.00 - 490.00 490.00
04 00033 ARENA FINA M3 0.92 60.00 55.20 - 55.20 55.20
05 00120 PIEDRA GRANDE DE 8" M3 0.25 60.00 15.00 15.00 - 15.00
12 07083 MOTOR ELECTRICO DE DESLIZAMIENTO DE LA MALLA RASCHEL UND 4.00 400.00 1,600.00 - 1,600.00 1,600.00
21 06201 CEMENTO PORTLAND TIPO I (42.5 kg) bls 173.36 29.00 5,027.44 2,506.00 2,521.44 5,027.44
26 07048 ARNES DE SEGURIDAD UND 5.00 120.00 600.00 600.00 - 600.00
29 06869 AGUA PUESTA EN OBRA m3 3.45 8.00 27.60 27.60 - 27.60
29 07052 CINTA DE SEÑALIZADORA UND 2.00 45.00 90.00 90.00 - 90.00
29 07078 MALLA RASCHELL AL 90% S/DISEÑO M2 428.41 17.00 7,282.97 - 7,282.97 7,282.97
29 00232 SOLDADURA CELLOCORD KG 12.00 50.00 600.00 - 600.00 600.00
29 07070 SOLDADURA SUPERCITO KG 12.00 50.00 600.00 - 600.00 600.00
30 07051 CONO DE SEGURIDAD und 8.00 20.00 160.00 160.00 - 160.00
30 07065 DISCO DE CORTE DE 7" UND 86.00 15.00 1,290.00 - 1,290.00 1,290.00
30 07086 DISCO DE CORTE CONCRETO DE 7" UND 28.80 15.00 432.00 122.00 310.00 432.00
30 07066 DISCO DE DESBASTE DE 7" UND 55.00 15.00 825.00 - 825.00 825.00
30 07044 LENTES DESEGURIDAD UND 5.00 8.00 40.00 40.00 - 40.00
30 05721 LIJA DE METAL UND 108.00 2.00 216.00 - 216.00 216.00
30 04922 LIJA PARA PARED UND 1.68 2.00 3.36 - 3.36 3.36
30 07050 MALLA DE SEGURIDAD RLL 2.00 50.00 100.00 80.00 20.00 100.00
30 04403 SOLDADURA ELECTRICA KG 84.55 50.00 4,227.50 - 4,227.50 4,227.50
30 01938 THINER GLN 60.00 30.00 1,800.00 - 1,800.00 1,800.00
37 07049 BOTAS DE JEBE PAR 5.00 25.00 125.00 125.00 - 125.00
37 07042 CASCO DE SEGURIDAD PARA PERSONAL OBRERO UND 5.00 20.00 100.00 100.00 - 100.00
37 06946 CHALECO REFLECTIVO UND 5.00 40.00 200.00 200.00 - 200.00
37 07045 GUANTES DE JEBE PAR 10.00 10.00 100.00 100.00 - 100.00
37 07043 MAMELUCO PARA OBRERO UND 5.00 50.00 250.00 250.00 - 250.00
38 00115 HORMIGON (PUESTO EN OBRA) M3 15.25 60.00 915.00 600.00 315.00 915.00
39 04620 CARTEL DE OBRA INCLUYE INST. Y TRANSP. UND 1.00 350.00 350.00 350.00 - 350.00
39 07091 PLACA RECORDATORIA SEGUN DETALLE UND 1.00 700.00 700.00 - 700.00 700.00
39 07089 SERV. DE ENSAYO DE RESIST. A LA COMP. CONCRETO UND 5.00 50.00 250.00 100.00 150.00 250.00
43 00020 MADERA TORNILLO P2 157.29 9.00 1,415.61 990.93 424.68 1,415.61
43 07033 ROLLIZO DE EUCALIPTO DE 3" X 5.00 M UND 3.00 25.00 75.00 75.00 - 75.00
48 07080 POLEA METALICA UND 10.00 30.00 300.00 - 300.00 300.00
50 07073 TUBERIA DE FIERRO 1 1/4" X 2.0 MM PZA 15.60 66.10 1,031.16 - 1,031.16 1,031.16
53 07072 PETROLEO D-2 GLN 12.00 19.00 228.00 143.00 85.00 228.00
54 00068 PINTURA ANTICORROSIVA GLN 42.00 75.00 3,150.00 - 3,150.00 3,150.00
54 00606 PINTURA ESMALTE SINTETICO GLN 42.00 75.00 3,150.00 - 3,150.00 3,150.00
54 00065 PINTURA LATEX GLN 1.49 65.00 96.85 - 96.85 96.85

Página 1 de 2
PLAZO DE EJECUCION

13 al 31 de 01 al 26 de
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial Marzo 2023 Abril 2023 26
45 Dias
19 Días Días

54 00064 SELLADOR BLANCO PARA MUROS GLN 1.49 45.00 67.05 - 67.05 67.05
56 07084 CALAMINAS GALVANIZADAS DE 0.80x1.80M INCL. ACC DE INSTA UND 24.50 61.04 1,495.48 - 1,495.48 1,495.48
EQUIPO
29 07041 SC ELABORACION DE PLAN COVID 19 UND 1.00 1,500.00 1,500.00 1,500.00 - 1,500.00
29 07036 SC FLETE TERRESTRE(TRANSPORTE DE MATERIAL) GLB 1.00 5,500.00 5,500.00 4,000.00 1,500.00 5,500.00
29 07034 SC INSTALACION PROVISIONAL DE ENERGIA ELECTRICA GLB 1.00 219.17 219.17 80.00 139.17 219.17
29 07035 SC MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA GLB 1.00 500.00 500.00 250.00 250.00 500.00
37 07056 APISONADO MANUAL HE 6.91 15.00 103.65 103.65 - 103.65
37 02732 BROCHA DE 4" UND 1.66 10.00 16.60 - 16.60 16.60
37 00004 HERRAMIENTAS MANUALES %MO 505.62 245.00 260.62 505.62
37 04979 MIRA TOPOGRAFICA HE 15.35 15.00 230.25 130.00 100.25 230.25
37 04980 NIVEL TOPOGRAFICO HE 15.35 15.00 230.25 130.00 100.25 230.25
39 07090 SERVICIO DE DISEÑO DE MEZCLA DE CONCRETO 210 KG/CM2 UND 1.00 350.00 350.00 350.00 - 350.00
48 07061 ANDAMIO DIA 32.34 18.00 582.12 - 582.12 582.12
48 00464 MAQUINA SOLDADORA HM 100.50 10.00 1,005.00 - 1,005.00 1,005.00
49 07074 AMOLADORA DE 7" HM 38.40 10.00 384.00 384.00 - 384.00
49 07055 COMPACTADOR VIBR. TIPO PLANCHA 4 HP DIA 0.58 45.00 26.10 26.10 - 26.10
49 00671 COMPRESORA HM 48.00 20.00 960.00 - 960.00 960.00
49 07087 COMPRESORA CON PISTOLA AEROGRAFO HE 48.00 12.50 600.00 - 600.00 600.00
49 05636 MARTILLO ELECTRO DEMOLEDOR HM 38.40 18.00 691.20 691.20 - 691.20
49 07058 MEZCLADORA CONCRETO TAMBOR 11P3-18HP HM 6.12 18.00 110.16 100.00 10.16 110.16
49 07060 VIBRADOR DE CONCRETO 4 HP 1.35" DIA 1.30 40.00 52.00 40.00 12.00 52.00
COSTO DIRECTO 99,069.29 24,870.03 74,199.26 99,069.29
Gastos Generales 20.32668 % 20,137.50 5,055.25 15,082.25 20,137.50
Gastos de Supervision 7.03901% 6,973.50 1,750.60 5,222.90 6,973.50
Gastos de Liquidacion 7.27975% 7,212.00 1,810.48 5,401.52 7,212.00
Gastos de Expediente 8.26644% 8,189.50 2,055.87 6,133.63 8,189.50
PRESUPUESTO TOTAL 141,581.79 35,542.23 106,039.56 119,206.79
TOTAL ACUMULADO 35,542.23 141,581.79
PORCENTAJE DE AVANCE 25.10% 74.90%
PORCENTAJE ACUMULADO 25.10% 100.00%

Página 2 de 2