Documentos de Cultura
3.1 PLANTILLA EN CONCRETO 3.000 PSI-EXP. 0.1 MT. M2 36.71 12,000.00 440,520.00
3.3 CERAMICA PARA PAREDES DEL BAÑO ALT. 1.6 M2 11.52 10,000.00 115,200.00
EXCAVACION MANUAL
DESCRIPCION LARGO ANCHO LARGO 2 ANCHO 2 CANTIDAD
RAMPA DISCAPACITDOS 7.7 1.5 9.2
PLANTILLA 1 3.6 1.6 5.2
PLANTILLA 2 4.1 1.8 2.8 8.7
PLANTILLA 3 2.1 1.5 3.6
PLANTILLA OFICINA 4.6 1.2 5.8
TOTAL 32.5
DESMONTE CUBIERTA
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CUBIERTA 7.60 6.2 1 47.1
ANTIGUA PERSONERIA
CUBIERTA 3.40 6 1 20.4
OFICINA
CENTRO 4.80 3 1 14.4
TOTAL 81.9
DEMOLICION
DESCRIPCION LARGO ANCHO ALTO CANTIDAD VOLUMEN ( m3)
COLUMNAS 0.3 2.5 4.5 4 13.5
PLACA SOPORTE TANQUE 2 3.5 0.2 1 1.4
TOTAL 14.9
RELLENO
DESCRIPCION LARGO ANCHO ALTO AREA (m2) VOLUMEN ( m3)
ANDEN OFICINA 4.6 1.2 0.1 5.5 0.552
PLANTILLA1 3.6 1.6 0.1 5.8 0.576
PLANTILLA2 4.4 4.1 0.1 18.0 1.804
PLANTILLA3 7.7 1.5 0.1 11.6 1.155
RAMPA PARA DISCAPACITASDOS 7.7 1.5 0.1 3.9 5.85
TOTAL 9.9
MAMPOSTERIA
DESCRIPCION LARGO ANCHO ALTO CARAS AREA (m2)
VENTANA FRONTAL 1 1.5 1.2 1.8
VENTANA FRONTAL 2 1 1.2 1.2
VENTANA TRASERA 1.2 1 1.2
PARED PERIMETRAL 4.5 1 4.5
VENTOLIN 1 0.15 0.2
TOTAL MAMPOSTERIA 8.9
PAÑETE
DESCRIPCION LARGO ANCHO ALTO CARAS AREA (m2)
VENTANA FRONTAL 1 1.5 1.2 2 3.6
VENTANA FRONTAL 2 1 1.2 2 2.4
PARED TRASERA BAÑO DE OFICINA 2.8 3 2 16.8
VENTANA TRASERA 1.2 1 2 2.4
VENTOLIN 1 0.15 2 0.3
TOTAL MAMPOSTERIA 25.5
ESTUCO
DESCRIPCION ANCHO ALTO CANTIDAD AREA (m2)
ARCHIVO
PARED FRONTAL 7.6 3.05 1 23.2
PARED TRASERA 7.6 3.05 1 23.2
PARED LATERAL DER 6 3.3 1 19.8
PARED LATERAL IZQ 6 2.8 1 16.8
ANTIGUA PERSONERIA
PARED FRONTAL 3.3 3.2 1 10.6
PARED TRASERA 3.3 3.2 1 10.6
PARED LATERAL DER 6 3.4 1 20.4
PARED LATERAL IZQ 6 3 1 18.0
OFICINA
PARED FRONTAL 6.75 3 1 20.3
PARED TRASERA 6.75 3.2 1 21.6
PARED LATERAL DER 3 3.4 1 10.2
PARED LATERAL IZQ 3 2.6 1 7.8
PARED INTERNA BAÑO 1.15 2.25 1 2.6
AREA A DESCONTAR
PUERTA OFICINA 1 2 1 2.0
PUERTA BAÑO OFICINA 1 2 1 2.0
PUERTA ARCHIVO 1 2 1 2.0
PUERTA ANTIGUA PERSONERIA 1 2 1 2.0
TOTAL 196.9
VIDRIO PUERTA ARCHIVO
DESCRIPCION LARGO ANCHO ALTO CANTIDAD VOLUMEN ( m3)
VIDRIO PUERTA ARCHIVO 1 0.3 1 0.30
PISA TOLETE
DESCRIPCION LONG CANTIDAD LONG TOTAL
ARCHIVO
PISA TOLETE 7.69 2 15.4
ANTIGUA PERSONERIA
PISA TOLETE 3.34 2 6.7
OFICINA
PISA TOLETE 6.76 2 13.5
TOTAL 35.6
PARED PERIMETRAL
DESCRIPCION LARGO ANCHO ALTO CANT VOLUMEN (M3)
COLUMNAS 0.15 0.15 2.2 2 0.10
VIGAS SOBRE MURO 4.5 0.15 0.2 1 0.14
ZAPATAS 0.4 0.4 0.4 2 0.13
ACERO
DESCRIPCION LARGO CANTI PESO (KG) PESO TOTAL
COLUMNAS
LONGITUDINAL ACERO 1/2 2.15 4 0.994 8.55
ESTRIBOS ACERO 3/8 0.35 13.3333 0.56 2.61
VIGA SOBRE MURO
LONGITUDINAL ACERO 1/2 4.5 3 0.994 13.42
ESTRIBOS ACERO 3/8 0.7 30 0.56 11.76
ZAPATA
LONGITUDINAL ACERO 1/2 0.3 8 0.994 2.39
TRASNVERSAL 1/2 0.3 8 1.994 4.79
TOTAL 43.51
PLANTILLA
DESCRIPCION LARGO ANCHO ALTO AREA ( m2)
VIGA CIMIENTO 32.5 0.2 6.5
ANDEN OFICINA 4.6 1.2 5.5
PLANTILLA1 3.6 1.6 5.8
PLANTILLA2 1.8 4.1 7.4
PLANTILLA3 7.7 1.5 11.6
TOTAL 36.7
CERAMICA
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CERRAMICA 7.28 5.7 1 41.5
OFICINA
CENTRO 3.3 2.8 1 9.2
BAÑO 2.8 1.3 1 3.6
HALL 2.2 1.55 1 3.4
TOTAL 57.8
CERAMICA PAREDES DEL BAÑO
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
OFICINA
BAÑO 4.7 2.5 1.6 11.5
TOTAL 11.5
RAMPA
DESCRIPCION LARGO ANCHO ALTO AREA ( m2) VOLUMEN ( m3)
RAMPA 7.7 1.5 0.2 1.5 11.6
ZOCALO
DESCRIPCION LARGO ANCHO CANTIDAD LONG TOTAL
ARCHIVO
ZOCALO 7.28 5.7 2 26.0
OFICINA
CENTRO 3.3 2.8 2 12.2
BAÑO 2.8 1.3 2 8.2
HALL 2.2 1.55 2 7.5
TOTAL 53.9
CUBIERTA
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CUBIERTA 7.69 6 1 46.2
ANTIGUA PERSONERIA
CUBIERTA 3.34 6 1 20.0
OFICINA
CENTRO 6.76 3.3 1 22.3
TOTAL 88.5
CORREA DE PERFIL
DESCRIPCION LARGO CANTIDAD AREA (m2)
ARCHIVO
CUBIERTA 6.20 2 12.4
OFICINA
PERFILES 3.20 6 19.2
TOTAL 31.6
CIELO RASO
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CIELO RASO 7.28 5.7 1 41.5
ANTIGUA PERSONERIA
CIELO RASO 5.75 2.95 1 17.0
OFICINA
CENTRO 3.3 2.8 1 9.2
BAÑO 2.8 1.3 1 3.6
HALL 2.2 1.55 1 3.4
TOTAL 74.7
VENTANILLA UNICA
DESCRIPCION LARGO ALTO AREA ( m2) VOLUMEN ( m3)
VENTANILLA UNICA 0.9 1.2 2.1 0.0
PUERTAS Y VENTANAS
DESCRIPCION ALTO ANCHO CANTIDAD AREA (m2)
ARCHIVO
PUERTA 2 1 1 2.0
VENTANAL 0.3 1 1 0.3
ANTIGUA PERSONERIA
PUERTA 2 1 1 2.0
VENTANA FRONTAL 1 1.2 1.5 1 1.8
VENTANA FRONTAL 2 1.2 1 1 1.2
VENTANA TRASERA 1 1.2 1 1.2
OFICINA
PUERTA 2 1 1 2.0
TOTAL 10.5
PINTURA
DESCRIPCION ANCHO ALTO CANTIDAD AREA (m2)
ARCHIVO
PARED FRONTAL 7.6 3.05 1 23.2
PARED TRASERA 7.6 3.05 1 23.2
PARED LATERAL DER 6 3.3 1 19.8
PARED LATERAL IZQ 6 2.8 1 16.8
ANTIGUA PERSONERIA
PARED FRONTAL 3.3 3.2 1 10.6
PARED TRASERA 3.3 3.2 1 10.6
PARED LATERAL DER 6 3.4 1 20.4
PARED LATERAL IZQ 6 3 1 18.0
OFICINA
PARED FRONTAL 6.75 3 1 20.3
PARED TRASERA 6.75 3.2 1 21.6
PARED LATERAL DER 3 3.4 1 10.2
PARED LATERAL IZQ 3 2.6 1 7.8
PARED INTERNA BAÑO 1.15 2.25 1 2.6
AREA A DESCONTAR
PUERTA OFICINA 1 2 1 2.0
PUERTA BAÑO OFICINA 1 2 1 2.0
PUERTA ARCHIVO 1 2 1 2.0
PUERTA ANTIGUA PERSONERIA 1 2 1 2.0
TOTAL 196.9
TOMAS 110
ARCHIVO 4
ANTIGUA PERSONERIA 5
OFICINA 5
TOTAL 14
LUMINARIA 1X18W
OFICINA 3
TOTAL 3
INTERRUPTORES
ARCHIVO 2
ANTIGUA PERSONERIA 1
OFICINA 2
TOTAL 5
EXTRACTORES
ARCHIVO 1
ANTIGUA PERSONERIA 1
OFICINA 0
TOTAL 2
REPUBLICA DE COLOMBIA
DEPARTAMENTO DEL CESAR
MUNICIPIO DE ASTREA
Nit. 892301541-1
Có digo Postal: 201040
7.5 UN 99,254.02
#NAME?
CABLE COBRE No. 12 AWG-THHN/THWN ML 18.00 1,621.58 29,188.44
CURVA CONDUIT PVC SCH 40 1/2" UND 2.00 1,302.07 2,604.14
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 2.00 7,820.40 15,640.80
CAJA 2X4 PVC UND 1.00 1,068.00 1,068.00
ADAPTADOR TERMINAL 1/2" UND 2.00 267.00 534.00
INTERRUPTOR SENCILLO UND 1.00 8,900.00 8,900.00
TRANSPORTE % 0.01 57,935.38 579.35
HERRAMIENTAS MENORES %MO 0.03 39,552.70 1,186.58
MANO DE OBRA BB hc 1.25 31,642.16 39,552.70
7.6 UN 105,984.29
#NAME?
CABLE COBRE No. 12 AWG-THHN/THWN ML 22.00 1,621.58 35,674.76
CURVA CONDUIT PVC SCH 40 1/2" UND 2.00 1,302.07 2,604.14
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 2.00 7,820.40 15,640.80
CAJA 2X4 PVC UND 1.00 1,068.00 1,068.00
ADAPTADOR TERMINAL 1/2" UND 2.00 267.00 534.00
INTERRUPTOR DOBLE UND 1.00 9,400.00 9,400.00
TRANSPORTE % 0.01 64,921.70 649.22
HERRAMIENTAS MENORES %MO 0.03 39,236.28 1,177.09
MANO DE OBRA BB hc 1.24 31,642.16 39,236.28
7.8 UN 3,650,332.96
#NAME?
AIRE MINI SPLIT INVERTER DE 18000 BTU UN 1.00 3,544,000.00 3,544,000.00
ANGULO PARA SOPORTE UN 2.00 12,500.00 25,000.00
CHAZOS DE 5/8" UN 4.00 1,016.00 4,064.00
CHAZOS DE 1/4" UN 8.00 116.00 928.00
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 3,571,633.20 35,716.33
ANDAMIO TUBULAR d 2.00 2,700.00 5,400.00
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16
7.9 UN 2,838,292.96
#NAME?
AIRE MINI SPLIT INVERTER DE 12000 BTU UN 1.00 2,740,000.00 2,740,000.00
ANGULO PARA SOPORTE UN 2.00 12,500.00 25,000.00
CHAZOS DE 5/8" UN 4.00 1,016.00 4,064.00
CHAZOS DE 1/4" UN 8.00 116.00 928.00
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 2,767,633.20 27,676.33
ANDAMIO TUBULAR d 2.00 2,700.00 5,400.00
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16
7.10 UN 680,553.07
#NAME?
EXTRACTOR DE AIRE DE 14" INDUSTRIAL ASPA METALICAS UN 1.00 632,000.00 632,000.00
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 634,633.20 6,346.33
ANDAMIO TUBULAR d 2.00 2,700.00 5,400.00
HERRAMIENTAS MENORES %MO 0.08 31,642.16 2,531.37
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16
PRESTACIONES BASE
Cesantias E 10.00% 1,325,995 10.98%
Intereses Cesantias 12.00% 159,119 1.32%
Vacaciones 15 Dias A 50.00% 500,000 4.11%
Primas 30 Dias C 100.00% 1,106,454 9.20%
OTROS COSTOS
Botas y Overol 82,500 3.00 247,500 4.09%
Seguro Colectivo D 0.50% 60,833 0.50%
SEGURIDAD SOCIAL
Pensiones D 12.00% 1,460,000 12.00%
Medicina Familiar D 8.50% 1,034,167 8.50%
Riesgos Profesionales D 5.60% 681,333 5.60%
APORTES SENA
Aporte Ordinario D 2.00% 243,333 2.00%
F.I.C Nota 4 18.00% 229,941 1.80%
OTROS APORTES
I.C.B.F D 3.00% 365,000 3.00%
Subsidio Familiar D 4.00% 486,667 4.00%
NOTAS:
1.- Subsidio de transporte solo se paga hasta sueldos de 2 salarios minimos mensules legales vigentes.
2.- Subsidio de transporte anual = Subsidio mensual / 30 x (365 dias-18 fiestas - 3 permisos- 15 dias vacaciones).
3.- Porcentajes solo son validos para actividades de construccion. Para otros empleados se debe utilizar 30 dias de cesantia
y 2.2% (promedio para empresas de bajo riesgo).
4.- Un salario minimo por cada 40 trabajadores. El valor se obtiene asi: (Salario minimo x 12 / 40) / Salario annual estudiado.
5.- El crecimiento promedio del PIB entre 2005 y 2006 fue superior al 4%y por ello la cotizacion a pensiones por parte del
patrono durante 2009 debe aumentar al 12%, segun lo dispuesto por la ley 297 del 2003.
* Todos los porcentajes estan relacionados con el salario para 365 dias.
* Los 18 feriados hacen referencia a los dias feriados que de lunes a viernes .
NOTAS:
Los factores de sobrecostos se utilizan para valorizar el tiempo efectivo que un obrero dedica a su labor y refleja el costo del
tiempo durante el cual no esta trabajando pero si esta devengando.
Si se toma como base la hora calendario, se incrementa 24.57% para obtener la hora efectiva.
Si se toma como base la hora laboral, se incrementa 6.83% para obtener la hora efectiva.
CALCULO DE CUADRILLAS
NOTAS:
Jornal = sueldo mensual x 12 meses / 365 dias.
6045617
663,808.75
556200
6767100
743027.58
0
230,125
5,753
ADECUACION Y/O MEJORAMIENTO DE LA INFRAESTRUCTURA FISICA DONDE FUNCIONA EL ARCHIVO
MUNICIPAL, EN EL MUNICIPIO DE ASTREA, CESAR