ITEM DESCRIPCION UND CANT V/UNITARIO V/PARCIAL


1.0 PRELIMINARES
1.1 DESMONTE DE CIELO RASO EXISTENTE M2 81.92 3,000.00 245,760.00
1.2 DESMONTE DE SECCION DE CUBIERTA EXISTENTE M2 81.92 6,000.00 491,520.00
DEMOLICION MECANICA DE ESTRUCTURAS EN
1.4 UND 1.00 300,000.00 300,000.00
CONCRETO

1.5 RELLENO COMPACTADO CON MAT, SELECC. M3 9.94 5,000.00 49,685.00

subtoral preliminares 1,086,965.00


2 ESTRUCTURA Y MAMPOSTERIA
MURO SENCILLO 0.15, LADRILLO COMUN .07X.11X.22
2.1 M2 8.85 8,000.00 70,800.00
INCLUYE MORTERO 1:4
2.2 PAÑETE ALLANADO EN MUROS 1:4 M2 25.50 7,000.00 178,500.00
2.3 ESTUCO IMPERMEABILIZANTE M2 196.92 6,000.00 1,181,505.00
2.4 SUMINISTRO E INSTALACION DE VIDRIO M2 0.30 30,000.00 9,000.00
PISA EN TOLETE COMUN 0.25 MORTERO DE PEGA 1.4,
2.5 ALTURA UNA HILADA- PAÑETADO MORTERO 1:4 ML 35.59 15,000.00 533,809.77
IMPERMEABILIZADO
2.6 ZAPATAS EN CONCRETO 3.000 PSI UND 2.00 50,000.00 100,000.00
2.7 VIGAS SOBRE MURO, CONCRETO 3.000 PSI UND 1.00 50,000.00 50,000.00
2.8 COLUMNAS EN CONCRETO 3.000 PSI. UND 2.00 50,000.00 100,000.00
subtotal estructura mamposteria 2,223,614.77
3 PISOS

3.1 PLANTILLA EN CONCRETO 3.000 PSI-EXP. 0.1 MT. M2 36.71 12,000.00 440,520.00

PISO EN CERAMICA DUROPISO DE PRIMERA CALIDAD,


3.2 M2 57.79 10,000.00 577,860.00
ALTO TRAFICO TIPO CORONA O SIMILAR BLANCO.

3.3 CERAMICA PARA PAREDES DEL BAÑO ALT. 1.6 M2 11.52 10,000.00 115,200.00

CONCRETO DE 3000 PSI ESTRIADO PARA RAMPAS -


3.4 M3 11.55 12,000.00 138,600.00
CICLOVIAS + MINUSVALIDOS-

ZOCALO CERAMICA DUROPISO DE PRIMERA CALIDAD,


3.5 ML 53.86 3,000.00 161,580.00
ALTO TRAFICO TIPO CORONA O SIMILAR BLANCO. H= 8 CM

subtotal pisos 1,433,760.00


4.0 CUBIERTA Y CIELO RASO
CUBIERTA EN LAMINA ARQUITECTONICA GALVANIZADA
4.1 M2 88.50 15,000.00 1,327,574.73
PINTADA DE ACESCO O SIMILAR CAL. 30

SUMINISTRO E INSTALACION CORREA EN PERFIL PHR-C


4.2 120X60 CAL. 14-2MM-INCL. ANTICORROSIVO Y ACABADO ML 31.60 5,000.00 158,000.00
EN ESMALTE

CIELO RASO EN LAMINA DE ICOPOR, INCLUYE


4.3 M2 74.75 10,000.00 747,485.00
ESTRUCTURA DE SOPORTE..

subtotal cubierta y cielo raso 2,233,059.73


5.0 CARPINTERIA DE MADERA Y METALICA

SUMINISTRO E INSTALACION DE PUERTA EN LAMINA CON


5.1 MARCO CAL. 18, INCL. ANTICORROSIVO Y ACABADO EN M2 1.00 50,000.00 50,000.00
ESMALTE, INCLUYE CERRADURA E INSTALACION.

SUMINISTRO E INSTALACION DE VENTANA 744 ANOLOCK-


5.2 VIDRIO, UNA NAVE FIJA Y UNA CORREDIZA ANOLOCK, M2 2.10 50,000.00 105,000.00
INCLUYE VIDRIO

MANTENIMIENTO DE PUERTAS Y VENTANAS, INCLUYE


5.3 LIMPIEZA DESMONTE Y REPOSICION DE MATERIALES, UND 3.00 20,000.00 60,000.00
ACCESORIOS Y/O INSUMOS Y PINTURA; MANO DE OBRA.

5.4 DESMONTE MARCOS, PUERTAS Y VENTANAS M2 10.50 8,000.00 84,000.00

subtotal carpinteria metalica 299,000.00


6.0 PINTURA Y ACABADOS
VINILO 2 MANOS, PINTURA TIPO 1 VINILTEX O SIMILAR EN
6.1 M2 196.92 2,000.00 393,835.00
MANTENIMIENTOS O ADECUACIONES
subtotal pinturas y acabados 393,835.00
7 INSTALACIONES ELECTRICAS

MANO DE OBRA ELECTRICO INCLUYE INSTALACION DE


7.1 AIRES, ADECUACION Y INSTALACION DE LO UND 1.00 3,000,000.00 3,000,000.00
CORRESPONDIENTE

subtotal instalaciones electricas 3,000,000.00

8.0 INSTALACIONES HIDROSANITARIAS


RED SANITARIA PVC 6- 160 MM - INCL. INSTALACION Y
8.1 ML 9.50 8,000.00 76,000.00
TAPE
RED HIDRAULICA EN PVC - 1/2" - INCL. INSTALACION Y
8.2 ML 11.70 8,000.00 93,600.00
TAPE

CAJAS INSPECCION .60 X .60, EN LADRILLO CORRIENTE,


PAÑETADA IMPERMABILIZADA INTEGRALMENTE,
INCLUYE EXCAVACIÓN Y TAPE, TAPA Y HERRAJES,
8.3 UND 2.00 50,000.00 100,000.00
CAÑUELAS, MARCOS EN ANGULO DE 1 1/2"X3/16 E
INCLUYE TODO LO NECESARIO PARA SU CORRECTO
FUNCIONAMIENTO

SUMINISTRO E INSTALACION DE SANITARIO Y


8.4 LAVAMANOS CON PEDESTAL, INCLUYE GRIFERIA Y UND 1.00 100,000.00 100,000.00
ACCESORIOS
subtotal instalaciones Hidrosanitarias 369,600.00

TOTAL COSTO DIRECTO DE OBRA 11,039,834.49


CANTIDADES ADECUACION Y MEJORAMIENTO DE LA INFRAESTRUCTURA
DONDE FUNCIONA EL ARCHIVO MUNICIPAL

EXCAVACION MANUAL
DESCRIPCION LARGO ANCHO LARGO 2 ANCHO 2 CANTIDAD
RAMPA DISCAPACITDOS 7.7 1.5 9.2
PLANTILLA 1 3.6 1.6 5.2
PLANTILLA 2 4.1 1.8 2.8 8.7
PLANTILLA 3 2.1 1.5 3.6
PLANTILLA OFICINA 4.6 1.2 5.8
TOTAL 32.5

DESMONTE TANQUE ELEVADO


DESCRIPCION LARGO ANCHO ALTO CANTIDAD TOTAL
DESMONTE TANQUE 1
TOTAL 1.0

DESMONTE CIELO RASO


DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ANTIGUA PERSONERIA
CIELO RASO 5.72 2.93 1 16.8
OFICINA
CENTRO 3.1 2.8 1 8.7
BAÑO 2.8 1.3 1 3.6
HALL 2.2 1.55 1 3.4
TOTAL 32.5

DESMONTE CUBIERTA
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CUBIERTA 7.60 6.2 1 47.1
ANTIGUA PERSONERIA
CUBIERTA 3.40 6 1 20.4
OFICINA
CENTRO 4.80 3 1 14.4
TOTAL 81.9

DEMOLICIÓN PISO ESPESOR HASTA .30


DESCRIPCION LARGO ANCHO ALTO CANTIDAD VOLUMEN ( m3)
PLANTILLA ANTIGUA 3.1 2.3 0.25 1 1.8
TOTAL 1.78

DEMOLICION
DESCRIPCION LARGO ANCHO ALTO CANTIDAD VOLUMEN ( m3)
COLUMNAS 0.3 2.5 4.5 4 13.5
PLACA SOPORTE TANQUE 2 3.5 0.2 1 1.4
TOTAL 14.9
RELLENO
DESCRIPCION LARGO ANCHO ALTO AREA (m2) VOLUMEN ( m3)
ANDEN OFICINA 4.6 1.2 0.1 5.5 0.552
PLANTILLA1 3.6 1.6 0.1 5.8 0.576
PLANTILLA2 4.4 4.1 0.1 18.0 1.804
PLANTILLA3 7.7 1.5 0.1 11.6 1.155
RAMPA PARA DISCAPACITASDOS 7.7 1.5 0.1 3.9 5.85
TOTAL 9.9

MAMPOSTERIA
DESCRIPCION LARGO ANCHO ALTO CARAS AREA (m2)
VENTANA FRONTAL 1 1.5 1.2 1.8
VENTANA FRONTAL 2 1 1.2 1.2
VENTANA TRASERA 1.2 1 1.2
PARED PERIMETRAL 4.5 1 4.5
VENTOLIN 1 0.15 0.2
TOTAL MAMPOSTERIA 8.9

PAÑETE
DESCRIPCION LARGO ANCHO ALTO CARAS AREA (m2)
VENTANA FRONTAL 1 1.5 1.2 2 3.6
VENTANA FRONTAL 2 1 1.2 2 2.4
PARED TRASERA BAÑO DE OFICINA 2.8 3 2 16.8
VENTANA TRASERA 1.2 1 2 2.4
VENTOLIN 1 0.15 2 0.3
TOTAL MAMPOSTERIA 25.5

ESTUCO
DESCRIPCION ANCHO ALTO CANTIDAD AREA (m2)
ARCHIVO
PARED FRONTAL 7.6 3.05 1 23.2
PARED TRASERA 7.6 3.05 1 23.2
PARED LATERAL DER 6 3.3 1 19.8
PARED LATERAL IZQ 6 2.8 1 16.8
ANTIGUA PERSONERIA
PARED FRONTAL 3.3 3.2 1 10.6
PARED TRASERA 3.3 3.2 1 10.6
PARED LATERAL DER 6 3.4 1 20.4
PARED LATERAL IZQ 6 3 1 18.0
OFICINA
PARED FRONTAL 6.75 3 1 20.3
PARED TRASERA 6.75 3.2 1 21.6
PARED LATERAL DER 3 3.4 1 10.2
PARED LATERAL IZQ 3 2.6 1 7.8
PARED INTERNA BAÑO 1.15 2.25 1 2.6
AREA A DESCONTAR
PUERTA OFICINA 1 2 1 2.0
PUERTA BAÑO OFICINA 1 2 1 2.0
PUERTA ARCHIVO 1 2 1 2.0
PUERTA ANTIGUA PERSONERIA 1 2 1 2.0
TOTAL 196.9
VIDRIO PUERTA ARCHIVO
DESCRIPCION LARGO ANCHO ALTO CANTIDAD VOLUMEN ( m3)
VIDRIO PUERTA ARCHIVO 1 0.3 1 0.30

PISA TOLETE
DESCRIPCION LONG CANTIDAD LONG TOTAL
ARCHIVO
PISA TOLETE 7.69 2 15.4
ANTIGUA PERSONERIA
PISA TOLETE 3.34 2 6.7
OFICINA
PISA TOLETE 6.76 2 13.5
TOTAL 35.6

PARED PERIMETRAL
DESCRIPCION LARGO ANCHO ALTO CANT VOLUMEN (M3)
COLUMNAS 0.15 0.15 2.2 2 0.10
VIGAS SOBRE MURO 4.5 0.15 0.2 1 0.14
ZAPATAS 0.4 0.4 0.4 2 0.13

ACERO
DESCRIPCION LARGO CANTI PESO (KG) PESO TOTAL
COLUMNAS
LONGITUDINAL ACERO 1/2 2.15 4 0.994 8.55
ESTRIBOS ACERO 3/8 0.35 13.3333 0.56 2.61
VIGA SOBRE MURO
LONGITUDINAL ACERO 1/2 4.5 3 0.994 13.42
ESTRIBOS ACERO 3/8 0.7 30 0.56 11.76
ZAPATA
LONGITUDINAL ACERO 1/2 0.3 8 0.994 2.39
TRASNVERSAL 1/2 0.3 8 1.994 4.79
TOTAL 43.51

PLANTILLA
DESCRIPCION LARGO ANCHO ALTO AREA ( m2)
VIGA CIMIENTO 32.5 0.2 6.5
ANDEN OFICINA 4.6 1.2 5.5
PLANTILLA1 3.6 1.6 5.8
PLANTILLA2 1.8 4.1 7.4
PLANTILLA3 7.7 1.5 11.6
TOTAL 36.7

CERAMICA
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CERRAMICA 7.28 5.7 1 41.5
OFICINA
CENTRO 3.3 2.8 1 9.2
BAÑO 2.8 1.3 1 3.6
HALL 2.2 1.55 1 3.4
TOTAL 57.8
CERAMICA PAREDES DEL BAÑO
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
OFICINA
BAÑO 4.7 2.5 1.6 11.5
TOTAL 11.5

RAMPA
DESCRIPCION LARGO ANCHO ALTO AREA ( m2) VOLUMEN ( m3)
RAMPA 7.7 1.5 0.2 1.5 11.6

ZOCALO
DESCRIPCION LARGO ANCHO CANTIDAD LONG TOTAL
ARCHIVO
ZOCALO 7.28 5.7 2 26.0
OFICINA
CENTRO 3.3 2.8 2 12.2
BAÑO 2.8 1.3 2 8.2
HALL 2.2 1.55 2 7.5
TOTAL 53.9

CUBIERTA
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CUBIERTA 7.69 6 1 46.2
ANTIGUA PERSONERIA
CUBIERTA 3.34 6 1 20.0
OFICINA
CENTRO 6.76 3.3 1 22.3
TOTAL 88.5

CORREA DE PERFIL
DESCRIPCION LARGO CANTIDAD AREA (m2)
ARCHIVO
CUBIERTA 6.20 2 12.4
OFICINA
PERFILES 3.20 6 19.2
TOTAL 31.6

CIELO RASO
DESCRIPCION LARGO ANCHO CANTIDAD AREA (m2)
ARCHIVO
CIELO RASO 7.28 5.7 1 41.5
ANTIGUA PERSONERIA
CIELO RASO 5.75 2.95 1 17.0
OFICINA
CENTRO 3.3 2.8 1 9.2
BAÑO 2.8 1.3 1 3.6
HALL 2.2 1.55 1 3.4
TOTAL 74.7

VENTANILLA UNICA
DESCRIPCION LARGO ALTO AREA ( m2) VOLUMEN ( m3)
VENTANILLA UNICA 0.9 1.2 2.1 0.0
PUERTAS Y VENTANAS
DESCRIPCION ALTO ANCHO CANTIDAD AREA (m2)
ARCHIVO
PUERTA 2 1 1 2.0
VENTANAL 0.3 1 1 0.3
ANTIGUA PERSONERIA
PUERTA 2 1 1 2.0
VENTANA FRONTAL 1 1.2 1.5 1 1.8
VENTANA FRONTAL 2 1.2 1 1 1.2
VENTANA TRASERA 1 1.2 1 1.2
OFICINA
PUERTA 2 1 1 2.0
TOTAL 10.5

PINTURA
DESCRIPCION ANCHO ALTO CANTIDAD AREA (m2)
ARCHIVO
PARED FRONTAL 7.6 3.05 1 23.2
PARED TRASERA 7.6 3.05 1 23.2
PARED LATERAL DER 6 3.3 1 19.8
PARED LATERAL IZQ 6 2.8 1 16.8
ANTIGUA PERSONERIA
PARED FRONTAL 3.3 3.2 1 10.6
PARED TRASERA 3.3 3.2 1 10.6
PARED LATERAL DER 6 3.4 1 20.4
PARED LATERAL IZQ 6 3 1 18.0
OFICINA
PARED FRONTAL 6.75 3 1 20.3
PARED TRASERA 6.75 3.2 1 21.6
PARED LATERAL DER 3 3.4 1 10.2
PARED LATERAL IZQ 3 2.6 1 7.8
PARED INTERNA BAÑO 1.15 2.25 1 2.6
AREA A DESCONTAR
PUERTA OFICINA 1 2 1 2.0
PUERTA BAÑO OFICINA 1 2 1 2.0
PUERTA ARCHIVO 1 2 1 2.0
PUERTA ANTIGUA PERSONERIA 1 2 1 2.0
TOTAL 196.9
TOMAS 110
ARCHIVO 4
ANTIGUA PERSONERIA 5
OFICINA 5
TOTAL 14

LUMINARIA 1X18W
OFICINA 3
TOTAL 3

LUMINARIA Panel 60X60 LED 46W


ARCHIVO 4
ANTIGUA PERSONERIA 2
TOTAL 6

INTERRUPTORES
ARCHIVO 2
ANTIGUA PERSONERIA 1
OFICINA 2
TOTAL 5

AIRE ACONDICIONADO DE 12,000 BTU


ARCHIVO 0
ANTIGUA PERSONERIA 1
OFICINA 1
TOTAL 2

AIRE ACONDICIONADO DE 18,000 BTU


ARCHIVO 1
ANTIGUA PERSONERIA 0
OFICINA 0
TOTAL 1

EXTRACTORES
ARCHIVO 1
ANTIGUA PERSONERIA 1
OFICINA 0
TOTAL 2
REPUBLICA DE COLOMBIA
DEPARTAMENTO DEL CESAR
MUNICIPIO DE ASTREA
Nit. 892301541-1
Có digo Postal: 201040

ADECUACION Y/O MEJORAMIENTO DE LA INFRAESTRUCTURA FISICA DONDE FUNCIONA EL ARCHIVO MUNICIPAL, EN EL


MUNICIPIO DE ASTREA, CESAR

ANALISIS DE PRECIOS UNITARIOS


Jul-22

EXCAVACION MANUAL HASTA .20 X .30 EN TERRENO


1.1 ML 1,925.86
COMUN
HERRAMIENTAS MENORES %MO 0.030 1,870 56
MANO DE OBRA AA hc 0.065 28,766 1,870

1.2 DESMONTE TANQUE ELEVADO M2 119,864.28


ANDAMIO TUBULAR d 0.50 2,700.00 1,350.00
HERRAMIENTAS MENORES %MO 0.03 115,062.41 3,451.87
MANO DE OBRA AA hc 4.00 28,765.60 115,062.41

1.3 DESMONTE CUBIERTAS Y CIELO RASO M2 19,086.00


ANDAMIO TUBULAR CON PLANCHON d 0.500 2,618 1,309
HERRAMIENTAS MENORES %MO 0.030 17,259 518
MANO DE OBRA AA hc 0.600 28,766 17,259

1.4 DESMONTE CUBIERTAS Y CIELO RASO M2 19,086.00


ANDAMIO TUBULAR CON PLANCHON d 0.500 2,618 1,309
HERRAMIENTAS MENORES %MO 0.030 17,259 518
MANO DE OBRA AA hc 0.600 28,766 17,259

1.5 DEMOLICIÓN PISO ESPESOR HASTA .30 M2 32,591.43


HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA AA hc 1.10 28,765.60 31,642.16

1.6 DEMOLICION MECANICA DE ESTRUCTURAS EN CONCRETO M3 161,130.74


ALT HASTA 5
COMPRESOR DE 120 HP, CON MARTILLOS HR 1.10 105,000.00 115,500.00
ANDAMIO TUBULAR d 0.50 2,700.00 1,350.00
HERRAMIENTAS MENORES %MO 0.30 32,540.06 9,762.02
MANO DE OBRA AA HR 1.20 28,765.60 34,518.72
1.7 RELLENO COMPACTADO CON MAT, SELECC. M3 158,642.19
RELLENO SELECCIONADO M3 1.30 51,170.00 66,521.00
VIBROCOMPACTADOR TIPO RANA DIA 0.045 116,620.00 5,247.90
TRANSPORTE DE MATERIAL A 82 KM M3/KM 1.30 1,300.00 138,580.00
HERRAMIENTAS MENORES %MO 0.03 14,382.80 431.48
MANO DE OBRA AA HR 0.50 28,765.60 14,382.80

2.1 MURO SENCILLO 0.15, LADRILLO COMUN .07X.11X.22 M2 78,485.00


INCLUYE MORTERO 1:4
LADRILLO CORRIENTE .07X.11X.22 UN 50.06 800.00 40,050.40
MORTERO 1:4 M3 0.03 515,687.31 13,407.87
DESPERDICIO % 0.03 53,458.27 1,603.75
TRANSPORTE % 0.03 40,050.40 1,201.51
HERRAMIENTAS MENORES %MO 0.03 21,574.20 647.23
MANO DE OBRA AA hc 0.75 28,765.60 21,574.20

2.2 PAÑETE EN MUROS 1:4 M2 25,437.00


MORTERO 1:4 M3 0.02 515,687.31 10,313.75
DESPERDICIO % 0.03 10,313.75 309.41
HERRAMIENTAS MENORES %MO 0.03 14,382.80 431.48
MANO DE OBRA AA hc 0.50 28,765.60 14,382.80

2.3 ESTUCO IMPERMEABILIZANTE M2 25,777.98


ESTUCO IMPERMEABILIZANTE Galon 0.25 50,900.00 12,725.00
LIJA DE AGUA 965 SUPER UN 0.02 1,300.00 26.00
DESPERDICIO % 0.05 12,751.00 637.55
TRANSPORTE % 0.05 13,388.55 669.43
ANDAMIO TUBULAR CON PLANCHON d 0.50 2,700.00 1,350.00
HERRAMIENTAS MENORES %MO 0.03 10,067.96 302.04
MANO DE OBRA AA hc 0.35 28,765.60 10,067.96

2.4 SUMINISTRO E INSTALACION DE VIDRIO M2 87,721.71


VIDRIO TRANSPARENTE 4 MM m2 1.05 70,000.00 73,500.00
HERRAMIENTAS MENORES %MO 0.03 13,807.49 414.22
MANO DE OBRA DD hc 0.40 34,518.72 13,807.49
PISA EN TOLETE COMUN 0.25 MORTERO DE PEGA 1.4,
2.5 ALTURA UNA HILADA- PAÑETADO MORTERO 1:4 ML 53,715.07
IMPERMEABILIZADO
LADRILLO CORRIENTE .07X.11X.22 UN 50.06 800.00 40,050.40
MORTERO 1:4 M3 0.004 515,687.31 2,062.75
DESPERDICIO % 0.02 42,113.15 842.26
TRANSPORTE % 0.05 40,050.40 2,002.52
ANDAMIO TUBULAR d 0.5 2,700.00 1,350.00
HERRAMIENTAS MENORES %MO 0.03 7,191.40 215.74
MANO DE OBRA AA hc 0.25 28,765.60 7191.40068493151

2.6 ZAPATAS EN CONCRETO 3.000 PSI M3 767,727.84


CONCRETO 1:2:3 ELABORADO EN OBRA M3 1 527,418.00 527,418.00
DESPERDICIO % 0.05 527,418.00 26,370.90
VIBRADOR CON OPERADOR d 0.1 102,800.00 10,280.00
ACARREO EN CARRETILLA DE MATERIALES, ESCOMBROS Y
M3 1.03 11,931.00 12,288.93
OTROS, DISTANCIA MAXIMA 100 ML
HERRAMIENTAS MENORES %MO 0.03 146,453.09 4,393.59
MANO DE OBRA AA hc 6.5 28,765.60 186,976.42

2.7 VIGAS SOBRE MURO, CONCRETO 3.000 PSI M3 1,258,433.54


PUNTILLA CON CABEZA 2 lb 1.67 3,089.50 5,159.46
CONCRETO 1:2:3 ELABORADO EN OBRA M3 1 527,418.00 527,418.00
DESPERDICIO % 0.03 527,418.00 15,822.54
VIBRADOR CON OPERADOR d 0.02 102,800.00 2,056.00
ANDAMIO TUBULAR d 2 2,700.00 5,400.00
FORMALETA PARA VIGAS SOBRE MURO M3 1 199,927.00 199,927.00
HERRAMIENTAS MENORES %MO 0.03 454,509.58 13,635.29
MANO DE OBRA AA hc 17 28,765.60 489,015.25

2.8 COLUMNAS EN CONCRETO 3.000 PSI. M3 1,337,129.28


CONCRETO 1:2:3 ELABORADO EN OBRA M3 1 527,418.00 527,418.00
DESPERDICIO % 0.03 327,786.00 9,833.58
ANDAMIO TUBULAR CON PLANCHON d 3 2,700.00 8,100.00
FORMALETA PARA COLUMNAS M3 1 262,392.00 262,392.00
VIBRADOR CON OPERADOR d 0.25 102,800.00 25,700.00
HERRAMIENTAS MENORES %MO 0.03 489,015.25 14,670.46
MANO DE OBRA AA hc 17 28,765.60 489,015.25

ACERO DE REFUERZO PDR-60


2.9 KG 8,369.33
-INCL. MANO DE OBRA
ALAMBRE NEGRO No.17 kG kg 0.027 7,066.00 190.78
ACERO DE REFUERZO PDR-60 kg 1 6,058.00 6,058.00
DESPERDICIO % 0.03 6,248.78 187.46
SEGUETA NICHOLSON UN 0.03 3,681.00 110.43
TRANSPORTE % 0.03 6,436.25 193.09
HERRAMIENTAS MENORES %MO 0.03 1,582.11 47.46
MANO DE OBRA AA hc 0.055 28,765.60 1,582.11
3.1 PLANTILLA EN CONCRETO 3.000 PSI-EXP. 0.1 MT. M2 58,975.15
CONCRETO 1:2:3 ELABORADO EN OBRA M3 0.1 527,418.00 52,741.80
DESPERDICIO % 0.05 52,741.80 2,637.09
TRANSPORTE % 0 24,092.27 -
FORMALETA d 0.15 18,000.00 2,700.00
HERRAMIENTAS MENORES %MO 0.03 870.16 26.10
MANO DE OBRA AA hc 0.55 1,582.11 870.16

3.2 PISO EN CERAMICA DUROPISO DE PRIMERA CALIDAD, M2 68,193.67


ALTO TRAFICO TIPO CORONA O SIMILAR.
CERÁMICA DUROPISO CORONA ALTO TRAFICO M2 1 38,262.00 38,262.00
BOQUILLA PORCELAN CONCOLOR BEIG X 2 KL kg 0.11 5,724.00 629.64
PEGANTE PEGACOR BLANCO X 25 KLS kg 3 1,662.00 4,986.00
DESPERDICIO % 0.05 43,877.64 2,193.88
TRANSPORTE % 0.03 46,071.52 1,382.15
HERRAMIENTAS MENORES %MO 0.03 20,135.92 604.08
MANO DE OBRA AA hc 0.7 28,765.60 20,135.92

3.3 CERAMICA PARA PAREDES DEL BAÑO ALT. 1.6 M2 48,770.51


CCC PISO PARED EGEO 20.5 X 20.5 BLANCO X 1,51 M2 M2 1 21,000.00 21,000.00
CONCOLOR 1.5 BLANCO NACAR O SIMILAR kg 0.11 4,748.00 522.28
PEGACOR BLANCO kg 3 1,320.00 3,960.00
DESPERDICIO % 0.05 25,482.28 1,274.11
TRANSPORTE % 0.05 25,482.28 1,274.11
HERRAMIENTAS MENORES %MO 0.03 20,135.92 604.08
MANO DE OBRA AA hc 0.7 28,765.60 20,135.92

3.4 CONCRETO DE 3000 PSI ESTRIADO PARA RAMPAS - M3 594,118.18


CICLOVIAS + MINUSVALIDOS-
CONCRETO 1:2:3 ELABORADO EN OBRA-3.000PSI CLASE D M3 1 527,418.00 527,418.00
DESPERDICIO % 0.05 527,418.00 26,370.90
TRANSPORTE % 0.03 553,788.90 16,613.67
RIEL PAVIMENTO 3ML d 0.01 1,276.00 12.76
HERRAMIENTAS MENORES %MO 0.03 23,012.48 690.37
MANO DE OBRA AA hc 0.8 28,765.60 23,012.48

3.5 ZOCALO CERAMICA DUROPISO DE PRIMERA CALIDAD, ML 20,523.24


ALTO TRAFICO TIPO CORONA O SIMILAR BLANCO. H= 8 CM
ZOCALO DUROPISO H= 8 CM M2 0.08 38,262.00 3,060.96
MORTERO 1:4 M3 0.0015 515,687.31 773.53
DESPERDICIO % 0.05 3,834.49 191.72
TRANSPORTE % 0.05 4,026.22 201.31
HERRAMIENTAS MENORES %MO 0.03 15,821.08 474.63
MANO DE OBRA AA hc 0.55 28,765.60 15,821.08
CUBIERTA EN LAMINA ARQUITECTONICA GALVANIZADA
4.1 M2 39,862.98
PINTADA DE ACESCO O SIMILAR CAL. 30

CUBIERTA ARQUITECTONICA ACESCO TZA CAL. 30 LONG 3.05 M-


UN 0.5955 24,252.00 14,442.07
TORNILLOS TPF 3/4 UN 1.65 564.00 930.60
TORNILLOS AUTOPERFORANTE 7/8 UN 1.28 530.00 678.40
DESPERDICIO % 0.03 16,051.07 481.53
TRANSPORTE % 0.03 16,532.60 495.98
ANDAMIO TUBULAR CON PLANCHON d 0.8 2,618.00 2,094.40
HERRAMIENTAS MENORES %MO 0.03 20,135.92 604.08
MANO DE OBRA AA hc 0.7 28,765.60 20,135.92

SUMINISTRO E INSTALACION CORREA EN PERFIL PHR-C


4.2 120X60 CAL. 14-2MM-INCL. ANTICORROSIVO Y ACABADO EN ML 42,468.12
ESMALTE
PERFIL PHR C 120X60 X 6 MTS CAL 16 UN 0.1666 88179 14690.6214
PINT ANTICORROSIVO ICO GRIS 1308 gl 0.02 35900 718
SOLDADURA 6011X1/8 kg 0.08 13646 1091.68
ESMALTE SINTETICO gl 0.02 78500 1570
THINNER CORRIENTE gl 0.04 20857 834.28
DESPERDICIO % 0.02 21529.7586 430.595172
EQUIPO DE SOLDADURA ELÉCTRICA d 0.04 102800 4112
TRANSPORTE % 0.03 22760.353772 682.81061316
ANDAMIO TUBULAR CON PLANCHON ms 0.5 2618 1309
HERRAMIENTAS MENORES %MO 0.03 11502.884725363 345.086541760882
MANO DE OBRA AA hc 0.58 28765.602739726 16684.0495890411

4.3 CIELO RASO EN LAMINA DE ICOPOR, INCLUYE M2 35,371.54


ESTRUCTURA DE SOPORTE..
ICOPOR 1 CM/DENS.20/1.24X.62 M2 1.32 4,208.00 5,554.56
PERFIL EN T ALUMINIO 1/2 X 1/2 m 2.41 1,250.00 3,012.50
ÁNGULO CIELO FALSO ALUMINIO 1'X 1" m 1.10 1,250.00 1,375.00
ALAMBRE GALV. K 10 KG 0.10 7,140.00 714.00
DESPERDICIO % 0.05 9,942.06 532.80
TRANSPORTE % 0.03 11,188.86 335.67
ANDAMIO TUBULAR d 1.00 2,618.00 2,618.00
HERRAMIENTAS MENORES %MO 0.03 20,711.23 517.78
MANO DE OBRA DD hc 0.60 34,518.72 20,711.23

SUMINISTRO E INSTALACION DE PUERTA EN LAMINA CON


5.1 MARCO CAL. 18, INCL. ANTICORROSIVO Y ACABADO EN M2 232,109
ESMALTE, INCLUYE TRAGALUZ, CERRADURA E
INSTALACION.
ÁNGULO HIERRO 3/4 X 1/8 mL 1.05 2,690.04 2,824.54
SOLDADURA 6011X1/8" kg 0.16 7,324.00 1,171.84
ANTICORROSIVO 507 GRIS gl 0.23 44,943.00 10,336.89
LÁMINA COLD ROLLED 1.00X2.00 CAL.18 UN 0.72 83,657.00 60,233.04
BISAGRA ALUMINIO EXT 3 UN 1.75 2,881.44 5,042.52
CERRADURA YALE DE SOBREPONER UN 0.50 61,712.00 30,856.00
PINTURA ESMALTE SINTET gl 0.10 61,225.00 6,122.50
DISOLVENTE THINNER gl 0.32 83,427.00 26,696.64
DESPERDICIO % 0.05 143,283.97 7,164.20
TRANSPORTE % 0.03 150,448.17 4,513.45
SUB-CONTRATO DE ORNAMENTACION % 0.20 150,448.17 30,089.63
HERRAMIENTAS MENORES %MO 0.03 38,258.25 1,147.75
MANO DE OBRA DD hc 1.33 34,518.72 45,909.90

SUMINISTRO E INSTALACION DE VENTANA 744 ANOLOCK-


5.2 VIDRIO, UNA NAVE FIJA Y UNA CORREDIZA ANOLOCK, M2 210,573.94
INCLUYE VIDRIO
VENTANA 744 ANOLOCK-VIDRIO BRONCE UNA NAVE FIJA Y 1 167040
UNA CORREDIZA 1.00X1.20 M2 167040.00

TRANSPORTE % 0.035 167040 5846.40


HERRAMIENTAS MENORES %MO 0.03 36589.85 1097.70
MANO DE OBRA DD INSTALACION hc 1.06 34,518.72 36589.85
5.3 MANTENIMIENTO DE PUERTAS Y VENTANAS, INCLUYE UND 113,331.43
LIMPIEZA DESMONTE Y REPOSICION DE MATERIALES,
ACCESORIOS Y/O INSUMOS Y PINTURA; MANO DE OBRA.
INSUMOS UND 1.00 60,000.00 60,000.00
HERRAMIENTAS MENORES %MO 0.03 51,778.08 1,553.34
MANO DE OBRA DD hc 1.50 34,518.72 51,778.08

5.4 DESMONTE MARCOS, PUERTAS Y VENTANAS M2 16,296.00


HERRAMIENTAS MENORES %MO 0.03 15,821.08 474.63
MANO DE OBRA AA hc 0.55 28,765.60 15,821.08

6.1 VINILO 2 MANOS, PINTURA TIPO 1 VINILTEX O SIMILAR EN M2 9,741.96


MANTENIMIENTOS O ADECUACIONES
VINILTEX tipo 1 gl 0.020 64,900 1,298
RODILLO DE FELPA 9" UN 0.008 10,492 84
LIJA AGUA FANDELI N° 150 UN 0.110 1,094 120
DESPERDICIO % 0.050 1,502 75
ANDAMIO TUBULAR d 0.500 2,700 1,350
HERRAMIENTAS MENORES %MO 0.030 6,616 198
MANO DE OBRA CC hc 0.200 33,080 6,616

7.1 SALIDA TOMACORRIENTE 110V UND 104,944.23


CABLE COBRE No. 12 AWG-THHN/THWN ML 18 1,621.58 29,188.44
CABLE COBRE No. 14 AWG-THHN/THWN ML 9 1,150.00 10,350.00
CAJA RECTANGULAR 2 X 4 GALVANIZADA UND 1 1,068.00 1,068.00
ADAPTADOR TERMINAL 1/2" UND 2 267.00 534.00
TOMACORRIENTE 110V-15A UND 1 8,900.00 8,900.00
CURVA CONDUIT PVC 1/2" UND 2 1,140.00 2,280.00
TUBO CONDUIT PVC 1/2"X3 METROS UND 2 4,100.00 8,200.00
SOLDADURA PVC LIQUIDA 1/4 UND 0.01 17,123.00 171.23
DESPERDICIO %MAT 0.05 50,189.67 2,509.48
TRANSPORTE % 0.02 50,189.67 1,003.79
HERRAMIENTAS MENORES %MO 0.03 39,552.70 1,186.58
MANO DE OBRA BB hc 1.25 31,642.16 39,552.70

7.2 SALIDA LUMINARIA 110V EN DUCTO PVC SCH 40 1/2" UN 91,018.49


CABLE COBRE No. 12 AWG-THHN/THWN UND 20.00 1,621.58 32,431.60
CAJA 4X4X2PVC UND 1.00 1,068.00 1,068.00
CURVA CONDUIT PVC SCH 40 1/2" UND 1.00 1,302.00 1,302.00
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 2.00 7,850.00 15,700.00
ADAPTADOR TERMINAL 1/2" UN 1.00 267.00 267.00
SOLDADURA PVC LIQUIDA 1/4 UN 0.01 75,438.30 754.38
DESPERDICIO % 0.05 51,522.98 2,576.15
TRANSPORTE % 0.08 54,099.13 4,327.93
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16

7.3 #NAME? UN 80,879.86

LUMINARIAS LED 8" LUZ BLANCA UN 1.00 45,000.00 45,000.00


TORNILLO LÁMINA DIAM. 3/8 UN 4.00 121.80 487.20
DESPERDICIO % 0.05 45,487.20 2,274.36
TRANSPORTE % 0.01 52,687.20 526.87
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16
7.4 UN 157,852.03
#NAME?
Panel 60X60 LED 46W 6500K 100-240V Ip20 UN 1.00 120,900.00 120,900.00
TORNILLO LÁMINA DIAM. 3/8 UN 4.00 121.80 487.20
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 124,020.40 1,240.20
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16

7.5 UN 99,254.02
#NAME?
CABLE COBRE No. 12 AWG-THHN/THWN ML 18.00 1,621.58 29,188.44
CURVA CONDUIT PVC SCH 40 1/2" UND 2.00 1,302.07 2,604.14
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 2.00 7,820.40 15,640.80
CAJA 2X4 PVC UND 1.00 1,068.00 1,068.00
ADAPTADOR TERMINAL 1/2" UND 2.00 267.00 534.00
INTERRUPTOR SENCILLO UND 1.00 8,900.00 8,900.00
TRANSPORTE % 0.01 57,935.38 579.35
HERRAMIENTAS MENORES %MO 0.03 39,552.70 1,186.58
MANO DE OBRA BB hc 1.25 31,642.16 39,552.70

7.6 UN 105,984.29
#NAME?
CABLE COBRE No. 12 AWG-THHN/THWN ML 22.00 1,621.58 35,674.76
CURVA CONDUIT PVC SCH 40 1/2" UND 2.00 1,302.07 2,604.14
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 2.00 7,820.40 15,640.80
CAJA 2X4 PVC UND 1.00 1,068.00 1,068.00
ADAPTADOR TERMINAL 1/2" UND 2.00 267.00 534.00
INTERRUPTOR DOBLE UND 1.00 9,400.00 9,400.00
TRANSPORTE % 0.01 64,921.70 649.22
HERRAMIENTAS MENORES %MO 0.03 39,236.28 1,177.09
MANO DE OBRA BB hc 1.24 31,642.16 39,236.28

7.7 #NAME? UN 110,860.76

CABLE COBRE No. 12 AWG-THHN/THWN ML 12.00 1,621.58 19,458.96


CURVA CONDUIT PVC SCH 40 1/2" UND 2.00 1,302.07 2,604.14
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 2.00 7,820.40 15,640.80
CAJA 2X4 PVC UND 1.00 1,068.00 1,068.00
TRANSPORTE % 0.01 38,771.90 387.72
HERRAMIENTAS MENORES %MO 0.03 69,612.76 2,088.38
MANO DE OBRA BB hc 2.20 31,642.16 69,612.76

7.8 UN 3,650,332.96
#NAME?
AIRE MINI SPLIT INVERTER DE 18000 BTU UN 1.00 3,544,000.00 3,544,000.00
ANGULO PARA SOPORTE UN 2.00 12,500.00 25,000.00
CHAZOS DE 5/8" UN 4.00 1,016.00 4,064.00
CHAZOS DE 1/4" UN 8.00 116.00 928.00
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 3,571,633.20 35,716.33
ANDAMIO TUBULAR d 2.00 2,700.00 5,400.00
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16

7.9 UN 2,838,292.96
#NAME?
AIRE MINI SPLIT INVERTER DE 12000 BTU UN 1.00 2,740,000.00 2,740,000.00
ANGULO PARA SOPORTE UN 2.00 12,500.00 25,000.00
CHAZOS DE 5/8" UN 4.00 1,016.00 4,064.00
CHAZOS DE 1/4" UN 8.00 116.00 928.00
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 2,767,633.20 27,676.33
ANDAMIO TUBULAR d 2.00 2,700.00 5,400.00
HERRAMIENTAS MENORES %MO 0.03 31,642.16 949.26
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16

7.10 UN 680,553.07
#NAME?
EXTRACTOR DE AIRE DE 14" INDUSTRIAL ASPA METALICAS UN 1.00 632,000.00 632,000.00
DESPERDICIO % 0.05 52,664.00 2,633.20
TRANSPORTE % 0.01 634,633.20 6,346.33
ANDAMIO TUBULAR d 2.00 2,700.00 5,400.00
HERRAMIENTAS MENORES %MO 0.08 31,642.16 2,531.37
MANO DE OBRA BB hc 1.00 31,642.16 31,642.16

7.11 REPARACION GENERAL ELECTRICA UN 797,392.18


CABLE COBRE No. 12 AWG-THHN/THWN ML 60.00 1,621.58 97,294.80
CURVA CONDUIT PVC SCH 40 1/2" UND 8.00 1,302.07 10,416.56
TUBO CONDUIT PVC SCH 40 1/2"X3 METROS UND 20.00 7,820.40 156,408.00
CAJA 2X4 PVC UND 8.00 1,068.00 8,544.00
ADAPTADOR TERMINAL 1/2" UND 2.00 267.00 534.00
TRANSPORTE % 0.01 273,197.36 2,731.97
HERRAMIENTAS MENORES %MO 0.03 506,274.61 15,188.24
MANO DE OBRA BB hc 16.00 31,642.16 506,274.61

8.1 RED SANITARIA PVC 6- 160 MM - INCL. INSTALACION Y ML $ 180,859


TAPE
TUBERIA PVC SANITARIA 6" ML 1 $ 66,656 $ 66,656
TEE PVC SANITARIA 6" UN 0.17 $ 195,274 $ 33,197
CODO 90° PVC SAN CXC 6" UN 0.17 $ 137,425 $ 23,362
UNIÓN PVC SAN 6" UN 0.17 $ 41,090 $ 6,985
LIMPIADOR REMOVEDOR PVC 1/4GALON UN 0.03 $ 59,921 $ 1,798
SOLDADURA PVC 1/4GALON UN 0.02 $ 124,272 $ 2,485
DESPERDICIO % 0.05 $ 134,483 $ 6,724
TRANSPORTE % 0.05 $ 141,207 $ 7,060
HERRAMIENTAS MENORES %MO 0.03 $ 31,642 $ 949
CUADRILLA BB Hr 1 $ 31,642 $ 31,642
8.2 PUNTO HIDRAULICO PVC PRESION DE 1/2" UN $ 58,393
CODO 90° PRESIÓN PVC 1/2 UN 2.00 487.00 974.00
SOLDADURA PVC LIQUIDA 1/4 UN 0.01 47,276.00 472.76
LIMPIADOR PVC LIQUIDA 1/4 UN 0.01 50,901.00 509.01
TUBO PRESIÓN /9 PVC 1/2 ML 5.00 4,020.00 20,100.00
DESPERDICIO % 0.05 5,975.77 298.79
TRANSPORTE % 0.03 6,274.56 188.24
HERRAMIENTAS MENORES %MO 0.03 34,806.38 1,044.19
MANO DE OBRA BB hc 1.10 31,642.16 34,806.38

CAJAS INSPECCION .60 X .60, EN LADRILLO CORRIENTE,


PAÑETADA IMPERMABILIZADA INTEGRALMENTE,
8.3 INCLUYE EXCAVACIÓN Y TAPE, TAPA Y HERRAJES, UN $ 330,460
CAÑUELAS, MARCOS EN ANGULO DE 1 1/2"X3/16 E INCLUYE
TODO LO NECESARIO PARA SU CORRECTO
FUNCIONAMIENTO
MORTERO 1:4 M3 0.1 $ 515,687 $ 51,569
MORTERO 1:4 IMPERMEABILIZADO M3 0.02 $ 506,683 $ 10,134
CONCRETO 1:2:3 ELABORADO EN OBRA-3.000PSI CLASE D-IMPE M3 0.0896 $ 445,207 $ 39,891
LADRILLO CORRIENTE .07X.11X.22 UN 92.8 $ 750 $ 69,600
TAPA Y MARCO PARA REGISTRO ELECTRICO O SANITARIO 0.60X0 UN 1 $ 62,640 $ 62,640
DESPERDICIO % 0.05 $ 233,833 $ 11,692
ACARREO EN CARRETILLA DE MATERIALES, ESCOMBROS Y OTRO M3 0.16 $ 12,348 $ 1,976
HERRAMIENTAS MENORES %MO 0.03 $ 80,544 $ 2,416
MANO DE OBRA AA hc 2.8 $ 28,766 $ 80,544

8.4 SUMINISTRO E INSTALACION DE SANITARIO Y LAVAMANOS UN $ 878,013


CON PEDESTAL, INCLUYE GRIFERIA Y ACCESORIOS
CEMENTO BLANCO kg 0.5 $ 1,044 $ 522
MANGUERA CONEXIÓN FLEXIBLE UN 1 $ 2,888 $ 2,888
DESPERDICIO % 0.05 $ 3,410 $ 171
SANITARIO HAPPY BLANCO INCLUYE ACCESORIO UN 1 $ 254.900 $ 254.900
LAVAMANOS AVANTI DE COLG CON PEDESTAL Y
UN 1 $ 190,364 $ 190,364
GRIFERIA
TRANSPORTE % 0.45 $ 194,200 $ 87,390
HERRAMIENTAS MENORES %MO 0.03 $ 579,052 $ 17,372
MANO DE OBRA BB hc 18.3 $ 31,642 $ 579,052

9.1 #NAME? M3 25,175.23

CARGADOR, POTENCIA AL VOLANTE DE 110 HP HR 0.05 151,300.00 7,565.00


TRANSPORTE DE MATERIALES M3-KM 5 1,300.00 6,500.00
HERRAMIENTAS MENORES %MO 0.1 10,100.21 1,010.02
MANO DE OBRA AA hc 0.4 25,250.53 10,100.21

ING. VICTOR HUGO RIZZO CAAMAÑO


Secretaria de Planeación y Obras públicas
REPUBLICA DE COLOMBIA
DEPARTAMENTO DEL CESAR
MUNICIPIO DE ASTREA
Nit. 892301541-1
Código Postal: 201040

ADECUACION Y/O MEJORAMIENTO DE LA INFRAESTRUCTURA FISICA DONDE FUNCIONA EL ARCHIVO


MUNICIPAL, EN EL MUNICIPIO DE ASTREA, CESAR
ANALISIS DE PRECIOS UNITARIOS
JULIO DE 2022

MORTERO 1:4 M3 515,687.31


CEMENTO GRIS kg 420 600.00 252,000.00
AGUA lt 185 80.00 14,800.00
ARENA M3 1.34 29,750.00 39,865.00
Desperdicio % 0.05 291,865.00 14,593.25
Transporte Cantera 82 Km Km 1.407 1,300.00 149,986.20
HERRAMIENTAS MENORES d 0.03 43,148.40 1,294.45
Valor Hr Cuadrilla hr 1.5 28765.6 43148.404109589

CONCRETO 1:2:3 ELABORADO EN


OBRA-3.000PSI CLASE D M3 527,418.00

CEMENTO GRIS kg 350.00 $ 600.00 $ 210,000.00


AGUA lt 180.00 $ 80.00 $ 14,400.00
ARENA M3 0.56 $ 29,750.00 $ 16,511.25
Transporte Cantera 82 Km M3 0.56 $ 1,300.00 $ 59,696.00
TRITURADO M3 0.84 $ 90,440.00 $ 75,969.60
Transporte Cantera 82 Km Km 0.84 $ 1,300.00 $ 89,544.00
Desperdicio % 0.05 $ 92,480.85 $ 4,624.04
MEZCLADORA CON OPERADOR d 0.12 $ 102,800.00 $ 12,230.53
HERRAMIENTAS MENORES d 0.03 $ 43,148.40 $ 1,294.45
CUADRILLA "AA" (Albañileria) hr 1.50 $ 28,765.60 $ 43,148.40

ING. VICTOR HUGO RIZZO CAAMAÑO


Secretaria de Planeación y Obras públicas
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL CESAR
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: 2022
TARIFAS MANO DE OBRA Y PRESTACIONES SOCIALES 2022.
1.-SALARIOS DE MANO DE OBRA %

A- Salario Minimo Legal 1,000,000


B- Auxilio de Transporte 106,454
C- Total Mensual 1,106,454
D- Anual (A/30x365) 12,166,667 100.00%
Subsidio de Transporte Anual 1,277,448 11.35%
E- Anual con Subsidio de Transporte 13,444,115

PRESTACIONES BASE
Cesantias E 10.00% 1,325,995 10.98%
Intereses Cesantias 12.00% 159,119 1.32%
Vacaciones 15 Dias A 50.00% 500,000 4.11%
Primas 30 Dias C 100.00% 1,106,454 9.20%

OTROS COSTOS
Botas y Overol 82,500 3.00 247,500 4.09%
Seguro Colectivo D 0.50% 60,833 0.50%

SEGURIDAD SOCIAL
Pensiones D 12.00% 1,460,000 12.00%
Medicina Familiar D 8.50% 1,034,167 8.50%
Riesgos Profesionales D 5.60% 681,333 5.60%

APORTES SENA
Aporte Ordinario D 2.00% 243,333 2.00%
F.I.C Nota 4 18.00% 229,941 1.80%

OTROS APORTES
I.C.B.F D 3.00% 365,000 3.00%
Subsidio Familiar D 4.00% 486,667 4.00%

VALOR REAL DEL SALARIO 21,344,457 67.10%


GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL CESAR
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: 2022
TARIFAS MANO DE OBRA Y PRESTACIONES SOCIALES 2022.

NOTAS:
1.- Subsidio de transporte solo se paga hasta sueldos de 2 salarios minimos mensules legales vigentes.
2.- Subsidio de transporte anual = Subsidio mensual / 30 x (365 dias-18 fiestas - 3 permisos- 15 dias vacaciones).
3.- Porcentajes solo son validos para actividades de construccion. Para otros empleados se debe utilizar 30 dias de cesantia
y 2.2% (promedio para empresas de bajo riesgo).
4.- Un salario minimo por cada 40 trabajadores. El valor se obtiene asi: (Salario minimo x 12 / 40) / Salario annual estudiado.
5.- El crecimiento promedio del PIB entre 2005 y 2006 fue superior al 4%y por ello la cotizacion a pensiones por parte del
patrono durante 2009 debe aumentar al 12%, segun lo dispuesto por la ley 297 del 2003.
* Todos los porcentajes estan relacionados con el salario para 365 dias.
* Los 18 feriados hacen referencia a los dias feriados que de lunes a viernes .

2- CALCULO DE SOBRECOSTO POR HORAS EFECTIVAS TRABAJADAS-OBREROS


CON UN SALARIO MINIMO TRABAJADO

A- Anual con Subsidio de Transporte 21,344,457


B- Horas Calendario Anuales 365 x 8 Hhr 2,920
(52 Sem x 48 Hr)
C- Horas Laborales Anuales +8Hr 2,504
2920 Hr-((52 Dom +
18 Fiestas + 3
Permisos) x 8 Hr)
D- Horas Habiles Anuales 2344
E- Valor Hora Calendario A/B 7,310 100.00%
F- Valor Hora Laboral A/C 8,524 116.61%
G- Valor Hora Efectiva A/D 9,106 124.57%

NOTAS:
Los factores de sobrecostos se utilizan para valorizar el tiempo efectivo que un obrero dedica a su labor y refleja el costo del
tiempo durante el cual no esta trabajando pero si esta devengando.

Si se toma como base la hora calendario, se incrementa 24.57% para obtener la hora efectiva.
Si se toma como base la hora laboral, se incrementa 6.83% para obtener la hora efectiva.

CALCULO DE CUADRILLAS

CUADRILLA "AA" (Albañileria)


Jornal Ayudante 1.2 Minimos 39,452
Valor Real del Jornal 214.77% 84,731
Valor Total Hr Ayudante 10,591

Jornal Oficial 2.1 Minimos 69,041


Valor Real del Jornal 210.59% 145,394
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL CESAR
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: 2022
TARIFAS MANO DE OBRA Y PRESTACIONES SOCIALES 2022.
Valor Total Hr Oficial 18,174

Valor Dia Cuadrilla 230,125


Valor Hr Cuadrilla 28,765.60

Salida Electrica 1.55 Hr AA

CUADRILLA "BB" (Instalaciones)


Jornal Ayudante 1.2 Minimos 43,397
Valor Real del Jornal 214.77% 93,204
Valor Total Hr Ayudante 11,651

Jornal Oficial 2.1 Minimos 75,945


Valor Real del Jornal 210.59% 159,933
Valor Total Hr Oficial 19,992

Valor Dia Cuadrilla 253,137


Valor Hr Cuadrilla 31,642.16

CUADRILLA "CC" (Pintura)


Jornal Ayudante 1.2 Minimos 45,370
Valor Real del Jornal 214.77% 97,441
Valor Total Hr Ayudante 12,180

Jornal Oficial 2.1 Minimos 79,397


Valor Real del Jornal 210.59% 167,203
Valor Total Hr Oficial 20,900

Valor Dia Cuadrilla 264,644


Valor Hr Cuadrilla 33,080.44

CUADRILLA "DD" (Carpinterias)


Jornal Ayudante 1.2 Minimos 47,342
Valor Real del Jornal 214.77% 101,677
Valor Total Hr Ayudante 12,710
GOBERNACION DEL CESAR
SECRETARIA DE INFRAESTRUCTURA
PRECIOS DE REFERENCIA PARA EL DEPARTAMENTO DEL CESAR
Calle 16 No 12 - 120 - Telefax: (5) 5749671 - e-mail:
obras@gobcesar.gov.co - Valledupar, Cesar.
FECHA: 2022
TARIFAS MANO DE OBRA Y PRESTACIONES SOCIALES 2022.
Jornal Oficial 2.1 Minimos 82,849
Valor Real del Jornal 210.59% 174,472
Valor Total Hr Oficial 21,809

Valor Dia Cuadrilla 276,150


Valor Hr Cuadrilla 34,518.72

CUADRILLA "EE" (Cableado Estructural)


Jornal Ayudante 1.2 Minimos 51,288
Valor Real del Jornal 214.77% 110,151
Valor Total Hr Ayudante 13,769

Jornal Oficial 2.1 Minimos 89,753


Valor Real del Jornal 210.59% 189,012
Valor Total Hr Oficial 23,626

Valor Dia Cuadrilla 299,162


Valor Hr Cuadrilla 37,395.28

NOTAS:
Jornal = sueldo mensual x 12 meses / 365 dias.
6045617
663,808.75

556200
6767100
743027.58
0

230,125
5,753
ADECUACION Y/O MEJORAMIENTO DE LA INFRAESTRUCTURA FISICA DONDE FUNCIONA EL ARCHIVO
MUNICIPAL, EN EL MUNICIPIO DE ASTREA, CESAR

ANÁLISIS DETALLADO DEL AIU


FECHA
COSTO DIRECTO DE LAS OBRAS $ 14,351,784.84
ÍTEM CONCEPTO % VALOR PARCIAL
A. ADMINISTRACIÓN
1 GASTOS DE LEGALIZACION
1.1 IMPUESTOS MUNICIPALES 13.00% $ 1,865,732.03
1.1.1 Estampilla pro-Deporte 1.50%
1.1.2 Estampilla pro-Cultura 2.00%
1.1.3 Estampilla pro-Universidad 0.50%
1.1.4 Estampilla pro-Anciano 4.00%
1.1.7 Fondo de seguridad ley 1421 de 2010 5.00%
2.1 POLIZAS 0.55% $ 78,934.82
2.1.1 SERIEDAD DEL PROYECTO 0.020%
2.1.2 BUEN MANEJO DE ANTICIPO 0.120%
2.1.3 CUMPLIMIENTO 0.020%
2.1.4 SALARIOS Y PRESTACIONES 0.030%
2.1.5 ESTABILIDAD DE LA OBRA 0.240%
2.1.6 RESPONSABILIDAD CIVIL EXTRACONTRACTUAL 0.120%

2 PERSONAL Y GASTOS DE OBRA


Tiempo
2.1 STAFF DE OBRA Cantidad Vr. Básico Prestaciones Dedicación Vr. Parcial
(mes)
2.1.1 Director de Obra 1.00 $ 3,834,267.95 1.99 2.00 40% $ 6,104,154.58
2.1.2 Residente Obra 1.00 $ 2,890,000.00 1.99 2.00 100% $ 11,502,200.00
3 PERSONAL Y GASTOS ADMINISTRATIVOS
STAFF ADMINISTRACIÓN (INCLUYE PRESTACIONES Tiempo
3.1 Cantidad Vr. Básico Prestaciones Dedicación Vr. Parcial
SOCIALES) (mes)
OFICINA CON SERVICIOS PÚBLICOS PROVISIONALES
3.2 1.00 $ 1,500,000.00 2.00 $ 3,000,000.00
DURANTE LA OBRA
3.3 VALLA INFORMATIVA DE 6.00X3.00M 1.00
$ 2,200,000.00 - - $ 2,200,000.00
SUBTOTAL PEERSONAL Y GASTOS 158.91% $22,806,380.58
ADMINISTRACION PROMEDIO ENTRE OBRAS Y SUMINISTROS 172.46% $24,751,047
B. IMPREVISTOS ** CON BASE AL COSTO DIRECTO DEL PROYECTO
CLIMATOLOGÍA ADVERSA Y/O OTRAS EXTERNALIDADES
AFECTACIONES A LAS REDES Y CONEXIONES DOMICILIARIAS DE LOS SERVICIOS PÚBLICOS EN LA EJECUCION DE LAS OBRAS
SUBTOTAL IMPREVISTOS 1.00% $ 1,113,583.00

C. UTILIDAD ** CON BASE AL COSTO DIRECTO DEL PROYECTO


UTILIDADES PORCENTUALES SOBRE LA INVERSIÓN
SUBTOTAL UTILIDAD 4.00% $ 574,071.00
TOTAL AIU PROMEDIO ENTRE OBRAS 177.46%
* CALCULADOS SOBRE EL COSTO TOTAL DE LA OBRA
** CALCULADOS SOBRE EL COSTO DIRECTO DE LA OBRA

ING. VICTOR HUGO RIZZO CAAMAÑO


Secretaria de Planeación y Obras públicas

También podría gustarte