CÁLCULO DE FLETE

OBRA
CREACIÓN DEL INSTITUTO SUPERIOR TECNOLÓGICO DE OYOLO
LOCALIDAD OYOLO
DISTRITO OYOLO PROV. : PAUCAR DEL SARA SARA DEPART.: AYACUCHO

ITEM PARTIDA DIMENSIONES


UNIDAD Cant C.D. TOTAL S/.
Kl Parcial C.U.
A MATERIALES POR KILO kg 182,521.38
CEMENTO bls 6,668.36 42.50 283,405.17 0.30 85,021.55
ALAMBRE kg 2,945.87 1.00 2,945.87 0.30 883.76
CLAVOS kg 616.56 1.00 616.56 0.30 184.97
ACERO CORRUGADO kg 71,489.82 1.00 71,489.82 0.30 21,446.95
MADERA p2 6,861.23 1.20 8,233.48 0.30 2,470.04
Pintura / Gasolina gln 1,079.16 4.00 4,316.64 0.30 1,294.99 c flete/u ladrillo c u/ladrillo
YESO bls 204.34 28.00 5,721.52 0.30 1,716.46 1.14 1.69492 2.83
LADRILLO DE TECHO 30X30X15 und 4,064.87 7.90 32,112.47 0.30 9,633.74
LADRILLO K.K. 18 HUECOS und 52,516.60 3.80 199,563.08 0.30 59,868.92 und 53,329.30 3.80 202,651.34 0.30 60,795.40

B MATERIALES POR VOLUMEN M3 Volumen 8,593.17 53329.3 1694.92


TUBO 4" m 61.20 0.01 0.61 116.00 70.99
TUBO 2" m 60.70 0.00 0.15 116.00 17.60 total ladrillo
OVALINES und 18.00 0.08 1.46 116.00 169.13 cladrillo 90388.9
URINARIOS und 11.00 0.08 0.88 116.00 102.08 cfleteladrilo 59,868.92
INODOROS und 17.00 0.20 3.40 116.00 394.40 150,257.82
TANQUE ELEVADO und 1.00 5.00 5.00 116.00 580.00 2.86 2.82
TERMOTECHO m2 417.81 0.10 41.78 116.00 4,846.60
POLICARBONATO m2 259.54 0.01 2.08 116.00 240.85
ESCRITORIO DE DOCENTES und 19.00 0.65 12.35 116.00 1,432.60
SILLAS GIRATORIAS und 19.00 0.25 4.75 116.00 551.00
SILLÓN 3 CUERPOS und 1.00 1.62 1.62 116.00 187.92

C TRANSPORTE DE AGREGADOS, DESDE CANTERA A LA OBRA 66,135.55


ARENA FINA m3 104.86 1.00 104.86 65.00 6,815.90
ARENA GRUESA m3 334.11 1.00 334.11 65.00 21,717.15
HORMIGÓN m3 98.93 1.00 98.93 65.00 6,430.45
PIEDRA CHANCADA 1/2" m3 415.48 1.00 415.48 65.00 27,006.20
AFIRMADO m3 41.04 1.00 41.04 65.00 2,667.60
GRAVA 2" a 4" m3 1.00 - 65.00 0.00
PIEDRA PILCA MEDIANA 6" m3 1.00 - 65.00 0.00
PIEDRA PILCA GRANDE 8" m3 23.05 1.00 23.05 65.00 1,498.25
FLETE TERRESTRE INTERPROVINCIAL 257,250.11