VALORIZACION N 08

CLIENTE : EMPODERAMIENTO PERU S.A.C

FECHA : 01-08-2022 al 15-08-2022 Nº de Orden de Compra : Modalidad del Contrato

PERIODO : 8.00 Contratista : MISUSA CONSTRUCTORA Y SERVICIOS GENERALES Suma Alzada

CONTRATO PRESENTE PERIODO


Ítem Descripción partida TOTAL
U.M CANT P.U. CANT P.U. MONTO S/.
S/.
1.00 OBRAS PRELIMINARES S/ 10,821.49 S/ 0.00
1.00.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS. GBL 1.00 S/ 3,900.00 S/ 3,900.00 0.00 S/ 3,900.00 S/ 0.00
1.00.02 TRAZO Y REPLANTEO. M2 140.00 S/ 3.47 S/ 486.49 0.00 S/ 3.47 S/ 0.00
1.00.03 DEMOLICION CONSTRUCCION EXISTENTE GBL 1.00 S/ 2,925.00 S/ 2,925.00 0.00 S/ 2,925.00 S/ 0.00
1.00.04 ELIMINACION DE DESMONTE GBL 1.00 S/ 2,925.00 S/ 2,925.00 0.00 S/ 2,925.00 S/ 0.00
1.00.05 CISTERNA PROVISIONAL PARA EL AGUA (CILINDROS) GBL 1.00 S/ 585.00 S/ 585.00 0.00 S/ 585.00 S/ 0.00
1.00.06 SUMINISTRO DE AGUA MES 0.00 S/ 292.50 S/ 0.00 0.00 S/ 292.50 S/ 0.00
2.00 MOVIMIENTO DE TIERRA S/ 29,056.40 S/ 0.00
2.00.01 EXCAVACION DE CIMIENTOS, ZAPATAS EN FORMA MANUAL H=1.50 M3 206.32 S/ 63.08 S/ 13,014.67 0.00 S/ 63.08 S/ 0.00
2.00.02 RELLENO CON MATERIAL PROPIO. M3 82.53 S/ 68.25 S/ 5,632.67 0.00 S/ 68.25 S/ 0.00
2.00.03 ACARREO DE MATERIAL EXCEDENTE. Dp =12 MTS M3 123.79 S/ 25.60 S/ 3,169.02 0.00 S/ 25.60 S/ 0.00
2.00.04 ELIMINACION DE MATERIAL EXCEDENTE M3 123.79 S/ 58.49 S/ 7,240.04 0.00 S/ 58.49 S/ 0.00
3.00 OBRA DE CONCRETO SIMPLE S/ 5,050.96 S/ 0.00
3.00.01 FALSO PISO 4” CON MEZCLA 1:8 C:H M2 96.94 S/ 52.10 S/ 5,050.96 0.00 S/ 52.10 S/ 0.00
4.00 CIMENTACION S/ 13,475.34 S/ 0.00
4.00.01 CIMIENTOS CORRIDOS DE CONCRETO 1:10 H:C. +30% P.G. M3 1.57 S/ 325.65 S/ 511.27 0.00 S/ 325.65 S/ 0.00
4.00.02 SOBRECIMIENTOS F’C=100 KG/CM2 M3 9.88 S/ 565.45 S/ 5,586.63 0.00 S/ 565.45 S/ 0.00
4.00.03 ENCOFRADO DE SOBRECIMIENTO. M2 131.74 S/ 56.00 S/ 7,377.44 0.00 S/ 56.00 S/ 0.00
5.00 OBRAS DE CONCRETO ARMADO S/ 57,308.78 S/ 0.00
ZAPATAS, VIGA DE CIMEN. Y MURO DE CONTENCION CONCRETO DE 210 KG / CM2 VACIADA
5.00.01 M3 20.74 S/ 555.64 S/ 11,524.03 0.00 S/ 555.64 S/ 0.00
CON EQUIPO
5.00.02 SOLADO ZAPATAS DE CONCRETO POBRE DE E= 4” M2 69.12 S/ 39.30 S/ 2,716.42 0.00 S/ 39.30 S/ 0.00
5.00.03 ACERO ZAPATAS FY = 4200 KG / CM2 KG 1244.16 S/ 8.89 S/ 11,060.58 0.00 S/ 8.89 S/ 0.00
5.00.04 EXCAVACION DE ZAPATAS H= 1.0 MTS.EN FORMA MANUAL M3 41.47 S/ 65.00 S/ 2,695.55 0.00 S/ 65.00 S/ 0.00
5.00.05 RELLENO CON MATERIAL PROPIO M3 18.85 S/ 93.13 S/ 1,755.58 0.00 S/ 93.13 S/ 0.00
5.00.06 ACARREO DE MATERIAL EXCEDENTE. Dp = 20 MTS M3 22.62 S/ 26.73 S/ 604.63 0.00 S/ 26.73 S/ 0.00
5.00.07 ELIMINACION DE MATERIAL EXCEDENTE M3 22.62 S/ 59.50 S/ 1,345.89 0.00 S/ 59.50 S/ 0.00
5.00.08 CONCRETO DE 210 KG / CM2 VIGA DE CIMEN. VACIADA CON EQUIPOS M3 13.18 S/ 555.75 S/ 7,324.79 0.00 S/ 555.75 S/ 0.00
5.00.09 SOLADO DE CONCRETO POBRE VIGA DE CIMEN. DE E =4” M2 33.94 S/ 39.30 S/ 1,333.84 0.00 S/ 39.30 S/ 0.00
5.00.10 ACERO COLUMNAS Fy = 4200 KG / CM2 KG 946.90 S/ 8.89 S/ 8,417.94 0.00 S/ 8.89 S/ 0.00
5.00.11 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO. VIGA DE CIMENTACION M2 105.42 S/ 80.91 S/ 8,529.53 0.00 S/ 80.91 S/ 0.00
6.00 COLUMNAS Y PLACAS DEL 1er. PISO S/ 18,393.90 S/ 0.00
6.00.01 CONCRETO DE 210 KG / CM2 VACEADA CON PERSONAL Y EQUIPO. M3 5.48 S/ 832.59 S/ 4,562.57 0.00 S/ 832.59 S/ 0.00
6.00.02 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO M2 65.70 S/ 80.88 S/ 5,313.55 0.00 S/ 80.88 S/ 0.00
6.00.03 ACERO Fy = 4200 KG / CM2 KG 958.13 S/ 8.89 S/ 8,517.78 0.00 S/ 8.89 S/ 0.00
7.00 VIGAS DEL 1er. PISO S/ 36,415.75 S/ 0.00
7.00.01 CONCRETO DE 210 KG / CM2 VACIADA CON PERSONAL Y EQUIPO. M3 16.17 S/ 624.09 S/ 10,091.54 0.00 S/ 624.09 S/ 0.00
7.00.02 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO M2 97.04 S/ 86.05 S/ 8,350.68 0.00 S/ 86.05 S/ 0.00
7.00.03 ACERO Fy = 4200 KG / CM2 KG 2021.77 S/ 8.89 S/ 17,973.54 0.00 S/ 8.89 S/ 0.00
8.00 LOSA ALIGERADA E= 20 CMTS PRIMER PISO S/ 43,071.02 S/ 0.00
8.00.02 CONCRETO DE 210 KG / CM2 VACIADA CON PERSONAL Y EQUIPO M3 18.10 S/ 595.34 S/ 10,775.65 0.00 S/ 595.34 S/ 0.00
8.00.03 ENCOFRADO Y DESENCOFRADO M2 201.06 S/ 57.92 S/ 11,645.40 0.00 S/ 57.92 S/ 0.00
8.00.04 ACERO FY = 4.200 KG/ CM2 KG 1306.87 S/ 8.89 S/ 11,618.07 0.00 S/ 8.89 S/ 0.00
8.00.05 LADRILLO DE TECHO 30 X 30 X 15 UND 1810.00 S/ 4.99 S/ 9,031.90 0.00 S/ 4.99 S/ 0.00
9.00 ESCALERA AL SEGUNDO PISO S/ 7,030.45 S/ 0.00
9.00.01 CONCRETO DE 210KG/CM2 VACEADO CON PERSONAL Y EQUIPO M3 3.30 S/ 595.20 S/ 1,964.16 0.00 S/ 595.20 S/ 0.00
9.00.02 ENCOFRADO Y DESENCOFRADO M2 15.30 S/ 132.67 S/ 2,029.91 0.00 S/ 132.67 S/ 0.00
9.00.03 ACERO FY = 4200 kg/ cm2 KG 341.55 S/ 8.89 S/ 3,036.38 0.00 S/ 8.89 S/ 0.00
ARQUITECTURA
10.00 MUROS S/ 21,109.55 S/ 10,554.77
10.00.01 MURO DE LADRILLO 18 HUECOS EN AMARRE DE SOGA M2 216.40 S/ 97.55 S/ 21,109.55 108.20 S/ 97.55 S/ 10,554.77
11.00 REVESTIMIENTO S/ 40,269.70 S/ 2,718.19
11.00.01 TARRAJEO FROTACHADO DE MUROS INTERIORES M2 432.80 S/ 40.17 S/ 17,385.58 0.00 S/ 40.17 S/ 0.00
11.00.02 TARRAJEO FROTACHADO DE MUROS EXTERIORES M2 32.00 S/ 46.80 S/ 1,497.60 16.00 S/ 46.80 S/ 748.80
11.00.03 TARRAJEO FROTACHADO DE COLUMNAS M2 50.40 S/ 54.60 S/ 2,751.84 25.20 S/ 54.60 S/ 1,375.92
11.00.04 TARRAJEO FROTACHADO DE CIELO RAZO M2 201.06 S/ 50.70 S/ 10,193.74 0.00 S/ 50.70 S/ 0.00
11.00.05 TARRAJEO FROTACHADO EN ESCALERA M2 25.00 S/ 47.48 S/ 1,186.94 12.50 S/ 47.48 S/ 593.47
11.00.06 ENCHAPE DE BAÑO CON CERAMICO BLANCO NACIONAL ALT.1.80 M2 93.00 S/ 78.00 S/ 7,254.00 0.00 S/ 78.00 S/ 0.00
12.00 SEGURIDAD
SEÑALIZACIONES BASICAS DE SALIDAS DE EMERGENCIA,SISTEMA CONTRA INCENDIO, QUE
12.00.01 INCLUYE SENSOR DE HUMO,SIRENA Y ROCIADORES,LUCES DE EMERGENCIA Y FILTRO DE
AGUA.
13.00 PISOS S/ 39,999.26 S/ 0.00
13.00.01 CONTRA PISO DE 2” EN PRIMER PISO M2 234.00 S/ 44.19 S/ 10,339.76 0.00 S/ 44.19 S/ 0.00
13.00.02 ENCHAPE DE PISO CON CERAMICO ANTIDESLIZANTE BLANCO M2 234.00 S/ 126.75 S/ 29,659.50 0.00 S/ 126.75 S/ 0.00
14.00 PARED DE PERIMETRAL S/ 8,796.04 S/ 0.00
14.00.01 PERIMETRO DE PARED EXTERIOR DE LA ZONA DERECHA ML 20.00 S/ 439.80 S/ 8,796.04 0.00 S/ 439.80 S/ 0.00
15.00 INSTALACIONES ELECTRICAS S/ 23,398.96 S/ 11,699.48
15.00.01 SALIDAS DE TECHO C/ TUBO SEL 3/ AL 4” PTO 72.00 S/ 98.02 S/ 7,057.44 36.00 S/ 98.02 S/ 3,528.72
15.00.02 SALIDAS PARA TOMA CORRIENTES BIPOLARES SIMPLES PTO 40.00 S/ 110.46 S/ 4,418.44 20.00 S/ 110.46 S/ 2,209.22
15.00.03 SALIDAS PARA LUZ CONMUTACION PTO 3.00 S/ 124.41 S/ 373.23 1.50 S/ 124.41 S/ 186.62
15.00.04 SALIDAS PARA BRAQUETS PTO 12.00 S/ 94.25 S/ 1,131.00 6.00 S/ 94.25 S/ 565.50
15.00.05 SALIDA DE FUERZA PARA PORTERO ELECTRICO PTO 1.00 S/ 195.00 S/ 195.00 0.50 S/ 195.00 S/ 97.50
15.00.06 CAJAS DE PASE DE 200X200X100 PTO 20.00 S/ 97.50 S/ 1,950.00 10.00 S/ 97.50 S/ 975.00
15.00.07 ACOMETIDA GENERAL PARA TABLERO ML 45.00 S/ 45.50 S/ 2,047.50 22.50 S/ 45.50 S/ 1,023.75
15.00.08 TABLERO GENERAL CON 22 PALOS. INCLUYE THERMICOS PTO 5.00 S/ 780.00 S/ 3,900.00 2.50 S/ 780.00 S/ 1,950.00
15.00.09 POZO DE TIERRA, INCLUYE ACOMETIDA PTO 1.00 S/ 1,365.00 S/ 1,365.00 0.50 S/ 1,365.00 S/ 682.50
15.00.10 SALIDA PARA TELEFONO PTO 3.00 S/ 94.25 S/ 282.75 1.50 S/ 94.25 S/ 141.38
15.00.11 SALIDAS PARA INTERCOMUNICADORES PTO 1.00 S/ 113.10 S/ 113.10 0.50 S/ 113.10 S/ 56.55
15.00.12 SALIDAS PARA CABLES PTO 6.00 S/ 94.25 S/ 565.50 3.00 S/ 94.25 S/ 282.75
16.00 INSTALACIONES SANITARIAS
16.01.00 SALIDAS DE DESAGUE S/ 6,867.95 S/ 0.00
16.01.01 SALIDAPARA DESAGUE DE 4” PTO 16.00 S/ 143.31 S/ 2,293.03 0.00 S/ 143.31 S/ 0.00
16.01.02 SALIDA DE DESAGUE DE 2” PTO 16.00 S/ 105.56 S/ 1,688.96 0.00 S/ 105.56 S/ 0.00
16.01.03 SALIDAS DE VENTILACION PTO 7.00 S/ 105.56 S/ 738.92 0.00 S/ 105.56 S/ 0.00
16.01.04 REDES DE DISTRIBUCION DE 4” ML 28.00 S/ 35.03 S/ 980.84 0.00 S/ 35.03 S/ 0.00
16.01.05 MONTANTES DE DISTRIBUCION DE 4” ML 4.00 S/ 35.06 S/ 140.24 0.00 S/ 35.06 S/ 0.00
16.01.06 MONTANTES DE DISTRIBUCION DE 2” ML 2.00 S/ 32.50 S/ 65.00 0.00 S/ 32.50 S/ 0.00
16.01.07 REGISTROS DE BRONCE CROMADO Ø2” PTO 4.00 S/ 45.24 S/ 180.96 0.00 S/ 45.24 S/ 0.00
16.01.08 REGISTROS DE BRONCE CROMADO Ø4” PTO 0.00 S/ 104.00 S/ 0.00 0.00 S/ 104.00 S/ 0.00
16.01.09 CAJAS DE INSPECCION 30X60 cm. PTO 2.00 S/ 286.00 S/ 572.00 0.00 S/ 286.00 S/ 0.00
16.01.10 SUMIDERO Ø2” PTO 4.00 S/ 52.00 S/ 208.00 0.00 S/ 52.00 S/ 0.00
16.01.11 INSTALACION DE SANITARIOS.Y LAVADEROS MULTIPLES
16.01.12 LAVADEROS EN PATIO PROTOCOLO CONTRA COVID - 19
16.02.00 SALIDAS DE AGUA S/ 9,108.16 S/ 0.00
16.02.01 SALIDAS DE AGUA FRIA PTO 40.00 S/ 124.41 S/ 4,976.40 0.00 S/ 124.41 S/ 0.00
16.02.02 REDES DE DISTRIBUCION EN PVC CLASE – 10 D=1” ML 44.00 S/ 41.47 S/ 1,824.68 0.00 S/ 41.47 S/ 0.00
16.02.03 REDES DE DISTRIBUCION EN PVC CLASE – 10 D=3/4” ML 28.00 S/ 33.55 S/ 939.48 0.00 S/ 33.55 S/ 0.00
16.02.04 REDES DE DISTRIBUCION EN PVC CLASE – 10 d=1/2” ML 30.00 S/ 28.60 S/ 858.00 0.00 S/ 28.60 S/ 0.00
16.02.05 VALVULAS CON PUERTAS PESADAS DE BRONCE / UNIVERS PTO 4.00 S/ 127.40 S/ 509.60 0.00 S/ 127.40 S/ 0.00
SUB TOTAL S/ 370,173.70 S/ 24,972.44
GASTOS GENERALES + UTILIDAD 5 % S/ 18,508.69 S/ 1,248.62
TOTAL S/ 388,682.39 6.75% S/ 26,221.06
GESTIÓN DE PROYECTOS

VALORIZACION N 10

CLIENTE : EMPODERAMIENTO PERU S.A.C

FECHA : 22-08-2022 al 27-08-2022 Nº de Orden de Compra : Modalidad del Contrato

PERIODO : 10.00 Contratista : MISUSA CONSTRUCTORA Y SERVICIOS GENERALES Suma Alzada

CONTRATO PRESENTE PERIODO


Ítem Descripción partida TOTAL
U.M CANT P.U. CANT P.U. MONTO S/.
S/.
1.00 OBRAS PRELIMINARES S/ 10,821.49 S/ 0.00
1.00.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS. GBL 1.00 S/ 3,900.00 S/ 3,900.00 0.00 S/ 3,900.00 S/ 0.00
1.00.02 TRAZO Y REPLANTEO. M2 140.00 S/ 3.47 S/ 486.49 0.00 S/ 3.47 S/ 0.00
1.00.03 DEMOLICION CONSTRUCCION EXISTENTE GBL 1.00 S/ 2,925.00 S/ 2,925.00 0.00 S/ 2,925.00 S/ 0.00
1.00.04 ELIMINACION DE DESMONTE GBL 1.00 S/ 2,925.00 S/ 2,925.00 0.00 S/ 2,925.00 S/ 0.00
1.00.05 CISTERNA PROVISIONAL PARA EL AGUA (CILINDROS) GBL 1.00 S/ 585.00 S/ 585.00 0.00 S/ 585.00 S/ 0.00
1.00.06 SUMINISTRO DE AGUA MES 0.00 S/ 292.50 S/ 0.00 0.00 S/ 292.50 S/ 0.00
2.00 MOVIMIENTO DE TIERRA S/ 29,056.40 S/ 0.00
2.00.01 EXCAVACION DE CIMIENTOS, ZAPATAS EN FORMA MANUAL H=1.50 M3 206.32 S/ 63.08 S/ 13,014.67 0.00 S/ 63.08 S/ 0.00
2.00.02 RELLENO CON MATERIAL PROPIO. M3 82.53 S/ 68.25 S/ 5,632.67 0.00 S/ 68.25 S/ 0.00
2.00.03 ACARREO DE MATERIAL EXCEDENTE. Dp =12 MTS M3 123.79 S/ 25.60 S/ 3,169.02 0.00 S/ 25.60 S/ 0.00
2.00.04 ELIMINACION DE MATERIAL EXCEDENTE M3 123.79 S/ 58.49 S/ 7,240.04 0.00 S/ 58.49 S/ 0.00
3.00 OBRA DE CONCRETO SIMPLE S/ 5,050.96 S/ 0.00
3.00.01 FALSO PISO 4” CON MEZCLA 1:8 C:H M2 96.94 S/ 52.10 S/ 5,050.96 0.00 S/ 52.10 S/ 0.00
4.00 CIMENTACION S/ 13,475.34 S/ 0.00
4.00.01 CIMIENTOS CORRIDOS DE CONCRETO 1:10 H:C. +30% P.G. M3 1.57 S/ 325.65 S/ 511.27 0.00 S/ 325.65 S/ 0.00
4.00.02 SOBRECIMIENTOS F’C=100 KG/CM2 M3 9.88 S/ 565.45 S/ 5,586.63 0.00 S/ 565.45 S/ 0.00
4.00.03 ENCOFRADO DE SOBRECIMIENTO. M2 131.74 S/ 56.00 S/ 7,377.44 0.00 S/ 56.00 S/ 0.00
5.00 OBRAS DE CONCRETO ARMADO S/ 57,308.78 S/ 0.00
ZAPATAS, VIGA DE CIMEN. Y MURO DE CONTENCION CONCRETO DE 210 KG / CM2
5.00.01 M3 20.74 S/ 555.64 S/ 11,524.03 0.00 S/ 555.64 S/ 0.00
VACIADA CON EQUIPO
5.00.02 SOLADO ZAPATAS DE CONCRETO POBRE DE E= 4” M2 69.12 S/ 39.30 S/ 2,716.42 0.00 S/ 39.30 S/ 0.00
5.00.03 ACERO ZAPATAS FY = 4200 KG / CM2 KG 1244.16 S/ 8.89 S/ 11,060.58 0.00 S/ 8.89 S/ 0.00
5.00.04 EXCAVACION DE ZAPATAS H= 1.0 MTS.EN FORMA MANUAL M3 41.47 S/ 65.00 S/ 2,695.55 0.00 S/ 65.00 S/ 0.00
5.00.05 RELLENO CON MATERIAL PROPIO M3 18.85 S/ 93.13 S/ 1,755.58 0.00 S/ 93.13 S/ 0.00
5.00.06 ACARREO DE MATERIAL EXCEDENTE. Dp = 20 MTS M3 22.62 S/ 26.73 S/ 604.63 0.00 S/ 26.73 S/ 0.00
5.00.07 ELIMINACION DE MATERIAL EXCEDENTE M3 22.62 S/ 59.50 S/ 1,345.89 0.00 S/ 59.50 S/ 0.00
5.00.08 CONCRETO DE 210 KG / CM2 VIGA DE CIMEN. VACIADA CON EQUIPOS M3 13.18 S/ 555.75 S/ 7,324.79 0.00 S/ 555.75 S/ 0.00
5.00.09 SOLADO DE CONCRETO POBRE VIGA DE CIMEN. DE E =4” M2 33.94 S/ 39.30 S/ 1,333.84 0.00 S/ 39.30 S/ 0.00
5.00.10 ACERO COLUMNAS Fy = 4200 KG / CM2 KG 946.90 S/ 8.89 S/ 8,417.94 0.00 S/ 8.89 S/ 0.00
5.00.11 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO. VIGA DE CIMENTACION M2 105.42 S/ 80.91 S/ 8,529.53 0.00 S/ 80.91 S/ 0.00
6.00 COLUMNAS Y PLACAS DEL 1er. PISO S/ 18,393.90 S/ 0.00
6.00.01 CONCRETO DE 210 KG / CM2 VACEADA CON PERSONAL Y EQUIPO. M3 5.48 S/ 832.59 S/ 4,562.57 0.00 S/ 832.59 S/ 0.00
6.00.02 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO M2 65.70 S/ 80.88 S/ 5,313.55 0.00 S/ 80.88 S/ 0.00
6.00.03 ACERO Fy = 4200 KG / CM2 KG 958.13 S/ 8.89 S/ 8,517.78 0.00 S/ 8.89 S/ 0.00
7.00 VIGAS DEL 1er. PISO S/ 36,415.75 S/ 0.00
7.00.01 CONCRETO DE 210 KG / CM2 VACIADA CON PERSONAL Y EQUIPO. M3 16.17 S/ 624.09 S/ 10,091.54 0.00 S/ 624.09 S/ 0.00
7.00.02 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO M2 97.04 S/ 86.05 S/ 8,350.68 0.00 S/ 86.05 S/ 0.00
7.00.03 ACERO Fy = 4200 KG / CM2 KG 2021.77 S/ 8.89 S/ 17,973.54 0.00 S/ 8.89 S/ 0.00
8.00 LOSA ALIGERADA E= 20 CMTS PRIMER PISO S/ 43,071.02 S/ 0.00
8.00.02 CONCRETO DE 210 KG / CM2 VACIADA CON PERSONAL Y EQUIPO M3 18.10 S/ 595.34 S/ 10,775.65 0.00 S/ 595.34 S/ 0.00
8.00.03 ENCOFRADO Y DESENCOFRADO M2 201.06 S/ 57.92 S/ 11,645.40 0.00 S/ 57.92 S/ 0.00
8.00.04 ACERO FY = 4.200 KG/ CM2 KG 1306.87 S/ 8.89 S/ 11,618.07 0.00 S/ 8.89 S/ 0.00
8.00.05 LADRILLO DE TECHO 30 X 30 X 15 UND 1810.00 S/ 4.99 S/ 9,031.90 0.00 S/ 4.99 S/ 0.00
9.00 ESCALERA AL SEGUNDO PISO S/ 7,030.45 S/ 0.00
9.00.01 CONCRETO DE 210KG/CM2 VACEADO CON PERSONAL Y EQUIPO M3 3.30 S/ 595.20 S/ 1,964.16 0.00 S/ 595.20 S/ 0.00
9.00.02 ENCOFRADO Y DESENCOFRADO M2 15.30 S/ 132.67 S/ 2,029.91 0.00 S/ 132.67 S/ 0.00
9.00.03 ACERO FY = 4200 kg/ cm2 KG 341.55 S/ 8.89 S/ 3,036.38 0.00 S/ 8.89 S/ 0.00
ARQUITECTURA
10.00 MUROS S/ 21,109.55 S/ 0.00
10.00.01 MURO DE LADRILLO 18 HUECOS EN AMARRE DE SOGA M2 216.40 S/ 97.55 S/ 21,109.55 0.00 S/ 97.55 S/ 0.00
11.00 REVESTIMIENTO S/ 40,269.70 S/ 0.00
11.00.01 TARRAJEO FROTACHADO DE MUROS INTERIORES M2 432.80 S/ 40.17 S/ 17,385.58 0.00 S/ 40.17 S/ 0.00
11.00.02 TARRAJEO FROTACHADO DE MUROS EXTERIORES M2 32.00 S/ 46.80 S/ 1,497.60 0.00 S/ 46.80 S/ 0.00
11.00.03 TARRAJEO FROTACHADO DE COLUMNAS M2 50.40 S/ 54.60 S/ 2,751.84 0.00 S/ 54.60 S/ 0.00
11.00.04 TARRAJEO FROTACHADO DE CIELO RAZO M2 201.06 S/ 50.70 S/ 10,193.74 0.00 S/ 50.70 S/ 0.00
11.00.05 TARRAJEO FROTACHADO EN ESCALERA M2 25.00 S/ 47.48 S/ 1,186.94 0.00 S/ 47.48 S/ 0.00
11.00.06 ENCHAPE DE BAÑO CON CERAMICO BLANCO NACIONAL ALT.1.80 M2 93.00 S/ 78.00 S/ 7,254.00 0.00 S/ 78.00 S/ 0.00
12.00 SEGURIDAD
SEÑALIZACIONES BASICAS DE SALIDAS DE EMERGENCIA,SISTEMA CONTRA INCENDIO,
12.00.01 QUE INCLUYE SENSOR DE HUMO,SIRENA Y ROCIADORES,LUCES DE EMERGENCIA Y
FILTRO DE AGUA.
13.00 PISOS S/ 39,999.26 S/ 8,897.85
13.00.01 CONTRA PISO DE 2” EN PRIMER PISO M2 234.00 S/ 44.19 S/ 10,339.76 0.00 S/ 44.19 S/ 0.00
13.00.02 ENCHAPE DE PISO CON CERAMICO ANTIDESLIZANTE BLANCO M2 234.00 S/ 126.75 S/ 29,659.50 70.20 S/ 126.75 S/ 8,897.85
14.00 PARED DE PERIMETRAL S/ 8,796.04 S/ 0.00
14.00.01 PERIMETRO DE PARED EXTERIOR DE LA ZONA DERECHA ML 20.00 S/ 439.80 S/ 8,796.04 0.00 S/ 439.80 S/ 0.00
15.00 INSTALACIONES ELECTRICAS S/ 23,398.96 S/ 0.00
15.00.01 SALIDAS DE TECHO C/ TUBO SEL 3/ AL 4” PTO 72.00 S/ 98.02 S/ 7,057.44 0.00 S/ 98.02 S/ 0.00
15.00.02 SALIDAS PARA TOMA CORRIENTES BIPOLARES SIMPLES PTO 40.00 S/ 110.46 S/ 4,418.44 0.00 S/ 110.46 S/ 0.00
15.00.03 SALIDAS PARA LUZ CONMUTACION PTO 3.00 S/ 124.41 S/ 373.23 0.00 S/ 124.41 S/ 0.00
15.00.04 SALIDAS PARA BRAQUETS PTO 12.00 S/ 94.25 S/ 1,131.00 0.00 S/ 94.25 S/ 0.00
15.00.05 SALIDA DE FUERZA PARA PORTERO ELECTRICO PTO 1.00 S/ 195.00 S/ 195.00 0.00 S/ 195.00 S/ 0.00
15.00.06 CAJAS DE PASE DE 200X200X100 PTO 20.00 S/ 97.50 S/ 1,950.00 0.00 S/ 97.50 S/ 0.00
15.00.07 ACOMETIDA GENERAL PARA TABLERO ML 45.00 S/ 45.50 S/ 2,047.50 0.00 S/ 45.50 S/ 0.00
15.00.08 TABLERO GENERAL CON 22 PALOS. INCLUYE THERMICOS PTO 5.00 S/ 780.00 S/ 3,900.00 0.00 S/ 780.00 S/ 0.00
15.00.09 POZO DE TIERRA, INCLUYE ACOMETIDA PTO 1.00 S/ 1,365.00 S/ 1,365.00 0.00 S/ 1,365.00 S/ 0.00
15.00.10 SALIDA PARA TELEFONO PTO 3.00 S/ 94.25 S/ 282.75 0.00 S/ 94.25 S/ 0.00
15.00.11 SALIDAS PARA INTERCOMUNICADORES PTO 1.00 S/ 113.10 S/ 113.10 0.00 S/ 113.10 S/ 0.00
15.00.12 SALIDAS PARA CABLES PTO 6.00 S/ 94.25 S/ 565.50 0.00 S/ 94.25 S/ 0.00
16.00 INSTALACIONES SANITARIAS
16.01.00 SALIDAS DE DESAGUE S/ 6,867.95 S/ 0.00
16.01.01 SALIDAPARA DESAGUE DE 4” PTO 16.00 S/ 143.31 S/ 2,293.03 0.00 S/ 143.31 S/ 0.00
16.01.02 SALIDA DE DESAGUE DE 2” PTO 16.00 S/ 105.56 S/ 1,688.96 0.00 S/ 105.56 S/ 0.00
16.01.03 SALIDAS DE VENTILACION PTO 7.00 S/ 105.56 S/ 738.92 0.00 S/ 105.56 S/ 0.00
16.01.04 REDES DE DISTRIBUCION DE 4” ML 28.00 S/ 35.03 S/ 980.84 0.00 S/ 35.03 S/ 0.00
16.01.05 MONTANTES DE DISTRIBUCION DE 4” ML 4.00 S/ 35.06 S/ 140.24 0.00 S/ 35.06 S/ 0.00
16.01.06 MONTANTES DE DISTRIBUCION DE 2” ML 2.00 S/ 32.50 S/ 65.00 0.00 S/ 32.50 S/ 0.00
16.01.07 REGISTROS DE BRONCE CROMADO Ø2” PTO 4.00 S/ 45.24 S/ 180.96 0.00 S/ 45.24 S/ 0.00
16.01.08 REGISTROS DE BRONCE CROMADO Ø4” PTO 0.00 S/ 104.00 S/ 0.00 0.00 S/ 104.00 S/ 0.00
16.01.09 CAJAS DE INSPECCION 30X60 cm. PTO 2.00 S/ 286.00 S/ 572.00 0.00 S/ 286.00 S/ 0.00
16.01.10 SUMIDERO Ø2” PTO 4.00 S/ 52.00 S/ 208.00 0.00 S/ 52.00 S/ 0.00
16.01.11 INSTALACION DE SANITARIOS.Y LAVADEROS MULTIPLES
16.01.12 LAVADEROS EN PATIO PROTOCOLO CONTRA COVID - 19
16.02.00 SALIDAS DE AGUA S/ 9,108.16 S/ 0.00
16.02.01 SALIDAS DE AGUA FRIA PTO 40.00 S/ 124.41 S/ 4,976.40 0.00 S/ 124.41 S/ 0.00
16.02.02 REDES DE DISTRIBUCION EN PVC CLASE – 10 D=1” ML 44.00 S/ 41.47 S/ 1,824.68 0.00 S/ 41.47 S/ 0.00
16.02.03 REDES DE DISTRIBUCION EN PVC CLASE – 10 D=3/4” ML 28.00 S/ 33.55 S/ 939.48 0.00 S/ 33.55 S/ 0.00
16.02.04 REDES DE DISTRIBUCION EN PVC CLASE – 10 d=1/2” ML 30.00 S/ 28.60 S/ 858.00 0.00 S/ 28.60 S/ 0.00
16.02.05 VALVULAS CON PUERTAS PESADAS DE BRONCE / UNIVERS PTO 4.00 S/ 127.40 S/ 509.60 0.00 S/ 127.40 S/ 0.00
SUB TOTAL S/ 370,173.70 S/ 8,897.85
GASTOS GENERALES + UTILIDAD 5 % S/ 18,508.69 S/ 2,669.36
TOTAL S/ 388,682.39 2.98% S/ 11,567.21
GESTIÓN DE PROYECTOS

VALORIZACION N 11

CLIENTE : EMPODERAMIENTO PERU S.A.C

FECHA : 29-08-2022 al 17-09-2022 Nº de Orden de Compra : Modalidad del Contrato

PERIODO : 11.00 Contratista : MISUSA CONSTRUCTORA Y SERVICIOS GENERALES Suma Alzada

CONTRATO PRESENTE PERIODO


Ítem Descripción partida TOTAL
U.M CANT P.U. CANT P.U. MONTO S/.
S/.
1.00 OBRAS PRELIMINARES S/ 10,821.49 S/ 0.00
1.00.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS. GBL 1.00 S/ 3,900.00 S/ 3,900.00 0.00 S/ 3,900.00 S/ 0.00
1.00.02 TRAZO Y REPLANTEO. M2 140.00 S/ 3.47 S/ 486.49 0.00 S/ 3.47 S/ 0.00
1.00.03 DEMOLICION CONSTRUCCION EXISTENTE GBL 1.00 S/ 2,925.00 S/ 2,925.00 0.00 S/ 2,925.00 S/ 0.00
1.00.04 ELIMINACION DE DESMONTE GBL 1.00 S/ 2,925.00 S/ 2,925.00 0.00 S/ 2,925.00 S/ 0.00
1.00.05 CISTERNA PROVISIONAL PARA EL AGUA (CILINDROS) GBL 1.00 S/ 585.00 S/ 585.00 0.00 S/ 585.00 S/ 0.00
1.00.06 SUMINISTRO DE AGUA MES 0.00 S/ 292.50 S/ 0.00 0.00 S/ 292.50 S/ 0.00
2.00 MOVIMIENTO DE TIERRA S/ 29,056.40 S/ 0.00
2.00.01 EXCAVACION DE CIMIENTOS, ZAPATAS EN FORMA MANUAL H=1.50 M3 206.32 S/ 63.08 S/ 13,014.67 0.00 S/ 63.08 S/ 0.00
2.00.02 RELLENO CON MATERIAL PROPIO. M3 82.53 S/ 68.25 S/ 5,632.67 0.00 S/ 68.25 S/ 0.00
2.00.03 ACARREO DE MATERIAL EXCEDENTE. Dp =12 MTS M3 123.79 S/ 25.60 S/ 3,169.02 0.00 S/ 25.60 S/ 0.00
2.00.04 ELIMINACION DE MATERIAL EXCEDENTE M3 123.79 S/ 58.49 S/ 7,240.04 0.00 S/ 58.49 S/ 0.00
3.00 OBRA DE CONCRETO SIMPLE S/ 5,050.96 S/ 0.00
3.00.01 FALSO PISO 4” CON MEZCLA 1:8 C:H M2 96.94 S/ 52.10 S/ 5,050.96 0.00 S/ 52.10 S/ 0.00
4.00 CIMENTACION S/ 13,475.34 S/ 0.00
4.00.01 CIMIENTOS CORRIDOS DE CONCRETO 1:10 H:C. +30% P.G. M3 1.57 S/ 325.65 S/ 511.27 0.00 S/ 325.65 S/ 0.00
4.00.02 SOBRECIMIENTOS F’C=100 KG/CM2 M3 9.88 S/ 565.45 S/ 5,586.63 0.00 S/ 565.45 S/ 0.00
4.00.03 ENCOFRADO DE SOBRECIMIENTO. M2 131.74 S/ 56.00 S/ 7,377.44 0.00 S/ 56.00 S/ 0.00
5.00 OBRAS DE CONCRETO ARMADO S/ 57,308.78 S/ 0.00
ZAPATAS, VIGA DE CIMEN. Y MURO DE CONTENCION CONCRETO DE 210 KG / CM2
5.00.01 M3 20.74 S/ 555.64 S/ 11,524.03 0.00 S/ 555.64 S/ 0.00
VACIADA CON EQUIPO
5.00.02 SOLADO ZAPATAS DE CONCRETO POBRE DE E= 4” M2 69.12 S/ 39.30 S/ 2,716.42 0.00 S/ 39.30 S/ 0.00
5.00.03 ACERO ZAPATAS FY = 4200 KG / CM2 KG 1244.16 S/ 8.89 S/ 11,060.58 0.00 S/ 8.89 S/ 0.00
5.00.04 EXCAVACION DE ZAPATAS H= 1.0 MTS.EN FORMA MANUAL M3 41.47 S/ 65.00 S/ 2,695.55 0.00 S/ 65.00 S/ 0.00
5.00.05 RELLENO CON MATERIAL PROPIO M3 18.85 S/ 93.13 S/ 1,755.58 0.00 S/ 93.13 S/ 0.00
5.00.06 ACARREO DE MATERIAL EXCEDENTE. Dp = 20 MTS M3 22.62 S/ 26.73 S/ 604.63 0.00 S/ 26.73 S/ 0.00
5.00.07 ELIMINACION DE MATERIAL EXCEDENTE M3 22.62 S/ 59.50 S/ 1,345.89 0.00 S/ 59.50 S/ 0.00
5.00.08 CONCRETO DE 210 KG / CM2 VIGA DE CIMEN. VACIADA CON EQUIPOS M3 13.18 S/ 555.75 S/ 7,324.79 0.00 S/ 555.75 S/ 0.00
5.00.09 SOLADO DE CONCRETO POBRE VIGA DE CIMEN. DE E =4” M2 33.94 S/ 39.30 S/ 1,333.84 0.00 S/ 39.30 S/ 0.00
5.00.10 ACERO COLUMNAS Fy = 4200 KG / CM2 KG 946.90 S/ 8.89 S/ 8,417.94 0.00 S/ 8.89 S/ 0.00
5.00.11 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO. VIGA DE CIMENTACION M2 105.42 S/ 80.91 S/ 8,529.53 0.00 S/ 80.91 S/ 0.00
6.00 COLUMNAS Y PLACAS DEL 1er. PISO S/ 18,393.90 S/ 0.00
6.00.01 CONCRETO DE 210 KG / CM2 VACEADA CON PERSONAL Y EQUIPO. M3 5.48 S/ 832.59 S/ 4,562.57 0.00 S/ 832.59 S/ 0.00
6.00.02 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO M2 65.70 S/ 80.88 S/ 5,313.55 0.00 S/ 80.88 S/ 0.00
6.00.03 ACERO Fy = 4200 KG / CM2 KG 958.13 S/ 8.89 S/ 8,517.78 0.00 S/ 8.89 S/ 0.00
7.00 VIGAS DEL 1er. PISO S/ 36,415.75 S/ 0.00
7.00.01 CONCRETO DE 210 KG / CM2 VACIADA CON PERSONAL Y EQUIPO. M3 16.17 S/ 624.09 S/ 10,091.54 0.00 S/ 624.09 S/ 0.00
7.00.02 ENCOFRADO Y DESENCOFRADO SEMI RUSTICO M2 97.04 S/ 86.05 S/ 8,350.68 0.00 S/ 86.05 S/ 0.00
7.00.03 ACERO Fy = 4200 KG / CM2 KG 2021.77 S/ 8.89 S/ 17,973.54 0.00 S/ 8.89 S/ 0.00
8.00 LOSA ALIGERADA E= 20 CMTS PRIMER PISO S/ 43,071.02 S/ 0.00
8.00.02 CONCRETO DE 210 KG / CM2 VACIADA CON PERSONAL Y EQUIPO M3 18.10 S/ 595.34 S/ 10,775.65 0.00 S/ 595.34 S/ 0.00
8.00.03 ENCOFRADO Y DESENCOFRADO M2 201.06 S/ 57.92 S/ 11,645.40 0.00 S/ 57.92 S/ 0.00
8.00.04 ACERO FY = 4.200 KG/ CM2 KG 1306.87 S/ 8.89 S/ 11,618.07 0.00 S/ 8.89 S/ 0.00
8.00.05 LADRILLO DE TECHO 30 X 30 X 15 UND 1810.00 S/ 4.99 S/ 9,031.90 0.00 S/ 4.99 S/ 0.00
9.00 ESCALERA AL SEGUNDO PISO S/ 7,030.45 S/ 0.00
9.00.01 CONCRETO DE 210KG/CM2 VACEADO CON PERSONAL Y EQUIPO M3 3.30 S/ 595.20 S/ 1,964.16 0.00 S/ 595.20 S/ 0.00
9.00.02 ENCOFRADO Y DESENCOFRADO M2 15.30 S/ 132.67 S/ 2,029.91 0.00 S/ 132.67 S/ 0.00
9.00.03 ACERO FY = 4200 kg/ cm2 KG 341.55 S/ 8.89 S/ 3,036.38 0.00 S/ 8.89 S/ 0.00
ARQUITECTURA
10.00 MUROS S/ 21,109.55 S/ 0.00
10.00.01 MURO DE LADRILLO 18 HUECOS EN AMARRE DE SOGA M2 216.40 S/ 97.55 S/ 21,109.55 0.00 S/ 97.55 S/ 0.00
11.00 REVESTIMIENTO S/ 40,269.70 S/ 7,254.00
11.00.01 TARRAJEO FROTACHADO DE MUROS INTERIORES M2 432.80 S/ 40.17 S/ 17,385.58 0.00 S/ 40.17 S/ 0.00
11.00.02 TARRAJEO FROTACHADO DE MUROS EXTERIORES M2 32.00 S/ 46.80 S/ 1,497.60 0.00 S/ 46.80 S/ 0.00
11.00.03 TARRAJEO FROTACHADO DE COLUMNAS M2 50.40 S/ 54.60 S/ 2,751.84 0.00 S/ 54.60 S/ 0.00
11.00.04 TARRAJEO FROTACHADO DE CIELO RAZO M2 201.06 S/ 50.70 S/ 10,193.74 0.00 S/ 50.70 S/ 0.00
11.00.05 TARRAJEO FROTACHADO EN ESCALERA M2 25.00 S/ 47.48 S/ 1,186.94 0.00 S/ 47.48 S/ 0.00
11.00.06 ENCHAPE DE BAÑO CON CERAMICO BLANCO NACIONAL ALT.1.80 M2 93.00 S/ 78.00 S/ 7,254.00 93.00 S/ 78.00 S/ 7,254.00
12.00 SEGURIDAD
SEÑALIZACIONES BASICAS DE SALIDAS DE EMERGENCIA,SISTEMA CONTRA INCENDIO,
12.00.01 QUE INCLUYE SENSOR DE HUMO,SIRENA Y ROCIADORES,LUCES DE EMERGENCIA Y
FILTRO DE AGUA.
13.00 PISOS S/ 39,999.26 S/ 14,829.75
13.00.01 CONTRA PISO DE 2” EN PRIMER PISO M2 234.00 S/ 44.19 S/ 10,339.76 0.00 S/ 44.19 S/ 0.00
13.00.02 ENCHAPE DE PISO CON CERAMICO ANTIDESLIZANTE BLANCO M2 234.00 S/ 126.75 S/ 29,659.50 117.00 S/ 126.75 S/ 14,829.75
14.00 PARED DE PERIMETRAL S/ 8,796.04 S/ 0.00
14.00.01 PERIMETRO DE PARED EXTERIOR DE LA ZONA DERECHA ML 20.00 S/ 439.80 S/ 8,796.04 0.00 S/ 439.80 S/ 0.00
15.00 INSTALACIONES ELECTRICAS S/ 23,398.96 S/ 0.00
15.00.01 SALIDAS DE TECHO C/ TUBO SEL 3/ AL 4” PTO 72.00 S/ 98.02 S/ 7,057.44 0.00 S/ 98.02 S/ 0.00
15.00.02 SALIDAS PARA TOMA CORRIENTES BIPOLARES SIMPLES PTO 40.00 S/ 110.46 S/ 4,418.44 0.00 S/ 110.46 S/ 0.00
15.00.03 SALIDAS PARA LUZ CONMUTACION PTO 3.00 S/ 124.41 S/ 373.23 0.00 S/ 124.41 S/ 0.00
15.00.04 SALIDAS PARA BRAQUETS PTO 12.00 S/ 94.25 S/ 1,131.00 0.00 S/ 94.25 S/ 0.00
15.00.05 SALIDA DE FUERZA PARA PORTERO ELECTRICO PTO 1.00 S/ 195.00 S/ 195.00 0.00 S/ 195.00 S/ 0.00
15.00.06 CAJAS DE PASE DE 200X200X100 PTO 20.00 S/ 97.50 S/ 1,950.00 0.00 S/ 97.50 S/ 0.00
15.00.07 ACOMETIDA GENERAL PARA TABLERO ML 45.00 S/ 45.50 S/ 2,047.50 0.00 S/ 45.50 S/ 0.00
15.00.08 TABLERO GENERAL CON 22 PALOS. INCLUYE THERMICOS PTO 5.00 S/ 780.00 S/ 3,900.00 0.00 S/ 780.00 S/ 0.00
15.00.09 POZO DE TIERRA, INCLUYE ACOMETIDA PTO 1.00 S/ 1,365.00 S/ 1,365.00 0.00 S/ 1,365.00 S/ 0.00
15.00.10 SALIDA PARA TELEFONO PTO 3.00 S/ 94.25 S/ 282.75 0.00 S/ 94.25 S/ 0.00
15.00.11 SALIDAS PARA INTERCOMUNICADORES PTO 1.00 S/ 113.10 S/ 113.10 0.00 S/ 113.10 S/ 0.00
15.00.12 SALIDAS PARA CABLES PTO 6.00 S/ 94.25 S/ 565.50 0.00 S/ 94.25 S/ 0.00
16.00 INSTALACIONES SANITARIAS
16.01.00 SALIDAS DE DESAGUE S/ 6,867.95 S/ 0.00
16.01.01 SALIDAPARA DESAGUE DE 4” PTO 16.00 S/ 143.31 S/ 2,293.03 0.00 S/ 143.31 S/ 0.00
16.01.02 SALIDA DE DESAGUE DE 2” PTO 16.00 S/ 105.56 S/ 1,688.96 0.00 S/ 105.56 S/ 0.00
16.01.03 SALIDAS DE VENTILACION PTO 7.00 S/ 105.56 S/ 738.92 0.00 S/ 105.56 S/ 0.00
16.01.04 REDES DE DISTRIBUCION DE 4” ML 28.00 S/ 35.03 S/ 980.84 0.00 S/ 35.03 S/ 0.00
16.01.05 MONTANTES DE DISTRIBUCION DE 4” ML 4.00 S/ 35.06 S/ 140.24 0.00 S/ 35.06 S/ 0.00
16.01.06 MONTANTES DE DISTRIBUCION DE 2” ML 2.00 S/ 32.50 S/ 65.00 0.00 S/ 32.50 S/ 0.00
16.01.07 REGISTROS DE BRONCE CROMADO Ø2” PTO 4.00 S/ 45.24 S/ 180.96 0.00 S/ 45.24 S/ 0.00
16.01.08 REGISTROS DE BRONCE CROMADO Ø4” PTO 0.00 S/ 104.00 S/ 0.00 0.00 S/ 104.00 S/ 0.00
16.01.09 CAJAS DE INSPECCION 30X60 cm. PTO 2.00 S/ 286.00 S/ 572.00 0.00 S/ 286.00 S/ 0.00
16.01.10 SUMIDERO Ø2” PTO 4.00 S/ 52.00 S/ 208.00 0.00 S/ 52.00 S/ 0.00
16.01.11 INSTALACION DE SANITARIOS.Y LAVADEROS MULTIPLES
16.01.12 LAVADEROS EN PATIO PROTOCOLO CONTRA COVID - 19
16.02.00 SALIDAS DE AGUA S/ 9,108.16 S/ 0.00
16.02.01 SALIDAS DE AGUA FRIA PTO 40.00 S/ 124.41 S/ 4,976.40 0.00 S/ 124.41 S/ 0.00
16.02.02 REDES DE DISTRIBUCION EN PVC CLASE – 10 D=1” ML 44.00 S/ 41.47 S/ 1,824.68 0.00 S/ 41.47 S/ 0.00
16.02.03 REDES DE DISTRIBUCION EN PVC CLASE – 10 D=3/4” ML 28.00 S/ 33.55 S/ 939.48 0.00 S/ 33.55 S/ 0.00
16.02.04 REDES DE DISTRIBUCION EN PVC CLASE – 10 d=1/2” ML 30.00 S/ 28.60 S/ 858.00 0.00 S/ 28.60 S/ 0.00
16.02.05 VALVULAS CON PUERTAS PESADAS DE BRONCE / UNIVERS PTO 4.00 S/ 127.40 S/ 509.60 0.00 S/ 127.40 S/ 0.00
SUB TOTAL S/ 370,173.70 S/ 20,245.29
GASTOS GENERALES + UTILIDAD 5 % S/ 18,508.69 S/ 32,869.70
TOTAL S/ 388,682.39 13.67% S/ 53,114.99