Presupuesto MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR
HUACACHIVATO HASTA LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA
2.00 DENOMINACION DE LA OBRA : "MEJORAMIENTO DEL SERVICIO DE AGUA PARA RIEGO DEL SISTEMA DE
RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA
EL SECTOR LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS E IMPERIAL DE
LA PROVINCIA DE CAÑETE - LIMA"
9 META : 25
90.00%
AVANCE FISICO DE OBRA , CURVA S
84.58%
82.59%
80.00%
71.96%
70.00%
62.02%
61.00%
60.00%
50.00% 50.12%
40.00%
AVANCE PROGRAMADO
AVANCE FISICO
30.00% 28.80%
23.38%
20.00%
11.56%
10.00%
0.80% 2.08%
0.00%
Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22
PLAZO DE EJECUCION
OBRA : "MEJORAMIENTO DEL SERVICIO DE PROVICION DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARIA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA EL SECTOR LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA"
01 OBRAS PROVISIONALES 8,284.54 8,284.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01 CAMPAMENTO PROVISIONAL EN LA OBRA glb 1.00 2,444.30 2,444.30 2,444.30
01.02 CARTEL DE OBRA 3.60x7.20 und 1.00 2,070.24 2,070.24 2,070.24
01.03 TRAZO, NIVELACION Y REPLANTEO m 1,300.00 2.90 3,770.00 3,770.00
02 OBRAS PRELIMINARES 55,578.90 15,432.50 6,297.65 10,042.50 10,042.50 8,742.50 4,371.25 0.00 0.00 650.00
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 6,500.00 6,500.00 3,250.00 1,300.00 1,300.00 650.00
02.02 LIMPIEZA Y DESBROCE DE CANAL m2 3,120.00 1.72 5,366.40 3,440.00 1,926.40
02.03 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE OBRA mes 5.00 8,742.50 43,712.50 8,742.50 4,371.25 8,742.50 8,742.50 8,742.50 4,371.25
03 CANAL TAPADO EN ZONA URBANA 2,739,812.29 0.00 25,396.49 256,688.67 330,878.97 133,539.13 620,980.03 307,503.47 633,977.82 430,847.71
03.01 MOVIMIENTO DE TIERRAS 152,987.97 0.00 7,947.22 53,898.72 14,767.05 27,684.35 12,965.74 9,820.00 12,186.46 13,718.43
03.01.01 EXCAVACIÓN DE MATERIAL SUELTO m3 909.21 33.34 30,313.06 1,639.66 11,619.66 2,778.33 7,307.46 2,433.82 3,000.00 1,534.13
03.01.02 RELLENO Y COMPACTADO CON MATERIAL DE AFIRMADO (CAMA=0.20m) m3 545.53 101.75 55,507.68 4,884.00 38,095.20 4,395.60 3,601.95 1,953.60 1,200.00 1,377.33
03.01.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m3 792.00 51.40 40,708.80 5,181.12 2,647.61 7,710.00 4,520.00 8,075.00 12,575.07
03.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1,096.95 24.12 26,458.43 1,423.56 4,183.86 2,412.00 14,127.33 868.32 1,100.00 1,200.00 1,143.36
03.02 DEMOLICION DE ESTRUCTURA DE CANAL EXISTENTE 17,449.27 0.00 17,449.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01 DEMOLICION DE ESTRUCTURA DE CANAL m3 160.40 77.43 12,419.77 12,419.77
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 208.52 24.12 5,029.50 5,029.50
03.03 CONCRETO ARMADO 2,569,375.05 0.00 0.00 202,789.95 316,111.92 105,854.78 608,014.29 297,683.47 621,791.36 417,129.28
03.03.01 CONCRETO F°C 175 KG/CM2 m3 1,404.00 480.95 675,253.80 50,018.80 129,125.46 19,391.90 173,892.28 85,472.00 121,881.36 95,472.00
03.03.02 CONCRETO F°C 210 KG/CM2 m3 624.00 520.61 324,860.64 44,860.64 160,000.00 120,000.00
03.03.03 ENCOFRADO Y DESENCOFRADO m2 5,980.00 42.98 257,020.40 5,776.51 39,197.76 24,756.48 49,813.82 37,065.83 65,410.00 35,000.00
03.03.04 ACERO F°Y=4200 KG/CM2 kg 123,300.62 10.25 1,263,831.36 146,994.64 147,788.70 55,362.61 375,630.73 120,785.00 260,000.00 157,269.68
03.03.05 JUNTA DE DILATACION CADA 12 m m 545.00 29.28 15,957.60 3,559.57 5,370.83 2,500.00 2,500.00 2,027.20
03.03.06 JUNTA DE CONTRACCION CADA 3 m. m 1,625.00 19.97 32,451.25 2,784.22 3,306.63 7,000.00 12,000.00 7,360.40
04 TOMAS LATERALES TIPICAS 37,471.46 0.00 0.00 0.00 0.00 0.00 0.00 4,000.00 22,345.20 11,126.26
04.01 MOVIMIENTO DE TIERRAS 3,158.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,158.84 0.00
04.01.01 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 45.90 44.70 2,051.73 2,051.73
04.01.02 ELIMINACION DE MATERIAL EXCEDENTE m3 45.90 24.12 1,107.11 1,107.11
04.02 CONCRETO ARMADO 10,903.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,436.66 3,466.48
04.02.01 SOLADO CONCRETO F°C100KG/CM2 m2 21.00 36.21 760.41 760.41
04.02.02 CONCRETO F°C 175 KG/CM2 m3 6.86 480.95 3,299.32 3,299.32
04.02.03 ENCOFRADO Y DESENCOFRADO m2 41.10 42.98 1,766.48 800.00 966.48
04.02.04 ACERO F°Y=4200 KG/CM2 kg 495.31 10.25 5,076.93 2,576.93 2,500.00
04.03 ALBAÑILERIA 1,509.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 749.70 759.78
04.03.01 EMBOQUILLADO DE PIEDRA ASENTADO EN CONCRETO F´C=175kg/cm2 m3 12.60 119.80 1,509.48 749.70 759.78
04.04 CARPINTERIA METALICA 21,900.00 0.00 0.00 0.00 0.00 0.00 0.00 4,000.00 11,000.00 6,900.00
04.04.01 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPICA und 15.00 1,460.00 21,900.00 4,000.00 11,000.00 6,900.00
05 PUENTE VEHICULAR TIPICO 27,357.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27,357.06 0.00
05.01 MOVIMIENTO DE TIERRAS 1,005.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,005.26 0.00
05.01.01 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 14.40 44.70 643.68 643.68
05.01.02 RELLENO Y COMPACTADO A MANO m3 2.88 29.07 83.72 83.72
05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 11.52 24.12 277.86 277.86
05.02 CONCRETO ARMADO 26,351.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,351.80 0.00
05.02.01 SOLADO CONCRETO F°C100KG/CM2 m2 12.00 36.21 434.52 434.52
05.02.02 CONCRETO F°C 210 KG/CM2 m3 19.20 520.61 9,995.71 9,995.71
05.02.03 ENCOFRADO Y DESENCOFRADO m2 73.84 42.98 3,173.64 3,173.64
05.02.04 ACERO F°Y=4200 KG/CM2 kg 1,243.70 10.25 12,747.93 12,747.93
06 PLAN DE MITIGACION AMBIENTAL 27,086.09 0.00 6,417.22 6,043.05 6,043.05 5,000.00 4,000.00 0.00 0.00 0.00
06.01 MEDIDAS DE MANEJO Y MITIGACION mes 5.00 5,000.00 25,000.00 6,000.00 5,000.00 5,000.00 5,000.00 4,000.00 0.00 0.00 0.00
06.02 MANEJO DE RESIDUOS SOLIDOS Y LIQUIDOS glb 1.00 2,086.09 2,086.09 417.22 1,043.05 1,043.05 0.00 0.00 0.00
07 PLAN DE SEGUIMIENTO Y MONITOREO ARQUEOLOGICO 30,000.00 0.00 0.00 0.00 0.00 0.00 0.00 9,600.00 10,400.00 10,000.00
07.01 SEGUIMIENTO Y MONITOREO ARQUEOLOGICO. mes 5.00 6,000.00 30,000.00 9,600.00 10,400.00 10,000.00
08 SEGURIDAD Y SALUD EN EL TRABAJO 31,834.10 0.00 0.00 8,135.80 3,655.00 13,370.22 3,112.50 1,448.08 1,000.00 1,112.50
08.01 CAPACITACIÓN DE SEGURIDAD Y SALUD mes 5.00 3,112.50 15,562.50 9,337.50 3,112.50 1,000.00 1,000.00 1,112.50
08.02 EQUIPO DE PROTECCIÓN INDIVIDUAL glb 1.00 8,961.60 8,961.60 4,480.80 0.00 4,032.72 448.08
08.03 EQUIPO DE PROTECCIÓN COLECTIVA glb 1.00 7,310.00 7,310.00 3,655.00 3,655.00
09 CAPACITACION DE USUARIOS 8,375.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,187.50 4,187.50
09.01 FORTALECIMIENTO DE CAPACIDADES DE LA ORGANIZACION DEL COMITÉ DE USUARIOS Taller 1.00 2,050.00 2,050.00 1,025.00 1,025.00
DE AGUA
09.02 FORTALECIMIENTO DE CAPACIDADES EN OPERACION Y MANTENIMIENTO DE LA Taller 1.00 3,275.00 3,275.00 1,637.50 1,637.50
INFRAESTRUCTURA DE RIEGO Y EN TECNICAS DE MANEJO DE RIEGO
09.03 FORTALECIMIENTO DE CAPACIDADES PARA LA ORGANIZACION DE PRODUCTORES Taller 1.00 3,050.00 3,050.00 1,525.00 1,525.00
AGRICOLAS
COSTO DIRECTO 2,965,799.44 23,717.04 38,111.36 280,910.02 350,619.52 160,651.85 632,463.78 322,551.55 699,267.58 457,923.97
GASTOS GENERALES (7.5%) 222,434.96 1,778.78 2,858.35 21,068.25 26,296.46 12,048.89 47,434.78 24,191.37 52,445.07 34,344.30
SUB TOTAL 3,188,234.40 25,495.82 40,969.71 301,978.27 376,915.98 172,700.74 679,898.56 346,742.92 751,712.65 492,268.27
% AVANCE 0.80% 1.29% 9.47% 11.82% 5.42% 21.33% 10.88% 23.58% 15.44%
% AVANCE ACUMULADO 0.80% 2.08% 11.56% 23.38% 28.80% 50.12% 61.00% 84.57% 100.00%
AVANCE FÍSICO POR PARTIDAS
OBRA MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA
DE CAÑETE - DEPARTAMENTO DE LIMA DRA
Dirección
Residente de Obra: ING. MIGUEL ALBERTO SANDOVAL OJEDA FECHA DE INICIO: 3/21/2022 Regional de
Supervisor de Obra: ING. MAX BERNABE ORELLANO FECHA TERMINO: 8/17/2022 Agricultura GRL
Cliente DIRECCION REGIONAL DE AGRICULTURA - LIMA PLAZO DE EJECUCIÓN: 150 días Calendario
Lugar LIMA - CAÑETE - IMPERIAL AMPLIACION PLAZO : 90 días Calendario
TOTAL MENSUAL PROGRAMADO (S/) PROGRAMADO 23,717.04 38,111.36 280,910.02 350,619.52 160,651.85 632,463.78 318,451.55 699,034.18 434,763.79
TOTAL MENSUAL EJECUTADO (S/) EJECUTADO 23,717.04 38,111.36 280,910.02 350,619.52 160,651.85 632,463.78 352,902.25 294,908.74 315,219.33
PROGRAMADO 0.80% 1.29% 9.47% 11.82% 5.42% 21.33% 10.74% 23.57% 14.66%
AVANCE MENSUAL (%)
EJECUTADO 0.80% 1.29% 9.47% 11.82% 5.42% 21.33% 11.90% 9.94% 10.63%
PROGRAMADO 0.80% 2.08% 11.56% 23.38% 28.80% 50.12% 60.86% 84.43% 99.09%
AVANCE ACUMULADO (%)
EJECUTADO 0.80% 2.08% 11.56% 23.38% 28.80% 50.12% 62.02% 71.96% 82.59%
OBRA: MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE
LIMA
PROPIETARIO: DIRECCIÓN REGIONAL DE AGRICULTURA - LIMA DRA
RESIDENTE: ING. MIGUEL ALBERTO SANDOVAL OJEDA Dirección
Regional de
SUPERVISOR : ING. MAX BERNABE ORELLANO
Agricultura GRL
MONTO DE LA OBRA: S/ 3'500,005.00
VALORIZACIÓN DE OBRA N° 09
CONTROL DE AVANCE DE OBRA CURVA "S" AVANCE FÍSICO PROGRAMADO VS EJECUTADO
DEL 01 AL 30 DE NOVIEMBRE DE 2022
180.00%
160.00% 87.65%
140.00%
71.68%
120.00%
63.29%
100.00%
82.59%
80.00%
71.96%
60.00% 62.02%
30.67%
25.55% 50.12%
40.00%
15.81% 28.80%
23.38%
20.00%
11.56%
4.44%
1.75%
0.80% 2.08%
0.00% 0.00%
0.00%
Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
Feb-22 0.00% 28-Feb-22 0.00%
1 Mar-22 23,717.04 23,717.04 0.80% 0.80% Mar-22 61,300.00 61,300.00 1.75% 1.75%
2 Apr-22 38,111.36 61,828.40 1.29% 2.08% Apr-22 94,171.49 155,471.49 2.69% 4.44%
3 May-22 280,910.02 342,738.42 9.47% 11.56% May-22 397,905.36 553,376.85 11.37% 15.81%
4 Jun-22 350,619.52 693,357.94 11.82% 23.38% Jun-22 340,861.39 894,238.24 9.74% 25.55%
5 Jul-22 160,651.85 854,009.79 5.42% 28.80% Jul-22 179,174.27 1,073,412.51 5.12% 30.67%
6 Aug-22 632,463.78 1,486,473.57 21.33% 50.12% Aug-22 1,141,609.07 2,215,021.58 32.62% 63.29%
7 Sep-22 352,902.25 1,839,375.82 11.90% 62.02% Sep-22 293,913.62 2,508,935.20 8.40% 71.68%
8 Oct-22 294,908.74 2,134,284.56 9.94% 71.96% Oct-22 558,880.78 3,067,815.98 15.97% 87.65%
Nov-22 315,219.33 2,449,503.89 10.11% 82.59% Nov-22 363,907.65 3,431,723.63 10.40% 98.05%
TOTAL 2,449,503.89 82.59% TOTAL 3,431,723.63 98.05%
CRONOGRAMA DE AVANCE VALORIZADO DE OBRA
OBRA : "MEJORAMIENTO DEL SERVICIO DE PROVICION DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARIA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA EL SECTOR LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA"
ITEM PARTIDAS UND METRADO P.U PARCIAL MARZO ABRIL MAYO JUNIO JULIO AGOSTO
OBRA : "MEJORAMIENTO DEL SERVICIO DE PROVICION DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARIA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA EL SECTOR LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA"
ITEM PARTIDAS UND METRADO P.U PARCIAL MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE
01 OBRAS PROVISIONALES 8,284.54 8,284.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01 CAMPAMENTO PROVISIONAL EN LA OBRA glb 1.00 2,444.30 2,444.30 2,444.30
01.02 CARTEL DE OBRA 3.60x7.20 und 1.00 2,070.24 2,070.24 2,070.24
01.03 TRAZO, NIVELACION Y REPLANTEO m 1,300.00 2.90 3,770.00 3,770.00
02 OBRAS PRELIMINARES 55,578.90 12,791.80 12,061.65 9,819.47 9,502.72 9,819.47 1,583.79 1,583.79 1,583.79 1,583.79
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 6,500.00 6,500.00 4,766.67 1,733.33
02.02 LIMPIEZA Y DESBROCE DE CANAL m2 3,120.00 1.72 5,366.40 4,540.80 825.60
02.03 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE OBRA mes 5.00 8,742.50 43,712.50 3,484.33 9,502.72 9,819.47 9,502.72 9,819.47 1,583.79 1,583.79 1,583.79 1,583.79
03 CANAL TAPADO EN ZONA URBANA 2,739,812.29 0.00 455,496.33 802,302.39 735,388.56 656,972.32 89,652.69 89,652.69 89,652.69 89,652.69
03.01 MOVIMIENTO DE TIERRAS 152,987.97 0.00 121,832.37 29,391.70 1,763.90 0.00 0.00 0.00 0.00 0.00
03.01.01 EXCAVACIÓN DE MATERIAL SUELTO m3 909.21 33.34 30,313.06 30,313.06
03.01.02 RELLENO Y COMPACTADO CON MATERIAL DE AFIRMADO (CAMA=0.20m) m3 545.53 101.75 55,507.68 55,507.68
03.01.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m3 792.00 51.40 40,708.80 36,011.63 4,697.17
03.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1,096.95 24.12 26,458.43 24,694.53 1,763.90
03.02 DEMOLICION DE ESTRUCTURA DE CANAL EXISTENTE 17,449.27 0.00 2,617.39 14,831.88 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01 DEMOLICION DE ESTRUCTURA DE CANAL m3 160.40 77.43 12,419.77 1,862.97 10,556.80
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 208.52 24.12 5,029.50 754.42 4,275.08
03.03 CONCRETO ARMADO 2,569,375.05 0.00 331,046.57 758,078.81 733,624.66 656,972.32 89,652.69 89,652.69 89,652.69 89,652.69
03.03.01 CONCRETO F°C 175 KG/CM2 m3 1,404.00 480.95 675,253.80 79,802.72 190,298.80 184,160.13 190,298.80 30,693.35 30,693.35 30,693.35 30,693.35
03.03.02 CONCRETO F°C 210 KG/CM2 m3 624.00 520.61 324,860.64 8,701.62 89,916.78 87,016.24 89,916.80 49,309.20 49,309.20 49,309.20 49,309.20
03.03.03 ENCOFRADO Y DESENCOFRADO m2 5,980.00 42.98 257,020.40 35,048.24 72,433.02 70,096.47 72,433.02 7,009.65 7,009.65 7,009.65 7,009.65
03.03.04 ACERO F°Y=4200 KG/CM2 kg 123,300.62 10.25 1,263,831.36 202,213.02 391,787.72 379,149.41 290,681.21
03.03.05 JUNTA DE DILATACION CADA 12 m m 545.00 29.28 15,957.60 1,740.83 4,497.14 4,352.07 4,497.14 870.42 870.42 870.42 870.42
03.03.06 JUNTA DE CONTRACCION CADA 3 m. m 1,625.00 19.97 32,451.25 3,540.14 9,145.35 8,850.34 9,145.35 1,770.07 1,770.07 1,770.07 1,770.07
04 TOMAS LATERALES TIPICAS 37,471.46 0.00 0.00 960.69 4,275.82 12,956.56 19,278.39 19,278.39 19,278.39 19,278.39
04.01 MOVIMIENTO DE TIERRAS 3,158.84 0.00 0.00 960.69 2,198.15 0.00 0.00 0.00 0.00 0.00
04.01.01 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 45.90 44.70 2,051.73 683.91 1,367.82
04.01.02 ELIMINACION DE MATERIAL EXCEDENTE m3 45.90 24.12 1,107.11 276.78 830.33
04.02 CONCRETO ARMADO 10,903.14 0.00 0.00 0.00 2,077.67 8,825.47 0.00 0.00 0.00 0.00
04.02.01 SOLADO CONCRETO F°C100KG/CM2 m2 21.00 36.21 760.41 760.41
04.02.02 CONCRETO F°C 175 KG/CM2 m3 6.86 480.95 3,299.32 412.41 2,886.91
04.02.03 ENCOFRADO Y DESENCOFRADO m2 41.10 42.98 1,766.48 227.93 1,538.55
04.02.04 ACERO F°Y=4200 KG/CM2 kg 495.31 10.25 5,076.93 676.92 4,400.01
04.03 ALBAÑILERIA 1,509.48 0.00 0.00 0.00 0.00 266.38 1,243.10 1,243.10 1,243.10 1,243.10
04.03.01 EMBOQUILLADO DE PIEDRA ASENTADO EN CONCRETO F´C=175kg/cm2 m3 12.60 119.80 1,509.48 266.38 1,243.10 1,243.10 1,243.10 1,243.10
04.04 CARPINTERIA METALICA 21,900.00 0.00 0.00 0.00 0.00 3,864.71 18,035.29 18,035.29 18,035.29 18,035.29
04.04.01 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPICA und 15.00 1,460.00 21,900.00 3,864.71 18,035.29 18,035.29 18,035.29 18,035.29
05 PUENTE VEHICULAR TIPICO 27,357.06 0.00 0.00 0.00 1,005.26 26,351.80 0.00 0.00 0.00 0.00
05.01 MOVIMIENTO DE TIERRAS 1,005.26 0.00 0.00 0.00 1,005.26 0.00 0.00 0.00 0.00 0.00
05.01.01 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 14.40 44.70 643.68 643.68
05.01.02 RELLENO Y COMPACTADO A MANO m3 2.88 29.07 83.72 83.72
05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 11.52 24.12 277.86 277.86
05.02 CONCRETO ARMADO 26,351.80 0.00 0.00 0.00 0.00 26,351.80 0.00 0.00 0.00 0.00
05.02.01 SOLADO CONCRETO F°C100KG/CM2 m2 12.00 36.21 434.52 434.52
05.02.02 CONCRETO F°C 210 KG/CM2 m3 19.20 520.61 9,995.71 9,995.71
05.02.03 ENCOFRADO Y DESENCOFRADO m2 73.84 42.98 3,173.64 3,173.64
05.02.04 ACERO F°Y=4200 KG/CM2 kg 1,243.70 10.25 12,747.93 12,747.93
06 PLAN DE MITIGACION AMBIENTAL 27,086.09 2,159.03 5,888.29 6,084.56 5,888.28 6,084.55 981.38 981.38 981.38 981.38
06.01 MEDIDAS DE MANEJO Y MITIGACION mes 5.00 5,000.00 25,000.00 1,992.75 5,434.78 5,615.95 5,434.78 5,615.94 905.80 905.80 905.80 905.80
06.02 MANEJO DE RESIDUOS SOLIDOS Y LIQUIDOS glb 1.00 2,086.09 2,086.09 166.28 453.51 468.61 453.50 468.61 75.58 75.58 75.58 75.58
07 PLAN DE SEGUIMIENTO Y MONITOREO ARQUEOLOGICO 30,000.00 2,391.30 6,521.74 6,739.13 6,521.74 6,739.13 1,086.96 1,086.96 1,086.96 1,086.96
07.01 SEGUIMIENTO Y MONITOREO ARQUEOLOGICO. mes 5.00 6,000.00 30,000.00 2,391.30 6,521.74 6,739.13 6,521.74 6,739.13 1,086.96 1,086.96 1,086.96 1,086.96
08 SEGURIDAD Y SALUD EN EL TRABAJO 31,834.10 13,105.03 7,536.86 3,304.37 3,197.77 3,304.37 1,385.70 1,385.70 1,385.70 1,385.70
08.01 CAPACITACIÓN DE SEGURIDAD Y SALUD mes 5.00 3,112.50 15,562.50 1,172.52 3,197.77 3,304.37 3,197.77 3,304.37 1,385.70 1,385.70 1,385.70 1,385.70
08.02 EQUIPO DE PROTECCIÓN INDIVIDUAL glb 1.00 8,961.60 8,961.60 6,571.84 2,389.76
08.03 EQUIPO DE PROTECCIÓN COLECTIVA glb 1.00 7,310.00 7,310.00 5,360.67 1,949.33
09 CAPACITACION DE USUARIOS 8,375.00 0.00 0.00 0.00 2,820.47 4,605.33 949.20 949.20 949.20 949.20
09.01 FORTALECIMIENTO DE CAPACIDADES DE LA ORGANIZACION DEL COMITÉ DE USUARIOS DE AGUA Taller 1.00 2,050.00 2,050.00 1,148.00 902.00
09.02 FORTALECIMIENTO DE CAPACIDADES EN OPERACION Y MANTENIMIENTO DE LA INFRAESTRUCTURA DE Taller 1.00 3,275.00 3,275.00 881.73 1,952.40 440.87 440.87 440.87 440.87
RIEGO Y EN TECNICAS DE MANEJO DE RIEGO
09.03 FORTALECIMIENTO DE CAPACIDADES PARA LA ORGANIZACION DE PRODUCTORES AGRICOLAS Taller 1.00 3,050.00 3,050.00 790.74 1,750.93 508.33 508.33 508.33 508.33
COSTO DIRECTO 2,965,799.44 38,731.70 487,504.87 829,210.61 768,600.62 726,833.53 114,918.11 114,918.11 114,918.11 114,918.11
GASTOS GENERALES (7.5%) 222,434.96 2,904.88 36,562.87 62,190.80 57,645.05 54,512.51 8,618.86 8,618.86 8,618.86 8,618.86
SUB TOTAL 3,188,234.40 41,636.58 524,067.74 891,401.41 826,245.67 781,346.04 123,536.97 123,536.97 123,536.97 123,536.97
% AVANCE 1.31% 16.44% 27.96% 25.92% 24.51% 3.87% 3.87% 3.87% 3.87%
% AVANCE ACUMULADO 1.31% 17.74% 45.70% 71.62% 96.13% 100.00% 103.87% 107.75% 111.62%
OBRA: MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA LA QUEBRADA EN LOS DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA
PROPIETARIO: GOBIERNO REGIONAL DE AGRICULTURA LIMA
DRA
RESIDENTE : ING. MIGUEL ALBERTO SANDOVAL OJEDA Dirección
SUPERVISO ING. MAX BERNABE ORELLANO Regional de
Agricultura
MONTO DE LA OBRA: S/ 3'500,005.00 GRL
CONTROL DE VALORIZACIONES
DEL 01 AL 30 DE NOVIEMBRE DE 2022
VAL. VAL. VAL. VAL. VAL. VAL. VAL. VAL.
DESCRIPCION PROGRAM. PROGRAM. PROGRAM. PROGRAM. REAL REAL REAL REAL
MENSUAL (S/) MENSUAL (%) ACUMULADA (S/) ACUMULADA (%) MENSUAL (S/) MENSUAL (%) ACUMULADA (S/) ACUMULADA (%)
VAL.N° 01 - MAR. 2022 23,717.04 0.80% 23,717.04 0.80% 23,717.04 0.80% 23,717.04 0.80%
VAL.N° 02 - ABR. 2022 38,111.36 1.29% 61,828.40 2.08% 38,111.36 1.29% 61,828.40 2.08%
VAL.N° 03 - MAY. 2022 280,910.02 9.47% 342,738.42 11.56% 280,910.02 9.47% 342,738.42 11.56%
VAL.N° 04 - JUN. 2022 350,619.52 11.82% 693,357.94 23.38% 350,619.52 11.82% 693,357.94 23.38%
VAL.N° 05 - JUL. 2022 160,651.85 5.42% 854,009.79 28.80% 160,651.85 5.42% 854,009.79 28.80%
VAL.N° 06 - AGO. 2022 632,463.78 21.33% 1,486,473.57 50.12% 632,463.78 21.33% 1,486,473.57 50.12%
VAL.N° 07 - SET 2022 322,534.32 10.88% 1,809,007.89 61.00% 315,219.33 11.90% 1,801,692.90 62.02%
VAL.N° 08 - OCT 2022 698,867.58 23.58% 2,507,875.47 84.58% 294,908.74 9.94% 2,096,601.64 71.96%
VAL.N° 09 - NOV 2022 457,923.97 15.44% 2,965,799.44 100.00% 315,219.33 10.63% 2,411,820.97 82.59%
2,507,875.47 84.58% 1,597,992.23 82.59%
AVANCE FÍSICO POR PARTIDAS
OBRA MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA LA QUEBRADA EN LOS DISTRITOS DE SAN
LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA
Residente de Obra: ING. MIGUEL ALBERTO SANDOVAL OJEDA FECHA DE INICIO: 3/21/2022
Supervisor de Obra: ING. MAX BERNABE ORELLANO FECHA TERMINO: 3/17/2022
Cliente DIRECCION REGIONAL DE AGRICULTURA - LIMA PLAZO DE EJECUCIÓN: 150 días Calendario
Lugar LIMA - CAÑETE - IMPERIAL
Acumulado Mes Anterior Presente Mes
Item Descripción Und. Metrado Precio S/ Parcial S/
Metrado % Metrado %
01 OBRAS PROVISIONALES 8,284.54
01.01 CAMPAMENTO PROVISIONAL EN LA OBRA glb 1.00 2,444.30 2,444.30 1.00 100.00% 0.00%
01.02 CARTEL DE OBRA 3.60x7.20 und 1.00 2,070.24 2,070.24 1.00 100.00% 0.00%
01.03 TRAZO, NIVELACION Y REPLANTEO m 1,300.00 2.90 3,770.00 1,300.00 100.00% 0.00%
02 OBRAS PRELIMINARES 55,578.90 -
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 6,500.00 6,500.00 0.90 90.00% 0.00%
02.02 LIMPIEZA Y DESBROCE DE CANAL m2 3,120.00 1.72 5,366.40 3,120.00 100.00% 0.00%
02.03 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE OBRA mes 5.00 8,742.50 43,712.50 5.00 100.00% 0.00%
03 CANAL TAPADO EN ZONA URBANA 2,739,812.29 -
03.01 MOVIMIENTO DE TIERRAS 152,987.97 -
03.01.01 EXCAVACIÓN DE MATERIAL SUELTO m3 909.21 33.34 30,313.06 909.21 100.00% 0.00%
03.01.02 RELLENO Y COMPACTADO CON MATERIAL DE AFIRMADO (CAMA=0.20m) m3 545.53 101.75 55,507.68 520.20 95.36% 0.00%
03.01.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m3 792.00 51.40 40,708.80 604.31 76.30% 56.49 7.13%
03.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1,096.95 24.12 26,458.43 1,096.95 100.00% 0.00%
03.02 DEMOLICION DE ESTRUCTURA DE CANAL EXISTENTE 17,449.27 -
03.02.01 DEMOLICION DE ESTRUCTURA DE CANAL m3 160.40 77.43 12,419.77 160.40 100.00% 0.00%
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 208.52 24.12 5,029.50 208.52 100.00% 0.00%
03.03 CONCRETO ARMADO 2,569,375.05 -
03.03.01 CONCRETO F°C 175 KG/CM2 m3 1,404.00 480.95 675,253.80 1,065.92 75.92% 0.00%
03.03.02 CONCRETO F°C 210 KG/CM2 m3 624.00 520.61 324,860.64 51.84 8.31% 250.00 40.06%
03.03.03 ENCOFRADO Y DESENCOFRADO m2 5,980.00 42.98 257,020.40 3,912.40 65.42% 177.28 2.96%
03.03.04 ACERO F°Y=4200 KG/CM2 kg 123,300.62 10.25 1,263,831.36 81,584.54 66.17% 15,001.79 12.17%
03.03.05 JUNTA DE DILATACION CADA 12 m m 545.00 29.28 15,957.60 305.00 55.96% 55.00 10.09%
03.03.06 JUNTA DE CONTRACCION CADA 3 m. m 1,625.00 19.97 32,451.25 305.00 18.77% 750.00 46.15%
04 TOMAS LATERALES TIPICAS 37,471.46 -
04.01 MOVIMIENTO DE TIERRAS 3,158.84 -
04.01.01 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 45.90 44.70 2,051.73 - 0.00% 0.00%
04.01.02 ELIMINACION DE MATERIAL EXCEDENTE m3 45.90 24.12 1,107.11 - 0.00% 0.00%
04.02 CONCRETO ARMADO 10,903.14 -
04.02.01 SOLADO CONCRETO F°C100KG/CM2 m2 21.00 36.21 760.41 - 0.00% 0.00%
04.02.02 CONCRETO F°C 175 KG/CM2 m3 6.86 480.95 3,299.32 - 0.00% 0.00%
04.02.03 ENCOFRADO Y DESENCOFRADO m2 41.10 42.98 1,766.48 - 0.00% 0.00%
04.02.04 ACERO F°Y=4200 KG/CM2 kg 495.31 10.25 5,076.93 - 0.00% 0.00%
04.03 ALBAÑILERIA 1,509.48 -
04.03.01 EMBOQUILLADO DE PIEDRA ASENTADO EN CONCRETO F´C=175kg/cm2 m3 12.60 119.80 1,509.48 - 0.00% 0.00%
04.04 CARPINTERIA METALICA 21,900.00 -
04.04.01 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPICA und 15.00 1,460.00 21,900.00 - 0.00% 0.00%
05 PUENTE VEHICULAR TIPICO 27,357.06 -
05.01 MOVIMIENTO DE TIERRAS 1,005.26 -
05.01.01 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 14.40 44.70 643.68 - 0.00% 0.00%
05.01.02 RELLENO Y COMPACTADO A MANO m3 2.88 29.07 83.72 - 0.00% 0.00%
05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 11.52 24.12 277.86 - 0.00% 0.00%
05.02 CONCRETO ARMADO 26,351.80 -
05.02.01 SOLADO CONCRETO F°C100KG/CM2 m2 12.00 36.21 434.52 - 0.00% 0.00%
05.02.02 CONCRETO F°C 210 KG/CM2 m3 19.20 520.61 9,995.71 - 0.00% 0.00%
05.02.03 ENCOFRADO Y DESENCOFRADO m2 73.84 42.98 3,173.64 - 0.00% 0.00%
05.02.04 ACERO F°Y=4200 KG/CM2 kg 1,243.70 10.25 12,747.93 - 0.00% 0.00%
06 PLAN DE MITIGACION AMBIENTAL 27,086.09 -
06.01 MEDIDAS DE MANEJO Y MITIGACION mes 5.00 5,000.00 25,000.00 5.00 100.00% 0.00%
06.02 MANEJO DE RESIDUOS SOLIDOS Y LIQUIDOS glb 1.00 2,086.09 2,086.09 1.00 100.00% 0.00%
07 PLAN DE SEGUIMIENTO Y MONITOREO ARQUEOLOGICO 30,000.00 -
07.01 SEGUIMIENTO Y MONITOREO ARQUEOLOGICO. mes 5.00 6,000.00 30,000.00 - 0.00% 0.00%
08 SEGURIDAD Y SALUD EN EL TRABAJO 31,834.10 -
08.01 CAPACITACIÓN DE SEGURIDAD Y SALUD mes 5.00 3,112.50 15,562.50 5.00 100.00% 0.00%
08.02 EQUIPO DE PROTECCIÓN INDIVIDUAL glb 1.00 8,961.60 8,961.60 1.00 100.00% 0.00%
08.03 EQUIPO DE PROTECCIÓN COLECTIVA glb 1.00 7,310.00 7,310.00 1.00 100.00% 0.00%
09 CAPACITACION DE USUARIOS 8,375.00 -
09.01 FORTALECIMIENTO DE CAPACIDADES DE LA ORGANIZACION DEL COMITÉ DE USUARIOS DE Taller 1.00 2,050.00 2,050.00 - 0.00% 0.50 50.00%
09.02 AGUA
FORTALECIMIENTO DE CAPACIDADES EN OPERACION Y MANTENIMIENTO DE LA Taller 1.00 3,275.00 3,275.00 - 0.00% 0.50 50.00%
09.03 INFRAESTRUCTURA
FORTALECIMIENTODE DERIEGO Y EN TECNICAS
CAPACIDADES DEORGANIZACION
PARA LA MANEJO DE RIEGO
DE PRODUCTORES Taller 1.00 3,050.00 3,050.00 - 0.00% 0.50 50.00%
AGRICOLAS
RESUMEN DE VALORIZACIONES DE OBRA
OBRA MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA LA QUEBRADA EN LOS
DISTRITOS DE SAN LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA
Residente de Obra: ING. MIGUEL ALBERTO SANDOVAL OJEDA FECHA DE INICIO: 3/21/2022 DRA
Supervisor de Obra: ING. AL BERTO MAX BERNABE ORELLAN FECHA TERMINO: 3/17/2022 Dirección
Regional de
Cliente DIRECCION REGIONAL DE AGRICULTURA - LIMA PLAZO DE EJECUCIÓN: 150 días Calendario Agricultura GRL
Lugar LIMA - CAÑETE - IMPERIAL
Presupuesto: S/ 3'500,005.00 3,500,005.00
Sub total: S/ 3'188,234.40 2,965,799.44
Valorizaciones
Mes Anterior Presente Mes Acumulado Actual Saldo por Valorizar
Item Descripción
Monto (S/) % Monto (S/) % Monto (S/) % Monto (S/) % Avance
01 VALORIZACIÓN DE OBRA Nº 01 - MARZO 2022 - 23,717.04 0.80% 23,717.04 0.80% 2,942,082.40 99.20%
02 VALORIZACIÓN DE OBRA Nº 02 - ABRIL 2022 23,717.04 0.80% 38,111.36 1.29% 61,828.40 2.08% 2,903,971.04 97.92%
03 VALORIZACIÓN DE OBRA Nº 03 - MAYO 2022 38,111.36 1.29% 280,910.02 9.47% 342,738.42 11.56% 2,623,061.02 88.44%
04 VALORIZACIÓN DE OBRA Nº 04 - JUNIO 2022 280,910.02 9.47% 350,619.52 11.82% 693,357.94 23.38% 2,272,441.50 76.62%
05 VALORIZACIÓN DE OBRA Nº 05 - JULIO 2022 350,619.52 11.82% 160,651.85 5.42% 854,009.79 28.80% 2,111,789.65 71.20%
06 VALORIZACIÓN DE OBRA Nº 06 - AGOSTO 2022 160,651.85 5.42% 632,463.78 21.33% 1,486,473.57 42.47% 1,479,325.87 49.88%
07 VALORIZACIÓN DE OBRA Nº 07 - SETIEMBRE 2022 632,463.78 21.33% 352,902.25 11.90% 1,839,375.82 62.02% 1,126,423.62 37.98%
08 VALORIZACIÓN DE OBRA Nº 08 - OCTUBRE 2022 352,902.25 11.90% 294,908.74 9.94% 2,134,284.56 71.96% 831,514.88 28.04%
09 VALORIZACIÓN DE OBRA Nº 09 - NOVIEMBRE 2023 294,908.74 9.94% 315,219.33 10.11% 2,449,503.89 82.59% 516,295.55 17.41%
TOTAL 2,134,315.40 71.96% 82.59% 2,449,503.89 82.59% 516,295.55 17.41%
RESUMEN DE VALORIZACION DE OBRA Nº 09
OBRA MEJORAMIENTO DEL SERVICIO DE PROVICIÓN DE AGUA PARA RIEGO DEL SISTEMA DE RIEGO CANAL MARÍA ANGOLA DESDE EL SECTOR HUACACHIVATO HASTA LA QUEBRADA EN LOS DISTRITOS DE SAN
LUIS Y IMPERIAL DE LA PROVINCIA DE CAÑETE - DEPARTAMENTO DE LIMA DRA
Dirección
Regional de
Agricultura
Cliente DIRECCION REGIONAL DE AGRICULTURA - LIMA GRL
Lugar LIMA - CAÑETE - IMPERIAL
Mes Anterior Mes Actual Acumulado Saldo por Valorizar
Item Descripción Presupuesto S/
Parcial % Parcial % Parcial % Parcial %
01 OBRAS PROVISIONALES 8,284.54 8,284.54 100.00% - 0.00% 8,284.54 100.00% - 0.00%
02 OBRAS PRELIMINARES 55,578.90 54,928.90 98.83% - 0.00% 54,928.90 98.83% 650.00 1.17%
03 CANAL TAPADO EN ZONA URBANA 2,739,812.29 2,007,350.59 73.27% 311,031.83 11.35% 2,318,382.42 84.62% 421,429.87 15.38%
04 TOMAS LATERALES TIPICAS 37,471.46 - 0.00% - 0.00% - 0.00% 37,471.46 100.00%
05 PUENTE VEHICULAR TIPICO 27,357.06 - 0.00% - 0.00% - 0.00% 27,357.06 100.00%
06 PLAN DE MITIGACION AMBIENTAL 27,086.09 27,086.09 100.00% - 0.00% 27,086.09 100.00% - 0.00%
07 PLAN DE SEGUIMIENTO Y MONITOREO ARQUEOLOGICO 30,000.00 - 0.00% - 0.00% - 0.00% 30,000.00 100.00%
08 SEGURIDAD Y SALUD EN EL TRABAJO 31,834.10 31,834.10 100.00% - 0.00% 31,834.10 100.00% - 0.00%
09 CAPACITACION DE USUARIOS 8,375.00 - 0.00% 4,187.50 50.00% 4,187.50 50.00% 4,187.50 50.00%