MUESTREO PROBETA

N° N DE FECHA DE CANTIDAD fc SLUMP


ESTRUCTURA Ubicación a 7 dias a 28 dias
PROBETAS NUESTREO EXISTENTE kg/cm2 (pulg)

1 01/02/22 MURO M10B 2 M10' 210 07 09/02/22 01/03/22


2 01/02/22 ZAPATA M10 6 M10' 210 07 12/02/22 01/03/22
3 02/02/22 MURO M4-M5 6 M10' 210 07 10/02/22 02/03/22
4 02/02/22 PEDESTAL 2 210 07 12/02/22 02/03/22
5 02/02/22 COLUMETAS 2 210 07 12/02/22 02/03/22 a 12 dias
6 04/02/22 MURO M5-M7 11 M10' 210 07 12/02/22 04/03/22
7 04/02/22 ZAPATA M10 6 M10' 210 07 12/02/22 04/03/22
8 05/02/22 MURO M10 3 M10' 210 07 13/02/22 05/03/22
9 05/02/22 PEDESTAL 3 210 07 13/02/22 05/03/22
10 04 08/02/22 MURO M10 4 M10' 210 07 16/02/22 08/03/22
11 10/02/22 MURO M10 9 M10' 210 07 18/02/22 10/03/22
12 11/02/22 MURO M10 7 M5 / M10 210 07 19/02/22 11/03/22 a 9 dias
13 04 11/02/22 MURO M10 - 3ER 210 07 19/02/22 11/03/22
14 04 12/02/22 MURO M10 4 M10 - 3ER 210 07 20/02/22 12/03/22
15 04 13/02/22 MURO 4 210 07 21/02/22 20/03/22
16 04 13/02/22 MURO 2/3 210 07 21/02/22 20/03/22
YA ENTREGADO
17 04 13/02/22 MURO 1 210 07 21/02/22 20/03/22
18 04 13/02/22 MURO 1A 210 07 21/02/22 20/03/22
19 04 14/02/22 PEDESTAL 210 07 22/02/22 14/03/22
20 04 14/02/22 ZAPATA M13 4 M13 210 07 22/02/22 14/03/22 A 10 DIAS
21 04 14/02/22 COLUMETAS 175 210 06 22/02/22 14/03/22
22 04 14/02/22 MURO 5 210 07 22/02/22 18/03/22
YA ENTREGADO
23 04 14/02/22 MURO 5A 210 07 22/02/22 18/03/22
24 04 16/02/22 MURO M10 4 M10 210 05 24/02/22 16/03/22
A 8 DIAS
25 04 16/02/22 ZAPATA M10 4 M10 210 06 24/02/22 16/03/22
26 17/02/22 MURO M6 3 M6 210 07 25/02/22 18/03/22
27 04 17/02/22 MURO 6A 210 07 25/02/22 18/03/22 YA ENTREGADO
28 04 17/02/22 MURO 7 210 07 25/02/22 18/03/22
29 17/02/22 MURO M13 3 M13 210 07 25/02/22 17/03/22
30 04 18/02/22 ZAPATA M10 4 M10 210 06 26/02/22 18/03/22
31 04 18/02/22 MURO 3 210 26/02/22 18/03/22
32 04 19/02/22 MURO 4 210 27/02/22 19/03/22
33 22/02/22 MURO M10 5 M10 210 07 02/03/22 22/03/22 A 14 DIAS
34 04 24/02/22 PEDESTAL 4 210 07 04/03/22 24/03/22
35 04 24/02/22 MURO 2 210 07 04/03/22 24/03/22
36 04 25/02/22 MURO 2 M10 210 07 05/03/22 25/03/22
37 04 28/02/22 PEDESTAL 4 210 07 08/03/22 28/03/22