Cronograma de Avance Valorizado Ne 038 - 2016
Cronograma de Avance Valorizado Ne 038 - 2016
FECHA 5/9/2017
P. DE EJECUCION DE OBRA
Mes 2° MES - JUNIO 3° MES - JULIO 4° MES -
ÍTEM PARTIDA PPTO
Semana 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Dia 9 AL 14 15 AL 21 22 AL 28 29 al 31 01 AL 04 05 AL 11 12 AL 18 19 AL 25 26 AL 30 01 AL 02 03 AL 09 10 AL 16 17 AL 23 24 AL 30 31-31 01 AL 06 07 AL 13
P = PROGRAMADO 1.67% 4.12% 5.24% 6.17% 5.34% 0.95% 0.27% 1.50% 3.87% 12.55% 12.34% 10.46% 6.20% 4.85%
AVANCE SEMANAL (%)
E = EJECUTADO 2.45% 1.59% 5.74% 8.74% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
P = PROGRAMADO 1.67% 5.79% 11.03% 17.20% 22.54% 23.49% 23.76% 25.26% 29.13% 41.68% 54.01% 64.47% 70.67% 75.52%
AVANCE ACUMULADO (%)
E = EJECUTADO 2.45% 4.04% 9.78% 18.51% 18.51% 18.51% 18.51% 18.51% 18.51% 18.51% 18.51% 18.51% 18.51% 18.51%
P. DE EJECUCION DE OBRA
4° MES - AGOSTO 5° MES - SET.
15 16 17 18
14 AL 20 21 AL 27 28 AL 31 01 AL 03 04 AL 05
9,741.66
29,106.00 29,106.00
4,593.24
36.18 1,809.00
1,400.32
AMPLIACION DE PLAZO
FIN DE OBRA OBSERV.
CONVENIO N° 038-2016-PUN/VMVU/PNVR
N° PARTIDA PRESUPUES
TO
TOTAL 1,034,346.59
P = PROGRAMADO
AVANCE SEMANAL (%)
AVANCE SEMANAL (%)
E = EJECUTADO
AVANCE ACUMULADO P = PROGRAMADO
(%) E = EJECUTADO
P = PROGRAMADO
AVANCE MENSUAL (%)
E = EJECUTADO
AVANCE ACUMULADO P = PROGRAMADO
(%) E = EJECUTADO
FECHA
TRANSFERENCIAS FECHA RECEPCIÓN
TRAMITE
FO
CRONOGRAMA DE
Programado 1,400.00
1 1400.00
Ejecutado
Programado 1,734.48
2 867.24
Ejecutado 963.60 417.56 353.32
Programado 5,200.20
1 5200.20
Ejecutado 3,370.50
Programado 500.00
1 500.00
Ejecutado
Programado 2,035.80
1 2035.80
Ejecutado
Programado 1,620.00
1 1620.00
Ejecutado 450.00
1,613.52 5,647.32 806.76
Programado
30 2460.19
Ejecutado
Programado
30 558.74
Ejecutado 651.83
Programado
30 167.62
Ejecutado 199.55
Programado
30 2564.14
Ejecutado
Programado
30 1462.96
Ejecutado
Programado
20 4691.49
Ejecutado
Programado
20 321.34
Ejecutado
Programado
20 2756.54
Ejecutado
Programado
5 366.12
Ejecutado
10,584.86 22,545.58 22,545.58 5,243.95
Programado
30 2982.10
Ejecutado
Programado
20 2804.55
Ejecutado
Programado
15 102.30
Ejecutado
Programado
12 10932.39
Ejecutado
Programado
3 355.86
Ejecutado
Programado
10 1787.97
Ejecutado
Programado
10 46.81
Ejecutado
Programado
10 3247.22
Ejecutado
Programado
4 9315.00
Ejecutado
Programado
4 5238.00
Ejecutado
Programado
6 765.54
Ejecutado
45.23 63.32 63.32 27.14
Programado
2 904.50
Ejecutado
5,245.72 7,344.01 7,344.01 3,147.43
141,932.32 13.72%
139,850.33 13.52%
141,932.32 13.72%
139,850.33 13.52%
MONTO
FORMATO N° 23
JUNIO JULIO
4 5 6 7 8 9
1-4 5-11 12-18 19-25 26-30 1-2 3-9
24,782.74
19,013.21
23,847.63 3,406.80
10,959.45
13,689.38 1,955.63
6,291.11
6,373.10 6,373.10 26,332.95
2,564.14
1,462.96
8,135.48
4,691.49
321.34
2,756.54
366.12
2,804.55
2,804.55
36.18 63.32 63.32 63.32 45.23 18.09 63.32
2,656.60 2,656.60
5,237.29 - - - - -
36,007.43 55,187.77 9,868.70 2,758.28 8,343.30 7,161.18 40,031.27
51,631.80 - - - - - -
JULIO AGOSTO
10 11 12 13 14 15
10-16 17-23 24-30 31-31 1-6 7-13 14-20
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
50,495.53 50,495.53 44,122.43 4,027.10 24,162.59 4,027.10
1,464.48
716.08
32,797.17
1,067.58
327.64 140.42
22,730.53 9,741.66
22,730.53 9,741.66
- - - - - - -
129,803.30 127,598.88 108,166.89 9,156.29 54,937.73 50,146.21 65,566.11
- - - - - - -
PLAZO
FECHA N° DÍAS FIN DE OBRA
VIGENCIA
1,249,535.59
1,034,346.59
AGOSTO SETIEMBRE
16 17 18
21-27 28-31 1-3 4-5
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
20,874.70 2,982.10
20,874.70 2,982.10
77,242.81 21,967.08
716.08 102.30
76,526.73 21,864.78
29,106.00 29,106.00
18,630.00 18,630.00
10,476.00 10,476.00
4,593.24
4,593.24
1,809.00
1,809.00
- -
- -
- -
- -
- -
- - -
98,117.51 58,648.42 29,106.00 1,809.00 1,034,346.59
- - - -