Está en la página 1de 4

Metrados de

estructuras
CURSO: INTRODUCCIÓN A INGENIERIA CIVIL
DOCENTE: ING. BETZABET EVELIN VILAVILA NORIEGA
AÑO: 2022

INTEGRANTES:
• HERMOZA SUAREZ BENJAMIN
• GOMEZ ESCOBAR ADRIANA
• PALOMINO HURTADO RAMIRO
• CHAMPI MAMANI JUAN FERNANDO
CODIGO DESCRIPCIÓN UND. CANT. N. VECES LARGO ANCHO ALTURA kg/m SUB TOTAL TOTAL
1 COLUMNAS 462.21
1.01 Concreto f'c=210 kg/cm2 m3 2.06
Segundo Piso
C-1 3 0.25 0.25 2.80 0.53
C-2 8 0.25 0.25 2.80 1.40
C-1´ 1 0.05 2.80 0.14
1.02 Encofrado y Desencofrado m2 66.00
Segundo Piso
C-1 3 2.00 1.00 2.80 16.80
C-2 8 2.00 1.00 2.80 44.80
C-1´ 1 2.00 0.79 2.80 4.40
1.03 ACERO fy=4200 kg/cm2 kg 394.15
Segundo Piso
C-1 f 5/8" vertical 3 4 2.80 1.55 52.15
C-1 f 1/2" vertical 3 2 2.80 0.99 16.70
C-1 f 3/8" estribos 3 28 0.88 0.56 41.40
C-2 f 5/8" vertical 8 4 2.80 1.55 139.06
C-2 f 3/8" estribos 8 28 0.88 0.56 110.39
C-1´ f 5/8" vertical 1 4 2.80 1.55 17.38
C-1´ f 1/2" vertical 1 2 2.80 0.99 5.57
C-1´ f 3/8" estribos 1 28 0.73 0.56 11.51
2 VIGAS 487.50
2.01 Concreto f'c=210 kg/cm2 m3 7.57
VP - 101, Eje 2-2 1 7.63 0.25 0.40 0.76
VP - 101, Eje 3-3 1 7.54 0.25 0.40 0.75
VP - 101, Eje 4-4 3 7.44 0.25 0.40 2.23
VP - 101, Eje 5-5 2 7.33 0.20 0.40 1.17
V-A eje c 1 10.25 0.25 0.20 0.51
V-A eje b 1 10.85 0.25 0.20 0.51
V-A eje a 3 10.85 0.25 0.20 1.63
2.02 Encofrado y Desencofrado m2 59.26
VP - 101, Eje 2-2 1 1.05 7.63 8.01
VP - 101, Eje 3-3 1 1.05 7.54 7.92
VP - 101, Eje 4-4 1 1.05 7.44 7.81
VP - 101, Eje 5-5 1 1.05 7.33 7.70
V-A eje c 1 0.65 10.25 6.66
V-A eje b 2 0.65 10.85 14.11
V-A eje a 1 0.65 10.85 7.05
2.03 ACERO fy=4200 kg/cm2 kg 420.67
VP - 101, Eje 2-2 f 5/8 " horizontal 1 4 7.63 1.55 47.37
VP - 101, Eje 2-2 f 1/2 " horizontal 1 2 7.63 0.99 15.17
VP - 101, Eje 2-2 f 3/8 " estribos 1 1.34 0.56 0.75
VP - 101, Eje 3-3 f 5/8 " horizontal 1 4 7.54 1.55 46.81
VP - 101, Eje 3-3 f 1/2 " horizontal 1 2 7.54 0.99 14.99
VP - 101, Eje 3-3 f 3/8 " estribos 1 1.34 0.56 0.75
VP - 101, Eje 3-3 f 5/8 " horizontal 1 4 7.44 1.55 46.19
VP - 101, Eje 3-3 f 1/2 " horizontal 1 2 7.44 0.99 14.79
VP - 101, Eje 3-3 f 3/8 " estribos 1 1.34 0.56 0.75
VP - 101, Eje 3-3 f 5/8 " horizontal 1 4 7.33 1.55 45.50
VP - 101, Eje 3-3 f 1/2 " horizontal 1 2 7.33 0.99 14.57
VP - 101, Eje 3-3 f 3/8 " estribos 1 1.34 0.56 0.75
V-A eje c f 1/2" horizontal 1 4 10.25 0.99 40.75
V-A eje c f 3/8" estribos 1 0.94 0.56 0.53
V-A eje b f 1/2" horizontal 2 4 10.85 0.99 86.28
V-A eje b f 3/8" estribos 2 0.94 0.56 1.05
V-A eje a f 1/2" horizontal 1 4 10.85 0.99 43.14
V-A eje a f 3/8" estribos 1 0.94 0.56 0.53
Item Descripción Und. Metrado

1 COLUMNAS
1.01 COLUMNAS, CONCRETO f'c=210 kg/cm2 m3 2.06
1.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 66.00
1.03 COLUMNAS, ACERO fy=4200 kg/cm2 kg 394.15
2 VIGAS
2.01 VIGAS, CONCRETO f'c=210 kg/cm2 m3 7.57
2
2.02 VIGAS, ENCOFRADO Y DESENCOFRADO m 59.26
2.03 VIGAS, ACERO fy=4200 kg/cm2 kg 420.67
Costo
Parcial S/. Total S/.
Unitario
7,115.84
460.00 948.72
60.00 3,959.89
5.60 2,207.22
8,858.45
350.00 2,651.01
65.00 3,851.71
5.60 2,355.74