INFORME Nº 03 - 2020-RNPM/RO/MDQ.
PRESUPUESTO
ITE
DESCRIPCION
M
PRECIO TOTAL
UN METRAD
UNITARI PRESUPUEST
D O
O S/. O S/.
04 BOCATOMA TIPO LATERAL UPULLO
04.0
CONCRETO CICLOPEO FC=210KG/CM2 + 30 % PG. M3 2.40 361.93
5 868.63
04.0
CONCRETO FC=210 KG/CM2 m3 4.07 465.27
6 1,893.65
04.0 ENROCADO CON 70 % PG. CON MEZCLA CONCRETO
M3 14.78 292.02
7 FC=210 KG/CM2 4,316.06
04.0
ENCOFRADO Y DESENCOFRADO M2 9.80 24.25
8 237.65
04.1
ACERO DE REFUERZO FY=4200 KG/CM2 KG 277.90 5.56
0 1,545.12
COSTO DIRECTO 8,861.11
GASTOS GENERALES 14.26% 1,263.85
GASTOS DE SUPERVISION 6.19% 548.78
GASTOS DE LIQUIDACION 0.00
GASTOS DE EXPEDIENTE TECNICO ACTUALIZADO 0.00
PRESUPUESTO TOTAL 10,673.74
PRESUPUESTO
ITEM DESCRIPCION
PRECIO TOTAL
UND METRADO UNITARIO PRESUPUESTO
S/. S/.
04 BOCATOMA TIPO LATERAL UPULLO 28,247.72
04.11 ELIMINACION DE MATERIAL EXCEDENTE D>50M M3 99.37 19.82 1969.51
DEMOLICION DE MURO DE CONCRETO CICLOPEO
04.12 M3 3.66 221.17
EXISTENTE 809.48
04.13 ACOPIO Y ACARREO DE PIEDRAS MEDIANAS D>50M M3 142.60 35.78 5102.23
04.14 ENROCADO CON MAQUINARIA M3 66.60 186.18 12399.59
MURO DE CONCRETO CICLOPEO CON 30% DE PIEDRA
04.15 M3 10.05 364.18
GRANDE 3660.01
04.16 CONCRETO ARMADO ( AZUD) FC=280 KG/CM2 M3 2.23 744.91 1661.15
04.17 COMPUERTAS FIERRO CON VOLANTE DE 0.30*0.30 M UND 1.00 597.44 597.44
04.18 RELLENO CON ROCAS M3 7.64 22.25 169.99
ESCALERA DE CONCRTO PARA INSPECCION Y
04.19 M3 0.22 542.51
MANTENIMIENTO EN COMPUERTA DE BOCATOMA 119.35
04.20 PINTURA EN TAPAS DE INSPECCION UND 10.00 32.36 323.60
04.21 LIMPIEZA DE CANAL ABIERTO M 172.00 5.15 885.80
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
04.22 JUNTAS ASFALTICAS M 35.52 8.11 288.07
COLOCADO DE CANDADO DE SEGURIDAD EN
04.23 UND 1.00 114.50
COMPUERTA DE BOCATOMA
114.50
COLOCADO DE CANDADO DE SEGURIDAD EN
04.24 UND 1.00 114.50
COMPUERTA DE CAMARA DESARENADORA 114.50
COLOCADO DE CANDADO DE SEGURIDAD EN PASE PARA
04.25 UND 1.00 32.50
LIMPIEZA DE AZUD 32.50
08 LINEA DE CONDUCCION 1 (1.320 Km.)
08.11 MATENIMIENTO LINEA DE CONDUCCION 1 (1.320 Km.) 19,048.92
08.11.01 TRAZO, NIVELACION Y REPLANTEO DE RED KM 0.61 550.60 335.87
08.11.02 VERIFICACION DE ESTADO DE LINEA DE CONDUCCION KM 1.32 594.72 785.03
EXCAVACION EN TERRENO COMPACTO A=0.60 X
08.11.03 M 320.00 32.07
H=0.80M. 10262.40
08.11.04 EXCAVACION EN TERRENO ROCOSO A=O.60 X H=0.80M. M 50.00 74.84 3742.00
08.11.05 REFINE Y NIVELACION DE ZANJAS EN TC Y TR A=0.60M M 370.00 5.61 2075.70
CAMA CON MATERIAL PROPIO ZARANDEADO H=0.10M
08.11.06 M 370.00 3.82
A=0.50M 1413.40
SUMINISTRO E INSTALACION DE TUBERIA DE
08.11.07 UND 1.00 94.12
ALCANTARILLADO ISO 4435 UF SN 2 D=200mm 94.12
RELLENO Y COMPACTACION DE ZANJA T.N. TUBERIA 8" A
08.11.08 M 370.00 0.92
10" HASTA 1.50 PROMEDIO 340.40
15 FLETE TERRESTRE 2,729.10
RAMPA EN PENDIENTE PARA TRANSPORTE DE
15.03 M 30.00 90.97
AGREGADO 2729.10
COSTO DIRECTO 50,025.74
GASTOS GENERALES 14.26% 7,135.13
GASTOS DE SUPERVISION 6.19% 3,098.15
GASTOS DE LIQUIDACION 0.00% 0.00
GASTOS DE EXPEDIENTE TECNICO ACTUALIZADO 0.00% 0.00
PRESUPUESTO TOTAL 60,259.02
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
PRESUPUESTO
MAYORES PARTIDAS
PARTIDAS DEDUCTIVOS PRESUPUESTO TOTAL
COMPONENTES METRADOS NUEVAS
PROGRAMADAS
MEMORIA DESCRIPTIVA
1) ASPECTOS GENERALES. -
PERFIL SNIP:
El PIP, fue aprobado con CÓDIGO SNIP: 302925, de fecha 15/09/2014
EXPEDIENTE TECNICO:
El Expediente Técnico fue aprobado con Resolución de GERENCIA MUNICIPAL
Nº 0182-2019-GM-MDQ/Q De fecha 10/12/2019 del Proyecto “MEJORAMIENTO Y
AMPLIACION DEL SISTEMA DE RIEGO UPULLOCOCHA, SECTORES DE
CCOLLPAPATA, HUYTUCANCHA Y BATANPATA, C.C. ACCOPATA, DISTRITO
DE QUIQUIJANA - QUISPICANCHI – CUSCO”. Del mismo se dispone dar inicio a
la ejecución del proyecto en un plazo de 04 MESES (120 días calendario). La
estructura de asignación presupuestal del expediente técnico original tiene la
siguiente estructura:
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
CUADRO Nº 02
CUADRO Nº 03
CUADRO N° 04
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
PRESUPUESTO
ACUMULADO
DESCRIPCION EJECUTADO SALDO (S/.)
EJECUTADO (S/.)
(S/.)
PRESUPUESTO
APROBADO
1,236,142.28 164,137.95 1,072004.33
PRESUP. EJECUTADO
AÑO 2016 - 2019 53,500.00 53,500.00 1,182642.28
JULIO - 2020 2,983.96 56,483.96 1,179658.32
AGOSTO-2020 4,803.56 61,287.52 1,174854.76
SETIEMBRE-2020 49,301.99 110,589.51 1,125552.77
OCTUBRE - 2020 53,548.44 164,137.95 1,072004.33
NOVIEMBRE - 2020 36,976.20 201,114.15 1,035,028.13
CUADRO N° 05
EXPEDIENTE TECNICO VALORIZACION A SALDO POR
DESCRIPCION APROBADO NOVIEMBRE-2020 VALORIZAR
RESIDENTES DE OBRA
Primer RESIDENTE DE OBRA : Ing. Cesar Augusto Quilca Vergara
Especialidad : Ingeniero Civil
Colegiatura : 110639
Fecha de inicio : julio del 2020
SUPERVISORES DE OBRA
PLAZO DE EJECUCIÓN:
El plazo de ejecución es de 120 días calendarios (04 meses) SEGÚN EL
EXPEDIENTE TECNICO, desde el inicio de obra el 21/07/2020 hasta
17/11/2020.
PARALIZACION Nº 01:
31 de julio del 2020, al 17 de agosto del 2020. 16 días calendarios.
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
Término de Obra Reprogramado 03/12/2020
PARALIZACION Nº 02:
30 de noviembre del 2020, al 17 de octubre. 321 días calendarios.
Término de Obra Reprogramado 31/12/2021
CUADRO N° 06
DEL AL DIAS
DESCRIPCION
PARALIZADOS
Primera paralización de 31/07/2020 17/08/2020 16 días
obra
Segunda paralización de 30/11/2020 18/10/2021 321 días
obra
TOTAL 337 días
CUADERNO DE OBRA:
Se cuenta con Cuaderno de obra N° 1 y N° 2
Asientos N°: 11, del 31 de julio del 2020. En la foja Nº 011 del cuaderno de obra
en las observaciones, el residente indica que se paraliza la obra por falta de
materiales, ya que la oficina de logística no puede realizar la adquisición oportuna
de los materiales solicitados, por motivos de la pandemia y la declaratoria de
estado de emergencia además de indicar en la misma observación que se tiene un
avance físico de 1.49% y un 2.59% en lo que respecta al avance financiero
generándose un desbalance.
CUADRO N° 07
Cuadro de mayores metrados
Durante la ejecución física del proyecto se generaron partidas nuevas, las cuales
eran de carácter esencial para la culminación y garantía del proyecto, partidas
nuevas generadas desde el mes de setiembre de 2020. Cuantifica 23 días.
CUADRO N° 08
Cuadro de partidas nuevas
CUADRO N° 09
SALDO
ITEM DESCRIPCION
UND METRADO
02 OBRAS PROVISIONALES
SUMINISTRO DE IMPLEMENTOS DE SEGURIDAD
02.02 PARA EL PERSONAL OBRERO und 15.00
06 DESARENADOR - CAMARA DE CARGA (02 UND.)
06.01 TRAZO, NIVELACION Y REPLANTEO m2 27.54
06.02 EXCAVACION PARA CIMIENTOS Y SOLADOS m3 24.30
06.03 CONCRETO FC=210 KG/CM2 m3 11.67
06.04 ENCOFRADO Y DESENCOFRADO m2 118.76
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
06.05 PENDIENTE DE FONDO m2 10.60
06.06 TARRAJEO CON IMPERMEABILIZANTES m2 47.76
06.07 TARRAJEO SIN IMPERMIABILIZANTE MEZCLA 1:3 m2 80.96
06.08 PRUEBA HIDRAULICA GLB 2.00
06.09 PINTURA EN MUROS EXTERIORES 2 MANOS m2 70.96
06.10 TAPA METALICA 0.60 X 0.60m. und 2.00
ACCESORIOS EN CAMARA DE CARGA Y
06.11 DESARENADOR GLB 2.00
COMPUERTAS FIERRO CON VOLANTE DE 0.25*0.40
06.12 M und 2.00
06.13 ACERO DE REFUERZO FY=4200 KG/CM2 kg 176.14
07 MEDIDOR RBC (02 UND.)
07.01 TRAZO, NIVELACION Y REPLANTEO m2 4.20
07.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.10
07.03 CONCRETO FC=210 KG/CM2 m3 0.98
07.04 ENCOFRADO Y DESENCOFRADO m2 14.00
07.05 TARRAJEO MEZCLA 1:3 m2 11.20
07.06 TUBERIA PVC SAP D=2" CLASE C-5 P/DRENAJE m 8.00
07.07 LIMNIMETRO und 2.00
08 LINEA DE CONDUCCION 1 (1.320 Km.)
08.01 TRAZO, NIVELACION Y REPLANTEO DE REDES KM 0.32
TRAZO, NIVELACION Y REPLANTEO FINAL DE
08.02 REDES KM 1.32
EXC. T. NORMAL D<=2" HASTA H=0.80, A=0.50
08.03 PULSO m 788.00
EXC. T. SEMIROCOSO D<=2" HASTA H=0.80, A=0.50
08.04 PULSO m 520.00
REFINE, NIVELACION EN ZANJA EN T.N. y T.SR.
08.05 A=0.50M. m 1320.00
CAMA CON MATERIAL PROPIO ZARANDEADO
08.06 H=0.10M A=0.50M m 1320.00
SUMINISTRO E INSTALACION DE TUBERIA DE
08.07 ALCANTARILLADO ISO 4435 UF SN 2 D=300mm. m 1320.00
CODO UF ESPIGA DE 45º TUBERIA DE
08.08 ALCANTARILLADO ISO 4435 UF SN 2 D=300mm. und 14.00
RELLENO Y COMPACTACION DE ZANJA T.N.
08.09 TUBERIA 8" A 10" HASTA 1.50 PROMEDIO m 1320.00
08.10 PRUEBA HIDRAULICA m 1320.00
09 BOCATOMA TIPO LATERAL HUAYLLONCCA
09.01 LIMPIEZA DE TERRENO MANUAL m2 83.00
09.02 TRAZO, NIVELACION Y REPLANTEO m2 83.00
09.03 DEMOLICION DE MURO EXISTENTE DE BOCATOMA m3 11.00
09.04 EXCAVACION PARA CIMIENTOS Y SOLADOS m3 20.69
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
Se solicita el plazo de 437 días calendario para la ejecución de las partidas descritas en
el ítem anterior, para lo cual se adjunta en el CRONOGRAMA REPROGRAMADO DE
EJECUCIÓN DE OBRAS correspondiente a las partidas pendientes por ejecutar:
CUADRO N° 10
CUADRO - PERIODO Y TIEMPO DE AMPLIACION DE PLAZO SOLICITADO
MOTIVO DÍAS
POR PARALIZACION DE OBRA N° 01 16
POR PARALIZACION DE OBRA N° 02 321
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
POR MAYORES METRADOS 11
POR PARTIDAS NUEVAS 23
SALDOS POR EJECUTAR 66
TOTAL DÍAS AMPLIACION DE PLAZO Nº 01 437
Ley N° 27293, Ley del Sistema Nacional de Inversión Pública, modificada por las
Leyes N° 28522 y 28802 y demás modificatorias.
Ley N° 27783, Ley del Bases de la Descentralización
Ley N° 27785, Ley Orgánica del Sistema Nacional de Control y de la Contraloría
General de la República y sus modificatorias
Ley N° 27972, Ley Orgánica de Municipalidades
Ley N° 28411, Ley General del Sistema Nacional de Presupuesto
Ley del Presupuesto del Sector Público para el ejercicio Fiscal de cada año.
Ley N° 294 76, Ley de autorizaciones para edificaciones y habilitaciones urbanas.
Ley N° 29090, Ley de regulaciones de licencia de edificaciones y habilitaciones.
Ley N° 28611, Ley General del Medio Ambiente.
Ley N° 30225 - De Contrataciones del Estado, que deroga Decreto Legislativo N°
1017; Decreto Supremo N° 350-2015-EF-Reglamento de la Ley de Contrataciones
del Estado.
Decreto Supremo N° 102-2007-EF que aprueba el nuevo reglamento del sistema
nacional de inversión pública.
Resolución de Contraloría N° 195-88-CG, "Normas que regulan la ejecución de las
obras públicas de administración directa
Directiva N° 012-2000-CG/OAT J-PRO, aprobada con R. C. N° 260-2000-CG
Autorización previo a la ejecución y pago de presupuesto adicional de obras
publicas
Directiva N° 001-2011-EF/68.01, Directiva General del Sistema Nacional de
Inversión Pública, aprobada por Resolución Directoral N° 003-2011-EF/68.01 y sus
modificatorias.
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
Reglamento de Organización y Funciones -ROF de la Municipalidad Distrital de
Quiquijana, aprobado con Ordenanza Municipal N° 001 -2016-MDQ/LC de fecha
28/01/2016
Resolución Di rectoral N° 006-2012-EF /63.01, que Aprueba disposiciones
especiales para proyectos de inversión pública de mejoramiento de carreteras y
actualiza parámetros del Sistema Nacional de Inversión Pública.
Resolución Directoral N° 008-2013-EF/63.01, que Modifican anexo de la Directiva
General del Sistema Nacional de Inversión Pública por Resolución Directoral N°
003-2011-EF/6 8.01 y sus modificatorias.
Resolución Directoral N° 004-2013-EF/63.01, Aprueban los anexos CME 18,19 y
20 de la Resolución Directoral N° 008-201 2-EF/63.01 y Modifican artículos y
anexos de la Directiva N° 001-2011-EF/68.01
Norma Técnica, Metrados para Obras de edificación y habilitaciones Urbana con
Resolución Directoral N°073-20107VIVIENDA/VMCS-DNC
Reglamento Nacional de Edificaciones y sus modificaciones de Ley W 29783 de
Seguridad y Salud en el Trabajo.
Decreto Legislativo N° 276 Ley de Bases de la Carrera Administrativa, Capítulo V
Del régimen disciplinario.
Ley N° 27815- Ley del Código de Ética de la Función Pública y sus modificatorias,
así como, su Reglamento aprobado por el Decreto Supremo N° 033-2005-PCM.
Ley N° 30372 - Ley de Presupuesto del Sector Público Para el Año Fiscal 2016.
Otras normas legales vigentes que se relacionan, con la ejecución de Proyectos
de Inversión Pública Bajo la modalidad de Ejecución Presupuestaria Directa.
CONCLUSION:
Se adjunta:
Copia de Resolución de Aprobación del expediente técnico.
Copia de Acta de Paralización de Obra 2020
Copia de Acta de Reinicio de Obra 2020 y 2021
Copia de cuaderno de obra
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año del Bicentenario del Perú: 200 años de independencia”
MUNICIPALIDAD DISTRITAL DE QUIQUIJANA
PROVINCIA QUISPICANCHI – REGIÓN CUSCO
“Año de la Universalización de la Salud”
1.0 CONCLUSIONES
1.1 El proyecto para el año 2020 al corte de obra, se encuentra con un avance físico del 14.30%, y
un avance financiero del 16.27%, esto sin considerar en las valorizaciones los mayores
metrados y partidas.
1.2 De la misma manera se pudo verificar la ejecución de Adicionales durante la ejecución de las
partidas en el año 2020, además se advierte que se seguirán incrementado los mayores
metrados y partidas nuevas durante la ejecución posterior el año 2021, de las partidas que
quedan por ejecutar, por lo que para el 2021 se programa mayores metrados y partidas nuevas
las cuales son necesarias para garantizar las actividades consideradas en el programado y las
metas programadas. Por lo cual se requiere ampliación presupuestal por Partidas Nuevas y
Mayores Metrados.
1.3 A la fecha la obra se encuentra en ejecución con disponibilidad presupuestal limitada. La
existencia de obra ya construida y la existencia de saldo de materiales en almacén hacen
necesario la continuidad de la ejecución de obra en salvaguarda del presupuesto ya invertido y
del avance en el cumplimiento de metas.
1.4 Para concluir con la ejecución de obra se precisa contar con la Ampliación Presupuestal nro.
01, sustentada en el presente documento, el cual debe contar con la debida Resolución de
aprobación
1.5 Es necesario solicitar que la oficina de logística implemente mejores estrategias para los
procesos de adquisición de tal manera que los materiales requeridos puedan llegar a obra
oportunamente, permitiendo la continuidad de obra evitando paralizaciones que no permiten
un ritmo creciente en la ejecución
2.0 RECOMENDACIONES