OBRA:

CONSTRUCCION LOSA DEPORTIVA HUANCAMACHAY

UBICACIÓN:
DEPARTAMENTO: HUANUCO
PROVINCIA: ANEXO HUANCAMACHAY
DISTRITO: PASCO
LUGAR: SAN FRANCISCO DE ASIS -YARUSYACAN
FECHA: AGOSTO--2008

COTIZACION 1 COTIZACION 2
ESPECIFICACION DEL GASTO UNIDAD METRADO PERCIO PERCIO PRESUPUESTO PERCIO PERCIO PRESUPUEST
SIN IGV CON IGV TOTAL SIN IGV CON IGV O TOTAL

MATERIALES DE CONSTRUCCION
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 KG 5,869.00 43.00 50.74 252,367.00 45.00 53.10 264,105.00
ALAMBRE NEGRO # 8 KG 270.00 43.00 50.74 11,610.00 45.00 53.10 12,150.00
ALAMBRE NEGRO # 16 KG 640.00 43.00 50.74 27,520.00 45.00 53.10 28,800.00
CEMENTO PORTLAND TIPO I (42.5 kg) BLS 1,451.00 43.00 50.74 62,393.00 45.00 53.10 65,295.00
CHEMALAC GAL 13.00 43.00 50.74 559.00 45.00 53.10 585.00
CINTA MASKINGTAPE UND 40.00 43.00 50.74 1,720.00 45.00 53.10 1,800.00
CLAVOS DE FIERRO PROMEDIO KG 250.00 43.00 50.74 10,750.00 45.00 53.10 11,250.00
FIERRO CORRUGADO DE 1/2" VAR 14.00 43.00 50.74 602.00 45.00 53.10 630.00
PINTURA ESMALTE GAL 2.00 43.00 50.74 86.00 45.00 53.10 90.00
PINTURA ESMALTE SINTETICO GAL 73.00 43.00 50.74 3,139.00 45.00 53.10 3,285.00
TECNOPORT DE 1",1.20mx2.40m PL 15.00 43.00 50.74 645.00 45.00 53.10 675.00
THINNER ACRILICO GAL 2.00 43.00 50.74 86.00 45.00 53.10 90.00
TUBERIA PVC-SP-C-7.5 DE 3" UND 8.00 43.00 50.74 344.00 45.00 53.10 360.00
YESO KG 73.50 43.00 50.74 3,160.50 45.00 53.10 3,307.50

AGREGADOS
AFIRMADO M3 100.00 43.00 50.74 4,300.00 45.00 53.10 4,500.00
ARENA FINA M3 1.00 43.00 50.74 43.00 45.00 53.10 45.00
ARENA GRUESA M3 40.00 43.00 50.74 1,720.00 45.00 53.10 1,800.00
ARENA GRUESA CLASIFICADA M3 1.00 43.00 50.74 43.00 45.00 53.10 45.00
HORMIGON M3 114.00 43.00 50.74 4,902.00 45.00 53.10 5,130.00
PIEDRA CHANCADA DE 1/2" M3 77.00 43.00 50.74 3,311.00 45.00 53.10 3,465.00
PIEDRA GRANDE M3 15.00 43.00 50.74 645.00 45.00 53.10 675.00
MATERIAL DE PRESTAMO SELECCIONADO OBRA M3 100.00 43.00 50.74 4,300.00 45.00 53.10 4,500.00

MADERA
LISTON DE MADERA TORNILLO O SIMILAR DE 2"X2"X10' UND 9.00 43.00 50.74 387.00 45.00 53.10 405.00
LISTON DE MADERA TORNILLO O SIMILAR DE 2"X3"X10' UND 20.00 43.00 50.74 860.00 45.00 53.10 900.00
MADERA EUCALIPTO ROLLIZO 4" X 3.6 m UND 2.00 43.00 50.74 86.00 45.00 53.10 90.00
MADERA EUCALIPTO ROLLIZO 4" X 5 m UND 10.00 43.00 50.74 430.00 45.00 53.10 450.00
MADERA EUCALIPTO ROLLIZO 4" X 6 m UND 14.00 43.00 50.74 602.00 45.00 53.10 630.00
MADERA PARA ENCOFRADO Y CARPINTERIA P2 5,514.00 43.00 50.74 237,102.00 45.00 53.10 248,130.00
TABLA DE MADERA TORNILLO O SIMILAR DE 1"X2"X10' UND 130.00 43.00 50.74 5,590.00 45.00 53.10 5,850.00
TABLA DE MADERA TORNILLO O SIMILAR DE 1"X4"X10' UND 80.00 43.00 50.74 3,440.00 45.00 53.10 3,600.00
TABLA DE MADERA TORNILLO O SIMILAR DE 1"X8"X10' UND 40.00 43.00 50.74 1,720.00 45.00 53.10 1,800.00
TRIPLAY DE 1.20m X 2.40m X 8 mm PL 12.00 43.00 50.74 516.00 45.00 53.10 540.00

GASOLINA, LUBRICANTES Y COMBUSTIBLES


ACEITE PARA MOTOR SAE-30 GAL 1.00 43.00 50.74 43.00 45.00 53.10 45.00
ASFALTO RC-250 GAL 44.00 43.00 50.74 1,892.00 45.00 53.10 1,980.00
GASOLINA 84 OCTANOS GAL 73.00 43.00 50.74 3,139.00 45.00 53.10 3,285.00

PAQUETE DE HERRAMIENTAS
BUGUI UNID 6.00 43.00 50.74 258.00 45.00 53.10 270.00
CILINDROS UNID 4.00 43.00 50.74 172.00 45.00 53.10 180.00
CASCOS UNID 12.00 43.00 50.74 516.00 45.00 53.10 540.00
HOJA DE SIERRA UNID 10.00 43.00 50.74 430.00 45.00 53.10 450.00
COMBAS DE 8 LB UNID 2.00 43.00 50.74 86.00 45.00 53.10 90.00
BALDES DE 18 LITROS DE PLASTICO UNID 4.00 43.00 50.74 172.00 45.00 53.10 180.00
BIRBIQUI-STANLEY UNID 2.00 43.00 50.74 86.00 45.00 53.10 90.00
BROCA Ø 5/8", PARA BIRBIQUI UNID 4.00 43.00 50.74 172.00 45.00 53.10 180.00
LLANTAS PARA BUGUI UNID 3.00 43.00 50.74 129.00 45.00 53.10 135.00
CAMARA PARA LLANTA BUGUI UNID 6.00 43.00 50.74 258.00 45.00 53.10 270.00
PERNOS DE Ø1/4"X1/2" PARA BUGUI UNID 12.00 43.00 50.74 516.00 45.00 53.10 540.00
CABLE DE LUZ N°14 ROLLO 1.00 43.00 50.74 43.00 45.00 53.10 45.00
CINTA AISLANTE ROLLO 1.00 43.00 50.74 43.00 45.00 53.10 45.00
FLORESCENTES DE 4OW(EQUIPO COMPLETO) UND 2.00 43.00 50.74 86.00 45.00 53.10 90.00
FLORESCENTE CIRCULAR ELECTRONICO DE 32w(EQ. COMP.) UND 2.00 43.00 50.74 86.00 45.00 53.10 90.00

FLETES
FLETE TERRESTRE(PROVEEDOR HASTA LA OBRA) KG ### 43.00 50.74 1,486,639.86 45.00 53.10 1,555,785.90

OTROS SERVICIOS DE TERCEROS


SERVICIO DE CARPINTERIA METALICA(SEGÚN DISEÑO EN PLANOS, INC.
PINTURA Y COLOCACION EN OBRA)

Página 1
OBRA:
CONSTRUCCION LOSA DEPORTIVA HUANCAMACHAY

UBICACIÓN:
DEPARTAMENTO: HUANUCO
PROVINCIA: ANEXO HUANCAMACHAY
DISTRITO: PASCO
LUGAR: SAN FRANCISCO DE ASIS -YARUSYACAN
FECHA: AGOSTO--2008

COTIZACION 1 COTIZACION 2
ESPECIFICACION DEL GASTO UNIDAD METRADO
ARCOS(INC. MALLA), TABLERO DE BASQUET(INC. MALLA), PARANTES
GLB 1.00
DE VOLEY(INC. MALLA), SEGUN PLANO 43.00 50.74 43.00 45.00 53.10 45.00
TUBERIA DE FºGº, 2"X2.5mm M 577.10 43.00 50.74 24,815.30 45.00 53.10 25,969.50
MALLA DE FºGº, COCADA 1 1/2", #12 M2 337.55 43.00 50.74 14,514.65 45.00 53.10 15,189.75
ANGULO DE ACERO A-36 DE 1 1/2" X 1 1/2" X 1/8" X 6 m M 733.45 43.00 50.74 31,538.35 45.00 53.10 33,005.25
ANCLAJES UND 40.00 43.00 50.74 1,720.00 45.00 53.10 1,800.00
43.00 50.74 0.00 45.00 53.10 0.00
CARTEL DE OBRA 43.00 50.74 0.00 45.00 53.10 0.00
GIGANTOGRAFIA, 3.60mX2.40m M2 8.64 43.00 50.74 371.52 45.00 53.10 388.80

TOPOGRAFIA
TOPOGRAFO GLB 1.00 43.00 50.74 43.00 45.00 53.10 45.00

ALQUILER DE EQUIPO
ALQUILER DE EQUIPOS MENORES
VIBRADORA A GASOLINA 1 3/4" - 4HP HM 80.00 43.00 50.74 3,440.00 45.00 53.10 3,600.00
VIBRADOR DE CONCRETO 4 HP 2.40" HM 5.00 43.00 50.74 215.00 45.00 53.10 225.00
PLANCHA COMPACTADORA 4 HP HM 22.00 43.00 50.74 946.00 45.00 53.10 990.00
MEZCLADORA DE CONCRETO TAMBOR 18 HP 11 p3 HM 43.00 50.74 0.00 45.00 53.10 0.00
MEZCLADORA DE CONCRETO DE 9 -11p3 HM 108.00 43.00 50.74 4,644.00 45.00 53.10 4,860.00
COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP HM 57.60 43.00 50.74 2,476.80 45.00 53.10 2,592.00
CIZALLA HM 133.17 43.00 50.74 5,726.22 45.00 53.10 5,992.56

ALQUILER DE EQUIPOS PESADOS


TRACTOR DE ORUGAS DE 190-240 HP HM 19.00 43.00 50.74 817.00 45.00 53.10 855.00
CARGADOR SOBRE LLANTAS 100-115 HP 2-2.25 yd3 HM 23.00 43.00 50.74 989.00 45.00 53.10 1,035.00
CAMION VOLQUETE 7 m3 HM 10.00 43.00 50.74 430.00 45.00 53.10 450.00
CAMION VOLQUETE 6 X 4 330 HP 10 m3 HM 19.00 43.00 50.74 817.00 45.00 53.10 855.00
CAMION PLATAFORMA 4 X 2 122 HP 8 ton HM 6.00 43.00 50.74 258.00 45.00 53.10 270.00

ALQUILER DE EQUIPOS TOPOGRAFICOS


TEODOLITO HE 98.00 43.00 50.74 4,214.00 45.00 53.10 4,410.00
NIVEL TOPOGRAFICO CON TRIPODE HE 98.00 43.00 50.74 4,214.00 45.00 53.10 4,410.00
MIRAS Y JALONES HE 98.00 43.00 50.74 4,214.00 45.00 53.10 4,410.00

MANO DE OBRA
MANO DE OBRA TODA LA EJECUCION, CALIFICADA Y NO CALIFICADA
MANO DE OBRA TODA LA EJECUCION, CALIFICADA Y NO CALIFICADA GLB 1.00 43.00 50.74 43.00 45.00 53.10 45.00

PRESUPUESTO TOTAL: 2,246,235.20 2,350,711.26