Articulo 161

Penalidad por los 9 dias


Penalidad por dia
0.10x795,000.00 x9 = 53,000.00 + IGV
90x0.15

PENALIDAD MAXIMA Es el 10% del adelanto directo

0.1 x 795000 = 79,500.00

a cuantos dias equivale el monto maximo de la multa 13.5 dias


enalidad por dia 5888.88889

5888.88889
FR 0.99375
Po 795,000.00
Pb 800,000.00

CALENDARIO PROGRAMADO
MES AGOSTO SETIEMBRE OCTUBRE
VAL. PROG 240,000.00 260,000.00 300,000.00
VAL. PROG. ACUM. 240,000.00 500,000.00 800,000.00

VALORZACIONES REALES REAJUSTE


VAL. AGOSTO 230,000.00 K(JUL) 1.109
VAL. SETIEMBRE 280,000.00 K(AGO) 1.110
VAL. OCTUBRE 140,000.00 K(SET) 1.115
VAL. NOVIEMBRE 150,000.00 K(OCT) 1.119
REAJUSTES
N MES VAL. PROG. VAL. REAL K-1 REAJ. PROGR REAJ. REAL REAJ. RECON
1 AGOSTO 238,500.00 228,562.50 0.109 25,996.50 24,913.31 24,913.31

N MES VAL. PROG. VAL. REAL K-1 REAJ. PROGR REAJ. REAL REAJ. RECON
1 AGOSTO 238,500.00 228,562.50 0.110 26,235.00 25,141.88 25,141.88
2 SETIEMBRE 258,375.00 278,250.00 0.110 28,421.25 30,607.50 29,514.38
54,656.25 54,656.25
- 24,913.31
29,742.94

N MES VAL. PROG. VAL. REAL K-1 REAJ. PROGR REAJ. REAL REAJ. RECON
1 AGOSTO 238,500.00 228,562.50 0.110 26,235.00 25,141.88 25,141.88
2 SETIEMBRE 258,375.00 278,250.00 0.115 29,713.13 31,998.75 30,806.25
55,948.13 55,948.13

3 OCTUBRE 298,125.00 139,125.00 0.115 34,284.38 15,999.38 15,999.38


71,947.50
- 54,656.25
17,291.25

N MES VAL. PROG. VAL. REAL K-1 REAJ. PROGR REAJ. REAL REAJ. RECON
1 AGOSTO 238,500.00 228,562.50 0.110 26,235.00 25,141.88 25,141.88
2 SETIEMBRE 258,375.00 278,250.00 0.115 29,713.13 31,998.75 30,806.25
3 OCTUBRE 298,125.00 139,125.00 0.119 35,476.88 16,555.88 16,555.88
4 NOVIEMBRE 0.00 149,062.50 0.119 0.00 17,738.44 17,738.44
91,425.00 90,242.44
- 71,947.50
18,294.94
AVANCE DE OBRA
MES A.P.A A.R.A ESTADO
AGOSTO 240,000.00 230,000.00 ATRASADO
SETIEMBRE 500,000.00 510,000.00 ADELANT.
OCTUBRE 800,000.00 650,000.00 ATRASADO
NOVIEMBRE 0 800,000.00 ATRASADO

REAJUSTE RECONOCIDO
1) Si la obra esta atrasada,se toma el reajuste real
2) La suma de los reintegros reconocidos debe ser menor o igual que el reitegro programado acumulado
EAJ. RECON
En la primera val la obra esta atrasada entonces se toma el reajuste real

EAJ. RECON
* 25,141.88 24,913.31 = 228.56
* 29,514.38 228.56 = 29,742.94

Reajuste reconocido para SETIEMBRE+REGULARIZACION

EAJ. RECON
* 30,806.25 29,514.38 = 1,291.87
* 15,999.38 1,291.87 = 17,291.25

ES UNA REGULARIZACION CON LOS K CORRESPONDIENTES, POR ELLO HAGO LO MISMO QUE EL ANTERIOR

Cuanto se le pago a cuenta? El acumulado del mes menos el acumulado anterior

EAJ. RECON
* 16,555.88 15,999.38 = 556.50
* 17,738.44 556.50 = 18,294.94

ogramado acumulado
MISMO QUE EL ANTERIOR
REAJUSTES AUTORIZADOS
N FECHA Vpro Vre K-1 Rprog Rreal
1 AG. 238,500.00 228,562.50 0.115 27,427.50 26,284.69
2 SET. 258,375.00 278,250.00 0.119 30,746.63 33,111.75
58,174.13
3 OCT. 298,125.00 139,125.00 0.121 36,073.13 16,834.13

4 NOV. 0.00 149,062.50 0.124 0.00 18,483.75


94,247.25

AG. SET. OCT.


5d (tiempo sup)

30 30 (pago)

VALORIZACION Kjul Kag Kset

LIQUIDACION Kset Koct Knov


K PROG K PROG AC
Rrecon Se trabajan con el K del mes de pago 27,427.50 27,427.50
26,284.69 Kset= 1.115 30,746.63 58,174.13
31,889.44 Koct= 1.119 36,073.13 94,247.25
58,174.13 Knov= 1.121 0 94,247.25
16,834.13 Kdic= 1.124

18,483.75
93,492.00

NOV. DIC.

Koct Knov

Kdic Kene
K REAL K REAL ACUM K RECO K RECONOCIDO ACU
26,284.69 26,284.69 26,284.69 26,284.69
33,111.75 59,396.44 31,889.44 58,174.13
16,834.13 76,230.56 16,834.13 75,008.25
18,483.75 94,714.31 19,239.00 94,247.25
A- LIQUIDACION FINAL DE CUENTAS

I. AUTORIZADO Y PAGADO

1.1.0 AUTORIZADO (SIN I.G.V)


1.1.1 CONTRATO PRINCIPAL 795,000.00
1.1.2 PRESUPUPESTO ADICIONAL 0.00
1.1.3 PRESPUESTO DEDUCTIVO 0.00
1.1.4 REINTEGROS NETOS CONTRATO PRINCIPAL 93,492.00
1.1.5 INTERESES 0.00
1.1.6 MAYOR GASTOS GENERALES 0.00 888,492.00

1.1.7 I.G.V DEL CONTRATO PRINCIPAL (18%) 143,100.00


I.G.V DEL ADICIONAL (18%) 0.00
I.G.V DEL DEDUCTIVO (18%) 0.00
I.G.V DEL REINTEGRO (18%) 16,828.56
I.G.V DE INTERESES (18%) 0.00
I.G.V DE MAYORES GASTOS GENERALES (18%) 0.00 159,928.56
TOTAL

1.2.0 PAGADO (SIN I.G.V)


1.2.1 CONTRATO PRINCIPAL 795,000.00
1.2.2 PRESUPUESTO ADICIONAL 0.00
1.2.3 PRESUPUESTO DEDUCTIVO 0.00
1.2.4 REINTEGROS NETOS, CONTRATO PRINCIPAL 90,242.44
1.2.5 INTERESES 0.00
1.2.6 MAYORES GASTOS GENERALES 0.00 885,242.44

1.2.7 I.G.V DEL CONTRATO PRINCIPAL (18%) 143,100.00


I.G.V DEL ADICIONAL (18%) 0.00
I.G.V DEL DEDUCTIVO (18%) 0.00
I.G.V DEL REINTEGRO (18%) 16,243.64
I.G.V DE INTERESES (18%) 0.00
I.G.V DE MAYORES GASTOS GENERALES (18%) 0.00 159,343.64
TOTAL

SALDO A FAVOR DEL CONTRATISTA


EN EFECTIVO (A FAVOR DEL CONTRATISTA) 3,249.56
I.G.V (A FAVOR DEL CONTRATISTA) 584.92
II. ADELANTOS
2.1.0 CONCEDIDOS
2.1.1 EFECTIVO
2.1.2 MATERIALES
2.2.0 AMORTIZADOS
2.2.1 EFECTIVOS
2.2.2 MATERIALES
SALDO A CARGO DEL CONTRATISTA

III. DEDUCCIONES
3.1.0 PAGADOS
3.1.1 AUTORIZADOS
SALDO A CARGO DEL CONTRATISTA

IV. MULTA POR ATRASO


4.1.0 EFECTUADOS 53,000.00
4.2.0 DESCONTADOS 53,000.00
SALDO A CARGO DEL CONTRATISTA 0.00
RESUMEN DE SALDOS

ITEM CONCEPTO A CARGO DEL CONTRATISTA A FAVOR DEL CONTRATISTA


EFECTIVO IGV EFECTIVO IGV
1.00 AUTORIZADO Y PAGADO 3,249.56 584.92
2.00 ADELANTOS
3.00 DEDUCCIONES
4.00 MULTA
TOTAL 3,249.56 584.92

RESUMEN FINAL

SALDO A FAVOR DEL CONTRASISTA 3,834.48


EN EFECTIVO 3,249.56
I.G.V 584.92