CONSORCIO HEROES DEL CENEPA

PRESUPUESTO DE DEDUCTIVO

MEJORAMIENTO DE BERMAS Y VEREDAS EN EL AA.HH. PROMUVI VILLA HEROES DEL CENEPA, DISTRITO GREGORIO ALBARRACIN
Obra
LANCHIPA - TACNA - TACNA

MEJORAMIENTO DE BERMAS Y VEREDAS EN EL AA.HH. PROMUVI VILLA HEROES DEL CENEPA, DISTRITO GREGORIO ALBARRACIN
Fórmula
LANCHIPA - TACNA - TACNA

Cliente MUNICIPALIDAD DISTRITAL DE GREGORIO ALBARRACIN LANCHIPA Costo al: 30/09/2013

Lugar GREGORIO ALBARRACIN LANCHIPA - TACNA - TACNA

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 INFRAESTRUCTURA VIAL
01.04 VEREDAS DE CONCRETO
01.04.03 OBRAS DE CONCRETO SIMPLE
01.04.03.05 JARDINERA DE CONCRETO F'C=175 KG/CM2 u 18.00 348.74 6,277.32

COSTO DIRECTO S/. 6,277.32


GASTOS GENERALES 15.00% 941.60
UTILIDAD 10.00% 627.73
SUBTOTAL S/. 7,846.65

FACTOR RELACION 1.00000 7,846.65


IMPUESTO (IGV) 18.00% 1,412.40
TOTAL PRESUPUESTO EN NUEVOS SOLES S/. 9,259.05
GRAFICA FINAL DE AVANCE DE OBRA - LIQUIDACION FINAL
MEJORAMIENTO DE BERMAS Y VEREDAS EN EL AA.HH. PROMUVI VILLA HEROES DEL CENEPA, DISTRITO GREGORIO ALBARRACIN LANCHIPA - TACNA - TACNA
OBRA
PLAZO DE EJECUCIÓN 180 DIAS CALENDARIO
EMPRESA CONSORCIO HEROES DEL CENEPA
UBICACIÓN: GREGORIO ALBARRACIN TACNA TACNA

No VALORIZACION MENSUAL % DE AVANCE MENSUAL VALORIZ. MENSUAL ACUMUL. % AVANCE MENSUAL ACUMUL. COMENTARIO
MES VALORIZACION PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO
(1) (2) (2)-(1)
0 0.00 0.00 0.00 0.00
JULIO 2012 1 154,802.90 355,026.40 6.26% 14.36% 154,802.90 355,026.40 6.26% 14.36% 8.10% Adelantado
AGOSTO 2013 2 389,537.60 756,678.13 15.75% 30.60% 544,340.50 1,111,704.53 22.01% 44.96% 22.95% Adelantado
SEPTIEMBRE 2013 3 582,323.68 644,750.80 23.55% 26.07% 1,126,664.18 1,756,455.33 45.56% 71.03% 25.47% Adelantado
OCTUBRE 2013 4 578,237.55 274,289.31 23.38% 11.09% 1,704,901.73 2,030,744.64 68.94% 82.12% 13.18% Adelantado
NOVIEMBRE 2013 5 403,195.66 342,206.79 16.30% 13.84% 2,108,097.39 2,372,951.43 85.25% 95.96% 10.71% Adelantado
DICI-ENER 2013 6 347,744.73 90,643.49 14.06% 3.67% 2,455,842.12 2,463,594.92 99.31% 99.63% 0.32% Adelantado
ENERO 2013 7 17,011.85 0.00 0.69% 0.00% 2,472,853.97 2,463,594.92 100.00% 99.63% -0.37% Atrasado

2,472,853.97 2,463,594.92 100.00% 99.63%

% AVANCE DE OBRA PROGRAMADO VS EJECUTADO % AVANCE DE OBRA PROGRAMADO ACUMULADO VS


% %
35% EJECUTADO ACUMULADO
110% 99.63% 99.63%
30% 100% 100.00%
30.60% 95.96%
90% 99.31%
25% 80% 82.12%
26.07% 23.38% 71.03%
23.55% 70% 85.25%
20% 68.94%
15.75% 60%
16.30% 50% 45.56%
15%
14.36% 14.06%
13.84%
40% 44.96%
11.09%
10% 30%
6.26% 22.01%
20% 14.36%
5% 6.26%
3.67% 10%
0% 0.69%
0.00% 0%
0 1 2 3 4 5 6 0 1 2 3 4 5 6
VALORIZACIONES MENSUAL VALORIZACIONES MENSUAL
AVANCE PROGRAMADO ACUMULADO AVANCE EJECUTADO ACUMULADO
AVANCE DE OBRA PROGRAMADO AVANCE DE OBRA EJECUTADO