VALORIZACIONES DE EJECUCION DE OBRA DE CONTRATO PRINCIPAL CON AMORTIZACIONES

CONTRATO DE OBRA : CONTRATO DE OBRA N° 003-2019-GM/MPCH


CONTRATISTA : CONSORCIO JUNIN
RESIDENTE : ING. CESAR J. MOLINA BERROCAL
OBRA : RENOVACION DE MURO DE CONTECION; EN EL (LA) MARGEN DERECHA EN LA LOCALIDAD PUENTE CAPELO, DISTRITO DE SAN LUIS DE SHUARO, PROVINCIA CHANCHAMAYO, DEPARTAMENTO JUNIN
CONTRATO PRINCIPAL VALORIZACIONES CALCULADAS
ITEM DESCRIPCION DE PARTIDA UNIDAD PRECIO VAL. 01 VAL. 02 VAL. 03 VAL. 04 VAL. 05 VAL. 06
UNITARIO
PRESUPUESTO ACUMULADO ACTUAL SALDOS POR VALORIZAR
MET. mes ENERO mes FEBRERO mes SET. mes OCT. mes NOV. mes DIC.
S/. S/. METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01 DESCOLMOTACION DEL CAUCE DEL RIO PAUCARTAMBO 307,348.75 107,094.36 52,362.00 81,998.95 57,466.60 10,813.85 49,570.44 306,944.20 404.55

01.01 OBRAS PROVICIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

01.01.01 OBRAS PROVICIONALES


01.01.01.01 CARTEL DE IDENTIFICACION DE OBRA 3.60X2.40 und 1.00 1,367.69 1,367.69 1.00 1,367.69 100.00% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 1.00 1,367.69 100.00% 0.00 0.00%
01.01.01.02 INSTALACION DE OFICINA, ALMACEN Y CASETA DE GUARIANIA mes 5.00 2,700.00 13,500.00 1.00 2,700.00 20.00% 0.00 0.00 0.00% 1.00 2,700.00 20.00% 1.00 2,700.00 20.00% 1.00 2,700.00 20.00% 1.00 2,700.00 20.00% 5.00 13,500.00 100.00% 0.00 0.00%
01.01.01.03 CERCO PERIMETRICO DE PATIO DE MAQUINARIAS Y GUARDIANIA und 1.00 10,936.44 10,936.44 0.50 5,468.22 50.00% 0.00 0.00 0.00% 0.50 5,468.22 50.00% 0.00% 0.00% 0.00% 1.00 10,936.44 100.00% 0.00 0.00%
01.01.01.04 HABILITACION DE ACCESOS A TRAMOS Y CANTERAS km 1.00 6,515.48 6,515.48 0.40 2,606.19 40.00% 0.00 0.00 0.00% 0.60 3,909.29 60.00% 0.00% 0.00% 0.00% 1.00 6,515.48 100.00% 0.00 0.00%
01.01.02 INSTALACIONES PROVISIONALES 0.00 0.00
01.01.02.01 ALQUILER DE SS.HH. PROVISIONALES mes 5.00 720.00 3,600.00 1.00 720.00 20.00% 0.00 0.00 0.00% 1.00 720.00 20.00% 1.00 720.00 20.00% 1.00 720.00 20.00% 1.00 720.00 20.00% 5.00 3,600.00 100.00% 0.00 0.00%
01.01.02.02 AGUA PARA LA CONSTRUCCION glb 1.00 154.10 154.10 0.20 30.82 20.00% 0.00 0.00 0.00% 0.20 30.82 20.00% 0.20 30.82 20.00% 0.20 30.82 20.00% 0.20 30.82 20.00% 1.00 154.10 100.00% 0.00 0.00%
01.01.02.03 ENERGIA ELECTRICA PROVISIONAL glb 1.00 1,079.25 1,079.25 0.20 215.85 20.00% 0.00 0.00 0.00% 0.20 215.85 20.00% 0.20 215.85 20.00% 0.20 215.85 20.00% 0.20 215.85 20.00% 1.00 1,079.25 100.00% 0.00 0.00%
01.01.03 TRABAJOS PRELIMINARES 0.00 0.00
01.01.03.01 LIMPIEZA DEL TERRENO MANUAL m2 2,850.00 8.09 23,059.35 2,100.00 16,991.10 73.68% 0.00 0.00 0.00% 260.00 2,103.66 9.12% 220.00 1,780.02 7.72% 220.00 1,780.02 7.72% 0.00% 2,800.00 22,654.80 98.25% 50.00 404.55 1.75%
01.01.03.02 OBRAS DE DESVIO DE RIO m3 1,060.20 6.25 6,622.01 900.00 5,621.40 84.89% 0.00 0.00 0.00% 160.20 1,000.61 15.11% 0.00% 0.00% 0.00% 1,060.20 6,622.01 100.00% 0.00 0.00%
01.01.04 MOVILIZACION DE CAMPAMENTO, MAQUINARIA Y HERRAMIENTAS 0.00 0.00
01.01.04.01 FLETE TERRESTRE glb 1.00 19,143.26 19,143.26 0.00 0.00 0.00% 0.60 11,485.96 60.00% 0.35 6,700.14 35.00% 0.05 957.16 5.00% 0.00% 1.00 19,143.26 100.00% 0.00 0.00%
01.01.04.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPOS glb 1.00 24,895.48 24,895.48 0.50 12,447.74 50.00% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.50 12,447.74 50.00% 1.00 24,895.48 100.00% 0.00 0.00%
01.01.05 TRAZOS, NIVELES Y REPLANTEO 0.00 0.00
01.01.05.01 TRAZO Y REPLANTEO PRELIMINAR m2 2,850.00 2.77 7,900.20 2,850.00 7,900.20 100.00% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 2,850.00 7,900.20 100.00% 0.00 0.00%
01.02 SEGURIDAD Y SALUD 0.00 0.00
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y
01.02.01 glb 1.00 4,500.00 4,500.00 0.00% 0.00 0.00 0.00% 0.30 1,350.00 30.00% 0.00% 0.50 2,250.00 50.00% 0.20 900.00 20.00% 1.00 4,500.00 100.00% 0.00 0.00%
SALUD EN EL TRABAJO
01.02.02 EQUIPO DE PROTECCION INDIVIDUAL und 35.00 296.68 10,383.66 15.00 4,450.14 42.86% 0.00 0.00 0.00% 10.00 2,966.76 28.57% 10.00 2,966.76 28.57% 0.00% 0.00% 35.00 10,383.66 100.00% 0.00 0.00%
01.02.03 EQUIPO DE PROTECCION COLECTIVA glb 1.00 2,704.50 2,704.50 0.30 811.35 30.00% 0.00 0.00 0.00% 0.70 1,893.15 70.00% 0.00% 0.00% 0.00% 1.00 2,704.50 100.00% 0.00 0.00%
01.02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1,903.52 1,903.52 0.30 571.06 30.00% 0.00 0.00 0.00% 0.70 1,332.46 70.00% 0.00% 0.00% 0.00% 1.00 1,903.52 100.00% 0.00 0.00%
01.02-05 CAPACITACION EN SEGURIDAD Y SALUD mes 5.00 2,160.00 10,800.00 1.00 2,160.00 20.00% 0.00 0.00 0.00% 1.00 2,160.00 20.00% 1.00 2,160.00 20.00% 1.00 2,160.00 20.00% 1.00 2,160.00 20.00% 5.00 10,800.00 100.00% 0.00 0.00%
01.03 DESCOLMOTACION DE RIO 0.00 0.00
01.03.01 DESCOLMOTACION CARGUIO DE MATERIAL CON EQUIPO m3 4,593.73 11.03 50,687.22 3,900.00 43,032.60 84.90% 500.00 5,517.00 10.88% 693.73 7,654.62 15.10% 0.00% 0.00% 0.00% 4,593.73 50,687.22 100.00% 0.00 0.00%
01.03.02 ELIMINACION DE MATERIAL, INCLUYE ACARREO INTERNO DE MATERIAL m3 5,742.16 18.74 107,596.59 0.00% 2500.00 46,845.00 43.54% 1,975.00 37,007.55 34.39% 2,145.00 40,193.01 37.36% 0.00% 1,622.16 30,396.03 28.25% 5,742.16 107,596.59 100.00% 0.00 0.00%
PREVENCION Y PROTECCION DE DESASTRE DEL CAUCE DEL RIO
02 1,223,596.21 3,878.10 - 422,838.76 344,110.70 208,833.09 30,577.11 0.00 1,010,237.76 0.00 213,358.45
PAUCARTAMBO
02.01 DEFENSA DE MURO GAVION 0.00 0.00
02.01.01 MOVIMIENTO DE TIERRAS 0.00 0.00
02.01.01.01 CORTE DE SECCION EN TERRENO NORMAL CON EQUIPO PESADO m3 2,519.40 5.60 14,103.60 400.00 2,239.20 15.88% 0.00 0.00 0.00% 1,280.00 7,165.44 50.81% 316.00 1,768.97 12.54% 72.40 405.30 2.87% 0.00% 2,068.40 11,578.91 82.10% 451.00 2,524.69 17.90%
02.01.01.02 PERFILADO Y NIVELACION DE SECCION EN CORTE PARA MURO m2 1,710.00 5.46 9,341.73 300.00 1,638.90 17.54% 0.00 0.00 0.00% 520.00 2,840.76 30.41% 412.00 2,250.76 24.09% 178.00 972.41 10.41% 0.00% 1,410.00 7,702.83 82.46% 300.00 1,638.90 17.54%
RELLENO Y COMPACTACION EN CAPAS DE 20 CM. CON MATERIAL SELECCIONADO Y
02.01.01.03 m3 2,519.40 44.32 111,649.73 0.00% 0.00 0.00 0.00% 1,280.00 56,724.48 50.81% 486.00 21,537.58 19.29% 0.00% 302.40 13,401.16 12.00% 2,068.40 91,663.22 82.10% 451.00 19,986.51 17.90%
EQUIPO EN ZONA DE RELLENO
02.01.01.04 ELIMINACION DE MATERIAL, INCLUYE ACARREO INTERNO DE MATERIAL m3 3,149.25 18.74 59,010.65 0.00% 0.00 0.00 0.00% 1,483.00 27,788.45 47.09% 785.00 14,709.33 24.93% 0.00% 317.49 5,946.85 10.08% 2,585.49 48,444.63 82.10% 563.76 10,566.02 17.90%
02.01.02 COLOCACION DE GAVIONES 0.00 0.00
02.01.02.01 EXTRACCION DE OVER m3 7,234.44 5.65 40,889.05 0.00% 0.00 0.00 0.00% 2,249.60 12,714.74 31.10% 2,380.00 13,451.76 32.90% 1,335.64 7,549.04 18.46% 0.00% 5,965.24 33,715.54 82.46% 1,269.20 7,173.51 17.54%
02.01.02.02 ZARANDEO Y ACOPIO (HASTA 30 M) DE PIEDRA SELECTA m3 7,234.44 5.93 42,907.46 0.00% 0.00 0.00 0.00% 2,249.60 13,342.38 31.10% 2,356.00 13,973.44 32.57% 1,359.64 8,064.02 18.79% 0.00% 5,965.24 35,379.84 82.46% 1,269.20 7,527.62 17.54%
02.01.02.03 CARGUIO Y TRANSPORTE DE PIEDRA PARA GAVIONES m3 4,332.00 16.86 73,024.52 0.00% 0.00 0.00 0.00% 1,406.00 23,700.94 32.46% 1,285.00 21,661.25 29.66% 881.00 14,851.02 20.34% 0.00% 3,572.00 60,213.21 82.46% 760.00 12,811.31 17.54%
02.01.02.04 GAVION TIPO A 10X8.0cm 3.70x4.40mm G+PVC 5.0X1.0X1.0m und 456.00 596.58 272,041.85 0.00% 0.00 0.00 0.00% 214.00 127,668.76 46.93% 115.00 68,607.05 25.22% 47.00 28,039.40 10.31% 0.00% 376.00 224,315.21 82.46% 80.00 47,726.64 17.54%
02.01.02.05 GAVION TIPO B 10X8.0cm 3.70x4.40mm G+PVC 5.0X1.5X1.0m und 228.00 656.10 149,590.80 0.00% 0.00 0.00 0.00% 10.00 6,561.00 4.39% 106.00 69,546.60 46.49% 72.00 47,239.20 31.58% 0.00% 188.00 123,346.80 82.46% 40.00 26,244.00 17.54%
02.01.02.06 GAVION TIPO D 10X8.0cm 3.70x4.40mm G+PVC 5.0X2.0X0.30m und 114.00 623.58 71,088.46 0.00% 0.00 0.00 0.00% 20.00 12,471.66 17.54% 26.00 16,213.16 22.81% 48.00 29,931.98 42.11% 0.00% 94.00 58,616.80 82.46% 20.00 12,471.66 17.54%
02.01.02.07 RELLENO DE PIEDRAS EN GAVIONES m3 4,332.00 75.49 327,031.34 0.00% 0.00 0.00 0.00% 1,406.00 106,141.75 32.46% 1,285.00 97,007.22 29.66% 881.00 66,508.45 20.34% 0.00% 3,572.00 269,657.42 82.46% 760.00 57,373.92 17.54%
02.01.02.08 GEOTEXTIL DE 250 gr/cm2 m2 5,187.00 8.04 41,687.92 0.00% 0.00 0.00 0.00% 3,200.00 25,718.40 61.69% 421.00 3,383.58 8.12% 656.00 5,272.27 12.65% 0.00% 4,277.00 34,374.25 82.46% 910.00 7,313.67 17.54%
02.01.03 MEDIDAS DE MITIGACION AMBIENTAL 0.00 0.00
02.01.03.01 REACONDICIONAMIENTO DE CAMPAMENTO Y PATIO DE MAQUINARIA ha 0.16 4,630.04 740.81 0.00% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.16 740.81 100.00% 0.16 740.81 100.00% 0.00 0.00%
02.01.03.02 LIMPIEZA FINAL DE OBRA m2 855.00 12.27 10,488.29 0.00% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 855.00 10,488.29 100.00% 855.00 10,488.29 100.00% 0.00 0.00%

(A) COSTO DIRECTO 1,530,944.96 110,972.46 7.25% 52,362.00 3.42% 504,837.71 32.98% 401,577.30 26.23% 219,646.94 14.35% 80,147.55 5.24% 1,317,181.95 86.04% 213,763.01 13.96%
(B) GASTOS GENERALES 10.00 % DE ( A ) 153,094.50 11,097.25 5,236.20 50,483.77 40,157.73 21,964.69 8,014.76 131,718.20 21,376.30
(C) UTILIDADES 10.00 % DE ( A ) 153,094.50 11,097.25 5,236.20 50,483.77 40,157.73 21,964.69 8,014.76 131,718.20 21,376.30

TOTAL VALORIZADO SIN I.G.V. ( A + B + C ) : 1,837,133.95 133,166.95 62,834.40 605,805.25 481,892.76 263,576.33 96,177.07 1,580,618.34 256,515.61
SUB TOTAL 1,837,133.95 133,166.95 62,834.40 605,805.25 481,892.76 263,576.33 96,177.07 1,580,618.34 256,515.61
IGV 18.00 % 330,684.11 23,970.05 11,310.19 109,044.95 86,740.70 47,443.74 17,311.87 284,511.30 46,172.81
TOTAL PRESUPUESTO 2,167,818.07 157,137.00 74,144.59 714,850.20 568,633.46 311,020.07 113,488.94 1,865,129.64 302,688.43
AMORTIZACION POR ADELANTO DIRECTO 10.00% 15,713.70 7,414.46 71,485.02 56,863.35 31,102.01 11,348.89 186,512.97
AMORTIZACION POR ADELANTO DIRECTO 20.00% 31,427.40 14,828.92 142,970.04 113,726.69 62,204.01 22,697.79 404,453.33
MONTO TOTAL A FACTURAR 109,995.90 51,901.21 500,395.14 398,043.42 217,714.05 79,442.26 1,274,163.34

NOTA: La valorizacion n° 02 que corresponde al mes de febrero no fue aprobado por la supervision, por lo tanto no fue pagado
RESUMEN DE VALORIZACIONES DE ADICIONAL DE OBRA N° 01
"RENOVACION DE MURO DE CONTENCION; EN EL(LA) MARGEN DERECHA EN LA LOCALIDAD PUENTE CAPELO, DISTRITO DE SAN LUIS DE SHUARO, PROVINCIA
OBRA
DE CHANCHAMAYO, DEPARTAMENTO DE JUNIN"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHANCHA PROVINCIA : CHANCHAMAYO
CONTRATISTA :CONSORCIO JUNIN DISTRITO : SAN LUIS DE SHUARO
RESIDENTE :ING. CESAR J. MOLINA BERROCAL LUGAR : PUENTE CAPELO
MONTO DE LA
SUPERVISOR : ING. LUIS M. MIRANDA VASQUEZ : 512656.68
OBRA

TOTAL 1° VALORIZACION 2° VALORIZACION 3° VALORIZACION 4° VALORIZACION ACUMULADO SALDO


DESCRIPCION PRESUPUEST0 MONTO MONTO MONTO MONTO MONTO MONTO
% % % % % %
S/. S/. S/. S/. S/. S/. S/.
COSTO DIRECTO S/ 362,045.67 S/ 46,131.50 S/ 167,631.50 S/ 83,592.02 S/ 64,690.65 S/ 362,045.67 S/ -
GASTOS GENERALES (10.00%)S/ 36,204.57 S/ 4,613.15 S/ 16,763.15 S/ 8,359.20 S/ 6,469.07 S/ 36,204.57 S/ -
UTILIDAD (10.00%) S/ 36,204.57 S/ 4,613.15 S/ 16,763.15 S/ 8,359.20 S/ 6,469.07 S/ 36,204.57 S/ -
12.74% 46.30% 23.09% 17.87% 100.00% 0.00%
SUB TOTAL PRESUPUESTO S/ 434,454.81 S/ 55,357.80 S/ 201,157.80 S/ 100,310.42 S/ 77,628.78 S/ 434,454.81 S/ -
IGV (18%) S/ 78,201.87 S/ 9,964.40 S/ 36,208.40 S/ 18,055.88 S/ 13,973.18 S/ 78,201.87 S/ -

TOTAL PRESUPUESTO S/ 512,656.68 S/ 65,322.20 S/ 237,366.20 S/ 118,366.30 S/ 91,601.96 S/ 512,656.68 S/ -


RESUMEN DE VALORIZACIONES DE ADICIONAL DE OBRA N° 02
"RENOVACION DE MURO DE CONTENCION; EN EL(LA) MARGEN DERECHA EN LA LOCALIDAD PUENTE
OBRA
CAPELO, DISTRITO DE SAN LUIS DE SHUARO, PROVINCIA DE CHANCHAMAYO, DEPARTAMENTO DE JUNIN"

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHANCHAMAYO PROVINCIA : CHANCHAMAYO


CONTRATISTA :CONSORCIO JUNIN DISTRITO : SAN LUIS DE SHUARO
RESIDENTE :ING. CESAR J. MOLINA BERROCAL LUGAR : PUENTE CAPELO
SUPERVISOR : ING. LUIS M. MIRANDA VASQUEZ MONTO S/30,784.43

TOTAL 1° VALORIZACION ACUMULADO SALDO


DESCRIPCION PRESUPUEST0 MONTO MONTO MONTO
% % %
S/. S/. S/. S/.
COSTO DIRECTO S/ 21,740.42 S/ 21,740.42 S/ 21,740.42 S/ -
GASTOS GENERALES (10.00%) S/ 2,174.04 S/ 2,174.04 S/ 2,174.04 S/ -
UTILIDAD (10.00%) S/ 2,174.04 S/ 2,174.04 S/ 2,174.04 S/ -
100.00% 100.00% 0.00%
SUB TOTAL PRESUPUESTO S/ 26,088.50 S/ 26,088.50 S/ 26,088.50 S/ -
IGV (18%) S/ 4,695.93 S/ 4,695.93 S/ 4,695.93 S/ -

TOTAL PRESUPUESTO S/ 30,784.43 S/ 30,784.43 S/ 30,784.43 S/ -


RESUMEN DE VALORIZACIONES DE PLAN COVID-19
"RENOVACION DE MURO DE CONTENCION; EN EL(LA) MARGEN DERECHA EN LA LOCALIDAD PUENTE
OBRA
CAPELO, DISTRITO DE SAN LUIS DE SHUARO, PROVINCIA DE CHANCHAMAYO, DEPARTAMENTO DE JUNIN"

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHANCHAMAYO PROVINCIA : CHANCHAMAYO


CONTRATISTA :CONSORCIO JUNIN DISTRITO : SAN LUIS DE SHUARO
RESIDENTE :ING. CESAR J. MOLINA BERROCAL LUGAR : PUENTE CAPELO
SUPERVISOR : ING. LUIS M. MIRANDA VASQUEZ MONTO S/73,997.29

TOTAL 1° VALORIZACION ACUMULADO SALDO


DESCRIPCION PRESUPUEST0 MONTO MONTO MONTO
% % %
S/. S/. S/. S/.
COSTO DIRECTO S/ 57,008.70 S/ 53,967.73 S/ 53,967.73 S/ 3,040.97
GASTOS GENERALES (10.00%) S/ 5,700.87 S/ 5,396.77 S/ 5,396.77 S/ 304.10
SUB TOTAL PRESUPUESTO S/ 62,709.57 S/ 59,364.50 94.67% S/ 59,364.50 94.67% S/ 3,345.07 5.33%
IGV (18%) S/ 11,287.72 S/ 10,685.61 S/ 10,685.61 S/ 602.11

TOTAL PRESUPUESTO S/ 73,997.29 S/ 70,050.11 S/ 70,050.11 S/ 3,947.18