CALENDARIO REPROGRAMADO DE AVANCE DE OBRA VALORIZADO

"AMPLIACIÓN DE REDES DE AGUA POTABLE Y ALCANTARILLADO PARA EL PASAJE INCA HUASI, PSJE BELLA DURMIENTE, PSJE PICHGA COCHA, PSJE S/N 01 Y PSJE S/N 02, INTEGRANTE DE PARCELA 22 - PREDIO EL TINGO, DISTRITO, PROVINCIA Y DEPARTAMENTO DE
HUÁNUCO"
► PROPIETARIO :
► LUGAR : HUÁNUCO
► PLAZO DE EJECUCION : 80 DIAS

DÍAS
ITEM NOMBRE DE LA TAREA UNIDAD METRADO COSTO TOTAL MES-1 MES-2 MES-3
80 días

1 “AMPLIACIÓN DE REDES DE AGUA POTABLE Y ALCANTARILLADO PARA EL PASAJE INCA HUASI, PSJE BELLA
DURMIENTE, PSJE PICHGA COCHA, PSJE S/N 01 Y PSJE S/N 02, INTEGRANTE DE PARCELA 22 - PREDIO EL TINGO,
DISTRITO, PROVINCIA Y DEPARTAMENTO DE HUÁNUCO " S/. 35,743.99 S/. 5,580.65 S/. 14,861.43 S/. 15,301.91 S/. 35,743.99
01 AMPLIACION DE LA RED DE AGUA POTABLE S/. 35,743.99 S/. 5,580.65 S/. 14,861.43 S/. 15,301.91 S/. 35,743.99

01.01 TRABAJOS PRELIMINARES S/. 50.00 S/. 50.00 S/. 50.00


01.01.01 TRANSPORTE EN GENERAL glb 1.00 S/. 50.00 S/. 50.00 S/. 50.00 S/. 50.00
01.02 TRAZO NIVELES Y REPLANTEO S/. 562.40 S/. 359.71 S/. 195.36 S/. 7.33 S/. 562.40
01.02.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m 296.00 S/. 1.02 S/. 301.92 S/. 301.92 S/. 301.92
01.02.02 REPLANTEO DURANTE EL PROCESO m 296.00 S/. 0.88 S/. 260.48 S/. 57.79 S/. 195.36 S/. 7.33 S/. 260.48
01.03 MOVIMIENTO DE TIERRAS S/. 24,421.65 S/. 5,170.94 S/. 7,059.24 S/. 12,191.47 S/. 24,421.65
01.03.01 EXCAVACIÓN MANUAL DE ZANJAS PARA TUBERIAS H.PROM=1.20M m3 355.20 S/. 28.84 S/. 10,243.97 S/. 4,929.91 S/. 5,121.99 S/. 192.07 S/. 10,243.97
01.03.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA m 296.00 S/. 3.67 S/. 1,086.32 S/. 241.03 S/. 814.74 S/. 30.55 S/. 1,086.32
01.03.03 CAMA DE APOYO P/TUBERÍAS CON MATERIAL PROPIO ZARANDEADO (h=0.10m) m 296.00 S/. 3.94 S/. 1,166.24 S/. 1,122.51 S/. 43.73 S/. 1,166.24
01.03.04 PROTECCIÓN PARA TUBERÍAS CON MATERIAL PROPIO ZARANDEADO (h=0.30m) m 296.00 S/. 5.40 S/. 1,598.40 S/. 1,598.40 S/. 1,598.40
01.03.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO EN ZANJAS m3 284.96 S/. 23.07 S/. 6,574.03 S/. 6,574.03 S/. 6,574.03
01.03.06 ELIMINACIÒN DE MATERIAL EXCEDENTE HASTA 60.00 M (MANUAL USANDO CARRETILLA) m3 88.80 S/. 42.26 S/. 3,752.69 S/. 3,752.69 S/. 3,752.69
01.04 OBRAS DE CONCRETO SIMPLE S/. 183.43 S/. 183.43 S/. 183.43
01.04.01 DADOS DE CONCRETO F'C=140KG/CM2 P/ANCLAJE DE ACCESORIOS m3 0.54 S/. 339.68 S/. 183.43 S/. 183.43 S/. 183.43
01.05 SUMINISTRO E INSTALACION DE TUBERÍAS S/. 7,903.20 S/. 7,606.83 S/. 296.37 S/. 7,903.20
01.05.01 SUMINISTRO E INSTALACIÓN DE TUBERÍAS PVC-UF NTP ISO 1452 DN 90MM C-7.5 m 296.00 S/. 26.70 S/. 7,903.20 S/. 7,606.83 S/. 296.37 S/. 7,903.20
01.06 SUMINISTRO E INSTALACIÓN DE ACCESORIOS S/. 533.55 S/. 533.55 S/. 533.55
01.06.01 TEE PVC NTP ISO 1452 UF Ø 90mm x 90mm und 5.00 S/. 57.15 S/. 285.75 S/. 285.75 S/. 285.75
01.06.02 TAPON PVC-UF NTP ISO 1452 DN 90MM und 6.00 S/. 41.30 S/. 247.80 S/. 247.80 S/. 247.80
01.07 PRUEBA HIDRÁULICA EN TUBERÍAS S/. 2,089.76 S/. 2,089.76 S/. 2,089.76
01.07.01 PRUEBA HIDRÁULICA EN TUBERÍA PVC-UF NTP ISO 1452 DN 90MM m 296.00 S/. 7.06 S/. 2,089.76 S/. 2,089.76 S/. 2,089.76
COSTO DIRECTO (1) S/. 35,743.99 S/. 5,580.65 S/. 14,861.43 S/. 15,301.91 S/. 35,743.99
GASTOS GENERALES (5.00%) S/. 1,787.20 S/. 279.03 S/. 743.07 S/. 765.10 S/. 1,787.20
COSTO DEL EXPEDIENTE TÉCNICO (5%) S/. 1,787.20 S/. 279.03 S/. 743.07 S/. 765.10 S/. 1,787.20
COSTO DE LA SUPERVISIÓN (6%) S/. 2,144.64 S/. 334.84 S/. 891.69 S/. 918.11 S/. 2,144.64
PRESUPUESTO TOTAL S/. 41,463.03 S/. 6,473.55 S/. 17,239.26 S/. 17,750.22 S/. 41,463.03
AVANCE PROGRAMADO DE OBRA 15.61% 41.58% 42.81% 100.00%
AVANCE ACUMULADO DE OBRA 15.61% 57.19% 100.00%