Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 2 TASK filter: All Activities
LINEA BASE Remaining Work Baseline Milestone © Oracle Corporation
200008.MOV TIERRAS/MM.CC WCRONOGRAMA GENERAL 28-Feb-22 12:18
Activity ID Activity Name Original Actual Variance Start Finish January 2022 February 2022 March 2022 April 2022 May 2022
Duration Duration - BL1
09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15
Finish
A2030 EXCAVACION LOCALIZADA 24 0 0 24-Feb-22 19-Mar-22 EXCAVACION LOCALIZADA
A2050 CONCRETO SIMPLE f'c=100Kg/cm2 24 0 0 01-Mar-22 24-Mar-22 CONCRETO SIMPLE f'c=100Kg/cm2
P15170 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2 34 0 0 04-Mar-22 07-Apr-22 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2
P15150 ENCOFRADO Y DESENCOFRADO NORMAL 34 0 0 06-Mar-22 09-Apr-22 ENCOFRADO Y DESENCOFRADO NORMAL
P15160 CONRETO EN MUROS f'c=280Kg/cm2 34 0 0 07-Mar-22 10-Apr-22 CONRETO EN MUROS f'c=280Kg/cm2
A2040 RELLENO CON MATERIAL DE PRESTAMO EN SOBREXCAVACION
15 0 0 10-Apr-22 25-Apr-22 RELLENO CON MATERIAL DE PRES
P15180 GEODREN + GRAVILLA DE RELLENO 15 0 0 10-Apr-22 25-Apr-22 GEODREN + GRAVILLA DE RELLEN
Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 2 TASK filter: All Activities
LINEA BASE Remaining Work Baseline Milestone © Oracle Corporation