200008.MOV TIERRAS/MM.

CC WCRONOGRAMA GENERAL 28-Feb-22 12:18


Activity ID Activity Name Original Actual Variance Start Finish January 2022 February 2022 March 2022 April 2022 May 2022
Duration Duration - BL1
09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15
Finish
126 0 0 06-Jan-22 11-May-22 11-May-22, 200005-
200005-MT 200008.MOV TIERRAS/MM.CC
126 0 0 06-Jan-22 11-May-22 11-May-22, 200005-
200005-MT.10 SUBESTRUCTURA
200005-MT.10.00 GENERAL 126 0 0 06-Jan-22 11-May-22 11-May-22, 200005-
200005-MT.10.00.MT MOVIMIENTOS DE TIERRA 126 0 0 06-Jan-22 11-May-22 11-May-22, 200005-
200005-MT.10.00.MT.1 PLATAFORMA 1 76 0 0 06-Jan-22 22-Mar-22 22-Mar-22, 200005-MT.10.00.MT.1 PLATAFORMA 1
P4090 CORTE Y RELLENO CON MATERIAL PROPIO 19 0 0 06-Jan-22* 24-Jan-22 CORTE Y RELLENO CON MATERIAL PROPIO
P4250 ELIMINACION DE MATERIAL EXCEDENTE 19 0 0 16-Jan-22 03-Feb-22 ELIMINACION DE MATERIAL EXCEDENTE
P4100 ESCARIFICADO, PERFILADO Y COMPACTADO DE SUB RASANTE2 0 0 25-Jan-22 26-Jan-22 ESCARIFICADO, PERFILADO Y COMPACTADO DE SUB RASANTE
P4110 RELLENO CON MATERIAL DE PRESTAMO EN CAPA DE E=0.25 30 0 0 27-Jan-22 25-Feb-22 RELLENO CON MATERIAL DE PRESTAMO EN CAPA DE E=0.25
P4240 CONFORMACION Y COMPACTACION DE TERRENO 20 0 0 03-Mar-22 22-Mar-22 CONFORMACION Y COMPACTACION DE TERRENO
200005-MT.10.00.MT.2 PLATAFORMA 2 81 0 0 25-Jan-22 15-Apr-22 15-Apr-22, 200005-MT.10.00.MT.2 PLATAFORMA
P14820 CORTE Y RELLENO CON MATERIAL PROPIO 21 0 0 25-Jan-22 14-Feb-22 CORTE Y RELLENO CON MATERIAL PROPIO
P14860 ELIMINACION DE MATERIAL EXCEDENTE 19 0 0 04-Feb-22 22-Feb-22 ELIMINACION DE MATERIAL EXCEDENTE
P14830 ESCARIFICADO, PERFILADO Y COMPACTADO DE SUB RASANTE2 0 0 15-Feb-22 16-Feb-22 ESCARIFICADO, PERFILADO Y COMPACTADO DE SUB RASANTE
P14840 RELLENO CON MATERIAL DE PRESTAMO EN CAPA DE E=0.25 30 0 0 17-Feb-22 18-Mar-22 RELLENO CON MATERIAL DE PRESTAMO EN CAPA DE E=0.25
P14850 CONFORMACION Y COMPACTACION DE TERRENO 20 0 0 27-Mar-22 15-Apr-22 CONFORMACION Y COMPACTACION DE TERR
200005-MT.10.00.MT.3 PLATAFORMA 3 78 0 0 23-Feb-22 11-May-22 11-May-22, 200005-
P14870 CORTE Y RELLENO CON MATERIAL PROPIO 21 0 0 23-Feb-22 15-Mar-22 CORTE Y RELLENO CON MATERIAL PROPIO
P14910 ELIMINACION DE MATERIAL EXCEDENTE 19 0 0 05-Mar-22 23-Mar-22 ELIMINACION DE MATERIAL EXCEDENTE
P14880 ESCARIFICADO, PERFILADO Y COMPACTADO DE SUB RASANTE2 0 0 16-Mar-22 17-Mar-22 ESCARIFICADO, PERFILADO Y COMPACTADO DE SUB RASANTE
P14890 RELLENO CON MATERIAL DE PRESTAMO EN CAPA DE E=0.25 30 0 0 18-Mar-22 16-Apr-22 RELLENO CON MATERIAL DE PRESTAMO EN
P14900 CONFORMACION Y COMPACTACION DE TERRENO 20 0 0 21-Apr-22 11-May-22 CONFORMACION
200005-MT.10.04 MUROS DE CONTENCIÓN 107 0 0 24-Jan-22 11-May-22 11-May-22, 200005-
200005-MT.10.04.1 MUROS DE CONTENCION INTERNOS 107 0 0 24-Jan-22 11-May-22 11-May-22, 200005-
200005-MT.10.04.1.1 PLATAFORMA 1-2 57 0 0 24-Jan-22 22-Mar-22 22-Mar-22, 200005-MT.10.04.1.1 PLATAFORMA 1-2
A2070 APROBACIÓN DE EXPEDIENTE 30 0 0 24-Jan-22 23-Feb-22 APROBACIÓN DE EXPEDIENTE
A1800 EXCAVACION LOCALIZADA 5 0 0 24-Feb-22 28-Feb-22 EXCAVACION LOCALIZADA
A1840 CONCRETO SIMPLE f'c=100Kg/cm2 4 0 0 01-Mar-22 04-Mar-22 CONCRETO SIMPLE f'c=100Kg/cm2
P2990 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2 11 0 0 04-Mar-22 15-Mar-22 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2
P2970 ENCOFRADO Y DESENCOFRADO NORMAL 13 0 0 06-Mar-22 19-Mar-22 ENCOFRADO Y DESENCOFRADO NORMAL
P2980 CONRETO EN MUROS f'c=280Kg/cm2 12 0 0 07-Mar-22 19-Mar-22 CONRETO EN MUROS f'c=280Kg/cm2
A1810 RELLENO CON MATERIAL DE PRESTAMO EN SOBREXCAVACION3 0 0 20-Mar-22 22-Mar-22 RELLENO CON MATERIAL DE PRESTAMO EN SOBREXCAVACION
P4260 GEODREN + GRAVILLA DE RELLENO 3 0 0 20-Mar-22 22-Mar-22 GEODREN + GRAVILLA DE RELLENO
200005-MT.10.04.1.2 PLATAFORMA 2-3 27 0 0 20-Mar-22 15-Apr-22 15-Apr-22, 200005-MT.10.04.1.2 PLATAFORMA 2
A1970 EXCAVACION LOCALIZADA 5 0 0 20-Mar-22 24-Mar-22 EXCAVACION LOCALIZADA
A1990 CONCRETO SIMPLE f'c=100Kg/cm2 4 0 0 25-Mar-22 28-Mar-22 CONCRETO SIMPLE f'c=100Kg/cm2
P15090 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2 11 0 0 28-Mar-22 08-Apr-22 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2
P15070 ENCOFRADO Y DESENCOFRADO NORMAL 13 0 0 30-Mar-22 12-Apr-22 ENCOFRADO Y DESENCOFRADO NORMAL
P15080 CONRETO EN MUROS f'c=280Kg/cm2 12 0 0 31-Mar-22 12-Apr-22 CONRETO EN MUROS f'c=280Kg/cm2
A1980 RELLENO CON MATERIAL DE PRESTAMO EN SOBREXCAVACION3 0 0 13-Apr-22 15-Apr-22 RELLENO CON MATERIAL DE PRESTAMO EN
P15100 GEODREN + GRAVILLA DE RELLENO 3 0 0 13-Apr-22 15-Apr-22 GEODREN + GRAVILLA DE RELLENO
200005-MT.10.04.1.3 PLATAFORMA 3-ANDENES 29 0 0 13-Apr-22 11-May-22 11-May-22, 200005-
A2000 EXCAVACION LOCALIZADA 6 0 0 13-Apr-22 18-Apr-22 EXCAVACION LOCALIZADA
A2020 CONCRETO SIMPLE f'c=100Kg/cm2 5 0 0 18-Apr-22 22-Apr-22 CONCRETO SIMPLE f'c=100Kg/cm2
P15130 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2 12 0 0 21-Apr-22 03-May-22 ACERO DE REFUERZO EN
P15110 ENCOFRADO Y DESENCOFRADO NORMAL 14 0 0 23-Apr-22 07-May-22 ENCOFRADO Y DESEN
P15120 CONRETO EN MUROS f'c=280Kg/cm2 13 0 0 24-Apr-22 07-May-22 CONRETO EN MUROS
A2010 RELLENO CON MATERIAL DE PRESTAMO EN SOBREXCAVACION4 0 0 07-May-22 11-May-22 RELLENO CON MA
P15140 GEODREN + GRAVILLA DE RELLENO 4 0 0 07-May-22 11-May-22 GEODREN + GRAV
200005-MT.10.04.2 MUROS DE CONTENCION EXTERNOS 61 0 0 24-Feb-22 25-Apr-22 25-Apr-22, 200005-MT.10.04.2 MURO

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 2 TASK filter: All Activities
LINEA BASE Remaining Work Baseline Milestone © Oracle Corporation
200008.MOV TIERRAS/MM.CC WCRONOGRAMA GENERAL 28-Feb-22 12:18
Activity ID Activity Name Original Actual Variance Start Finish January 2022 February 2022 March 2022 April 2022 May 2022
Duration Duration - BL1
09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15
Finish
A2030 EXCAVACION LOCALIZADA 24 0 0 24-Feb-22 19-Mar-22 EXCAVACION LOCALIZADA
A2050 CONCRETO SIMPLE f'c=100Kg/cm2 24 0 0 01-Mar-22 24-Mar-22 CONCRETO SIMPLE f'c=100Kg/cm2
P15170 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2 34 0 0 04-Mar-22 07-Apr-22 ACERO DE REFUERZO EN MUROS fy=4200Kg/cm2
P15150 ENCOFRADO Y DESENCOFRADO NORMAL 34 0 0 06-Mar-22 09-Apr-22 ENCOFRADO Y DESENCOFRADO NORMAL
P15160 CONRETO EN MUROS f'c=280Kg/cm2 34 0 0 07-Mar-22 10-Apr-22 CONRETO EN MUROS f'c=280Kg/cm2
A2040 RELLENO CON MATERIAL DE PRESTAMO EN SOBREXCAVACION
15 0 0 10-Apr-22 25-Apr-22 RELLENO CON MATERIAL DE PRES
P15180 GEODREN + GRAVILLA DE RELLENO 15 0 0 10-Apr-22 25-Apr-22 GEODREN + GRAVILLA DE RELLEN

Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 2 TASK filter: All Activities
LINEA BASE Remaining Work Baseline Milestone © Oracle Corporation