CRONOGRAMA DE UTILIZACION DE EQUIPOS

MEJORAMIENTO Y AMPLIACION DEL ESTADIO MUNICIPAL DE SAN RAFAEL - DISTRITO DE SAN RAFAEL -
PROYECTO:
PROVINCIA DE AMBO - DEPARTAMENTO DE HUANUCO

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN RAFAEL


PLAZO: 150 DIAS CALENDARIOS

PRESUPUESTO MES 1 MES 2 MES 3 MES 4 MES 5


PRECIO
DESCRIPCION UND.
S/.
CANT. PRESUP. (S/.) PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL

EQUIPOS
CAMION VOLQUETE 140-210 HP x 6 M3 hm 188.97 57.22 10,812.45 262.50 750.56 2,978.05 4,717.01 2,104.34
PROYECTOR hm 150.00 4.00 600.00 14.57 41.65 165.26 261.75 116.77
LAPTOP hm 10.00 8.00 80.00 1.94 5.55 22.03 34.90 15.57
MIRA TOPOGRAFICA hm 5.20 20.89 108.61 2.64 7.54 29.91 47.38 21.14
ANDAMIOS TIPO ACROW día 20.00 212.17 4,243.45 103.02 294.56 1,168.77 1,851.23 825.87
MEZCLADORA DE CONCRETO DE 9 -11P3 hm 11.20 276.68 3,098.80 75.23 215.11 853.50 1,351.87 603.09
MAQUINA SOLDADORA hm 12.71 90.67 1,152.37 27.98 79.99 317.40 502.73 224.28
EQUIPO DE SOLDAR hm 4.38 134.40 588.67 14.29 40.86 162.14 256.81 114.57
EQUIPO DE CORTE hm 10.00 70.40 704.00 17.09 48.87 193.90 307.12 137.01
EQUIPO DE PINTURA hm 2.50 911.47 2,278.68 55.32 158.18 627.61 994.09 443.48
GRUA TELESCOPICA hm 129.99 156.89 20,393.55 495.10 1,415.63 5,616.96 8,896.83 3,969.03
VOLQUETE DE 6M3 hm 80.00 86.13 6,890.23 167.28 478.29 1,897.76 3,005.91 1,340.99
MOTONIVELADORA DE 125 HP hm 250.00 82.28 20,570.98 499.41 1,427.95 5,665.83 8,974.23 4,003.56
RETROEXCAVADORA CAT hm 110.00 89.60 9,856.00 239.28 684.16 2,714.62 4,299.75 1,918.19
VIBRADOR DE CONCRETO 4 HP 2.40" hm 6.15 103.77 638.20 15.49 44.30 175.78 278.42 124.21
VIBRADOR DE CONCRETO 4 HP 1.50" hm 5.96 131.50 783.75 19.03 54.40 215.87 341.92 152.53
TEODOLITO hm 12.50 20.89 261.08 6.34 18.12 71.91 113.90 50.81
GPS hm 2.00 2.09 4.18 0.10 0.29 1.15 1.82 0.81
CRONOGRAMA DE UTILIZACION DE EQUIPOS

MEJORAMIENTO Y AMPLIACION DEL ESTADIO MUNICIPAL DE SAN RAFAEL - DISTRITO DE SAN RAFAEL -
PROYECTO:
PROVINCIA DE AMBO - DEPARTAMENTO DE HUANUCO

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN RAFAEL


PLAZO: 150 DIAS CALENDARIOS

PRESUPUESTO MES 1 MES 2 MES 3 MES 4 MES 5


PRECIO
DESCRIPCION UND.
S/.
CANT. PRESUP. (S/.) PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL

MULTIMETRO HE 2.00 1.60 3.20 0.08 0.22 0.88 1.40 0.62


TERROMETRO DE ALTA SENSIBILIDAD HE 10.00 1.33 13.33 0.32 0.93 3.67 5.82 2.59
MEGOMETRO DE 500 VOLT. hm 5.00 1.60 8.00 0.19 0.56 2.20 3.49 1.56
PINZA AMPERIMTRICA HE 2.00 1.60 3.20 0.08 0.22 0.88 1.40 0.62

TOTALES S/.83,092.73 S/.2,017.28 S/.5,767.95 S/.22,886.08 S/.36,249.77 S/.16,171.65


AVANCE MENSUAL 100.00% 2.43% 6.94% 27.54% 43.63% 19.46%
AVANCE MENSUAL ACUMULADO 100.00% 2.43% 9.37% 36.91% 80.54% 100.00%
CALENDARIO DE UTILIZACION DE EQUIPOS
CREACION DEL SERVICIO DE AGUA POTABLE Y DISPOSICION SANITARIA DE EXCRETAS EN LOS CENTROS POBLADOS DE FELIPE PINGLO ALVA, PALMERAS, 28 DE JULIO,
PROYECTO:
SANJA SECA, UNION LIBERTAD, ALTO SAN JUAN II Y PUENTE PIEDRA, DISTRITO DE LUYANDO - LEONCIO PRADO - HUANUCO
CLIENTE: MUNICIPALIDAD DISTRITAL DE LUYANDO
FECHA: AGOSTO - 2020
PRECIO PRESUPUESTO MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10
DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
PREPARACION DE TEMA A TRATAR hm 140.00 14.00 196.00 19.60 19.60 19.60 19.60 39.20 39.20 39.20
TEODOLITO he 6.36 50.13 318.80 63.76 63.76 63.76 63.76 63.76
COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 5.50 59.86 329.25 32.93 32.93 65.85 65.85 65.85 65.85
MEZCLADORA DE CONCRETO DE 9 - 11 P3 hm 15.00 667.44 10,011.67 1,001.17 1,001.17 1,001.17 1,001.17 2,002.33 2,002.33 2,002.33
VIBRADOR DE CONCRETO 4 HP 1.50" hm 6.50 93.12 605.28 60.53 60.53 60.53 60.53 121.06 121.06 121.06
SOLDADORA ELECTRICA MONOFASICA ALTERNA/CONTINUA350 A hm 10.00 1,045.00 10,450.00 2,090.00 2,090.00 2,090.00 2,090.00 2,090.00
WINCHA DE 30 m und 21.30 23.18 493.80 98.76 98.76 98.76 98.76 98.76

TOTALES S/.22,404.80 S/.19.60 S/.1,276.74 S/.1,276.74 S/.1,309.67 S/.1,329.27 S/.4,480.96 S/.4,318.44 S/.4,213.39 S/.2,090.00 S/.2,090.00
AVANCE MENSUAL 100.00% 0.09% 5.70% 5.70% 5.85% 5.93% 20.00% 19.27% 18.81% 9.33% 9.33%
AVANCE MENSUAL ACUMULADO 100.00% 0.09% 5.79% 11.48% 17.33% 23.26% 43.26% 62.54% 81.34% 90.67% 100.00%