PROYECTO: CONST. PAV.

EMERGENCIA NORTE
PRESUPUESTO: Bs. LOSA PLATAF. CEMENTO
AREA H25= 749.00 M2 L= 87 1110.00 Bolsas 50,012.00
AREA CUNETA H21= 57.90 M2 Ancho Calz.= 6.4
E= 0.165 M Ancho Cunt= 0.4 133.1385 16.6423125

CANTIDAD CANTIDAD
AGREGADOS FACTOR
SOLICITADA REQUERIDA UNIDAD
MAYORADO TOTAL UNIDAD CANT. PRECIO UNI. TOTAL
ARENA 0.55 133.1385 73.226175 M3 1.15 84.2101 M3 85 120.00 10,200.00
GRAVA 0.37 133.1385 49.261245 M3 1.15 56.65043 M3 57 110.00 6,270.00
GRAVILLA 0.33 133.1385 43.935705 M3 1.15 50.52606 M3 51 105.00 5,355.00
SUB-TOTAL 21,825.00
CEMENTO
CEMENTO-H25 8 123.585 988.68 BOL 1.05 1038.114 BOLSAS 1039 46.50 48,313.50
CEMENTO-H21 7 9.5535 66.8745 BOL 1.05 70.21823 BOLSAS 71 46.50 3,301.50
SUB-TOTAL 49,987.00
MANO DE OBRA
MANO DE OBRA 1.112 806.9 897.2728 M2 1 897.2728 M2 898 20.50 18,567.00

SUB-TOTAL 18,567.00
ADITIVOSP HORMIGON
ALQUITRAN TAMBOR 0.18 806.90 145.242 KG 1 0.72621 TURRIL 1 1,400.00 1,400.00
ANTISOL S BLANCO 0.16 806.90 129.104 KG 1 0.64552 TURRIL 1 2,405.00 2,405.00
ACELERANTE TAMBOR 133.14 0 LTS 1 0 TURRIL 0 5,400.00 -
PLASTIMENT HER 2 133.14 266.277 KG 1.05 1.397954 TAMBOR 2 2,100.00 4,200.00
SUB-TOTAL 8,005.00

HERRAMIENTAS COMPLEMEN
DISCO DE CORTE 0.0014 749.00 1.0486 PZA 1 1.0486 PZA 2 280.00 560.00
Rollo de Plastico de Hule PZA 1 1 700.00 700.00
SUB-TOTAL 1,260.00

MATERIALES NIVELADO DE C
BROCAL Y TAPA DE ALCANTARILL 1 4.00 4 PZA 1 4 PZA 0 850.00 -
LADRILLO P/NIVELADO DE CAMARA 24.00 0 PZA 2 0 PZA 71 5.00 355.00
LADRILLO P/TAPA CUADRADA 48.00 0 PZA 2 0 PZA 0 6.00 -
SUB-TOTAL 355.00
PLATAFORMA

SUB-TOTAL -
TOTAL Bs. 99,999.00
PROYECTO: CONST. PAV. CALLE LADO OESTE HOSPITAL CAPACACHI DISTRITO B
PRESUPUESTO Bs.
AREA TOTAL: 2018 M2
ESPESOR DE CARPETA: 12 CM
VOLUMEN TOTAL : 242.16
E= 12 CM
CANTIDAD
GREGADOS FACTOR CANTIDAD UNIDAD MAYORADO TOTAL UNIDAD CANT. PRECIO UNI. TOTAL
REQUERIDA
ARENA 0.51 243 123.93 M3 1.15 142.5195 M3 70 120.00 8,400.00
GRAVA 0.75 243 91.125 M3 1.15 104.7938 M3 53 110.00 5,830.00
GRAVILLA 0.65 243 78.975 M3 1.15 90.82125 M3 45 105.00 4,725.00
SUB-TOTAL 18,955.00
CEMENTO
CEMENTO-H25 8 243 1944 BOL 1 1944 BOL 940 57.00 53,580.00

SUB-TOTAL 53,580.00
MANO DE OBRA
MANO DE OBRA 1 243 243 M2 1 243 M2 780 20.50 15,990.00

SUB-TOTAL 15,990.00
OTROS
ALQUITRAN TAMBOR 1 1 1 TURRIL 1 1 PZA 1 1,500.00 1,500.00
ANTISOL 0.02 243 4.86 KG 1 4.86 BALDE 1 398.00 398.00

SUB-TOTAL 1,898.00
TOTAL Bs. 90,423.00
VOLUMENES DE OBRA CONTRACTULES

ITEM DESCRIPCION UNID. CANTIDAD

PROVISION DE MATERIAL GRANULAR (CAPA BASE) PARA LA CONFORMACION


1 M3 403.6
DE PLATAFORMA EN LAS CALLE ALEDAÑAS AL HOSPITAL DE CAPACACHI DIST. B

TOTAL PROYECTO S/CONTRATO REVISADO


P.U. [Bs.] TOTAL [Bs.]

65 26,234.00

26,234.00 18,955.00