DATOS DEL CONVENIO: 362-2020 AYA/VMVU/PNVR

“MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE


AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS RESUMEN DEL ESTADO FINANCIERO
NUCLEO EJECUTOR
CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - COSTO DIRECTO 2,080,898.08
DEPARTAMENTO DE AYACUCHO”
MANO DE OBRA CALIFICADA 488,262.84
MANO DE OBRA NO CALIFICADA 82,455.95
CONVENIO 362-2020 AYA/VMVU/PNVR RESPONSABLE DE CAPACITACIÓN
CUENTA BANCARIA BANCO: BANCO DE LA NACIÓN MATERIALES 1,064,573.58
COORDINADOR REGIONAL ING. PERCY MARIN ALIAGA CIP EQUIPO 12,405.15
ESPECIALISTA FINANCIERO C.P.C. INA GARCIA CPC HERRAMIENTAS 16,193.02
COORDINADOR DE SUPERVISIÓN ING. MARLON ALBERTO ALVAREZ BARRANTES CIP FLETE 417,007.54
ESPECIALISTA SOCIAL LIC. MIGUEL ROMERO CPP COSTO INDIRECTO 391,854.21
GASTOS GENERALES FIJOS Y VARIABLES 177,111.67
GASTOS NÚCLEO EJECUTOR 10,233.50
AGENTES DEL CONVENIO GASTOS FINANCIEROS 379.04
GESTOR SOCIAL KAREN MABEL SANCHEZ ROQUE DNI 46818482 RESIDENTE DE OBRA 54,680.00
ESPECIALIDAD TELF 955699990 ASISTENTE DE RESIDENTE 47,360.00
DIRECCION / EMAIL KAREN.MSR24@GMAIL.COM ASISTENTE ADMINISTRATIVO 22,930.00
RESIDENTE JOSEPH G. MELENDEZ RAMIREZ DNI 70494258 SUPERVISION 53,480.00
INGENIERIO
ESPECIALIDAD
CIVIL
CIP 197275 TELEF. GESTOR SOCIAL
25,680.00
DIRECCION / EMAIL ghandillo6@gmail.com TOTAL 2,472,752.29
SUPERVISOR DAUBIE CAMPOS PEÑA DNI 72098961 APORTES BENEFICIARIOS 286,477.81
INGENIERIO
ESPECIALIDAD
CIVIL
CIP 183342 TELEF. MONTO A TRANSFERIR AL N.E. 2,186,274.48

DIRECCION / EMAIL daubie21@gmail.com COMPONENTES


PRESIDENTE JUAN QUISPE QUINTANA DNI 42171993 COSTO DIRECTO 2,080,898.08
SECRETARIA CLEBER QUISPE MENDOZA DNI 41972637 COSTO INDIRECTO 391,854.21
NUCLEO EJECUTOR
TESORERA WALTER ROLANDO VELASQUE CCORIMANYA DNI 48491095 TOTAL 2,472,752.29
FISCAL LURGIO LUNAZCO QUISPE DNI 46821208 RESUMEN
C.D. SIN APORTE DE BENEF. 1,794,420.27
DATOS GENERALES DEL PROYECTO FECHAS IMPORTANTES COSTO INDIRECTO 391,854.21
REGION AYACUCHO FECHA FIRMA CONVENIO MONTO FINANCIADO PNVR S/. 2,186,274.48
DEPARTAMENTO AYACUCHO FECHA 1º VISITA EVALUACION
PROVINCIA HUANTA FECHA DE INICIO DE OBRA 14-06-21
DISTRITO UCHURACCAY, AYAHUANCO Y HUANTA FECHA DE PARALIZACION DE OBRA 15-07-21

C.P LLAMANNIYUQ, RUMI URMASCCA,


LOCALIDAD CHOQUEWICHQA, LAPPCCES Y FECHA DE REINICIO DE OBRA 01-09-21
VIZCACHAYOCC

REGION GEOGRAFICA SIERRA FECHA TERMINO PROGRAMADA. 10-11-21


BENEFICIARIOS DIRECTOS 75 FECHA TERMINO NUEVA PROGRAMADA. 28-12-21
CATEGORIA AMBIENTAL 3 TIEMPO DE EJECUCION 150
DESEMBOLSOS
FECHA APERTURA DE CUENTA
FECHA COMP. DE PAGO
FICHA TECNICA DEL CONVENIO: 362-2020 AYA/VMVU/PNVR
“MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO
PROYECTO: POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”

UBICACIÓN
Departamento : AYACUCHO
Provincia : HUANTA
Distrito : UCHURACCAY, AYAHUANCO Y HUANTA
CP-Localidades : 362-2020 AYA/VMVU/PNVR
DATOS DEL PROYECTO
Convenio : 362-2020 AYA/VMVU/PNVR
Monto Financiado (PNVR) : 2,186,274.48
Monto Financiado modificado (PNVR) :
Desembolso Efectuado a la fecha : 2,186,274.48
Desembolso : 2,186,274.48
N° Beneficiarios : 75
DATOS DE EJECUCIÓN:
Fecha de Inicio de Obra : 6/14/2021
Fecha de Paralizacion de Obra 7/15/2021
Fecha de Reinicio de Obra : 9/1/2021
Plazo de Ejecución : 150 dias calendario
Fecha de Término de Obra : 11/10/2021
Fecha de Nuevo Término de Obra : 12/28/2021
Ejecución Financiera : 15.95%

INFORMACION RELEVANTE

ESTADO SITUACIONAL A LA FECHA


75 VIV. # VIVIENDAS HITOS
C.P LLAMANNIYUQ, RUMI URMASCCA, 75 VIV. MOVIMIENTO DE TIERRA
CHOQUEWICHQA, LAPPCCES Y
VIZCACHAYOCC

DEL RESIDENTE:
LOS TRABAJOS SE VIENEN EJECUTANDO CON ALGUNAS DIFICULTADES YA QUE LAS LLUVIAS NO NOS DEJAN AVANZAR, TENEMOS DIAS QUE NO SE AVANZA POR EL FACTOR
CLIMATICO, AHORA LAS LLUVIAS NOS JUEGAN EN CONTRA PARA PODER AVANZAR SEGÚN LO REPROGRAMADO.

DEL SUPERVISOR:
OBSERVACIONES

ACCIONES ADOPTADAS 1.- ANALISIS DEL ASPECTO TECNICO:


A.- AVANCE FÍSICO ACUMULADO (*) 40.03%
B.- MONTO VALORIZADO : 833,016.15
C.- ESTADO DE LA OBRA : EN EJECUCIÓN
D.- FECHA DE INICIO : 6/14/2021
E.- FECHA DE PARALIZACION 7/15/2021
F.- FECHA DE REINICIO 9/1/2021
G.- PLAZO DE EJECUCIÓN PROGR. D.C.: 150 Dias
H.- FECHA DE TERM. PROGRAMADA : 11/10/2021
I.-1ra AMPLIACION DE PLAZO SOLICIT. 0 Dias
J.- FECHA DE TERM. REPROGRAMADA 01: 11/10/2021
K.- 2da AMPLIACION DE PLAZO SOLICIT. 48 Dias
L.- FECHA DE TERM. REPROGRAMADA 02: 12/28/2021
N.- 3da AMPLIACION DE PLAZO SOLICIT.
M.- FECHA DE TERM. REPROGRAMADA 03: 12/28/2021
2.- ANALISIS DEL ASPECTO ECONOMICO:
A.- AVANCE FINANCIERO ACUMULADO : 15.95%
B.- PRESUPUESTO DE OBRA : 2,472,752.29
C.- PRESUPUESTO DE OBRA MODIFICADO : 2,472,752.29
D.- AMPLIACIONES PRESUPUESTALES :
E.- TOTAL DESEMBOLSADO ORIGINAL : 2,186,274.48
F.- TOTAL DESEMBOLSO MODIFICADO: 2,186,274.48
G.- GASTO TOTAL EFECTUADO : 0.00
ESTADO SITUACIONAL DE EJECUCIÓN DE LOS PROYECTOS - REPORTE SEMANAL ACUMULADO

FECHA INICIAL NOMBRE DEL


Código FECHA FINAL DEL REPORTE DE LA COORDINADO TIPO DE
PNVR DEL REPORTE SEMANA R REGIONAL N° DE CONVENIO NOMBRE DEL NÚCLEO EJECUTOR REGIÓN PROVINCIA DISTRITO VIVIENDA
DE LA SEMANA TÉCNICO

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 DISTRITO DE HUANTA; CENTROS UCHURACCAY,
C-362 6/14/2021 6/19/2021 AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-362 6/21/2021 6/26/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 DISTRITO DE HUANTA; CENTROS UCHURACCAY,
C-362 6/28/2021 7/3/2021 AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-362 7/5/2021 7/10/2021 AYA/VMVU/PNVR DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA AYAHUANCO Y HUANTA LADRILLO
POBLADOS CHOQEWICHQA,
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-363 7/12/2021 7/17/2021 AYA/VMVU/PNVR DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA AYAHUANCO Y HUANTA LADRILLO
POBLADOS CHOQEWICHQA,
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
C-363 9/1/2021 9/5/2021 362-2020 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA UCHURACCAY, LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-363 9/6/2021 9/12/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-363 9/13/2021 9/19/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
C-364 9/20/2021 9/26/2021 362-2020 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA UCHURACCAY, LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-365 9/27/2021 10/2/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-366 10/4/2021 10/9/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-366 10/11/2021 10/16/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-366 10/18/2021 10/23/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”

“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-366 10/25/2021 10/30/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
ACIONAL DE EJECUCIÓN DE LOS PROYECTOS - REPORTE SEMANAL ACUMULADO DEL: 28/06/20221

MONTO APROBADO SEGÚN EXPEDIENTE TÉCNICO


NÚMERO
DE NÚMERO DE NÚMERO DE VIVIENDAS MONTO TOTAL DE MONTO TOTAL DE
VIVIENDAS VIVIENDAS
SEGÚN DEDUCIDAS RESULTANTE LUEGO DE DESEMBOLSO, AUTORIZADO DESEMBOLSO, AUTORIZADO
EXPEDIENT ACUMULADAS DEDUCIR POR EL PNVR POR EL PNVR MODIFICADO COSTO
COSTO DIRECTO INDIRECTO TOTAL FINANCIADO PNVR APORTE BENEF. TOTAL
E TÉCNICO

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29


75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29

75 0 75 S/2,186,274.48 S/2,080,898.08 S/391,854.21 S/2,472,752.29 S/2,186,274.48 S/286,477.81 S/2,472,752.29


MONTO MODIFICADO SEGÚN RD 183-2020

COSTO DIRECTO COSTO INDIRECTO TOTAL FINANCIADO PNVR APORTE BENEF. TOTAL

S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00

S/0.00 S/1.00 S/1.00

S/0.00 S/1.00 S/1.00

S/0.00 S/1.00 S/1.00

S/0.00 S/1.00 S/1.00

S/0.00 S/2.00 S/2.00

S/0.00 S/3.00 S/3.00

S/0.00 S/4.00 S/4.00

S/0.00 S/4.00 S/4.00


S/0.00 S/4.00 S/4.00

S/0.00 S/4.00 S/4.00


AL: 7/3/2021

PROCEDIMIENTO OBLIGATORIO PARA INICIO DE LOS


TRABAJOS MOVIMIENTO DE TIERRAS CONCRETO SIMPLE

VALOR.
N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. %

6 S/34,198.97 S/2,775.19 8.11% 20 S/47,132.00 S/12,568.54 26.67% 0.0 113,429.72 - -

54 S/34,198.97 S/24,401.89 71.35% 48 S/47,132.00 S/30,296.55 64.28% 0.6 113,429.72 935.68 0.82%

1 S/34,198.97 S/293.21 0.86% -2 S/47,132.00 -S/1,388.92 -2.95% 3.2 113,429.72 4,890.02 4.31%

0 S/34,198.97 S/146.60 0.43% 22 S/47,132.00 S/13,883.62 29.46% 1.6 113,429.72 2,445.01 2.16%

6 S/34,198.97 S/2,945.75 8.61% 10 S/47,132.00 S/6,003.42 12.74% 3.2 113,429.72 4,878.37 4.30%

0 S/34,198.97 S/0.00 - 11 S/47,132.00 S/6,879.59 14.60% 4.3 113,429.72 6,437.38 5.68%

24 S/34,198.97 S/10,845.85 31.71% 8 S/47,132.00 S/4,828.03 10.24% 0.0 113,429.72 - -

36 S/34,198.97 S/16,187.58 47.33% 0 S/47,132.00 - 0.0 113,429.72 - -

6 S/34,198.97 S/2,514.60 7.35% 0 S/47,132.00 - 0.0 113,429.72 - -

1 S/34,198.97 S/385.44 1.13% 0 S/47,132.00 - 4.9 113,430.72 7,431.14 6.55%

7 S/34,198.97 S/3,340.47 9.77% 0 S/47,132.00 - 13.3 113,431.72 20,155.93 17.77%

0 S/34,198.97 S/0.00 - 0 S/47,132.00 - 1.9 113,431.72 2,854.48 2.52%


22 S/34,198.97 S/9,842.97 28.78% 0 S/47,132.00 - 5.2 113,431.72 7,842.61 6.91%

16 S/34,198.97 S/7,431.14 21.73% 0 S/47,132.00 - 0.0 113,431.72 - -


CONCRETO ARMADO TIJERALES Y RETICULADOS COBERTURAS CIELO RASOS

VALOR. VALOR. VALOR.


N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. ACUM. %

0.0 235,266.93 - - 142,442.82 - - 126,887.49 - - 65,547.75 - -

2.6 235,266.93 8,046.72 3.42% 142,442.82 - - 126,887.49 - 65,547.75 -

1.0 235,266.93 3,218.69 1.37% 142,442.82 - - 126,887.49 - 65,547.75 -

0.5 235,266.93 1,609.34 0.68% 142,442.82 - - 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 - - 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 - - 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 - - 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 - - 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 - - 126,887.49 - 65,547.75 -

0.9 235,266.93 2,854.48 1.21% 142,442.82 - - 126,887.49 - 65,547.75 -

2.5 235,266.93 7,842.61 3.33% 142,442.82 1.00 0.00% 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 1.00 0.00% 126,887.49 - 65,547.75 -


1.8 235,266.93 5,640.50 2.40% 142,442.82 1.00 0.00% 126,887.49 - 65,547.75 -

0.0 235,266.93 - - 142,442.82 1.00 0.00% 126,887.49 - 65,547.75 -


MUROS REVOQUES ENLUCIDO DE YESO PISO VEREDAS

VALOR. VALOR.
N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. VALOR. ACUM. %

390,033.64 - - 1,443.66 - - 102,443.80 - - 63,341.71 - - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 57,204.94 14.67% 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -


390,033.64 - - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -

390,033.64 - - 1,443.66 - 102,443.80 - 63,341.71 - 7,971.06 -


ZOCALOS Y CONTRAZOCALOS PUERTAS VENTANAS INSTALACIONES ELECTRICAS EVACUACIÓN AGUAS PLUVIALES MITIGACIÓN DEL IMPACTO AMBIENTAL Y LIMPIEZA

VALOR. VALOR. VALOR. VALOR.


N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN.

38,915.95 - - 106,459.50 77,235.75 30,551.25 49,812.29 4

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 4

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 0

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 0

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 0

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 363

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 593

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 609

38,915.95 - 106,459.50 77,235.75 30,551.25 49,812.29 459

38,915.95 2,258.25 5.80% 106,459.50 77,235.75 30,551.25 49,812.29 9

38,915.95 - - 106,459.50 77,235.75 30,551.25 49,812.29 0

38,915.95 - - 106,459.50 77,235.75 30,551.25 49,812.29 0


38,915.95 - - 106,459.50 77,235.75 30,551.25 49,812.29 127

38,915.95 - - 106,459.50 77,235.75 30,551.25 49,812.29 0


MITIGACIÓN DEL IMPACTO AMBIENTAL Y LIMPIEZA ACARREOS FLETES Y TRANSPORTE

AUTORIZACION N° VALOR
01 ACUMULADO DEVOLUCION AUTORIZACION N°
PRESUP. VALOR. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % VALOR. ACUMULADA ACTUAL % ACUMULADA 02
ACTUAL

10,258.50 478.73 4.67% 20,517.75 - - 417,007.54 - - 15,822.46 0.76% S/0.00 S/0.00

10,258.50 478.73 4.67% 20,517.75 - 5 417,007.54 27,298.67 6.55% 91,458.24 4.40% S/0.00 S/0.00

10,258.50 - - 20,517.75 - 10 417,007.54 55,829.71 13.39% 62,842.70 3.02% S/0.00 S/0.00

10,258.50 - - 20,517.75 - 5 417,007.54 30,389.21 7.29% 48,473.79 2.33% S/0.00 S/0.00

10,258.50 - - 20,517.75 - 7 417,007.54 39,214.05 9.40% 53,041.59 2.55% S/0.00 S/0.00

10,258.50 49,711.99 484.59% 20,517.75 - 8 417,007.54 42,943.55 10.30% 105,972.50 5.09% S/0.00 S/0.00

10,258.50 81,107.99 790.64% 20,517.75 - 0 417,007.54 - - 96,781.88 4.65% S/0.00 S/0.00

10,258.50 83,345.87 812.46% 20,517.75 - 0 417,007.54 0.02 0.00% 99,533.47 4.78% S/0.00 S/0.00

10,258.50 62,842.70 612.59% 20,517.75 - 0 417,007.54 0.02 0.00% 65,357.32 3.14% S/0.00 S/0.00

10,258.50 1,231.02 12.00% 20,517.75 - 0 417,007.54 - - 71,365.27 3.43% S/348,712.45 S/348,712.45 S/348,712.45

10,258.50 - - 20,517.75 - 0 417,007.54 1.00 0.00% 31,341.00 1.51% S/348,713.45 S/348,713.45 S/348,713.45

10,258.50 - - 20,517.75 - 0 417,007.54 1.00 0.00% 2,856.48 0.14% S/348,713.45 S/348,713.45 S/348,713.45
10,258.50 17,327.86 168.91% 20,517.75 - 0 417,007.54 1.00 0.00% 40,655.93 1.95% S/348,713.45 S/348,713.45 S/348,713.45

10,258.50 - - 20,517.75 - 0 417,007.54 1.00 0.00% 7,433.14 0.36% S/348,713.45 S/348,713.45 S/348,713.45
RETIROS AUTORIZADOS Y DEVOLUCIONES

VALOR AUTORIZACION VALOR


ACUMULADO DEVOLUCION N° 03 ACUMULADO DEVOLUCION AUTORIZACION N° VALOR ACUMULADO DEVOLUCION AUTORIZACION N° VALOR ACUMULADO DEVOLUCION AUTORIZACION N° VALOR ACUMULADO DEVOLUCION
ACUMULADA ACUMULADA 04 ACTUAL ACUMULADA 05 ACTUAL ACUMULADA 06 ACTUAL ACUMULADA
ACTUAL ACTUAL

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45

S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45

S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45
S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45

S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45
EJECUCIÓN FINANCIERA (APORTE PNVR)

OBSERVACIONES DEL
AUTORIZACION N° AUTORIZACION N° VALOR. VALOR. COORDINADOR
AUTORIZACION N° VALOR ACUMULADO DEVOLUCION 08 VALOR ACUMULADO DEVOLUCION 09 VALOR ACUMULADO DEVOLUCION ACUMULADA ACUMULADA REGIONAL TÉCNICO
07 ACTUAL ACUMULADA ACTUAL ACUMULADA ACTUAL ACUMULADA %
ANTERIOR ACTUAL

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 1.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 0.00 0.00 0.00%

S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 1.00 348,712.45 15.95%

S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 2.00 348,713.45 15.95%

S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 2.00 348,713.45 15.95%


S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 2.00 348,713.45 15.95%

S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 2.00 348,713.45 15.95%


OBSERVACIONES DEL CON DOCUMENTO
COORDINADOR SUSTENTATORIO DEL
GENERAL DEDUCTIVO
FORMATO N° 26

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 03

PROYECTO: “MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”

CONVENIO N°: 362-2020 AYA/VMVU/PNVR S/2,080,898.08


RESIDENTE: Ing. JOSEPH G. MELENDEZ RAMIREZ SUPERVISOR: Ing. DAUBIE CAMPOS PEÑA
FECHA INICIO: 9/1/2021

Mes JUNIO JULIO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE


N° PARTIDA PRESUPUESTO
Semana 1 2 3A 3B 4 5 6 7 8 9 10A 10B 11 12 13 14 15 16 17 18 19A 19B 20 21 22 23
Dia 14-19 21-26 28-30 1-3 5-10 12-14 1-4 6-11 13-18 20-25 27-30 1-2 4-9 11-16 18-23 25-31 1-6 8-13 15-20 22-27 29-30 1-4 6-11 13-18 20-25 27-28
01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 34,198.970 3593.04 5852.74 3875.88 2485.13 1478.57 1171.66 1192.99 1664.51 1704.90 1321.61 943.05 239.34 717.29 717.29 717.29 717.29 717.29 717.29 717.29 717.29 239.10 478.19 717.29 717.29 717.29 68.07
PLAN PARA LA VIGILANCIA, PREVENCION Y CONTROL DE
01.01 6,663.00 352.54 512.54 219.66 260.88 288.54 192.36 192.36 288.54 288.54 288.54 192.36 96.42 288.54 288.54 288.54 288.54 288.54 288.54 288.54 288.54 96.18 192.36 288.54 288.54 288.54 27.24
COVID-19
655.00 Programado 30.57 30.57 13.10 17.47 30.57 20.38 20.38 30.57 30.57 30.57 20.38 10.43 30.57 30.57 30.57 30.57 30.57 30.57 30.57 30.57 10.19 20.38 30.57 30.57 30.57 2.67
01.01.01 LIMPIEZA Y DESINFECCIÓN DEL CENTRO DE TRABAJO
Ejecutado 30.57 543.65 1.09 1.09 - - - - - - - - - - - - - - - - - - - - -
EVALUACIÓN DE LAS CONDICIONES DE SALUD DEL 480.00 Programado 64.00 224.00 96.00 96.00 - - - - - - - - - - - - - - - - - - - - -
01.01.02 TRABAJADOR PREVIO AL INICIO A OBRA Ejecutado 422.40 0.80 0.80 - - - - - - - - - - - - - - - - - - - - -
1,658.00 Programado 77.37 77.37 33.16 44.21 77.37 51.58 51.58 77.37 77.37 77.37 51.58 25.79 77.37 77.37 77.37 77.37 77.37 77.37 77.37 77.37 25.79 51.58 77.37 77.37 77.37 7.37
01.01.03 LAVADO Y DESINFECCIÓN DE MANOS
Ejecutado 77.37 1,376.14 2.76 2.76 - - - - - - - - - - - - - - - - - - - - -
SENSIBILIZACIÓN DE LA PREVENCIÓN DEL CONTAGIO EN EL 3,870.00 Programado 180.60 180.60 77.40 103.20 180.60 120.40 120.40 180.60 180.60 180.60 120.40 60.20 180.60 180.60 180.60 180.60 180.60 180.60 180.60 180.60 60.20 120.40 180.60 180.60 180.60 17.20
01.01.04 CENTRO DE TRABAJO Ejecutado 180.60 3,212.10 6.45 6.45 - - - - - - - - - - - - - - - - - - - - -
PROCEDIMIENTO OBLIGATORIO PARA INICIO DE LOS
1.02 9,187.50 428.75 428.75 183.75 245.00 428.75 285.83 285.83 428.75 428.75 428.75 285.83 142.92 428.75 428.75 428.75 428.75 428.75 428.75 428.75 428.75 142.92 285.83 428.75 428.75 428.75 40.83
TRABAJOS
9,187.50 Programado 428.75 428.75 183.75 245.00 428.75 285.83 285.83 428.75 428.75 428.75 285.83 142.92 428.75 428.75 428.75 428.75 428.75 428.75 428.75 428.75 142.92 285.83 428.75 428.75 428.75 40.83
01.02.01 PROCESO PARA INICIO DEL TRABAJO
Ejecutado 428.75 7,625.63 15.31 15.31 - - - - - - - - - - - - - - - - - - - - -
1.03 TRABAJOS PRELIMINARES 597.34 - 597.34 - - - - - - - - - - - - - - - - - - - - - - - -
597.34 Programado 597.34 - - - - - - - - - - - - - - - - - - - - -
01.03.01 CARTEL DE OBRA DE 4.00 X 2.50
Ejecutado 597.34 - - - - - - - - - - - - - - - - - - - - -
1.04 TRAZO NIVELES Y REPLANTEO PRELIMINAR 4,025.38 1,006.35 1,811.42 1,006.35 201.27 - - - - - - - - - - - - - - - - - - - - - -
4,025.38 Programado 1,006.35 1,811.42 1,006.35 201.27 - - - - - - - - - - - - - - - - - - - - -
01.04.01 TRAZOS, NIVELES (REPLANTEO PRELIMINAR)
Ejecutado 1,073.43 2,468.90 - - - - - - - - - - - - - - - - - - - - - -
1.05 SEGURIDAD Y SALUD 13,725.75 1,805.41 2,502.69 2,466.13 1,777.98 761.28 693.46 714.79 947.22 987.61 604.32 464.86 - - - - - - - - - - - - - - -
7,391.25 Programado 278.92 976.20 976.20 278.92 697.29 650.80 650.80 883.23 929.72 604.32 464.86 - - - - - - - - - - - - - - -
01.05.01 EQUIPO DE SEGURIDAD INDIVIDUAL
Ejecutado 923.91 5,580.89 - 0.25 - 0.25 - - - - - - - - - - - - - - - - - - - - - -
2,236.50 Programado 559.13 559.13 559.13 559.13 - - - - - - - - - - - - - - - - - - - - -
01.05.02 EQUIPO DE SEGURIDAD COLECTIVA
Ejecutado 1,968.12 - - - - - - - - - - - - - - - - - - - - - - - -
484.50 Programado 63.99 63.99 27.42 36.57 63.99 42.66 63.99 63.99 57.90 - - - - - - - - - - - - - - - - -
01.05.03 SEÑALIZACION TEMPORAL DE SEGURIDAD
Ejecutado 60.56 365.83 - 0.02 - 0.02 - - - - - - - - - - - - - - - - - - - - - -
3,613.50 Programado 903.38 903.38 903.38 903.38 - - - - - - - - - - - - - - - - - - - - -
01.05.04 CAPACITACION EN SALUD Y SEGURIDAD
Ejecutado - 240.90 120.45 120.45 144.54 96.36 - 289.08 240.90 289.08 289.08 96.36 144.54 240.90 240.90 240.90 - - - - - - - - - -
02 MOVIMIENTO DE TIERRAS 47,132.00 6,873.42 6,873.42 2,945.75 1,963.83 2,945.75 1,963.83 3,600.36 5,678.34 5,553.97 5,392.87 3,340.47 - - - - - - - - - - - - - - -
02.01 EXCAVACIONES 47,132.00 6,873.42 6,873.42 2,945.75 1,963.83 2,945.75 1,963.83 3,600.36 5,678.34 5,553.97 5,392.87 3,340.47 - - - - - - - - - - - - - - -
CORTE Y EXPLANACIÒN DE TERRENO NORMAL MANUAL 35,557.64 Programado 5,185.49 5,185.49 2,222.35 1,481.57 2,222.35 1,481.57 2,716.21 4,352.11 4,190.06 4,068.53 2,451.92 - - - - - - - - - - - - - - -
02.01.01
(APORTE) Ejecutado 9,482.04 21,808.69 - - - - - - - - - - - - - - - - -
11,574.36 Programado 1,687.93 1,687.93 723.40 482.26 723.40 482.26 884.15 1,326.23 1,363.91 1,324.34 888.55 - - - - - - - - - - - - - - -
02.01.02 EXCAVACION DE ZANJA HASTA H=1.00m (APORTE)
Ejecutado 3,086.50 8,487.86 - 694.46 - 694.46 - - - - - - - - - - - - - - - - - - - - -
03 OBRAS DE CONCRETO SIMPLE 113,429.72 - 3,711.04 5,311.15 8,572.48 10,845.85 7,270.28 15,114.97 17,757.88 17,838.38 17,164.72 8,448.26 1,394.71 - - - - - - - - - - - - -
03.01 CIMIENTOS 60,180.90 - 3,711.04 4,738.07 4,435.55 6,094.05 3,720.35 8,320.85 7,566.70 7,647.20 6,973.54 5,578.83 1,394.71 - - - - - - - - - - - - -
CIMIENTO CORRIDO DE CONCRETO CICLOPEO MEZCLA 46,148.45 Programado 2,051.04 2,051.04 2,051.04 3,076.56 2,051.04 6,973.54 6,973.54 6,973.54 6,973.54 5,578.83 1,394.71 - - - - - - - - - - - - -
03.01.01 CEMENTO-HORMIGON 1:10 + 50% P. G. Ejecutado - - 2,461.25 9,229.69 5,537.81 6,153.13 4,307.19 6,768.44 1,845.94 615.31 - - - - - - - - - - - - - -
7,702.70 Programado 1,027.03 2,054.05 1,540.54 1,540.54 684.68 456.46 171.17 228.23 - - - - - - - - - - - - - - - - -
03.01.02 SUMINISTRO DE PIEDRA MEDIANA (APORTE)
Ejecutado - 513.70 1,643.24 1,643.24 1,097.16 1,129.73 - - 1,232.43 - - - - - - - - - - - - - - - - -
NIVELACION RELLENO Y APISONADO DE CAMA DE PIEDRA 6,329.75 Programado 632.98 632.98 843.97 1,476.94 984.63 890.85 421.98 445.43 - - - - - - - - - - - - - - - - -
03.01.03
MEDIANA ( APORTE) Ejecutado 421.98 801.77 801.77 928.36 - - 1,012.76 - - - - - - - - - - - - - - - - -
03.02 SOBRECIMIENTOS 53,248.82 - - 573.08 4,136.93 4,751.81 3,549.92 6,794.12 10,191.18 10,191.18 10,191.18 2,869.42 - - - - - - - - - - - - - - -
SOBRECIMIENTOS MEZCLA CEMENTO-HORMIGON 1:8 + 30% 24,595.07 Programado 1,844.63 2,459.51 1,639.67 2,869.42 4,304.14 4,304.14 4,304.14 2,869.42 - - - - - - - - - - - - - - -
03.02.01
PM Ejecutado - 327.93 4,919.01 3,935.21 1,639.67 1,639.67 1,967.61 327.93 2,951.41 1,967.61 1,967.61 - 1,967.61 - - - - - - - - - -
28,653.75 Programado 573.08 2,292.30 2,292.30 1,910.25 3,924.70 5,887.04 5,887.04 5,887.04 - - - - - - - - - - - - - - - -
03.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO h=0.35 m
Ejecutado - - - 382.05 5,730.75 4,584.60 1,910.25 1,910.25 2,292.30 382.05 3,438.45 2,292.30 2,292.30 - 2,292.30 - - - - - - - - - -
04 CONCRETO ARMADO 235,266.93 - - 2,514.60 2,514.60 4,878.37 4,364.99 10,765.79 20,044.08 25,791.66 28,347.19 10,982.56 9,173.37 27,520.12 27,520.12 27,520.12 19,553.52 13,775.84 - - - - - - - - -
04.01 COLUMNAS 126,926.73 - - 2,514.60 2,514.60 4,878.37 4,364.99 10,765.79 16,148.68 16,148.68 16,148.68 1,850.39 4,581.43 13,744.28 13,744.28 13,744.28 5,777.68 - - - - - - - - - -
33,382.18 Programado 1,112.74 1,112.74 1,669.11 1,669.11 1,669.11 1,112.74 1,925.89 5,777.68 5,777.68 5,777.68 5,777.68 - - - - - - - - - -
04.01.01 CONCRETO COLUMNAS f'c=175 kg/cm2
Ejecutado - - - 4,450.96 890.19 445.10 - 890.19 3,560.77 1,335.29 2,225.48 - - - - - - - - - -
33,194.15 Programado 1,106.47 737.65 737.65 1,106.47 1,106.47 1,106.47 737.65 2,655.53 7,966.60 7,966.60 7,966.60 - - - - - - - - - -
04.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS
Ejecutado - - - - 4,425.89 885.18 442.59 - 885.18 3,540.71 1,327.77 2,212.94 - - - - - - - - - -
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 PARA 60,350.40 Programado 2,514.60 2,514.60 3,771.90 2,514.60 8,915.40 13,373.10 13,373.10 13,373.10 - - - - - - - - - - - - - - - -
04.01.03 COLUMNAS Ejecutado 8,046.72 1,609.34 1,609.34 8,851.39 6,437.38 3,218.69 6,437.38 6,437.38 5,632.70 - - - - - - - - - - - - - - - -
04.02 VIGAS 108,340.19 - - - - - - - 3,895.40 9,642.98 12,198.51 9,132.17 4,591.95 13,775.84 13,775.84 13,775.84 13,775.84 13,775.84 - - - - - - - - -
35,444.62 Programado - - - 2,835.57 4,253.35 3,308.16 1,565.47 4,696.41 4,696.41 4,696.41 4,696.41 4,696.41 - - - - - - - - -
04.02.01 CONCRETO VIGAS f'c=175 kg/cm2
Ejecutado - - - - - - 1,890.38 2,835.57 - - - - - - - - - -
43,393.57 Programado - - 1,928.60 3,857.21 4,339.36 3,857.21 1,838.20 5,514.60 5,514.60 5,514.60 5,514.60 5,514.60 - - - - - - - - -
04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS
Ejecutado - - - - - - 578.58 1,735.74 3,471.49 - - - - - - - - - -
29,502.00 Programado - - 1,966.80 2,950.20 3,605.80 1,966.80 1,188.28 3,564.83 3,564.83 3,564.83 3,564.83 3,564.83 - - - - - - - - -
04.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 PARA VIGAS
Ejecutado - - - - - 1,573.44 393.36 786.72 3,933.60 3,540.24 4,720.32 - - - - - - - - - -
05 TIJERALES Y RETICULADOS 142,442.82 - - - - - - - - - - 7,842.61 20,168.60 23,527.82 23,527.82 23,527.82 8,232.46 15,826.98 13,295.47 6,493.23 - - - - -
90,699.00 Programado - - - - - 5,038.83 11,757.28 15,116.50 15,116.50 15,116.50 5,038.83 10,077.67 8,398.06 5,038.83 - - - - - -
05.01. TIJERAL DE MADERA DE 2"X4"
Ejecutado - - - - - - - - - - - - - - - - - - - - -
46,002.32 Programado - - - - - - 2,555.68 7,667.05 7,667.05 7,667.05 7,667.05 2,555.68 5,111.37 4,259.47 851.89 - - - - - -
05.02. CORREAS DE MADERA 2"X2"
Ejecutado - - - - - - - - - - - - - - - - - - - - -
5,741.50 Programado - - - - - - 248.09 744.27 744.27 744.27 744.27 637.94 637.94 637.94 602.50 - - - - -
05.03. FRISO DE MADERA DE 1 1/2"X2 1/2"
Ejecutado - - - - - - - - - - - - - - - - - - - - -
06 COBERTURA 126,887.49 - - - - - - - - - - - 5,640.50 16,481.01 16,481.01 16,481.01 16,481.01 16,481.01 16,481.01 15,918.17 6,442.79 - - - - -
118,077.83 Programado - - - - - - 5,102.13 15,306.39 15,306.39 15,306.39 15,306.39 15,306.39 15,306.39 15,306.39 5,831.00 - - - - -
06.01. COBERTURA DE PLANCHA CORRUGADA GALVANIZADA
Ejecutado - - - - - - - - - - - - - - - - - - - -
8,809.65 Programado - - - - - - 538.37 1,174.62 1,174.62 1,174.62 1,174.62 1,174.62 1,174.62 611.78 611.78 - - - - -
06.02. CUMBRERA CALAMINA 0.30 mm, 11 CANALES INCL PINTADO
Ejecutado - - - - - - - - - - - - - - - - - - - -
07 CIELO RASOS 65,547.75 - - - - - - - - - - - - - - - - 13,109.55 13,109.55 13,109.55 13,109.55 13,109.55 - - - - -
CIELORASO CON PLACA DE YESO LAMINADO CON VINYL Y 65,547.75 Programado - - - - - - - - - - - 13,109.55 13,109.55 13,109.55 13,109.55 13,109.55 - - - - -
07.01. FOIL DE ALUMINIO 0.61x0.61 e=6MM / INL. ACCESORIOS E
INSTALACIÓN Ejecutado - - - - - - - - - - - - - - - - - - - - -
08 MUROS 390,033.64 - - - - - 5,417.13 5,417.13 47,399.92 47,399.92 47,399.92 31,599.95 15,799.97 47,399.92 47,399.92 47,399.92 47,399.92 - - - - - - - -
MURO DE LADRILLO TIPO PANDERETA MEDIDAS SEGÚN 319,789.11 Programado 4,441.52 4,441.52 38,863.26 38,863.26 38,863.26 25,908.84 12,954.42 38,863.26 38,863.26 38,863.26 38,863.26 - - - - - - - -
08.01.
PLANO Ejecutado - - 42,638.55 38,374.69 42,638.55 4,263.85 12,791.56 21,319.27 12,791.56 25,583.13 - - - - - - - -
SUMINISTRO E INSTALACION DE POLIESTIRENO DE 1" 28,996.26 Programado 402.73 402.73 3,523.85 3,523.85 3,523.85 2,349.23 1,174.62 3,523.85 3,523.85 3,523.85 3,523.85 - - - - - - - -
08.02.
DENSIDAD 10 Ejecutado - - 3,866.17 3,479.55 3,866.17 386.62 1,159.85 1,933.08 1,159.85 2,319.70 - - - - - - - -
41,248.29 Programado 572.89 572.89 5,012.81 5,012.81 5,012.81 3,341.88 1,670.94 5,012.81 5,012.81 5,012.81 5,012.81 - - - - - - - -
08.03. BRUÑAS EN MUROS DE LADRILLO
Ejecutado - - - 5,499.77 4,949.79 5,499.77 549.98 1,649.93 2,749.89 1,649.93 3,299.86 - - - - - - - - - -
09 REVOQUES 1,443.66 - - - - - - - - - - - - - - - - - 721.83 721.83 - - - - - - -
BOTA AGUA EN VANO DE VENTANA CON CORTA GOTERA. CON 1,443.66 Programado - - - - - - - - - - - 721.83 721.83 - - - - - - -
09.01. MORTERO 1:4 E0 1.5 CM Ejecutado - - - - - - - - - - - - - - - - - - - - -
10 ENLUCIDO DE YESO 102,443.80 - - - - - - - - - - - 798.21 1,862.50 13,303.57 13,303.57 17,828.05 18,582.13 18,582.13 10,954.75 7,228.91
79,821.40 Programado - - - - - - 798.21 1,862.50 13,303.57 13,303.57 13,303.57 13,303.57 13,303.57 5,676.19 4,966.67
10.01. ENLUCIDO DE YESO EN MURO DE LADRILLO
Ejecutado - - - - - - - - - - - - - - - -
22,622.40 Programado - - - - - - - - - - - 4,524.48 5,278.56 5,278.56 5,278.56 2,262.24
10.02. DERRAMES DE VANOS CON YESO E=1.5CM
Ejecutado - - - - - - - - - - - - - - - - - - - - -
11 PISO 63,341.71 - - - - - - - - - - 15,457.15 15,457.15 14,222.10 14,222.10 3,983.21 - - - - -
BASE DE TIERRA MATERIAL PROPIO 7,029.68 Programado - - - - - 1,802.48 1,802.48 1,441.99 1,441.99 540.74 - - - - -
11.01.
COMPACTADO/NIVELADO E= 10 CM
FORMATO N° 26

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 03

PROYECTO: “MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”

CONVENIO N°: 362-2020 AYA/VMVU/PNVR S/2,080,898.08


RESIDENTE: Ing. JOSEPH G. MELENDEZ RAMIREZ SUPERVISOR: Ing. DAUBIE CAMPOS PEÑA
FECHA INICIO: 9/1/2021

Mes JUNIO JULIO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE


N° PARTIDA PRESUPUESTO
Semana 1 2 3A 3B 4 5 6 7 8 9 10A 10B 11 12 13 14 15 16 17 18 19A 19B 20 21 22 23
BASE DE TIERRA MATERIAL PROPIO Dia 14-19 21-26 28-30 1-3 5-10 12-14 1-4 6-11 13-18 20-25 27-30 1-2 4-9 11-16 18-23 25-31 1-6 8-13 15-20 22-27 29-30 1-4 6-11 13-18 20-25 27-28
11.01.
COMPACTADO/NIVELADO E= 10 CM Ejecutado - - - - - - - - - - - - - - -
11,984.78 Programado - - - - - 2,396.96 2,396.96 2,929.61 2,929.61 1,331.64 - - - - -
11.02. ACERO DE TEMPERATURA
Ejecutado - - - - - - - - - - - - - - -
PISO DE CEMENTO PULIDO E:4" ACAB. CON OCRE INC. 44,327.25 Programado - - - - - 11,257.71 11,257.71 9,850.50 9,850.50 2,110.82 - - - - -
11.03. BRUÑADO Ejecutado - - - - - - - - - - - - - - - - - - - -
12 VEREDAS 7,971.06 - - - - - - - - - - - 47.10 1,613.05 1,613.05 460.24 1,152.81 3,084.80 - - -
NIVELACIÓN, RELLENO Y APISONADO INTERIOR C/MAT 847.80 Programado - - - - - - 47.10 188.40 188.40 62.80 125.60 235.50 - - -
12.01.
PROPIO (APORTE) Ejecutado - - - - - - - - - - - - -
VEREDA DE CONCRETO SIMPLE F'C=140 KG/CM2 E=10 CM 5,961.60 Programado - - - - - - - 1,192.32 1,192.32 397.44 794.88 2,384.64 - - -
12.02.
ACABADO FROTACHADO INCLUYE BRUÑADO Ejecutado - - - - - - - - - - - - - -
1,161.66 Programado - - - - - - - 232.33 232.33 - 232.33 464.66 - - -
12.03. ENCOFRADO Y DESENCOFRADO DE VEREDAS
Ejecutado - - - - - - - - - - - - - - -
13 ZOCALOS Y CONTRAZOCALOS 38,915.95 - - - - - - - - - - - - 268.84 806.52 1,209.78 806.52 3,024.44 3,226.07 7,221.54 6,295.64 2,098.55 3,066.90 4,600.36 3,928.26 2,180.80 181.73
ZÓCALO DE CEMENTO SOBRE MURO EXTERIOR H=60CM 24,195.55 Programado - - - - - - - 268.84 806.52 1,209.78 806.52 3,024.44 3,226.07 5,040.74 3,024.44 1,008.15 1,613.04 2,419.56 1,747.46
13.01.
INCLUYE BRUÑA Ejecutado - - - 5,806.93 6,452.15 1,935.64 322.61 2,903.47 1,935.64 - - - - - - - - - - - -
CONTRAZOCALO DE MADERA CON RODON, DE 5.80 CM X 1.90 14,720.40 Programado - - - - - - - - - - - - - 2,180.80 3,271.20 1,090.40 1,453.87 2,180.80 2,180.80 2,180.80 181.73
13.02. CM X 2.40 M Ejecutado - - - - - - - - - - - - - - - - - - - - -
14 PUERTAS 106,459.50 - - - - - - - - - - - - - - - - 16,560.37 16,560.37 16,560.37 16,560.37 5,520.12 16,560.37 16,560.37 1,577.18
PUERTA MACHIHEMBRADA DE 0.90X2.10 M. INCLUYE 48,081.00 Programado - - - - - - - - - - - 7,479.27 7,479.27 7,479.27 7,479.27 2,493.09 7,479.27 7,479.27 712.31
14.01.
INSTALACION P-01 Ejecutado - - - - - - - - - - - - - - - - - - -
PUERTA CONTRAPLACADA DE 0.90 X 2.10 M. INCLUYE 19,459.50 Programado - - - - - - - - - - - 3,027.03 3,027.03 3,027.03 3,027.03 1,009.01 3,027.03 3,027.03 288.29
14.02.
INSTALACION P-02 Ejecutado - - - - - - - - - - - - - - - - - - -
PUERTA CONTRAPLACADA DE 0.80 X 2.10 M. INCLUYE 38,919.00 Programado - - - - - - - - - - - 6,054.07 6,054.07 6,054.07 6,054.07 2,018.02 6,054.07 6,054.07 576.58
14.03. INSTALACION P-03 Ejecutado - - - - - - - - - - - - - - - - - -
15 VENTANAS 77,235.75 - - - - - - - - - - - - - - - - 11,033.68 11,033.68 11,033.68 11,033.68 3,677.89 7,355.79 11,033.68 11,033.68
VENTANA DE ALUMINIO DE 0.78X1.08 M INC/VIDRIO, CON 55,165.50 Programado - - - - - - - - - - - 7,880.79 7,880.79 7,880.79 7,880.79 2,626.93 5,253.86 7,880.79 7,880.79
15.01.
CONTRAVENTANA DE MADERA V-01 Ejecutado - - - - - - - - - - -
22,070.25 Programado - - - - - - - - - - - 3,152.89 3,152.89 3,152.89 3,152.89 1,050.96 2,101.93 3,152.89 3,152.89
15.02. VENTANA CENITAL
Ejecutado - - - - - - - - - - - - - - - - - - - - -
16 INSTALACIONES ELECTRICAS 30,551.25 - - - - - - - - - - - - - - - - 5,313.26 7,969.89 7,969.89 7,969.89 1,328.32
30,551.25 Programado - - - - - - - - - - - 5,313.26 7,969.89 7,969.89 7,969.89 1,328.32
16.01. INSTALACION ELECTRICA EN MÓDULO
Ejecutado - - - - - - - - - - - - - - - - - - - -
17 EVACUACION AGUAS PLUVIALES 49,812.29 - - - - - - - - - - - - - 5,053.42 8,663.01 5,775.34 5,053.42 9,384.93 10,828.76 5,053.42 - - - - -
47,845.50 Programado - - - - - - - - 4,853.89 8,320.96 5,547.30 4,853.89 9,014.37 10,401.20 4,853.89 - - - - -
17.01. SISTEMA DE EVACUACION DE AGUAS PLUVIALES
Ejecutado - - - - - - - - - - - - - - - - - - - -
1,227.45 Programado - - - - - - - - 124.52 213.47 142.31 124.52 231.26 266.84 124.52 - - - - -
17.02. ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO
Ejecutado - - - - - - - - - - - - - - - - - - - -
CONCRETO SIMPLE F'C=100 KG/CM2 PARA DADOS DE 739.34 Programado - - - - - - - - 75.01 128.58 85.72 75.01 139.30 160.73 75.01 - - - - -
17.03. PROTECCIÓN Ejecutado - - - - - - - - - - - - - - - - - - -
18 MITIGACION DEL IMPACTO AMBIENTAL Y LIMPIEZA 10,258.50 478.73 478.73 205.17 273.56 478.73 319.15 319.15 478.73 478.73 478.73 319.15 163.38 467.33 490.13 478.73 490.13 478.73 433.14 524.32 478.73 159.58 319.15 478.73 478.73 478.73 30.40
10,258.50 Programado 478.73 478.73 205.17 273.56 478.73 319.15 319.15 478.73 478.73 478.73 319.15 163.38 467.33 490.13 478.73 490.13 478.73 433.14 524.32 478.73 159.58 319.15 478.73 478.73 478.73 30.40
18.01. MITIGACION DEL IMPACTO AMBIENTAL (APORTE)
Ejecutado 478.73 478.73 273.56 - - 683.90 820.68 957.46 273.56 410.34 683.90 820.68 957.46 - - - - - - - - - -
19 ACARREOS 20,517.75 - - - - - - - - - - - - - - - 2,451.81 2,967.98 2,709.89 903.30 1,806.59 2,709.89 2,709.89 2,709.89 1,548.51
ACARREO DE MATERIAL EXCEDENTE Y LIMPIEZA DE OBRA 20,517.75 Programado - - - - - - - - - - 2,451.81 2,967.98 2,709.89 903.30 1,806.59 2,709.89 2,709.89 2,709.89 1,548.51
19.01. FINAL (APORTE) Ejecutado - - - - - - - - - - - - - - - - - - - - -
20 FLETES Y TRANSPORTE 417,007.54 - 16,758.12 42,373.07 10,310.65 18,586.78 6,873.76 7,338.92 19,065.50 24,673.45 30,259.04 7,338.92 9,988.94 46,463.10 29,966.83 16,176.62 29,966.83 25,330.89 13,930.83 17,915.23 9,809.01 2,899.66 9,392.55 14,088.82 7,500.00 - -
20.01 FLETE Y TRANSPORTE DE MATERIALES 172,323.76 - - 8,640.64 - 8,276.13 - - 6,583.72 6,239.76 6,903.95 - 3,675.45 14,635.49 11,026.36 11,080.79 11,026.36 8,698.98 13,930.83 17,915.23 9,809.01 2,899.66 9,392.55 14,088.82 7,500.00
FLETE TERRESTRE TRANSP. MATERIALES DEL PROVEEDOR 88,031.07 Programado 4,401.55 2,934.37 - - 1,956.25 2,934.37 3,912.49 - 2,037.76 8,069.51 6,113.27 4,890.62 6,113.27 4,401.55 5,868.74 7,335.92 4,401.55 1,467.18 6,194.78 9,292.17 5,705.72
20.01.01 AL ALMACEN ( INCL. CARGA Y DESCARGA) Ejecutado 1,261.19 1,760.62 1,760.62 3,573.63 1,760.62 1,619.77 1,619.77 39,464.33 - - - - - - - - - - - - -
FLETE TERRESTRE TRANSP. MATERIALES DE ALMACEN A 24,781.96 Programado 1,486.92 2,973.84 - - 1,982.56 1,321.70 826.07 - 413.03 1,569.52 1,239.10 1,156.49 1,239.10 991.28 1,321.70 660.85 991.28 330.43 1,982.56 2,973.84 1,321.70
20.01.02 PUNTA DE CARRETERA ( INCL. CARGA Y DESCARGA) Ejecutado 247.82 495.64 495.64 495.64 495.64 1,073.89 1,073.89 10,490.21 - - - - - - - - - - - - -
FLETE RURAL DE MATERIALES PUNTA DE CARRETERA A 36,456.40 Programado 1,215.21 1,215.21 - - 1,620.28 1,215.21 1,012.68 - 776.39 3,139.30 2,329.16 3,240.57 2,329.16 2,025.36 4,050.71 6,076.07 2,025.36 675.12 1,215.21 1,822.82 472.58
20.01.03
VIVIENDA (APORTE) Ejecutado 364.56 729.13 729.13 729.13 729.13 1,579.78 1,579.78 15,431.99 - - - - - - - - - - - - - - - -

ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE 23,054.33 Programado 1,536.96 1,152.72 - - 1,024.64 768.48 1,152.72 - 448.28 1,857.15 1,344.84 1,793.11 1,344.84 1,280.80 2,689.67 3,842.39 2,390.82 426.93 - - - - -
20.01.04 MATERIALES PUNTA DE CARRETERA A VIVIENDA (APORTE)
Ejecutado 230.54 461.09 461.09 461.09 461.09 999.02 999.02 9,758.90 - - - - - - - - - - - - - - - -
20.02 FLETE Y TRANSPORTE DE PIEDRA Y AGREGADOS 244,683.78 - 16,758.12 33,732.43 10,310.65 10,310.65 6,873.76 7,338.92 12,481.78 18,433.68 23,355.09 7,338.92 6,313.49 31,827.61 18,940.47 5,095.83 18,940.47 16,631.91 - - - - - - - - -
FLETE TERRESTRE TRANSP. AGREGADOS DEL PROVEDOR A 84,340.40 Programado 5,060.42 11,807.66 3,373.62 3,373.62 2,249.08 2,249.08 4,498.15 6,184.96 7,871.77 2,249.08 2,249.08 12,369.93 6,747.23 1,686.81 6,747.23 5,622.69 - - - - - - - - -
20.02.01 PUNTA DE CARRETERA (INCL. CARGA-DESCARGA) Ejecutado 12,499.48 8,434.04 8,434.04 17,112.56 1,686.81 8,062.94 8,062.94 3,179.51 - - - - - - - - - - - - - - -
FLETE TERRESTRE TRANSP. PIEDRA DE CANTERA A PUNTA 26,164.80 Programado 2,616.48 3,139.78 1,569.89 1,569.89 1,046.59 1,511.74 2,616.48 2,616.48 2,616.48 1,511.74 290.72 1,395.46 872.16 174.43 872.16 1,744.32 - - - - - - - - -
20.02.02 DE CARRETERA (INCL. CARGA-DESCARGA) Ejecutado 3,749.84 2,616.48 2,616.48 1,308.24 523.30 4,971.31 4,971.31 174.88 - - - - - - - - - - - - - - -
FLETE TERRESTRE TRANSP. DE AGREGADO Y PIEDRA DE 82,653.38 Programado 4,959.20 11,571.47 3,306.14 3,306.14 2,204.09 2,204.09 3,306.14 5,510.23 7,714.32 2,204.09 2,571.44 11,020.45 7,714.32 2,204.09 7,714.32 5,142.88 - - - - - - - - -
20.02.03 PUNTA DE CARRETERA A VIVIENDA (APORTE) Ejecutado 5,510.23 8,265.34 8,265.34 4,132.67 1,653.07 21,489.88 21,489.88 - 4,683.69 - - - - - - - - - - - - - - -
ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE 51,525.20 Programado 4,122.02 7,213.53 2,061.01 2,061.01 1,374.01 1,374.01 2,061.01 4,122.02 5,152.52 1,374.01 1,202.25 7,041.78 3,606.76 1,030.50 3,606.76 4,122.02 - - - - - - - - -
20.02.04 AGREGADO Y PIEDRA DE PUNTA DE CARRETERA A VIVIENDA
(APORTE) Ejecutado 3,435.01 5,152.52 5,152.52 2,576.26 1,030.50 13,396.55 13,396.55 - 2,919.76 - - - - - - - - - - - - - - - -
10,945.19 33,674.06 57,225.62 26,120.25 39,214.05 27,380.80 43,749.31 112,088.96 123,441.01 130,364.08 62,972.35 50,242.82 160,284.42 153,825.56 155,477.86 158,021.95 147,082.87 137,963.85 145,231.46 105,493.49 40,280.10 45,445.62 61,243.83 35,914.92 14,056.60 3,157.02
TOTAL 2,080,898.08
15,822.46 91,458.24 31,421.35 31,421.35 42,943.55 27,145.21 72,599.41 74,592.53 155,049.10 72,092.38 63,753.65 7,611.63 28,011.64 44,736.25 30,752.25 43,606.94 - - - - - - - - - -

P = PROGRAMADO 0.53% 1.62% 2.75% 1.26% 1.88% 1.32% 2.10% 5.39% 5.93% 6.26% 3.03% 2.41% 7.70% 7.39% 7.47% 7.59% 7.07% 6.63% 6.98% 5.07% 1.94% 2.18% 2.94% 1.73% 0.68% 0.15%
AVANCE SEMANAL (%)
E = EJECUTADO 0.76% 4.40% 1.51% 1.51% 2.06% 1.30% 3.49% 3.58% 7.45% 3.46% 3.06% 0.37% 1.35% 2.15% 1.48% 2.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
P = PROGRAMADO 0.53% 2.14% 4.89% 6.15% 8.03% 9.35% 11.45% 16.84% 22.77% 29.04% 32.06% 34.48% 42.18% 49.57% 57.04% 64.64% 71.71% 78.34% 85.31% 90.38% 92.32% 94.50% 97.45% 99.17% 99.85% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 0.76% 5.16% 6.67% 8.18% 10.24% 11.54% 15.03% 18.62% 26.07% 29.53% 32.60% 32.96% 34.31% 36.46% 37.94% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03%

P = PROGRAMADO 101,844.87 4.89% 92,715.11 4.46% 472,615.72 22.71% 677,852.61 32.58% 576,051.78 27.68% 159,818.00 7.68%
AVANCE MENSUAL (%)
E = EJECUTADO 138,702.05 6.67% 101,510.11 4.88% 438,087.06 21.05% 154,718.70 7.44% 0.00 0.00% 0.00 0.00%
P = PROGRAMADO 101,844.87 4.89% 194,559.97 9.35% 667,175.69 32.06% 1,345,028.31 64.64% 1,921,080.09 92.32% 2,080,898.08 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 138,702.05 6.67% 240,212.17 11.54% 678,299.23 32.60% 833,017.93 40.03% 833,017.93 40.03% 833,017.93 40.03%

FECHA DE INICIO DE OBRA 6/14/2021


TRANSFERENCIAS MONTO
FECHA DE PARALIZACION DE OBRA 7/15/2021
FINANCIMIENTO PNVR S/. 2,080,898.08 FECHA DE REINIO DE OBRA 9/1/2021
PLAZO DE EJECUCIÓN 150
FECHA DE TERMINO 11/10/2021
FECHA DE NUEVO TERMINO 12/28/2021
RESUMEN DEL FORMATO N° 26
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

CONVENIO N° 362-2020-AYA/VMVU/PNRV PRESUPUESTO TOTAL :

PROYECTO: “MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; COSTO DIRECTO :
CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”

FECHA DE ENTREGA 10/30/2021 2461.25088

PERIODO
Mes JUNIO JULIO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE
ITEM DESCRIPCION PRESUPUESTO
Semana 1 2 3A 3B 4 5 6 7 8 9 10A 10B 11 12 13 14 15 16 17 18 19A 19B 20 21 22 23
Dias 14-19 21-26 28-30 1-3 5-10 12-14 1-4 6-11 13-18 20-25 27-30 1-2 4-9 11-16 18-23 25-31 1-6 8-13 15-20 22-27 29-30 1-4 6-11 13-18 20-25 27-28
OBRAS PROVISIONALES, TRABAJOS PROGRAMADO 3,593.04 5,852.74 3,875.88 2,485.13 1,478.57 1,171.66 1,192.99 1,664.51 1,704.90 1,321.61 943.05 239.34 717.29 717.29 717.29 717.29 717.29 717.29 717.29 717.29 239.10 478.19 717.29 717.29 717.29 68.07
1.00 S/34,198.97
PRELIMINARES, SEGURIDAD Y SALUD EJECUTADO 2,775.19 24,401.89 146.60 146.60 144.54 96.36 - 289.08 240.90 289.08 289.08 96.36 144.54 240.90 240.90 240.90 - - - - - - - - - -
PROGRAMADO 6,873.42 6,873.42 2,945.75 1,963.83 2,945.75 1,963.83 3,600.36 5,678.34 5,553.97 5,392.87 3,340.47 - - - - - - - - - - - - - - -
2.00 MOVIMIENTO DE TIERRAS S/47,132.00
EJECUTADO 12,568.54 30,296.55 -694.46 -694.46 - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - 3,711.04 5,311.15 8,572.48 10,845.85 7,270.28 15,114.97 17,757.88 17,838.38 17,164.72 8,448.26 1,394.71 - - - - - - - - - - - - - -
3.00 CONCRETO SIMPLE S/113,429.72
EJECUTADO - 935.68 2,445.01 2,445.01 3,558.41 11,997.77 16,187.58 14,672.94 10,102.30 10,318.36 6,105.85 1,325.29 6,389.86 4,259.90 4,259.90 -4,259.90 - - - - - - - - - -
PROGRAMADO - - 2,514.60 2,514.60 4,878.37 4,364.99 10,765.79 20,044.08 25,791.66 28,347.19 10,982.56 9,173.37 27,520.12 27,520.12 27,520.12 19,553.52 13,775.84 - - - - - - - - -
4.00 CONCRETO ARMADO S/235,266.93
EJECUTADO - 8,046.72 1,609.34 1,609.34 8,851.39 6,437.38 3,218.69 6,437.38 15,314.22 7,408.07 2,461.12 393.36 2,562.09 11,613.66 9,829.42 15,465.80 - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - 7,842.61 20,168.60 23,527.82 23,527.82 23,527.82 8,232.46 15,826.98 13,295.47 6,493.23 - - - - - -
5.00 TIJERALES Y RETICULADOS S/142,442.82
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - 5,640.50 16,481.01 16,481.01 16,481.01 16,481.01 16,481.01 16,481.01 15,918.17 6,442.79 - - - - - -
6.00 COBERTURAS S/126,887.49
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 13,109.55 13,109.55 13,109.55 13,109.55 13,109.55 - - - - -
7.00 CIELO RASOS S/65,547.75
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - 5,417.13 5,417.13 47,399.92 47,399.92 47,399.92 31,599.95 15,799.97 47,399.92 47,399.92 47,399.92 47,399.92 - - - - - - - - - -
8.00 MUROS S/390,033.64
EJECUTADO - - - - - - - - 52,004.49 46,804.04 52,004.49 5,200.45 15,601.35 26,002.24 15,601.35 31,202.69 - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - 721.83 721.83 - - - - - - -
9.00 REVOQUES S/1,443.66
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - 798.21 1,862.50 13,303.57 13,303.57 17,828.05 18,582.13 18,582.13 10,954.75 7,228.91 - - - - -
10.00 ENLUCIDO DE YESO S/102,443.80
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 15,457.15 15,457.15 14,222.10 14,222.10 3,983.21 - - - - -
11.00 PISO S/63,341.71
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - 47.10 1,613.05 1,613.05 460.24 1,152.81 3,084.80 - - -
12.00 VEREDAS S/7,971.06
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - 268.84 806.52 1,209.78 806.52 3,024.44 3,226.07 7,221.54 6,295.64 2,098.55 3,066.90 4,600.36 3,928.26 2,180.80 181.73
13.00 ZOCALOS Y CONTRAZOCALOS S/38,915.95
EJECUTADO - - - - - - - - 5,806.93 6,452.15 1,935.64 322.61 2,903.47 1,935.64 - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 16,560.37 16,560.37 16,560.37 16,560.37 5,520.12 16,560.37 16,560.37 1,577.18 - -
14.00 PUERTAS S/106,459.50
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 11,033.68 11,033.68 11,033.68 11,033.68 3,677.89 7,355.79 11,033.68 11,033.68 - -
15.00 VENTANAS S/77,235.75
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - - - - - 5,313.26 7,969.89 7,969.89 7,969.89 1,328.32
16.00 INSTALACIONES ELECTRICAS S/30,551.25
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - 5,053.42 8,663.01 5,775.34 5,053.42 9,384.93 10,828.76 5,053.42 - - - - - -
17.00 EVACUACION AGUAS PLUVIALES S/49,812.29
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
MITIGACION DEL IMPACTO AMBIENTAL Y PROGRAMADO 478.73 478.73 205.17 273.56 478.73 319.15 319.15 478.73 478.73 478.73 319.15 163.38 467.33 490.13 478.73 490.13 478.73 433.14 524.32 478.73 159.58 319.15 478.73 478.73 478.73 30.40
18.00 S/10,258.50
LIMPIEZA EJECUTADO 478.73 478.73 - - - 273.56 - - 683.90 820.68 957.46 273.56 410.34 683.90 820.68 957.46 - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - 2,451.81 2,967.98 2,709.89 903.30 1,806.59 2,709.89 2,709.89 2,709.89 1,548.51
19.00 ACARREOS S/20,517.75
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - 16,758.12 42,373.07 10,310.65 18,586.78 6,873.76 7,338.92 19,065.50 24,673.45 30,259.04 7,338.92 9,988.94 46,463.10 29,966.83 16,176.62 29,966.83 25,330.89 13,930.83 17,915.23 9,809.01 2,899.66 9,392.55 14,088.82 7,500.00 - -
20.00 FLETES Y TRANSPORTE S/417,007.54
EJECUTADO - 27,298.67 27,914.85 27,914.85 30,389.21 8,340.15 53,193.14 53,193.14 70,896.36 - - - - - - - - - - - - - - - -
PROGRAMADO S/10,945.19 S/33,674.06 S/57,225.62 S/26,120.25 S/39,214.05 S/27,380.80 S/43,749.31 S/112,088.96 S/123,441.01 S/130,364.08 S/62,972.35 S/50,242.82 S/160,284.42 S/153,825.56 S/155,477.86 S/158,021.95 S/147,082.87 S/137,963.85 S/145,231.46 S/105,493.49 S/40,280.10 S/45,445.62 S/61,243.83 S/35,914.92 S/14,056.60 S/3,157.02
COSTO DIRECTO S/2,080,898.08
EJECUTADO S/15,822.46 S/91,458.24 S/31,421.35 S/31,421.35 S/42,943.55 S/27,145.21 S/72,599.41 S/74,592.53 S/155,049.10 S/72,092.38 S/63,753.65 S/7,611.63 S/28,011.64 S/44,736.25 S/30,752.25 S/43,606.94 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00

P = PROGRAMADO 0.53% 1.62% 2.75% 1.26% 1.88% 1.32% 2.10% 5.39% 5.93% 6.26% 3.03% 2.41% 7.70% 7.39% 7.47% 7.59% 7.07% 6.63% 6.98% 5.07% 1.94% 2.18% 2.94% 1.73% 0.68% 0.15%
AVANCE SEMANAL (%)
E = EJECUTADO 0.76% 4.40% 1.51% 1.51% 2.06% 1.30% 3.49% 3.58% 7.45% 3.46% 3.06% 0.37% 1.35% 2.15% 1.48% 2.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
P = PROGRAMADO 0.53% 2.14% 4.89% 6.15% 8.03% 9.35% 11.45% 16.84% 22.77% 29.04% 32.06% 34.48% 42.18% 49.57% 57.04% 64.64% 71.71% 78.34% 85.31% 90.38% 92.32% 94.50% 97.45% 99.17% 99.85% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 0.76% 5.16% 6.67% 8.18% 10.24% 11.54% 15.03% 18.62% 26.07% 29.53% 32.60% 32.96% 34.31% 36.46% 37.94% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03%

P = PROGRAMADO S/101,844.87 S/92,715.11 S/472,615.72 S/677,852.61 S/576,051.78 S/159,818.00


AVANCE MENSUAL (%)
E = EJECUTADO S/138,702.05 S/101,510.11 S/438,087.06 S/154,718.70 S/0.00 S/0.00
P = PROGRAMADO S/101,844.87 S/194,559.97 S/667,175.69 S/1,345,028.31 S/1,921,080.09 S/2,080,898.08
AVANCE ACUMULADO (%)
E = EJECUTADO S/138,702.05 S/240,212.17 S/678,299.23 S/833,017.93 S/833,017.93 S/833,017.93
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH;
PROYECTO:
CENTRO POBLADO HUACA CORRAL - DISTRITO DE GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27
1 OBRAS PROVISIONALES Y TRABAJOS PRELIMINA 19,050.37
1.01 TRABAJOS PRELIMINARES 399.61
Programado 399.61
1.01.01 CARTEL DE OBRA 4.00X2.50 399.61
Ejecutado
1.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 2,050.26
LIMPIEZA, TRAZOS, NIVELES (REPLANTEO Programado 1,058.20 925.93 66.13
1.02.02 2,050.26
PRELIMINAR) Ejecutado 1,058.20 925.93 66.14
1.03 SEGURIDAD Y SALUD 16,600.50
Programado 577.50 1,980.00
1.03.01 EQUIPO DE SEGURIDAD INDIVIDUAL 2,557.50
Ejecutado 577.50 1,980.00
Programado 175.46 175.46 87.73
1.03.02 EQUIPO DE SEGURIDAD COLECTIVA 438.65
Ejecutado 127.35 127.35 183.95
Programado 3,829.74 3,829.74 1,914.87
1.03.03 SEÑALIZACION TEMPORAL DE SEGURIDAD 9,574.35
Ejecutado 2,779.65 2,779.65 4,015.05
Programado 1,612.00 1,612.00 806.00
1.03.04 CAPACITACION EN SALUD Y SEGURIDAD 4,030.00
Ejecutado 1,170.00 1,170.00 1,690.00
2 MOVIMIENTO DE TIERRAS Y NIVELACION 40,121.62
2.1 EXCAVACIONES 21,680.44
CORTE Y EXPLANACION DE TERRENO NORMAL Programado 11,076.07 1,186.83
2.01.01 12,262.90
MANUAL (APORTE) Ejecutado 11,076.07 1,186.83
EXCAVACION DE ZANJAS PARA CIMIENTO Programado 2,960.11 1,184.04 789.36 789.10 394.69
2.01.02 6,117.30
CORRIDO (HASTA 1.2 M) Ejecutado 2,960.11 1,184.04 789.36 789.10 197.35 197.33
EXCAVACION DE ZANJAS PARA ENROCADO DE Programado 911.31 303.73 188.33 188.33 188.33 103.24
2.01.03 1,883.26
PIEDRA E=40 CM. Ejecutado 911.31 303.73 182.21 121.50 60.75 121.50 121.50 60.75
EXCAVACION PARA DENTELLON DE LOSA DE Programado 681.16 227.03 140.77 140.77 140.77 77.19
2.01.04 1,407.69
CIMENTACION Ejecutado 681.16 227.03 136.22 90.82 45.41 90.82 90.82 45.41
EXCAVACION PARA CIMENTACION DE Programado 3.72 3.72 1.86
2.01.05 9.29
COLUMNETA DE CONCRETO Ejecutado 6.90 0.60 0.30 0.60 0.60 0.30
2.2 RELLENO Y ENROCADO 18,441.18
Programado 7,415.97 2,554.45 2,554.45 1,277.23 1,524.61
2.02.01 ENROCADO DE PIEDRA E=35 CM A MANO 15,326.70
Ejecutado 7,415.97 1,483.40 988.82 1,483.23 494.41 988.82
NIVELACION Y RELLENO CON MATERIAL Programado 1,507.01 479.15 479.15 239.58 409.59
2.02.02 3,114.48
SELECTO COMPACTADO E=10 Ejecutado 1,507.01 100.47 200.93 200.93 301.40 100.47 200.93
3 OBRAS DE CONCRETO SIMPLE 44,332.84
3.01 CIMIENTOS 42,750.81
Programado 18,259.97 10,955.72 5,031.42 2,515.71 972.82
3.01.01 MAMPOSTERIA DE PIEDRA, MEZCLA 1:10 + 40%PG 37,735.63
Ejecutado 18,259.97 10,955.72 4,868.10 1,217.28 1,217.28
Programado 1,456.49 1,456.49 1,941.98
3.01.02 CONCRETO F´C=100KG/CM2 PARA SOLADO 4,854.96
Ejecutado 1,879.34 783.06 313.22 156.61 156.61 313.22
CONCRETO F'C=140KG/CM2 PARA CIMIENTO Programado 48.07 48.07 32.04 32.04
3.01.01 160.22
COLUMNA CIRCULAR EN FACHADA Ejecutado 20.67
3.02 SOBRECIMIENTO 514.16
ENCOFRADO Y DESENCOFRADO EN Programado 129.66 129.66 129.66
3.02.01 SOBRECIMIENTO EN COLUMNA CIRCULAR EN 388.99
FACHADA
Ejecutado 50.19
CONCRETO F'C=140KG/CM2 PARA BASE DE Programado 41.72 41.72 41.72
3.02.02 125.17
COLUMNETA CIRCULAR DE FACHADA Ejecutado 16.15
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH;
PROYECTO:
CENTRO POBLADO HUACA CORRAL - DISTRITO DE GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27
3.03 ALFEIZAR EN PUERTA 1,067.87
ENCOFRADO Y DESENCOFRADO PARA ALFEIZAR Programado 212.43 212.43 212.43
3.03.01 637.29
EN PUERTA (P-01) Ejecutado 82.23
CONCRETO F´C=140KG/CM2 PARA ALFEIZAR EN Programado 143.53 143.53 143.53
3.03.02 430.58
PUERTA (P-01) Ejecutado 55.56
4 OBRAS DE CONCRETO ARMADO 211,786.11
4.01 LOSA DE CIMENTACIÓN 125,082.88
ENCOFRADO Y DESENCOFRADO DE LOSA DE Programado 2,071.82 2,071.82 2,071.82
4.01.01 6,215.46
CIMENTACIÓN Ejecutado 801.99 1,002.49 1,603.99 200.50 401.00 200.50
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 7,724.22 6,186.72 18,623.95 13,302.82 2,052.44
4.01.02 47,890.15
DOBLADO Y COLOCADO (LOSA DE CIMENTACIÓN) Ejecutado 7,724.22 6,186.72 6,172.03 12,358.75 4,634.53 6,179.37
CONCRETO F´C=210KG/CM2 PARA LOSA DE Programado 27,602.27 27,602.27 15,772.73
4.01.03 70,977.27
CIMENTACIÓN Ejecutado 9,158.36 6,868.77 22,895.89 2,289.59 2,289.59 4,579.18
4.02 VIGAS 16,691.82
Programado 1,445.15 1,445.15 1,238.70
4.02.01 ENCOFRADO Y DESENCOFRADO DE VIGAS 4,129.01
Ejecutado 532.78
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 1,819.47 1,819.47 1,559.55
4.02.02 5,198.49
DOBLADO Y COLOCADO (VIGA) Ejecutado 670.77 0.00 1,173.85
Programado 2,577.51 2,577.51 2,209.30
4.02.03 CONCRETO F´C=210KG/CM2 PARA VIGAS 7,364.32
Ejecutado
4.03 LOSA ALIGERADA 68,143.23
ENCOFRADO Y DESENCOFRADOPARA LOSA Programado 8,731.94 8,731.94 7,484.52
4.03.01 24,948.40
ALIGERADA Ejecutado
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 3,617.19 3,617.19 3,100.45
4.03.02 10,334.84
DOBLADO Y COLOCADO (LOSA ALIGERADA) Ejecutado 1,333.53 333.38 2,000.29
CONCRETO F´C=175KG/CM2 PARA LOSA Programado 6,511.65 6,511.65 5,581.41
4.03.03 18,604.71
ALIGERADA Ejecutado
LADRILLO HUECO PARA TECHO 8x30x30 CM (LOSA Programado 4,989.35 4,989.35 4,276.58
4.03.04 14,255.28
ALIGERADA) Ejecutado
4.04 COLUMNETA DE FACHADA 1,868.18
ENCOFRADO Y DESENCOFRADO DE COLUMNA Programado 349.32 261.99 261.99
4.04.01 873.29
CIRCULAR EN FACHADA Ejecutado 84.51
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 244.15 183.11 183.11
4.04.02 DOBLADO Y COLOCADO (PARA COLUMNETA DE 610.37
FACHADA)
Ejecutado 157.51 59.07 39.38 137.83
CONCRETO F´C=175KG/CM2 PARA COLUMNETA Programado 153.81 115.36 115.36
4.04.03 384.52
CIRCULAR Ejecutado
5 MUROS Y TABIQUES DE ALBAÑILERIA 170,110.10
5.01 MUROS Y SOBRECIMIENTO 170,110.10
Programado 5,722.20 39,940.65 9,196.15 317.90
5.01.01 BLOQUE DE CONCRETO DE 39X19X14CM 55,176.90
Ejecutado 5,722.20 39,940.65 4,222.80 5,291.25
Programado 809.60 3,634.00 334.63 241.29
5.01.02 MEDIO BLOQUE DE CONCRETO DE 39X19X14CM 5,019.52
Ejecutado 809.60 3,634.00 575.92
Programado 275.40 3,202.80 737.80 210.80
5.01.03 BLOQUE DE CONCRETO EN L DE 39X19X14CM 4,426.80
Ejecutado 275.40 3,202.80 826.20 76.50
Programado 229.50 52.70 34.00
5.01.04 BLOQUE DE CONCRETO TIPO VIGA DE 39X19X14CM 316.20
Ejecutado 229.50 86.70
Programado 11,377.18 11,377.18 11,377.18 11,377.18 3,250.62
5.01.05 MURO CON BLOQUES DE CONCRETO DE 39X19X14C 48,759.36
Ejecutado 1,572.88 3,145.77 4,718.65 1,572.88 6,291.53 4,718.65 3,145.77
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH;
PROYECTO:
CENTRO POBLADO HUACA CORRAL - DISTRITO DE GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 7,995.66 7,995.66 7,995.66 7,995.66 2,284.47
5.01.06 DOBLADO Y COLOCADO (MUROS CON BLOQUES 34,267.12
DE CONCRETO)
Ejecutado 1,105.39 2,210.78 3,316.17 1,105.39 4,421.56 3,316.17 2,210.78
CONCRETO GROUT F´C=210KG/CM2 PARA MUROS Programado 4,859.47 4,859.47 4,859.47 4,859.47 1,388.42
5.01.07 20,826.28
CON BLOQUES DE CONCRETO Ejecutado 671.82 1,343.63 2,015.45 671.82 2,687.26 2,015.45 1,343.63
Programado 307.51 307.51 307.51 307.51 87.86
5.01.08 JUNTA DE CONSTRUCCIÓN EN ALFÉIZAR 1,317.92
Ejecutado 297.60 127.54
6 COBERTURAS 90,271.61
6.01 COBERTURA EN FACHADA 29,030.58
COBERTURA EN FACHADA CON BAMBÚ O CAÑA Programado 7,272.97 7,272.97 1,039.00
6.01.01 15,584.94
GUAYAQUIL Ejecutado
HABILITACIÓN Y PRESERVACIÓN DE BAMBÚ O Programado 1,046.52 1,046.52 149.50
6.01.02 2,242.54
CAÑA GUAYAQUIL Ejecutado
RECUBRIMIENTO CON POLIETILENO Y CEMENTO, Programado 5,601.55 4,801.33 800.22
6.01.03 11,203.10
ARENA Y CONFITILLO 3/8" MEZCLA 1:5:7 E = 1 1/2" Ejecutado
6.02 RECUBRIMIENTO DE TECHO 61,241.03
RECUBRIMIENTO CON POLIETILENO Y SUELO Programado 24,496.41 32,661.88 4,082.74
6.02.01 61,241.03
CEMENTO 12:1 E=5 CM Ejecutado
7 ACABADOS, REVOQUES, REVESTIMIENTO Y PINT 84,795.79
7.01 VESTIDURAS, DERRAMES Y CENEFAS 16,373.52
Programado 7,498.00 7,498.00
7.01.01 VESTIDURAS Y DERRAMES DE PUERTAS Y VENTAN 14,995.99
Ejecutado
Programado 688.77 688.77
7.01.02 CENEFAS EN BORDE DE VANOS 1,377.53
Ejecutado
7.02 PINTURA 22,234.42
PINTURA EN MUROS EXTERIORES (FACHADA Y Programado 2,805.96 2,805.96 1,402.98
7.01.01 7,014.90
POSTERIOR) Ejecutado
Programado 5,832.69 5,832.69 2,916.35
7.01.02 PINTURA EN MUROS INTERIORES (IMPRIMANTE) 14,581.73
Ejecutado
Programado 255.12 255.12 127.56
7.01.03 PINTURA EN CENEFAS 637.79
Ejecutado
7.03 ACABADO CIELO RASO 46,187.85
FALSO CIELO RASO CON PLACAS DE YESO Y Programado 18,475.14 18,475.14 9,237.57
7.03.01 46,187.85
PERFILERIA DE ALUMINIO Ejecutado
8 PISOS Y PAVIMENTOS 10,089.32
8.01 PISOS 4,911.94
FROTACHADO EN CONCRETO CON MORTERO C/A Programado 1,309.85 1,964.78 982.39 654.93
8.01.01 4,911.94
1:1 LOSA DE CIMENTACIÓN Ejecutado 316.90 1,109.15 1,267.60 158.45 158.45 316.90 158.45
8.02 VEREDAS 5,177.38
NIVELACION, RELLENO Y APISONADO E=0.175m Programado 160.10 240.16 120.08 80.05
8.02.01 600.39
C/MAT DE PRESTAMO, VEREDA Ejecutado
VEREDA DE CONCRETO F'C=140KG/CM2, E=0.175m Programado 915.67 1,373.51 686.76 457.84
8.02.02 3,433.78
ACABADO SEMIPULIDO INCL/BRUÑADO Ejecutado
Programado 175.11 262.67 131.33 87.56
8.02.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS 656.67
Ejecutado
Programado 129.74 194.62 97.31 64.87
8.02.04 JUNTAS ASFALTICAS DE 1/2" X 4" 486.54
Ejecutado
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH;
PROYECTO:
CENTRO POBLADO HUACA CORRAL - DISTRITO DE GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27
9 ZOCALOS Y CONTRAZOCALOS 5,546.65
9.01 ZOCALOS 5,546.65
ZOCALO DE CEMENTO SOBRE MURO EXTERIOR Programado 1,479.11 2,218.66 1,109.33 739.55
9.01.01 5,546.65
H=55CM INC/BRUÑAS Ejecutado
10 PUERTAS Y VENTANAS 76,078.65
10.01 PUERTAS 63,678.65
PUERTA METALICA 0.90X2.41 CON PAÑO FIJO Y Programado 4,381.33 17,525.33 10,953.33
10.01.01 VENTANILLA PIVOTANTE INC. VIDRIO, CHAPA E 32,860.00
Ejecutado
INSTALACIÓN (P-01)
PUERTA CONTRAPLACADA 0.85X2.41 CON Programado 2,780.49 11,121.97 6,951.23
10.01.02 SOBRELUZ INC. CHAPA,VIDRIO E INSTALACION (P- 20,853.70
Ejecutado
02)
Programado 1,328.66 5,314.64 3,321.65
10.01.03 ATAGUIA EN PUERTAS (FACHADA Y POSTERIOR) 9,964.95
Ejecutado
10.02 VENTANAS 12,400.00
VENTANA DE ALUMINIO 1.10X1.60 M INCLUYE Programado 2,480.00 6,200.00 3,720.00
10.02.01 12,400.00
VIDRIO E INSTALACIÓN (V-01) Ejecutado
11 INSTALACIONES ELECTRICAS 20,502.16
11.01 INSTALACION ELECTRICAS 20,502.16
Programado 4,100.43 4,100.43 4,100.43 2,928.88 2,928.88 2,343.10
11.01.01 INSTALACION ELECTRICA EN MODULO 20,502.16
Ejecutado 1,322.72 1,322.72 3,306.80 661.36 1,984.08 1,322.72 1,984.08
12 INSTALACIONES SANITARIAS 5,655.95
12.01 INSTALACIONES PARA DRENAJE 5,655.95
Programado 1,939.18 1,939.18 1,777.58
12.01.01 MONTANTES DE DRENAJE 5,655.95
Ejecutado 182.45 547.35 912.25 729.80 364.90 547.35
13 MITIGACION DEL IMPACTO AMBIENTAL Y LIMPI 12,089.07
13.01 MITIGACION Y LIMPIEZA 12,089.07
Programado 137.23 137.23 274.45 274.45 411.68 411.68 411.68
13.01.01 MITIGACION DEL IMPACTO AMBIENTAL (APORTE) 2,058.40
Ejecutado 398.40 929.60 531.20
MITIGACION DEL IMPACTO AMBIENTAL Programado 620.00 620.00 310.00
13.01.02 1,550.00
(ARBUSTOS ORNAMENTALES) Ejecutado
ACARREO MATERIAL EXCED, EXCAV, DRENAJES Y Programado 5,744.97 820.71 565.38 565.38 565.38 218.86
13.01.03 8,480.67
LIMPIEZA DE OBRA FINAL (APORTE) Ejecutado 5,744.97 820.71 273.57 820.71
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH;
PROYECTO:
CENTRO POBLADO HUACA CORRAL - DISTRITO DE GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27
14 FLETE Y TRANSPORTE 26,697.69
14.01 FLETE Y TRANSPORTE DE MATERIALES 22,314.45
FLETE TERRESTRE TRANSP. MATERIALES DEL Programado 146.45 1,669.56 2,841.18 669.06 764.64 477.90 573.48 669.06 573.48 573.48 95.58 26.21
14.01.01 PROVEEDOR AL ALMACEN (INC. CARGA - 9,080.05
DESCARGA)
Ejecutado 146.45 1,669.56 2,841.18 322.20 2,343.24 292.90 585.81 292.90 292.90 292.90
FLETE TERRESTRE TRANSP. MATERIALES DE Programado 3,131.58 1,318.56 1,450.41 1,582.27 1,186.70 1,054.85 1,054.85 1,054.85 659.28 32.96
14.01.02 ALMACEN A PUNTA DE CARRETERA (INC. CARGA - 12,526.30
DESCARGA)
Ejecutado 3,131.58 101.02 4,848.89 2,424.45 808.15 404.07 404.07 404.07
FLETE TERRESTRE TRANSP. MATERIALES PUNTA Programado 7.60 7.60 7.18 4.22 3.80 3.38 3.38 2.53 0.42
14.01.03 40.11
DE CARRETERA A VIVIENDA Ejecutado 3.88 22.00 7.76 2.59 1.29 1.29 1.29
ACOMPAÑAMIENTO, CARGA Y DESCARGA Programado 200.40 77.35 84.38 70.31 63.28 49.22 42.19 35.16 42.19 3.51
14.01.04 TRANSP. DE MATERIALES PUNTA DE CARRETERA 667.99
A VIVIENDA (APORTE)
Ejecutado 200.40 15.08 215.48 129.29 43.10 21.55
14.02 FLETE Y TRANSPORTE DE AGREGADOS Y PIEDRA 4,383.24
FLETE TERRESTRE TRANSP. PIEDRA DE CANTERA Programado 0.10 0.07 0.20 0.17 0.13 0.10 0.07 0.10 0.07
14.02.01 A PUNTA DE CARRETERA (INC. CARGA - 1.00
DESCARGA)
Ejecutado 0.29 0.19 0.35 0.06 0.03 0.03 0.03
FLETE TERRESTRE TRANSP. DE AGREGADO Y Programado 130.25 3.95 7.89 19.74 19.74 15.79 11.84 7.89 11.84 7.89
14.02.02 236.82
PIEDRA DE PUNTA DE CARRETERA A VIVIENDA Ejecutado 130.25 7.26 53.48 7.64 15.28 7.64 7.64 7.64
ACOMPAÑAMIENTO, CARGA Y DESCARGA Programado 276.29
2,279.43 69.07 138.15 345.37 345.37 207.22 138.15 207.22 138.15
14.02.03 TRANSP. DE AGREGADO Y PIEDRA DE PUNTA DE 4,144.42
CARRETERA A VIVIENDA (APORTE) Ejecutado 2,279.43 127.01 935.84 133.69 267.38 133.69
FLETE TERRESTRE TRANSP. AGREGADOS DEL Programado 0.55 0.02 0.03 0.08 0.08 0.07 0.05 0.03 0.05 0.03
14.02.04 PROVEEDOR A PUNTA DE CARRETERA (INC. 1.00
CARGA - DESCARGA) Ejecutado 0.55 0.03 0.23 0.03 0.06 0.03 0.03 0.03
Programado 15,094.38 9,041.77 2,187.57 146.45 3,849.96 5,251.41 38,304.53 73,603.13 8,223.72 77,080.85 87,227.37 86,595.42 59,668.90 49,989.05 123,215.72 127,990.70 49,656.99
TOTAL 817,127.93
Ejecutado 15,094.38 9,041.77 2,187.57 146.45 3,849.96 5,251.41 38,304.53 73,603.13 22,362.95 43,896.47 34,079.18 51,758.80 8,879.97 20,353.86 28,075.25 14,828.84 0.00

P = PROGRAMADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 1.01% 9.43% 10.67% 10.60% 7.30% 6.12% 15.08% 15.66% 6.08%
AVANCE SEMANAL (%)
E = EJECUTADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 2.74% 5.37% 4.17% 6.33% 1.09% 2.49% 3.44% 1.81% 0.00%
P = PROGRAMADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 19.05% 28.49% 39.16% 49.76% 57.06% 63.18% 78.26% 93.92% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 20.79% 26.16% 30.33% 36.66% 37.75% 40.24% 43.68% 45.49% 45.49%

P = PROGRAMADO 26,470.17 3.24% 121,009.03 14.81% 259,127.36 31.71% 410,521.37 50.24%


AVANCE MENSUAL (%)
E = EJECUTADO 26,470.17 3.24% 121,009.03 14.81% 152,097.39 18.61% 72,137.91 8.83%
P = PROGRAMADO 26,470.17 3.24% 147,479.20 18.05% 406,606.56 49.76% 817,127.93 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 26,470.17 3.24% 147,479.20 18.05% 299,576.60 36.66% 371,714.51 45.49%

FECHA DE INICIO DE OBRA 8/10/2020


TRANSFERENCIAS MONTO
PLAZO DE EJECUCIÓN 140
FINANCIMIENTO PNVR S/. 817,127.93 FECHA DE TERMINO REPROGRAMADO AMPL PLAZO 01 12/27/2020
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 02


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH; CENTRO POBLADO HUACA CORRAL - DISTRITO DE
PROYECTO:
GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE ENERO


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20 21 22 23 24 25 26
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27 28-31 01-03 04-10 11-17 18-24 25-27
1 OBRAS PROVISIONALES Y TRABAJOS PRELIMINA 19,050.37
1.01 TRABAJOS PRELIMINARES 399.61
Programado 399.61
1.01.01 CARTEL DE OBRA 4.00X2.50 399.61
Ejecutado
1.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 2,050.26
LIMPIEZA, TRAZOS, NIVELES (REPLANTEO Programado 1,058.20 925.93 66.13
1.02.02 2,050.26
PRELIMINAR) Ejecutado 1,058.20 925.93 66.13
1.03 SEGURIDAD Y SALUD 16,600.50
Programado 577.50 1,980.00
1.03.01 EQUIPO DE SEGURIDAD INDIVIDUAL 2,557.50
Ejecutado 577.50 1,980.00
Programado 127.35 127.35 183.95
1.03.02 EQUIPO DE SEGURIDAD COLECTIVA 438.65
Ejecutado 127.35 127.35 183.95
Programado 2,779.65 2,779.65 4,015.05
1.03.03 SEÑALIZACION TEMPORAL DE SEGURIDAD 9,574.35
Ejecutado 2,779.65 2,779.65 4,015.05
Programado 1,170.00 1,170.00 1,690.00
1.03.04 CAPACITACION EN SALUD Y SEGURIDAD 4,030.00
Ejecutado 1,170.00 1,170.00 1,690.00
2 MOVIMIENTO DE TIERRAS Y NIVELACION 40,121.62
2.1 EXCAVACIONES 21,680.44
CORTE Y EXPLANACION DE TERRENO NORMAL Programado 11,076.07 1,186.83
2.01.01 12,262.90
MANUAL (APORTE) Ejecutado 11,076.07 1,186.83
EXCAVACION DE ZANJAS PARA CIMIENTO Programado 2,960.11 1,184.04 789.36 789.10 197.35 67.97 67.97 45.31 16.09
2.01.02 6,117.30
CORRIDO (HASTA 1.2 M) Ejecutado 2,960.11 1,184.04 789.36 789.10 197.35 197.33
EXCAVACION DE ZANJAS PARA ENROCADO DE Programado 911.31 303.73 182.21 121.50 60.75 121.50 121.50 31.39 20.93 8.44
2.01.03 1,883.26
PIEDRA E=40 CM. Ejecutado 911.31 303.73 182.21 121.50 60.75 121.50 121.50 60.75
EXCAVACION PARA DENTELLON DE LOSA DE Programado 681.16 227.03 136.22 90.82 45.41 90.82 90.82 14.08 14.08 14.08 3.18
2.01.04 1,407.69
CIMENTACION Ejecutado 681.16 227.03 136.22 90.82 45.41 90.82 90.82 45.41
EXCAVACION PARA CIMENTACION DE Programado 6.90 0.60 0.30 0.60 0.60 0.09 0.09 0.09 0.02
2.01.05 9.29
COLUMNETA DE CONCRETO Ejecutado 6.90 0.60 0.30 0.60 0.60 0.30
2.2 RELLENO Y ENROCADO 18,441.18
Programado 7,415.97 1,483.40 988.82 1,483.23 494.41 638.61 638.61 638.61 638.61 425.74 425.74 54.94
2.02.01 ENROCADO DE PIEDRA E=35 CM A MANO 15,326.70
Ejecutado 7,415.97 1,483.40 988.82 1,483.23 494.41 988.82 988.82
NIVELACION Y RELLENO CON MATERIAL Programado 1,507.01 100.47 200.93 200.93 301.40 100.47 119.79 119.79 119.79 119.79 79.86 79.86 64.40
2.02.02 3,114.48
SELECTO COMPACTADO E=10 Ejecutado 1,507.01 100.47 200.93 200.93 301.40 100.47 200.93 200.93
3 OBRAS DE CONCRETO SIMPLE 44,332.84
3.01 CIMIENTOS 42,750.81
Programado 18,259.97 10,955.72 4,868.10 1,217.28 1,257.85 838.57 338.14
3.01.01 MAMPOSTERIA DE PIEDRA, MEZCLA 1:10 + 40%PG 37,735.63
Ejecutado 18,259.97 10,955.72 4,868.10 1,217.28 1,217.28 1,217.28
Programado 1,879.34 783.06 313.22 156.61 156.61 485.50 485.50 242.75 242.75 109.63
3.01.02 CONCRETO F´C=100KG/CM2 PARA SOLADO 4,854.96
Ejecutado 1,879.34 783.06 313.22 156.61 156.61 313.22 313.22 313.22
CONCRETO F'C=140KG/CM2 PARA CIMIENTO Programado 40.06 40.06 40.06 40.06
3.01.03 160.22
COLUMNA CIRCULAR EN FACHADA Ejecutado 20.67
3.02 SOBRECIMIENTO 514.16
ENCOFRADO Y DESENCOFRADO EN Programado 64.83 64.83 64.83 64.83 43.22 43.22 43.22
3.02.01 SOBRECIMIENTO EN COLUMNA CIRCULAR EN 388.99
FACHADA Ejecutado 50.19 25.10
CONCRETO F'C=140KG/CM2 PARA BASE DE Programado 20.86 20.86 20.86 20.86 13.91 13.91 13.91
3.02.02 125.17
COLUMNETA CIRCULAR DE FACHADA Ejecutado 16.15 8.08
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 02


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH; CENTRO POBLADO HUACA CORRAL - DISTRITO DE
PROYECTO:
GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE ENERO


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20 21 22 23 24 25 26
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27 28-31 01-03 04-10 11-17 18-24 25-27
3.03 ALFEIZAR EN PUERTA 1,067.87
ENCOFRADO Y DESENCOFRADO PARA ALFEIZAR Programado 31.86 31.86 127.46 127.46 127.46 127.46 63.73
3.03.01 637.29
EN PUERTA (P-01) Ejecutado 82.23
CONCRETO F´C=140KG/CM2 PARA ALFEIZAR EN Programado 35.88 35.88 71.76 143.53 71.76 71.76
3.03.02 430.58
PUERTA (P-01) Ejecutado 55.56
4 OBRAS DE CONCRETO ARMADO 211,786.11
4.01 LOSA DE CIMENTACIÓN 125,082.88
ENCOFRADO Y DESENCOFRADO DE LOSA DE Programado 801.99 1,002.49 1,603.99 200.50 401.00 200.50 172.65 258.98 517.96 517.96 517.96 19.50
4.01.01 6,215.46
CIMENTACIÓN Ejecutado 801.99 1,002.49 1,603.99 200.50 401.00 200.50 401.00 801.99
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 7,724.22 6,186.72 6,172.03 12,358.75 4,634.53 6,179.37 886.85 665.14 1,330.28 886.85 665.14 200.26
4.01.02 47,890.15
DOBLADO Y COLOCADO (LOSA DE CIMENTACIÓN) Ejecutado 7,724.22 6,186.72 6,172.03 12,358.75 4,634.53 6,179.37
CONCRETO F´C=210KG/CM2 PARA LOSA DE Programado 9,158.36 6,868.77 22,895.89 2,289.59 2,289.59 4,579.18 4,436.08 4,436.08 4,436.08 4,436.08 2,957.39 2,194.19
4.01.03 70,977.27
CIMENTACIÓN Ejecutado 9,158.36 6,868.77 22,895.89 2,289.59 2,289.59 4,579.18 4,579.18 9,158.36
4.02 VIGAS 16,691.82
Programado 688.17 688.17 688.17 688.17 688.17 688.17
4.02.01 ENCOFRADO Y DESENCOFRADO DE VIGAS 4,129.01
Ejecutado 532.78 133.19 133.19
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 670.77 0.00 1,173.85 649.81 649.81 649.81 649.81 433.21 321.41
4.02.02 5,198.49
DOBLADO Y COLOCADO (VIGA) Ejecutado 670.77 0.00 1,173.85
Programado 1,227.39 2,454.77 1,227.39 1,227.39 818.26 409.13
4.02.03 CONCRETO F´C=210KG/CM2 PARA VIGAS 7,364.32
Ejecutado 237.56 1,187.79
4.03 LOSA ALIGERADA 68,143.23
ENCOFRADO Y DESENCOFRADOPARA LOSA Programado 2,494.84 4,989.68 4,989.68 1,995.87 1,995.87 4,989.68 3,492.78
4.03.01 24,948.40
ALIGERADA Ejecutado 4,023.93 804.79
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 1,333.53 333.38 2,000.29 2,066.97 1,033.48 1,033.48 1,033.48 1,033.48 466.74
4.03.02 10,334.84
DOBLADO Y COLOCADO (LOSA ALIGERADA) Ejecutado 1,333.53 333.38 2,000.29
CONCRETO F´C=175KG/CM2 PARA LOSA Programado 3,720.94 1,860.47 3,720.94 1,860.47 1,860.47 3,720.94 1,860.47
4.03.03 18,604.71
ALIGERADA Ejecutado 600.15 3,000.76
LADRILLO HUECO PARA TECHO 8x30x30 CM (LOSA Programado 1,781.91 1,781.91 1,781.91 3,563.82 3,563.82 1,425.53 356.38
4.03.04 14,255.28
ALIGERADA) Ejecutado 2,299.24 459.85
4.04 COLUMNETA DE FACHADA 1,868.18
ENCOFRADO Y DESENCOFRADO DE COLUMNA Programado 109.16 109.16 109.16 218.32 218.32 87.33 21.83
4.04.01 873.29
CIRCULAR EN FACHADA Ejecutado 84.51
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 157.51 59.07 39.38 137.83 15.26 30.52 15.26 30.52 30.52 30.52 63.99
4.04.02 DOBLADO Y COLOCADO (PARA COLUMNETA DE 610.37
FACHADA) Ejecutado 157.51 59.07 39.38 137.83 19.69
CONCRETO F´C=175KG/CM2 PARA COLUMNETA Programado 38.45 76.90 38.45 76.90 76.90 76.90
4.04.03 384.52
CIRCULAR Ejecutado
5 MUROS Y TABIQUES DE ALBAÑILERIA 170,110.10
5.01 MUROS Y SOBRECIMIENTO 170,110.10
Programado 5,722.20 39,940.65 4,222.80 5,291.25
5.01.01 BLOQUE DE CONCRETO DE 39X19X14CM 55,176.90
Ejecutado 5,722.20 39,940.65 4,222.80 5,291.25
Programado 809.60 3,634.00 167.32 83.66 167.32 157.63
5.01.02 MEDIO BLOQUE DE CONCRETO DE 39X19X14CM 5,019.52
Ejecutado 809.60 3,634.00 575.92
Programado 275.40 3,202.80 826.20 44.27 22.13 44.27 11.73
5.01.03 BLOQUE DE CONCRETO EN L DE 39X19X14CM 4,426.80
Ejecutado 275.40 3,202.80 826.20 76.50 45.90
Programado 229.50 86.70
5.01.04 BLOQUE DE CONCRETO TIPO VIGA DE 39X19X14CM 316.20
Ejecutado 229.50 86.70
Programado 1,572.88 3,145.77 4,718.65 1,572.88 6,291.53 4,718.65 4,875.94 9,751.87 4,875.94 3,250.62 2,437.97 1,546.67
5.01.05 MURO CON BLOQUES DE CONCRETO DE 39X19X14C 48,759.36
Ejecutado 1,572.88 3,145.77 4,718.65 1,572.88 6,291.53 4,718.65 3,145.77 3,145.77 11,010.18
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 02


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH; CENTRO POBLADO HUACA CORRAL - DISTRITO DE
PROYECTO:
GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE ENERO


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20 21 22 23 24 25 26
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27 28-31 01-03 04-10 11-17 18-24 25-27
ACERO CORRUGADO F´Y=4200 KG/CM2 INC Programado 1,105.39 2,210.78 3,316.17 1,105.39 4,421.56 3,316.17 3,426.71 6,853.42 3,426.71 2,284.47 1,713.36 1,086.97
5.01.06 DOBLADO Y COLOCADO (MUROS CON BLOQUES 34,267.12
DE CONCRETO)
Ejecutado 1,105.39 2,210.78 3,316.17 1,105.39 4,421.56 3,316.17 2,210.78 2,210.78 7,737.74
CONCRETO GROUT F´C=210KG/CM2 PARA MUROS Programado 671.82 1,343.63 2,015.45 671.82 2,687.26 2,015.45 2,082.63 4,165.26 2,082.63 1,388.42 1,041.31 660.62
5.01.07 20,826.28
CON BLOQUES DE CONCRETO Ejecutado 671.82 1,343.63 2,015.45 671.82 2,687.26 2,015.45 1,343.63 1,343.63 4,702.71
Programado 297.60 87.86 439.31 219.65 146.44 87.86 39.21
5.01.08 JUNTA DE CONSTRUCCIÓN EN ALFÉIZAR 1,317.92
Ejecutado 297.60 127.54 637.70
6 COBERTURAS 90,271.61
6.01 COBERTURA EN FACHADA 29,030.58
COBERTURA EN FACHADA CON BAMBÚ O CAÑA Programado 3,896.24 3,896.24 3,896.24 3,896.24
6.01.01 15,584.94
GUAYAQUIL Ejecutado
HABILITACIÓN Y PRESERVACIÓN DE BAMBÚ O Programado 560.64 560.64 560.64 560.64
6.01.02 2,242.54
CAÑA GUAYAQUIL Ejecutado
RECUBRIMIENTO CON POLIETILENO Y CEMENTO, Programado 2,800.78 2,800.78 2,800.78 2,800.78
6.01.03 11,203.10
ARENA Y CONFITILLO 3/8" MEZCLA 1:5:7 E = 1 1/2" Ejecutado
6.02 RECUBRIMIENTO DE TECHO 61,241.03
RECUBRIMIENTO CON POLIETILENO Y SUELO Programado 1,531.03 15,310.26 15,310.26 15,310.26 13,779.23
6.02.01 61,241.03
CEMENTO 12:1 E=5 CM Ejecutado 1,975.52
7 ACABADOS, REVOQUES, REVESTIMIENTO Y PINT 84,795.79
7.01 VESTIDURAS, DERRAMES Y CENEFAS 16,373.52
Programado 4,284.57 4,284.57 4,284.57 2,142.28
7.01.01 VESTIDURAS Y DERRAMES DE PUERTAS Y VENTAN 14,995.99
Ejecutado
Programado 393.58 393.58 393.58 196.79
7.01.02 CENEFAS EN BORDE DE VANOS 1,377.53
Ejecutado
7.02 PINTURA 22,234.42
PINTURA EN MUROS EXTERIORES (FACHADA Y Programado 3,507.45 1,169.15 2,338.30
7.02.01 7,014.90
POSTERIOR) Ejecutado
Programado 5,832.69 5,832.69 2,916.35
7.02.02 PINTURA EN MUROS INTERIORES (IMPRIMANTE) 14,581.73
Ejecutado
Programado 255.12 255.12 127.56
7.02.03 PINTURA EN CENEFAS 637.79
Ejecutado
7.03 ACABADO CIELO RASO 46,187.85
FALSO CIELO RASO CON PLACAS DE YESO Y Programado 18,475.14 18,475.14 9,237.57
7.03.01 46,187.85
PERFILERIA DE ALUMINIO Ejecutado
8 PISOS Y PAVIMENTOS 10,089.32
8.01 PISOS 4,911.94
FROTACHADO EN CONCRETO CON MORTERO C/A Programado 316.90 1,109.15 1,267.60 158.45 158.45 316.90 140.34 982.39 327.46 134.31
8.01.01 4,911.94
1:1 LOSA DE CIMENTACIÓN Ejecutado 316.90 1,109.15 1,267.60 158.45 158.45 316.90 158.45 158.45 633.80
8.02 VEREDAS 5,177.38
NIVELACION, RELLENO Y APISONADO E=0.175m Programado 33.36 50.03 100.07 100.07 40.03 40.03 100.07 136.76
8.02.01 600.39
C/MAT DE PRESTAMO, VEREDA Ejecutado
VEREDA DE CONCRETO F'C=140KG/CM2, E=0.175m Programado 228.92 343.38 686.76 686.76 274.70 274.70 686.76 251.81
8.02.02 3,433.78
ACABADO SEMIPULIDO INCL/BRUÑADO Ejecutado
Programado 36.48 54.72 109.45 109.45 43.78 43.78 109.45 149.57
8.02.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS 656.67
Ejecutado
Programado 32.44 48.65 97.31 97.31 38.92 38.92 97.31 35.68
8.02.04 JUNTAS ASFALTICAS DE 1/2" X 4" 486.54
Ejecutado
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 02


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH; CENTRO POBLADO HUACA CORRAL - DISTRITO DE
PROYECTO:
GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE ENERO


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20 21 22 23 24 25 26
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27 28-31 01-03 04-10 11-17 18-24 25-27
9 ZOCALOS Y CONTRAZOCALOS 5,546.65
9.01 ZOCALOS 5,546.65
ZOCALO DE CEMENTO SOBRE MURO EXTERIOR Programado 693.33 693.33 693.33 1,386.66 1,386.66 693.33
9.01.01 5,546.65
H=55CM INC/BRUÑAS Ejecutado
10 PUERTAS Y VENTANAS 76,078.65
10.01 PUERTAS 63,678.65
PUERTA METALICA 0.90X2.41 CON PAÑO FIJO Y Programado 4,107.50 4,107.50 4,107.50 8,215.00 8,215.00 2,053.75 2,053.75
10.01.01 VENTANILLA PIVOTANTE INC. VIDRIO, CHAPA E 32,860.00
Ejecutado
INSTALACIÓN (P-01)
PUERTA CONTRAPLACADA 0.85X2.41 CON Programado 2,606.71 2,606.71 2,606.71 5,213.43 5,213.43 1,303.36 1,303.36
10.01.02 SOBRELUZ INC. CHAPA,VIDRIO E INSTALACION (P- 20,853.70
Ejecutado
02)
Programado 1,245.62 1,245.62 1,245.62 2,491.24 2,491.24 622.81 622.81
10.01.03 ATAGUIA EN PUERTAS (FACHADA Y POSTERIOR) 9,964.95
Ejecutado
10.02 VENTANAS 12,400.00
VENTANA DE ALUMINIO 1.10X1.60 M INCLUYE Programado 1,550.00 1,550.00 1,550.00 3,100.00 3,100.00 775.00 775.00
10.02.01 12,400.00
VIDRIO E INSTALACIÓN (V-01) Ejecutado
11 INSTALACIONES ELECTRICAS 20,502.16
11.01 INSTALACION ELECTRICAS 20,502.16
Programado 1,322.72 1,322.72 3,306.80 661.36 1,984.08 1,322.72 6,834.05 2,278.02 1,469.69
11.01.01 INSTALACION ELECTRICA EN MODULO 20,502.16
Ejecutado 1,322.72 1,322.72 3,306.80 661.36 1,984.08 1,322.72 1,984.08 3,306.80 1,322.72
12 INSTALACIONES SANITARIAS 5,655.95
12.01 INSTALACIONES PARA DRENAJE 5,655.95
Programado 182.45 547.35 912.25 729.80 364.90 706.99 1,413.99 706.99 91.23
12.01.01 MONTANTES DE DRENAJE 5,655.95
Ejecutado 182.45 547.35 912.25 729.80 364.90 547.35 912.25 364.90
13 MITIGACION DEL IMPACTO AMBIENTAL Y LIMPI 12,089.07
13.01 MITIGACION Y LIMPIEZA 12,089.07
Programado 398.40 929.60 531.20 32.16 128.65 32.16 6.22
13.01.01 MITIGACION DEL IMPACTO AMBIENTAL (APORTE) 2,058.40
Ejecutado 398.40 929.60 531.20 199.20
MITIGACION DEL IMPACTO AMBIENTAL Programado 193.75 775.00 193.75 387.50
13.01.02 1,550.00
(ARBUSTOS ORNAMENTALES) Ejecutado
ACARREO MATERIAL EXCED, EXCAV, DRENAJES Y Programado 5,744.97 820.71 273.57 820.71 132.51 530.04 132.51 25.65
13.01.03 8,480.67
LIMPIEZA DE OBRA FINAL (APORTE) Ejecutado 5,744.97 820.71 273.57 820.71 820.71
FORMATO N° 23

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO REPROGRAMADO 02


"MEJORAMIENTO DE VIVIENDA RURAL EN LOS CENTROS POBLADOS EL CASTILLO, CASCAJAL BAJO - LA CUADRA Y OTROS - DISTRITO DE CHIMBOTE - PROVINCIA DE SANTA - DEPARTAMENTO DE ANCASH; CENTRO POBLADO HUACA CORRAL - DISTRITO DE
PROYECTO:
GUADALUPITO - PROVINCIA DE VIRU - DEPARTAMENTO DE LA LIBERTAD"
CONVENIO N°: 176-2019 LLIB/VMVU/PNVR S/817,127.93
RESIDENTE: Ing. TITO MARTIN RAMOS JIMENEZ SUPERVISOR: Arq.LILIAN ESTHER TORRES CUMPA
FECHA INICIO: 8/10/2020

PRESUPUEST Mes AGOSTO SETIEMBRE NOVIEMBRE DICIEMBRE ENERO


N° PARTIDA
O Semana 1 2 3 4A 4B 5 6 7 13 15 16 17 17A 18 19 20 20 21 22 23 24 25 26
Dia 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 2-8 9-15 16-22 23-29 30 1-6 7-13 14-20 21-27 28-31 01-03 04-10 11-17 18-24 25-27
14 FLETE Y TRANSPORTE 26,697.69
14.01 FLETE Y TRANSPORTE DE MATERIALES 22,314.45
FLETE TERRESTRE TRANSP. MATERIALES DEL Programado 146.45 1,669.56 2,841.18 322.20 2,343.24 292.90 585.81 292.90 292.90 90.80 90.80 90.80 20.50
14.01.01 PROVEEDOR AL ALMACEN (INC. CARGA - 9,080.05
DESCARGA) Ejecutado 146.45 1,669.56 2,841.18 322.20 2,343.24 292.90 585.81 292.90 292.90 292.90
FLETE TERRESTRE TRANSP. MATERIALES DE Programado 3,131.58 101.02 4,848.89 2,424.45 808.15 404.07 404.07 125.26 125.26 125.26 28.29
14.01.02 ALMACEN A PUNTA DE CARRETERA (INC. CARGA - 12,526.30
DESCARGA)
Ejecutado 3,131.58 101.02 4,848.89 2,424.45 808.15 404.07 404.07 404.07
FLETE TERRESTRE TRANSP. MATERIALES PUNTA Programado 3.88 22.00 7.76 2.59 1.29 1.29 0.40 0.40 0.40 0.09
14.01.03 40.11
DE CARRETERA A VIVIENDA Ejecutado 3.88 22.00 7.76 2.59 1.29 1.29 1.29
ACOMPAÑAMIENTO, CARGA Y DESCARGA Programado 200.40 15.08 215.48 129.29 43.10 21.55 6.68 6.68 6.68 23.05
14.01.04 TRANSP. DE MATERIALES PUNTA DE CARRETERA 667.99
A VIVIENDA (APORTE) Ejecutado 200.40 15.08 215.48 129.29 43.10 21.55 43.10
14.02 FLETE Y TRANSPORTE DE AGREGADOS Y PIEDRA 4,383.24
FLETE TERRESTRE TRANSP. PIEDRA DE CANTERA Programado 0.29 0.19 0.35 0.06 0.03 0.03 0.01 0.01 0.01
14.02.01 A PUNTA DE CARRETERA (INC. CARGA - 1.00
DESCARGA) Ejecutado 0.29 0.19 0.35 0.06 0.03 0.03 0.03
FLETE TERRESTRE TRANSP. DE AGREGADO Y Programado 130.25 7.26 53.48 7.64 15.28 7.64 7.64 2.37 2.37 2.37 0.53
14.02.02 236.82
PIEDRA DE PUNTA DE CARRETERA A VIVIENDA Ejecutado 130.25 7.26 53.48 7.64 15.28 7.64 7.64 7.64
ACOMPAÑAMIENTO, CARGA Y DESCARGA Programado 935.84 133.69 267.38 41.44 41.44 41.44 143.05
2,279.43 127.01 133.69
14.02.03 TRANSP. DE AGREGADO Y PIEDRA DE PUNTA DE 4,144.42
CARRETERA A VIVIENDA (APORTE) Ejecutado 2,279.43 127.01 935.84 133.69 267.38 133.69 267.38
FLETE TERRESTRE TRANSP. AGREGADOS DEL Programado 0.55 0.03 0.23 0.03 0.06 0.03 0.03 0.01 0.01 0.01
14.02.04 PROVEEDOR A PUNTA DE CARRETERA (INC. 1.00
CARGA - DESCARGA)
Ejecutado 0.55 0.03 0.23 0.03 0.06 0.03 0.03 0.03
Programado 15,094.38 9,041.77 2,187.57 146.45 3,849.96 5,251.41 38,304.53 73,603.13 22,362.95 43,896.47 34,079.18 51,758.80 8,879.97 20,353.86 28,075.25 19,859.26 50,774.24 44,685.67 49,920.08 71,343.72 104,037.75 74,962.42 44,659.11
TOTAL 817,127.93
Ejecutado 15,094.38 9,041.77 2,187.57 146.45 3,849.96 5,251.41 38,304.53 73,603.13 22,362.95 43,896.47 34,079.18 51,758.80 8,879.97 20,353.86 28,075.25 14,828.84 0.00 0.00 0.00 0.00 26,923.54 44,823.02 0.00

P = PROGRAMADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 2.74% 5.37% 4.17% 6.33% 1.09% 2.49% 3.44% 2.43% 6.21% 5.47% 6.11% 8.73% 12.73% 9.17% 5.47%
AVANCE SEMANAL (%)
E = EJECUTADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 2.74% 5.37% 4.17% 6.33% 1.09% 2.49% 3.44% 1.81% 0.00% 0.00% 0.00% 0.00% 3.29% 5.49% 0.00%
P = PROGRAMADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 20.79% 26.16% 30.33% 36.66% 37.75% 40.24% 43.68% 46.11% 52.32% 57.79% 63.90% 72.63% 85.36% 94.53% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 20.79% 26.16% 30.33% 36.66% 37.75% 40.24% 43.68% 45.49% 45.49% 45.49% 45.49% 45.49% 48.79% 54.27% 54.27% ###

P = PROGRAMADO 26,470.17 3.24% 121,009.03 14.81% 160,977.35 19.70% 163,748.29 20.04% 344,923.09 42.21%
AVANCE MENSUAL (%)
E = EJECUTADO 26,470.17 3.24% 121,009.03 14.81% 160,977.35 19.70% 63,257.95 7.74% 71,746.55 8.78%
P = PROGRAMADO 26,470.17 3.24% 147,479.20 18.05% 308,456.55 37.75% 472,204.84 57.79% 817,127.93 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 26,470.17 3.24% 147,479.20 18.05% 308,456.55 37.75% 371,714.50 45.49% 443,461.05 54.27%

FECHA DE INICIO DE OBRA 8/10/2020


TRANSFERENCIAS MONTO
PLAZO DE EJECUCIÓN 171
FINANCIMIENTO PNVR S/. 817,127.93 FECHA DE TERMINO REPROGRAMADO AMPL PLAZO 02 1/27/2021
FORMATO Nº 15
VALORIZACION DE AVANCE SEMANAL DE OBRA
“MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI MONTO DEL PROYECTO : S/ 2,186,274.48
PROYECTO: URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA
DE HUANTA - DEPARTAMENTO DE AYACUCHO”

NE CONVENIO:362-2020 AYA/VMVU/PNVR FECHA DE VALORIZACIÓN 28/06/2022 al 7/3/2021


PLAZO DE EJECUCION 150
PLAZO DE EJECUCION SEGÚN AMPLIACION DE PLAZO 01 CORRESPONDE AL MES DE: SETIEMBRE- 2021
PLAZO DE EJECUCION SEGÚN AMPLIACION DE PLAZO 02
PLAZO DE EJECUCION SEGÚN AMPLIACION DE PLAZO 03

AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Unid Metrado P. Unit. Presup. Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. %

01. 00. 00. OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 34,198.97


PROCEDIMIENTO OBLIGATORIO PARA INICIO DE LOS
01. 01. 00. TRABAJOS 6,663.00
1.01.01 LIMPIEZA Y DESINFECCIÓN DEL CENTRO DE TRABAJO und 1.00 655.00 655.000 0.88 576.40 88.00% 0.88 576.40 88.00% 0.12 78.60 12.00%
EVALUACIÓN DE LAS CONDICIONES DE SALUD DEL
1.01.02 TRABAJO PREVIO AL INICIO A OBRA 1.00 480.00 480.000 0.88 422.40 88.00% 0.88 422.40 88.00% 0.12 57.60 12.00%
und
1.01.03 LAVADO Y DESINFECCIÓN DE MANOS und 1.00 1,658.00 1,658.000 0.88 1,459.04 88.00% 0.88 1,459.04 88.00% 0.12 198.96 12.00%
SENSIBILIZACIÓN DE LA PREVENCIÓN DEL CONTAGIO EN
1.01.04 EL CENTRO DE TRABAJO 1.00 3,870.00 3,870.000 0.88 3,405.60 88.00% 0.88 3,405.60 88.00% 0.12 464.40 12.00%
und
PROCEDIMIENTO OBLIGATORIO PARA INICIO DE LOS
01. 02. 00. TRABAJOS 9,187.50
01. 02. 01. PROCESO PARA INICIO DEL TRABAJO und 1.00 9,187.50 9,187.500 0.88 8,085.00 88.00% 0.88 8,085.00 88.00% 0.12 1,102.50 12.00%
01. 03. 00. TRABAJOS PRELIMINARES 597.34
01. 03. 01. CARTEL DE OBRA DE 4.00 X 2.50 und 1.00 597.34 597.340 1.00 597.34 100.00% 1.00 597.34 100.00% - - 0.00%
01. 03. 02. TRAZO NIVELES Y REPLANTEO PRELIMINAR 4,025.38
01. 03. 03. LIMPIEZA, TRAZOS, NIVELES (REPLANTEO PRELIMINAR) 3,120.450 1.290 4,025.380 2,746.00 3,542.33 88.00% 2,746.00 3,542.33 88.00% 374.45 483.05 12.00%
m2
01. 03. 00. SEGURIDAD Y SALUD 13,725.75
01. 03. 01. EQUIPO DE SEGURIDAD INDIVIDUAL glb 75.00 98.55 7,391.250 66.00 6,504.30 88.00% 66.00 6,504.30 88.00% 9.00 886.95 12.00%
01. 03. 02. EQUIPO DE SEGURIDAD COLECTIVA glb 75.00 29.82 2,236.500 66.00 1,968.12 88.00% 66.00 1,968.12 88.00% 9.00 268.38 12.00%
01. 03. 03. SEÑALIZACION TEMPORAL DE SEGURIDAD glb 75.00 6.46 484.500 66.00 426.36 88.00% 66.00 426.36 88.00% 9.00 58.14 12.00%
01. 03. 04. CAPACITACION EN SALUD Y SEGURIDAD glb 75.00 48.18 3,613.500 53.00 2,553.54 70.67% 5.00 240.90 6.67% 58.00 2,794.44 77.33% 17.00 819.06 22.67%
02. 00. 00. MOVIMIENTO DE TIERRAS 47,132.00
02. 01. 00. EXCAVACIONES 47,132.00
CORTE Y EXPLANACION DE TERRENO NORMAL MANUAL
02. 01. 01. (APORTE) 1,560.23 22.79 35,557.642 1,373.00 31,290.72 88.00% 1,373.00 31,290.72 88.00% 187.23 4,266.92 12.00%
m3
EXCAVACION DE ZANJAS PARA CIMIENTO (HASTA H=1.20
02. 01. 02. M) 507.87 22.79 11,574.357 446.93 10,185.43 88.00% 446.93 10,185.43 88.00% 60.94 1,388.92 12.00%
m3
03. 00. 00. OBRAS DE CONCRETO SIMPLE 113,429.71
03. 01. 00. CIMIENTO 60,180.90
CIMIENTO CORRIDO DE CONCRETO CICLOPEO MEZCLA
03. 01. 01. CEMENTO HORMIGON 1:10 + 50% P.G. m3 338.58 136.30 46,148.450 270.86 36,918.76 80.00% - 0.00% 270.86 36,918.76 80.00% 67.72 9,229.69 20.00%
03. 01. 02. SUMINISTRO DE PIEDRA MEDIANA (APORTE) m3 169.29 45.50 7,702.695 135.43 6,162.16 80.00% - 0.00% 135.43 6,162.16 80.00% 33.86 1,540.54 20.00%
NIVELACION RELLENO Y APISONADO DE CAMA DE
03. 01. 03. PIEDRA MEDIANA ( APORTE) m3 169.29 37.39 6,329.753 135.43 5,063.80 80.00% - 0.00% 135.43 5,063.80 80.00% 33.86 1,265.95 20.00%
03. 02. 00. SOBRECIMIENTO 53,248.81 - 0.00%
SOBRECIMIENTOS MEZCLA CEMENTO-HORMIGON 1:8 +
03. 02. 01. 30% PM m3 131.63 186.85 24,595.066 115.83 21,643.66 88.00% -10.53 -1,967.61 -8.00% 105.30 19,676.05 80.00% 26.33 4,919.01 20.00%
ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO
03. 02. 02. h=0.35m 1,283.77 22.32 28,653.746 1,129.72 25,215.30 88.00% -102.70 -2,292.30 -8.00% 1,027.02 22,923.00 80.00% 256.75 5,730.75 20.00%
m2
04. 00. 00. OBRAS DE CONCRETO ARMADO 235,266.92
04. 01. 00. COLUMNAS 126,926.72
04. 01. 01. CONCRETO COLUMNAS f'c=175 kg/cm2 m3 96.05 347.55 33,382.178 33.30 11,572.49 34.67% 6.40 2,225.48 6.67% 39.70 13,797.97 41.33% 56.35 19,584.21 58.67%
04. 01. 02. ENCOFRADO Y DESENCOFRADO DE COLUMNAS 1,074.94 30.88 33,194.147 372.65 11,507.30 34.67% 71.66 2,212.94 6.67% 444.31 13,720.25 41.33% 630.63 19,473.90 58.67%
m2
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
04. 01. 03. COLUMNAS 13,716.00 4.40 60,350.400 10,972.80 48,280.32 80.00% 10,972.80 48,280.32 80.00% 2,743.20 12,070.08 20.00%
kg
04. 02. 00. VIGAS 108,340.19
04. 02. 01. CONCRETO VIGAS f'c=175 kg/cm2 m3 117.96 300.48 35,444.621 6.29 1,890.38 5.33% 9.44 2,835.57 8.00% 15.73 4,725.95 13.33% 102.23 30,718.67 86.67%
04. 02. 02. ENCOFRADO Y DESENCOFRADO EN VIGAS 1,226.50 35.38 43,393.570 65.41 2,314.32 5.33% 98.12 3,471.49 8.00% 163.53 5,785.81 13.33% 1,062.97 37,607.76 86.67%
m2
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 PARA
04. 02. 03. VIGAS 6,705.00 4.40 29,502.000 2,324.40 10,227.36 34.67% 1,072.80 4,720.32 16.00% 3,397.20 14,947.68 50.67% 3,307.80 14,554.32 49.33%
kg
04. 03. 00. TIJERALES Y RETICULADOS 142,442.82
04. 03. 02. TIJERAL DE MADERA DE 2"X4" und 300.00 302.33 90,699.000 - - 0.00% - - 0.00% 300.00 90,699.00 100.00%
04. 03. 03. CORREAS DE MADERA 2"X2" 4,757.22 9.67 46,002.317 - - 0.00% - - 0.00% 4,757.22 46,002.32 100.00%
p2
04. 03. 04. FRISO DE MADERA DE 1 1/2" X 2 1/2" 574.15 10.00 5,741.500 - - 0.00% - - 0.00% 574.15 5,741.50 100.00%
p2
06. 00. 00. COBERTURAS 126,887.49
06. 01. 01. COBERTURA DE PLANCHA CORRUGADA GALVANIZADA 3,078.15 38.36 118,077.834 - - 0.00% - - 0.00% 3,078.15 118,077.83 100.00%
m2
CUMBRERA CALAMINA 0.30 mm, 11 CANALES INCL
06. 01. 02. PINTADO 461.48 19.09 8,809.653 - - 0.00% - - 0.00% 461.48 8,809.65 100.00%
m
06. 01. 02. CIELO RASOS 65,547.75 0.00%
AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Unid Metrado P. Unit. Presup. Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. %
CIELORASO CON PLACA DE YESO LAMINADO CON VINYL
06. 01. 03. Y FOIL DE ALUMINIO 0.61x0.61 e=6MM / INC. ACCESORIOS 1,351.50 48.50 65,547.750 - - 0.00% - - 0.00% 1,351.50 65,547.75 100.00%
E INSTALACION m
05. 00. 00. MUROS Y TABIQUES DE ALBAÑILERIA ARMADA 390,033.65
MURO DE LADRILLO TIPO PANDERETA MEDIDAS SEGUN
05. 01. 01. PLANO 5,653.98 56.56 319,789.109 3,090.84 174,818.05 54.67% 452.32 25,583.13 8.00% 3,543.16 200,401.17 62.67% 2,110.82 119,387.93 37.33%
m2
SUMINISTRO E INSTALACION DE POLIESTIRENO DE 1"
05. 01. 02. DENSIDAD 10 4,089.74 7.09 28,996.257 2,235.72 15,851.29 54.67% 327.18 2,319.70 8.00% 2,562.90 18,170.99 62.67% 1,526.84 10,825.27 37.33%
m2
05. 01. 03. BRUÑAS DE MUROS DE LADRILLO m 21,372.17 1.93 41,248.288 11,683.45 22,549.06 54.67% 1,709.77 3,299.86 8.00% 13,393.23 25,848.93 62.67% 7,978.94 15,399.36 37.33%
07. 00. 00. REVOQUES 1,443.66
BOTA AGUA EN VANO DE VENTANA CON CORTA GOTERA.
07. 01. 01. CON MORTERO 1:4 E= 1.5 CM m2 52.65 27.42 1,443.663 - - 0.00% - - 0.00% 52.65 1,443.66 100.00%
07. 01. 01. ENLUCIDO DE YESO 102,443.80
07. 02. 00. ENLUCIDO DE YESO EN MURO DE LADRILLO m2 4,595.36 17.37 79,821.403 - - 0.00% - - 0.00% 4,595.36 79,821.40 100.00%
DERRAMES DE VANOS CON YESO E=1.5CM m 2,356.50 9.60 22,622.400 - - 0.00% - - 0.00% 2,356.50 22,622.40 100.00%
08. 00. 00. PISOS 63,341.71
BASE DE TIERRA MATERIAL PROPIO
08. 01. 01. COMPACTADO/NIVELADO E= 10 CM m2 1,492.50 4.71 7,029.680 - - 0.00% - - 0.00% 1,492.50 7,029.68 100.00%

08. 02. 01. ACERO DE TEMPERATURA m2 1,492.50 8.03 11,984.780 - - 0.00% - - 0.00% 1,492.50 11,984.78 100.00%

PISO DE CEMENTO PULIDO E:4" ACAB. CON OCRE INC.


08. 02. 02. BRUÑADO m2 1,492.50 29.70 44,327.250 - - 0.00% - - 0.00% 1,492.50 44,327.25 100.00%
08. 02. 01. VEREDAS 7,971.06
NIVELACION, RELLENO Y APISONADO INTERIOR C/MAT
08. 02. 03. PROPIO (APORTE) m2 180.00 4.71 847.800 - - 0.00% - - 0.00% - - 0.00% 180.00 847.80 100.00%

VEREDA DE CONCRETO SIMPLE F'C=140 KG/CM2 E= 10


09. 00. 00. CM ACABADO FROTACHADO INCLUYE BRUÑADO m2 180.00 33.12 5,961.600 - - 0.00% - - 0.00% 180.00 5,961.60 100.00%

09. 01. 00. ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 52.54 22.11 1,161.660 - - 0.00% - - 0.00% 52.54 1,161.66 100.00%
09. 00. 00. ZOCALOS Y CONTRAZOCALOS 38,915.95
ZOCALO DE CEMENTO SOBRE MURO EXTERIOR
09. 01. 00. H=60CM INC/BRUÑAS m2 857.39 28.22 24,195.550 685.91 19,356.44 80.00% - - 0.00% 685.91 19,356.44 80.00% 171.48 4,839.11 20.00%
CONTRAZOCALO DE MADERA CON RODON, DE 5.80 CM X
09. 01. 01. 1.90 CM X 2.40 M m 1,269.00 11.60 14,720.400 - - 0.00% - - 0.00% 1,269.00 14,720.40 100.00%
10. 00. 00. PUERTAS 106,459.50
PUERTA MACHIHEMBRADA DE 0.90X2.10 M. INCLUYE.
10. 01. 01. INSTALACION und 75.00 641.08 48,081.000 - - 0.00% - - 0.00% 75.00 48,081.00 100.00%
PUERTA CONTRAPLACADA DE 0.90X2.10 M. INCLUYE.
10. 01. 02. INSTALACION und 75.00 259.46 19,459.500 - - 0.00% - - 0.00% 75.00 19,459.50 100.00%
PUERTA CONTRAPLACADA DE 0.80X2.10 M. INCLUYE.
10. 01. 03. INSTALACION und 150.00 259.46 38,919.000 - - 0.00% - - 0.00% 150.00 38,919.00 100.00%
10. 01. 03. VENTANAS 77,235.75
VENTANA DE ALUMINIO DE 0.78 X 1.08 M INC/VIDRIO,
10. 02. 01. CON CONTRAVENTANA DE MADERA und 225.00 245.18 55,165.500 - - 0.00% - - 0.00% 225.00 55,165.50 100.00%

11. 00. 00. VENTANA CENITAL und 75.00 294.27 22,070.250 - - 0.00% - - 0.00% 75.00 22,070.25 100.00%
11. 00.
00. INSTALACIONES ELECTRICAS 30,551.25
11. 01.
01. INSTALACION ELECTRICA EN MÓDULO glb 75.00 407.35 30,551.250 - - 0.00% - - 0.00% 75.00 30,551.25 100.00%
12. 00.
00. EVACUACION AGUA PLUVIALES 49,812.29
12. 00.
00. SISTEMA DE EVACUACION DE AGUAS PLUVIALES und 150.00 318.97 47,845.500 - - 0.00% - - 0.00% 150.00 47,845.50 100.00%
ENCOFRADO Y DESENCOFRADO DE DADOS DE
12. 01. 00. CONCRETO. m2 52.50 23.38 1,227.450 - - 0.00% - - 0.00% 52.50 1,227.45 100.00%
CONCRETO SIMPLE f'c=100 kg/cm2 PARA DADOS DE
12. 02. 00. PROTECCION m3 3.28 225.41 739.345 - - 0.00% - - 0.00% 3.28 739.34 100.00%
AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Unid Metrado P. Unit. Presup. Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. %

13. 00. 00. MITIGACION DEL IMPACTO AMBIENTAL Y LIMPIEZA 10,258.50


13. 01. 01. MITIGACION DEL IMPACTO AMBIENTAL (APORTE) glb 75.00 136.78 10,258.500 43.00 5,881.54 57.33% 7.00 957.46 9.33% 50.00 6,839.00 66.67% 25.00 3,419.50 33.33%
13. 01. 01. ACARREOS 20,517.75
ACARREO DE MATERIAL EXCEDENTE Y LIMPIEZA DE
13. 01. 03. OBRA FINAL (APORTE) 75.00 273.57 20,517.750 - - 0.00% - - 0.00% 75.00 20,517.75 100.00%
glb
14. 00. 00. FLETES Y TRANSPORTE 417,007.54
14. 01. 00. FLETE Y TRANSPORTE DE MATERIALES 172,323.76
FLETE TERRESTRE TRANSP. MATERIALES DEL
14. 01. 01. PROVEEDOR AL ALMACEN (INCL. CARGA-DESCARGA) glb 1.00 88,031.07 88,031.070 0.60 52,820.56 60.00% 0.60 52,820.56 60.00% 0.40 35,210.52 40.00%
FLETE TERRESTRE TRANSP. MATERIALES DE ALMACEN A
14. 01. 02. PUNTA DE CARRETERA (INCL. CARGA-DESCARGA) glb 1.00 24,781.96 24,781.960 0.60 14,868.35 60.00% 0.60 14,868.35 60.00% 0.40 9,913.61 40.00%
FLETE RURAL DE MATERIALES PUNTA DE CARRETERA A
14. 01. 03. VIVIENDA (APORTE) glb 1.00 36,456.40 36,456.400 0.60 21,872.62 60.00% 0.60 21,872.62 60.00% 0.40 14,583.77 40.00%

ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE


14. 01. 04. MATERIALES PUNTA DE CARRETERA A VIVIENDA glb 1.00 23,054.33 23,054.330 0.60 13,831.83 60.00% 0.60 13,831.83 60.00% 0.40 9,222.50 40.00%
(APORTE)

14. 02. 00. FLETE Y TRANSPORTE DE DE AGREGADOS Y PIEDRAS 244,683.78 -

FLETE TERRESTRE TRANSP. AGREGADOS DEL PROVEDOR


14. 02. 01. A PUNTA DE CARRETERA (INCL. CARGA-DESCARGA) glb 1.00 84,340.40 84,340.400 0.80 67,472.32 80.00% 0.80 67,472.32 80.00% 0.20 16,868.08 20.00%

FLETE TERRESTRE TRANSP. PIEDRA DE CANTERA A


14. 02. 02. PUNTA DE CARRETERA (INCL. CARGA-DESCARGA) glb 1.00 26,164.80 26,164.800 0.80 20,931.84 80.00% 0.80 20,931.84 80.00% 0.20 5,232.96 20.00%

FLETE TERRESTRE TRANSP. DE AGREGADO Y PIEDRA DE


14. 02. 03. PUNTA DE CARRETERA A VIVIENDA (APORTE) glb 1.00 82,653.38 82,653.380 0.80 66,122.70 80.00% 0.80 66,122.70 80.00% 0.20 16,530.68 20.00%

ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE


14. 02. 04. AGREGADO Y PIEDRA DE PUNTA DE CARRETERA A glb 1.00 51,525.20 51,525.200 0.80 41,220.16 80.00% 0.80 41,220.16 80.00% 0.20 10,305.04 20.00%
VIVIENDA (APORTE)
COSTO DIRECTO TOTAL S/ 2,080,898.07 789,409.21 37.94% 43,606.94 2.10% 833,016.15 40.03% 1,247,881.92 59.97%

RESIDENTE DE OBRA SUPERVISOR DE OBRA


CURVA "S" PROGRAMADO VS EJECUTADO

CONVENIO PNVR 362-2020-AYA/VMVU/PNVR


“MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC -
OBRA:
DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”
MODALIDAD DE EJECUCION : NUCLEO EJECUTOR
COSTO DIRECTO : 2,080,898.07 Soles
NUEVO PLAZO DE EJECUCION : 150 DIAS CALENDARIOS
RESIDENTE DE OBRA : ING. JOSEPH G. MELENDEZ RAMIREZ

CURVA DE AVANCE DE OBRA ACUMULADOS


PROGRAMADO VS EJECUTADO
120.00%

99.17% 99.85% 100.00%


AVANCE MENSUAL ACUMULADO EN (%)

100.00% 97.45%
94.50%
92.32%
90.38%
85.31%

80.00% 78.34%

71.71%

64.64%

60.00% 57.04%

49.57%
42.18%

34.48% 40.03%
40.00% 29.04% 37.94%
32.06% 36.46%
34.31%
22.77% 32.60% 32.96%
29.53%
26.07%

16.84%
11.45%
20.00%
5.16%
6.67% 18.62%
2.14% 4.89% 6.15% 11.54%
10.24% 9.35%
0.76% 8.03% 15.03%
0.00%
0.53% 8.18% PROG. ACUMULADO PROG. EJECUTADO
0.00%
0.00%
INICIO 14-19 21-26 28-30 1-3 5-10 12-14 1-4 6-11 13-18 20-25 27-30 1-2 4-9 11-16 18-23 25-31 1-6 8-13 15-20 22-27 29-30 1-4 6-11 13-18 20-25 27-28

PLAZO DE EJECUCION 150 DIAS CALENDARIO