Documentos de Académico
Documentos de Profesional
Documentos de Cultura
UBICACIÓN
Departamento : AYACUCHO
Provincia : HUANTA
Distrito : UCHURACCAY, AYAHUANCO Y HUANTA
CP-Localidades : 362-2020 AYA/VMVU/PNVR
DATOS DEL PROYECTO
Convenio : 362-2020 AYA/VMVU/PNVR
Monto Financiado (PNVR) : 2,186,274.48
Monto Financiado modificado (PNVR) :
Desembolso Efectuado a la fecha : 2,186,274.48
Desembolso : 2,186,274.48
N° Beneficiarios : 75
DATOS DE EJECUCIÓN:
Fecha de Inicio de Obra : 6/14/2021
Fecha de Paralizacion de Obra 7/15/2021
Fecha de Reinicio de Obra : 9/1/2021
Plazo de Ejecución : 150 dias calendario
Fecha de Término de Obra : 11/10/2021
Fecha de Nuevo Término de Obra : 12/28/2021
Ejecución Financiera : 15.95%
INFORMACION RELEVANTE
DEL RESIDENTE:
LOS TRABAJOS SE VIENEN EJECUTANDO CON ALGUNAS DIFICULTADES YA QUE LAS LLUVIAS NO NOS DEJAN AVANZAR, TENEMOS DIAS QUE NO SE AVANZA POR EL FACTOR
CLIMATICO, AHORA LAS LLUVIAS NOS JUEGAN EN CONTRA PARA PODER AVANZAR SEGÚN LO REPROGRAMADO.
DEL SUPERVISOR:
OBSERVACIONES
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 DISTRITO DE HUANTA; CENTROS UCHURACCAY,
C-362 6/14/2021 6/19/2021 AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-362 6/21/2021 6/26/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 DISTRITO DE HUANTA; CENTROS UCHURACCAY,
C-362 6/28/2021 7/3/2021 AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-362 7/5/2021 7/10/2021 AYA/VMVU/PNVR DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA AYAHUANCO Y HUANTA LADRILLO
POBLADOS CHOQEWICHQA,
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-363 7/12/2021 7/17/2021 AYA/VMVU/PNVR DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA AYAHUANCO Y HUANTA LADRILLO
POBLADOS CHOQEWICHQA,
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
C-363 9/1/2021 9/5/2021 362-2020 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA UCHURACCAY, LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-363 9/6/2021 9/12/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-363 9/13/2021 9/19/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
C-364 9/20/2021 9/26/2021 362-2020 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA UCHURACCAY, LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-365 9/27/2021 10/2/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-366 10/4/2021 10/9/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-366 10/11/2021 10/16/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
POBLADO RUMI URMASCCA -
362-2020 UCHURACCAY,
C-366 10/18/2021 10/23/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
“MEJORAMIENTO DE VIVIENDA
RURAL EN EL CENTRO POBLADO
LLAMANNIYUQ - DISTRITO DE
AYAHUANCO; EN EL CENTRO
362-2020 POBLADO RUMI URMASCCA - UCHURACCAY,
C-366 10/25/2021 10/30/2021 DISTRITO DE HUANTA; CENTROS AYACUCHO HUANTA LADRILLO
AYA/VMVU/PNVR POBLADOS CHOQEWICHQA, AYAHUANCO Y HUANTA
LAPCCES Y VIZCACHAYOCC -
DISTRITO DE UCHURACCAY -
PROVINCIA DE HUANTA -
DEPARTAMENTO DE AYACUCHO”
ACIONAL DE EJECUCIÓN DE LOS PROYECTOS - REPORTE SEMANAL ACUMULADO DEL: 28/06/20221
COSTO DIRECTO COSTO INDIRECTO TOTAL FINANCIADO PNVR APORTE BENEF. TOTAL
VALOR.
N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. %
54 S/34,198.97 S/24,401.89 71.35% 48 S/47,132.00 S/30,296.55 64.28% 0.6 113,429.72 935.68 0.82%
1 S/34,198.97 S/293.21 0.86% -2 S/47,132.00 -S/1,388.92 -2.95% 3.2 113,429.72 4,890.02 4.31%
0 S/34,198.97 S/146.60 0.43% 22 S/47,132.00 S/13,883.62 29.46% 1.6 113,429.72 2,445.01 2.16%
6 S/34,198.97 S/2,945.75 8.61% 10 S/47,132.00 S/6,003.42 12.74% 3.2 113,429.72 4,878.37 4.30%
VALOR. VALOR.
N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. ACUM. % N° BEN. PRESUP. VALOR. ACUM. %
AUTORIZACION N° VALOR
01 ACUMULADO DEVOLUCION AUTORIZACION N°
PRESUP. VALOR. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % N° BEN. PRESUP. VALOR. ACUM. % VALOR. ACUMULADA ACTUAL % ACUMULADA 02
ACTUAL
10,258.50 478.73 4.67% 20,517.75 - 5 417,007.54 27,298.67 6.55% 91,458.24 4.40% S/0.00 S/0.00
10,258.50 49,711.99 484.59% 20,517.75 - 8 417,007.54 42,943.55 10.30% 105,972.50 5.09% S/0.00 S/0.00
10,258.50 83,345.87 812.46% 20,517.75 - 0 417,007.54 0.02 0.00% 99,533.47 4.78% S/0.00 S/0.00
10,258.50 62,842.70 612.59% 20,517.75 - 0 417,007.54 0.02 0.00% 65,357.32 3.14% S/0.00 S/0.00
10,258.50 1,231.02 12.00% 20,517.75 - 0 417,007.54 - - 71,365.27 3.43% S/348,712.45 S/348,712.45 S/348,712.45
10,258.50 - - 20,517.75 - 0 417,007.54 1.00 0.00% 31,341.00 1.51% S/348,713.45 S/348,713.45 S/348,713.45
10,258.50 - - 20,517.75 - 0 417,007.54 1.00 0.00% 2,856.48 0.14% S/348,713.45 S/348,713.45 S/348,713.45
10,258.50 17,327.86 168.91% 20,517.75 - 0 417,007.54 1.00 0.00% 40,655.93 1.95% S/348,713.45 S/348,713.45 S/348,713.45
10,258.50 - - 20,517.75 - 0 417,007.54 1.00 0.00% 7,433.14 0.36% S/348,713.45 S/348,713.45 S/348,713.45
RETIROS AUTORIZADOS Y DEVOLUCIONES
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45 S/348,712.45
S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45
S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45
S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45
S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45 S/348,713.45
EJECUCIÓN FINANCIERA (APORTE PNVR)
OBSERVACIONES DEL
AUTORIZACION N° AUTORIZACION N° VALOR. VALOR. COORDINADOR
AUTORIZACION N° VALOR ACUMULADO DEVOLUCION 08 VALOR ACUMULADO DEVOLUCION 09 VALOR ACUMULADO DEVOLUCION ACUMULADA ACUMULADA REGIONAL TÉCNICO
07 ACTUAL ACUMULADA ACTUAL ACUMULADA ACTUAL ACUMULADA %
ANTERIOR ACTUAL
PROYECTO: “MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”
PROYECTO: “MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”
ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE 23,054.33 Programado 1,536.96 1,152.72 - - 1,024.64 768.48 1,152.72 - 448.28 1,857.15 1,344.84 1,793.11 1,344.84 1,280.80 2,689.67 3,842.39 2,390.82 426.93 - - - - -
20.01.04 MATERIALES PUNTA DE CARRETERA A VIVIENDA (APORTE)
Ejecutado 230.54 461.09 461.09 461.09 461.09 999.02 999.02 9,758.90 - - - - - - - - - - - - - - - -
20.02 FLETE Y TRANSPORTE DE PIEDRA Y AGREGADOS 244,683.78 - 16,758.12 33,732.43 10,310.65 10,310.65 6,873.76 7,338.92 12,481.78 18,433.68 23,355.09 7,338.92 6,313.49 31,827.61 18,940.47 5,095.83 18,940.47 16,631.91 - - - - - - - - -
FLETE TERRESTRE TRANSP. AGREGADOS DEL PROVEDOR A 84,340.40 Programado 5,060.42 11,807.66 3,373.62 3,373.62 2,249.08 2,249.08 4,498.15 6,184.96 7,871.77 2,249.08 2,249.08 12,369.93 6,747.23 1,686.81 6,747.23 5,622.69 - - - - - - - - -
20.02.01 PUNTA DE CARRETERA (INCL. CARGA-DESCARGA) Ejecutado 12,499.48 8,434.04 8,434.04 17,112.56 1,686.81 8,062.94 8,062.94 3,179.51 - - - - - - - - - - - - - - -
FLETE TERRESTRE TRANSP. PIEDRA DE CANTERA A PUNTA 26,164.80 Programado 2,616.48 3,139.78 1,569.89 1,569.89 1,046.59 1,511.74 2,616.48 2,616.48 2,616.48 1,511.74 290.72 1,395.46 872.16 174.43 872.16 1,744.32 - - - - - - - - -
20.02.02 DE CARRETERA (INCL. CARGA-DESCARGA) Ejecutado 3,749.84 2,616.48 2,616.48 1,308.24 523.30 4,971.31 4,971.31 174.88 - - - - - - - - - - - - - - -
FLETE TERRESTRE TRANSP. DE AGREGADO Y PIEDRA DE 82,653.38 Programado 4,959.20 11,571.47 3,306.14 3,306.14 2,204.09 2,204.09 3,306.14 5,510.23 7,714.32 2,204.09 2,571.44 11,020.45 7,714.32 2,204.09 7,714.32 5,142.88 - - - - - - - - -
20.02.03 PUNTA DE CARRETERA A VIVIENDA (APORTE) Ejecutado 5,510.23 8,265.34 8,265.34 4,132.67 1,653.07 21,489.88 21,489.88 - 4,683.69 - - - - - - - - - - - - - - -
ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE 51,525.20 Programado 4,122.02 7,213.53 2,061.01 2,061.01 1,374.01 1,374.01 2,061.01 4,122.02 5,152.52 1,374.01 1,202.25 7,041.78 3,606.76 1,030.50 3,606.76 4,122.02 - - - - - - - - -
20.02.04 AGREGADO Y PIEDRA DE PUNTA DE CARRETERA A VIVIENDA
(APORTE) Ejecutado 3,435.01 5,152.52 5,152.52 2,576.26 1,030.50 13,396.55 13,396.55 - 2,919.76 - - - - - - - - - - - - - - - -
10,945.19 33,674.06 57,225.62 26,120.25 39,214.05 27,380.80 43,749.31 112,088.96 123,441.01 130,364.08 62,972.35 50,242.82 160,284.42 153,825.56 155,477.86 158,021.95 147,082.87 137,963.85 145,231.46 105,493.49 40,280.10 45,445.62 61,243.83 35,914.92 14,056.60 3,157.02
TOTAL 2,080,898.08
15,822.46 91,458.24 31,421.35 31,421.35 42,943.55 27,145.21 72,599.41 74,592.53 155,049.10 72,092.38 63,753.65 7,611.63 28,011.64 44,736.25 30,752.25 43,606.94 - - - - - - - - - -
P = PROGRAMADO 0.53% 1.62% 2.75% 1.26% 1.88% 1.32% 2.10% 5.39% 5.93% 6.26% 3.03% 2.41% 7.70% 7.39% 7.47% 7.59% 7.07% 6.63% 6.98% 5.07% 1.94% 2.18% 2.94% 1.73% 0.68% 0.15%
AVANCE SEMANAL (%)
E = EJECUTADO 0.76% 4.40% 1.51% 1.51% 2.06% 1.30% 3.49% 3.58% 7.45% 3.46% 3.06% 0.37% 1.35% 2.15% 1.48% 2.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
P = PROGRAMADO 0.53% 2.14% 4.89% 6.15% 8.03% 9.35% 11.45% 16.84% 22.77% 29.04% 32.06% 34.48% 42.18% 49.57% 57.04% 64.64% 71.71% 78.34% 85.31% 90.38% 92.32% 94.50% 97.45% 99.17% 99.85% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 0.76% 5.16% 6.67% 8.18% 10.24% 11.54% 15.03% 18.62% 26.07% 29.53% 32.60% 32.96% 34.31% 36.46% 37.94% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03%
P = PROGRAMADO 101,844.87 4.89% 92,715.11 4.46% 472,615.72 22.71% 677,852.61 32.58% 576,051.78 27.68% 159,818.00 7.68%
AVANCE MENSUAL (%)
E = EJECUTADO 138,702.05 6.67% 101,510.11 4.88% 438,087.06 21.05% 154,718.70 7.44% 0.00 0.00% 0.00 0.00%
P = PROGRAMADO 101,844.87 4.89% 194,559.97 9.35% 667,175.69 32.06% 1,345,028.31 64.64% 1,921,080.09 92.32% 2,080,898.08 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 138,702.05 6.67% 240,212.17 11.54% 678,299.23 32.60% 833,017.93 40.03% 833,017.93 40.03% 833,017.93 40.03%
PROYECTO: “MEJORAMIENTO DE VIVIENDA RURAL EN EL CENTRO POBLADO LLAMANNIYUQ - DISTRITO DE AYAHUANCO; EN EL CENTRO POBLADO RUMI URMASCCA - DISTRITO DE HUANTA; COSTO DIRECTO :
CENTROS POBLADOS CHOQEWICHQA, LAPCCES Y VIZCACHAYOCC - DISTRITO DE UCHURACCAY - PROVINCIA DE HUANTA - DEPARTAMENTO DE AYACUCHO”
PERIODO
Mes JUNIO JULIO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE
ITEM DESCRIPCION PRESUPUESTO
Semana 1 2 3A 3B 4 5 6 7 8 9 10A 10B 11 12 13 14 15 16 17 18 19A 19B 20 21 22 23
Dias 14-19 21-26 28-30 1-3 5-10 12-14 1-4 6-11 13-18 20-25 27-30 1-2 4-9 11-16 18-23 25-31 1-6 8-13 15-20 22-27 29-30 1-4 6-11 13-18 20-25 27-28
OBRAS PROVISIONALES, TRABAJOS PROGRAMADO 3,593.04 5,852.74 3,875.88 2,485.13 1,478.57 1,171.66 1,192.99 1,664.51 1,704.90 1,321.61 943.05 239.34 717.29 717.29 717.29 717.29 717.29 717.29 717.29 717.29 239.10 478.19 717.29 717.29 717.29 68.07
1.00 S/34,198.97
PRELIMINARES, SEGURIDAD Y SALUD EJECUTADO 2,775.19 24,401.89 146.60 146.60 144.54 96.36 - 289.08 240.90 289.08 289.08 96.36 144.54 240.90 240.90 240.90 - - - - - - - - - -
PROGRAMADO 6,873.42 6,873.42 2,945.75 1,963.83 2,945.75 1,963.83 3,600.36 5,678.34 5,553.97 5,392.87 3,340.47 - - - - - - - - - - - - - - -
2.00 MOVIMIENTO DE TIERRAS S/47,132.00
EJECUTADO 12,568.54 30,296.55 -694.46 -694.46 - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - 3,711.04 5,311.15 8,572.48 10,845.85 7,270.28 15,114.97 17,757.88 17,838.38 17,164.72 8,448.26 1,394.71 - - - - - - - - - - - - - -
3.00 CONCRETO SIMPLE S/113,429.72
EJECUTADO - 935.68 2,445.01 2,445.01 3,558.41 11,997.77 16,187.58 14,672.94 10,102.30 10,318.36 6,105.85 1,325.29 6,389.86 4,259.90 4,259.90 -4,259.90 - - - - - - - - - -
PROGRAMADO - - 2,514.60 2,514.60 4,878.37 4,364.99 10,765.79 20,044.08 25,791.66 28,347.19 10,982.56 9,173.37 27,520.12 27,520.12 27,520.12 19,553.52 13,775.84 - - - - - - - - -
4.00 CONCRETO ARMADO S/235,266.93
EJECUTADO - 8,046.72 1,609.34 1,609.34 8,851.39 6,437.38 3,218.69 6,437.38 15,314.22 7,408.07 2,461.12 393.36 2,562.09 11,613.66 9,829.42 15,465.80 - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - 7,842.61 20,168.60 23,527.82 23,527.82 23,527.82 8,232.46 15,826.98 13,295.47 6,493.23 - - - - - -
5.00 TIJERALES Y RETICULADOS S/142,442.82
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - 5,640.50 16,481.01 16,481.01 16,481.01 16,481.01 16,481.01 16,481.01 15,918.17 6,442.79 - - - - - -
6.00 COBERTURAS S/126,887.49
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 13,109.55 13,109.55 13,109.55 13,109.55 13,109.55 - - - - -
7.00 CIELO RASOS S/65,547.75
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - 5,417.13 5,417.13 47,399.92 47,399.92 47,399.92 31,599.95 15,799.97 47,399.92 47,399.92 47,399.92 47,399.92 - - - - - - - - - -
8.00 MUROS S/390,033.64
EJECUTADO - - - - - - - - 52,004.49 46,804.04 52,004.49 5,200.45 15,601.35 26,002.24 15,601.35 31,202.69 - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - 721.83 721.83 - - - - - - -
9.00 REVOQUES S/1,443.66
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - 798.21 1,862.50 13,303.57 13,303.57 17,828.05 18,582.13 18,582.13 10,954.75 7,228.91 - - - - -
10.00 ENLUCIDO DE YESO S/102,443.80
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 15,457.15 15,457.15 14,222.10 14,222.10 3,983.21 - - - - -
11.00 PISO S/63,341.71
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - 47.10 1,613.05 1,613.05 460.24 1,152.81 3,084.80 - - -
12.00 VEREDAS S/7,971.06
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - 268.84 806.52 1,209.78 806.52 3,024.44 3,226.07 7,221.54 6,295.64 2,098.55 3,066.90 4,600.36 3,928.26 2,180.80 181.73
13.00 ZOCALOS Y CONTRAZOCALOS S/38,915.95
EJECUTADO - - - - - - - - 5,806.93 6,452.15 1,935.64 322.61 2,903.47 1,935.64 - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 16,560.37 16,560.37 16,560.37 16,560.37 5,520.12 16,560.37 16,560.37 1,577.18 - -
14.00 PUERTAS S/106,459.50
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - 11,033.68 11,033.68 11,033.68 11,033.68 3,677.89 7,355.79 11,033.68 11,033.68 - -
15.00 VENTANAS S/77,235.75
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - - - - - 5,313.26 7,969.89 7,969.89 7,969.89 1,328.32
16.00 INSTALACIONES ELECTRICAS S/30,551.25
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - 5,053.42 8,663.01 5,775.34 5,053.42 9,384.93 10,828.76 5,053.42 - - - - - -
17.00 EVACUACION AGUAS PLUVIALES S/49,812.29
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
MITIGACION DEL IMPACTO AMBIENTAL Y PROGRAMADO 478.73 478.73 205.17 273.56 478.73 319.15 319.15 478.73 478.73 478.73 319.15 163.38 467.33 490.13 478.73 490.13 478.73 433.14 524.32 478.73 159.58 319.15 478.73 478.73 478.73 30.40
18.00 S/10,258.50
LIMPIEZA EJECUTADO 478.73 478.73 - - - 273.56 - - 683.90 820.68 957.46 273.56 410.34 683.90 820.68 957.46 - - - - - - - - - -
PROGRAMADO - - - - - - - - - - - - - - - - - 2,451.81 2,967.98 2,709.89 903.30 1,806.59 2,709.89 2,709.89 2,709.89 1,548.51
19.00 ACARREOS S/20,517.75
EJECUTADO - - - - - - - - - - - - - - - - - - - - - - - - - -
PROGRAMADO - 16,758.12 42,373.07 10,310.65 18,586.78 6,873.76 7,338.92 19,065.50 24,673.45 30,259.04 7,338.92 9,988.94 46,463.10 29,966.83 16,176.62 29,966.83 25,330.89 13,930.83 17,915.23 9,809.01 2,899.66 9,392.55 14,088.82 7,500.00 - -
20.00 FLETES Y TRANSPORTE S/417,007.54
EJECUTADO - 27,298.67 27,914.85 27,914.85 30,389.21 8,340.15 53,193.14 53,193.14 70,896.36 - - - - - - - - - - - - - - - -
PROGRAMADO S/10,945.19 S/33,674.06 S/57,225.62 S/26,120.25 S/39,214.05 S/27,380.80 S/43,749.31 S/112,088.96 S/123,441.01 S/130,364.08 S/62,972.35 S/50,242.82 S/160,284.42 S/153,825.56 S/155,477.86 S/158,021.95 S/147,082.87 S/137,963.85 S/145,231.46 S/105,493.49 S/40,280.10 S/45,445.62 S/61,243.83 S/35,914.92 S/14,056.60 S/3,157.02
COSTO DIRECTO S/2,080,898.08
EJECUTADO S/15,822.46 S/91,458.24 S/31,421.35 S/31,421.35 S/42,943.55 S/27,145.21 S/72,599.41 S/74,592.53 S/155,049.10 S/72,092.38 S/63,753.65 S/7,611.63 S/28,011.64 S/44,736.25 S/30,752.25 S/43,606.94 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
P = PROGRAMADO 0.53% 1.62% 2.75% 1.26% 1.88% 1.32% 2.10% 5.39% 5.93% 6.26% 3.03% 2.41% 7.70% 7.39% 7.47% 7.59% 7.07% 6.63% 6.98% 5.07% 1.94% 2.18% 2.94% 1.73% 0.68% 0.15%
AVANCE SEMANAL (%)
E = EJECUTADO 0.76% 4.40% 1.51% 1.51% 2.06% 1.30% 3.49% 3.58% 7.45% 3.46% 3.06% 0.37% 1.35% 2.15% 1.48% 2.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
P = PROGRAMADO 0.53% 2.14% 4.89% 6.15% 8.03% 9.35% 11.45% 16.84% 22.77% 29.04% 32.06% 34.48% 42.18% 49.57% 57.04% 64.64% 71.71% 78.34% 85.31% 90.38% 92.32% 94.50% 97.45% 99.17% 99.85% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 0.76% 5.16% 6.67% 8.18% 10.24% 11.54% 15.03% 18.62% 26.07% 29.53% 32.60% 32.96% 34.31% 36.46% 37.94% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03% 40.03%
P = PROGRAMADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 1.01% 9.43% 10.67% 10.60% 7.30% 6.12% 15.08% 15.66% 6.08%
AVANCE SEMANAL (%)
E = EJECUTADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 2.74% 5.37% 4.17% 6.33% 1.09% 2.49% 3.44% 1.81% 0.00%
P = PROGRAMADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 19.05% 28.49% 39.16% 49.76% 57.06% 63.18% 78.26% 93.92% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 20.79% 26.16% 30.33% 36.66% 37.75% 40.24% 43.68% 45.49% 45.49%
P = PROGRAMADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 2.74% 5.37% 4.17% 6.33% 1.09% 2.49% 3.44% 2.43% 6.21% 5.47% 6.11% 8.73% 12.73% 9.17% 5.47%
AVANCE SEMANAL (%)
E = EJECUTADO 1.85% 1.11% 0.27% 0.02% 0.47% 0.64% 4.69% 9.01% 2.74% 5.37% 4.17% 6.33% 1.09% 2.49% 3.44% 1.81% 0.00% 0.00% 0.00% 0.00% 3.29% 5.49% 0.00%
P = PROGRAMADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 20.79% 26.16% 30.33% 36.66% 37.75% 40.24% 43.68% 46.11% 52.32% 57.79% 63.90% 72.63% 85.36% 94.53% 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 1.85% 2.95% 3.22% 3.24% 3.71% 4.35% 9.04% 18.05% 20.79% 26.16% 30.33% 36.66% 37.75% 40.24% 43.68% 45.49% 45.49% 45.49% 45.49% 45.49% 48.79% 54.27% 54.27% ###
P = PROGRAMADO 26,470.17 3.24% 121,009.03 14.81% 160,977.35 19.70% 163,748.29 20.04% 344,923.09 42.21%
AVANCE MENSUAL (%)
E = EJECUTADO 26,470.17 3.24% 121,009.03 14.81% 160,977.35 19.70% 63,257.95 7.74% 71,746.55 8.78%
P = PROGRAMADO 26,470.17 3.24% 147,479.20 18.05% 308,456.55 37.75% 472,204.84 57.79% 817,127.93 100.00%
AVANCE ACUMULADO (%)
E = EJECUTADO 26,470.17 3.24% 147,479.20 18.05% 308,456.55 37.75% 371,714.50 45.49% 443,461.05 54.27%
AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Unid Metrado P. Unit. Presup. Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. %
08. 02. 01. ACERO DE TEMPERATURA m2 1,492.50 8.03 11,984.780 - - 0.00% - - 0.00% 1,492.50 11,984.78 100.00%
09. 01. 00. ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 52.54 22.11 1,161.660 - - 0.00% - - 0.00% 52.54 1,161.66 100.00%
09. 00. 00. ZOCALOS Y CONTRAZOCALOS 38,915.95
ZOCALO DE CEMENTO SOBRE MURO EXTERIOR
09. 01. 00. H=60CM INC/BRUÑAS m2 857.39 28.22 24,195.550 685.91 19,356.44 80.00% - - 0.00% 685.91 19,356.44 80.00% 171.48 4,839.11 20.00%
CONTRAZOCALO DE MADERA CON RODON, DE 5.80 CM X
09. 01. 01. 1.90 CM X 2.40 M m 1,269.00 11.60 14,720.400 - - 0.00% - - 0.00% 1,269.00 14,720.40 100.00%
10. 00. 00. PUERTAS 106,459.50
PUERTA MACHIHEMBRADA DE 0.90X2.10 M. INCLUYE.
10. 01. 01. INSTALACION und 75.00 641.08 48,081.000 - - 0.00% - - 0.00% 75.00 48,081.00 100.00%
PUERTA CONTRAPLACADA DE 0.90X2.10 M. INCLUYE.
10. 01. 02. INSTALACION und 75.00 259.46 19,459.500 - - 0.00% - - 0.00% 75.00 19,459.50 100.00%
PUERTA CONTRAPLACADA DE 0.80X2.10 M. INCLUYE.
10. 01. 03. INSTALACION und 150.00 259.46 38,919.000 - - 0.00% - - 0.00% 150.00 38,919.00 100.00%
10. 01. 03. VENTANAS 77,235.75
VENTANA DE ALUMINIO DE 0.78 X 1.08 M INC/VIDRIO,
10. 02. 01. CON CONTRAVENTANA DE MADERA und 225.00 245.18 55,165.500 - - 0.00% - - 0.00% 225.00 55,165.50 100.00%
11. 00. 00. VENTANA CENITAL und 75.00 294.27 22,070.250 - - 0.00% - - 0.00% 75.00 22,070.25 100.00%
11. 00.
00. INSTALACIONES ELECTRICAS 30,551.25
11. 01.
01. INSTALACION ELECTRICA EN MÓDULO glb 75.00 407.35 30,551.250 - - 0.00% - - 0.00% 75.00 30,551.25 100.00%
12. 00.
00. EVACUACION AGUA PLUVIALES 49,812.29
12. 00.
00. SISTEMA DE EVACUACION DE AGUAS PLUVIALES und 150.00 318.97 47,845.500 - - 0.00% - - 0.00% 150.00 47,845.50 100.00%
ENCOFRADO Y DESENCOFRADO DE DADOS DE
12. 01. 00. CONCRETO. m2 52.50 23.38 1,227.450 - - 0.00% - - 0.00% 52.50 1,227.45 100.00%
CONCRETO SIMPLE f'c=100 kg/cm2 PARA DADOS DE
12. 02. 00. PROTECCION m3 3.28 225.41 739.345 - - 0.00% - - 0.00% 3.28 739.34 100.00%
AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Unid Metrado P. Unit. Presup. Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. % Metrado Valorizado s/. %
100.00% 97.45%
94.50%
92.32%
90.38%
85.31%
80.00% 78.34%
71.71%
64.64%
60.00% 57.04%
49.57%
42.18%
34.48% 40.03%
40.00% 29.04% 37.94%
32.06% 36.46%
34.31%
22.77% 32.60% 32.96%
29.53%
26.07%
16.84%
11.45%
20.00%
5.16%
6.67% 18.62%
2.14% 4.89% 6.15% 11.54%
10.24% 9.35%
0.76% 8.03% 15.03%
0.00%
0.53% 8.18% PROG. ACUMULADO PROG. EJECUTADO
0.00%
0.00%
INICIO 14-19 21-26 28-30 1-3 5-10 12-14 1-4 6-11 13-18 20-25 27-30 1-2 4-9 11-16 18-23 25-31 1-6 8-13 15-20 22-27 29-30 1-4 6-11 13-18 20-25 27-28