S10 Página : 1

CCCEIC

Precios y cantidades de insumos requeridos

Obra 492001 CONST Y MEJ DE LA CARRETERA PILCOCANCHA, ATAYLLAMA, CHAYNAPAMPA, ACORIA, DISTRITO
Fórmula 1 CONSTRUCCION Y MEJORAMIENTO CARRETERA PICLCOCANCHA - ACORIA
Fecha 2/20/2013

Código Descripción insumo Unidad Precio Cant. Requerida Parcial

MANO DE OBRA
470032 TOPOGRAFO HH 15.12 257.67 3,895.97
470037 CAPACITADOR TECNICO DIA 500.00 4.00 2,000.00
470041 TECNICO EN SEGURIDAD HH 180.00 64.00 11,520.00
470102 OPERARIO HH 15.12 10,683.71 161,537.70
470103 OFICIAL HH 13.14 1,495.56 19,651.66
470104 PEON HH 11.84 25,170.97 298,024.28
470123 CONTROLADOR OFICIAL HH 13.14 4,815.17 63,271.33
470125 PERFORISTA OFICIAL HH 13.14 4,396.87 57,774.87
470391 OFICIAL NIVELADOR HH 13.14 156.16 2,051.94
487648 PROFESIONAL ESPECIALISTA EN MEDIO AMBIENTE TLL 850.00 4.00 3,400.00

623,127.76
MATERIALES
20007 ALAMBRE NEGRO RECOCIDO # 16 KG 3.39 143.30 485.79
20008 ALAMBRE NEGRO RECOCIDO # 8 KG 3.39 891.47 3,022.08
20105 CLAVOS PARA MADERA C/C 3" KG 3.39 676.38 2,292.93
21099 CLAVOS KG 3.39 105.26 356.83
25101 PERNOS 1/4" X 2 1/2" PZA 3.39 94.00 318.66
25109 PERNOS 3/8" X 2 1/2" PZA 2.60 36.00 93.60
25151 PERNOS 5/8" X 14" PZA 14.83 72.00 1,067.76
30347 FIERRO CO. FY=4200 KG/CM2 KG 3.15 2,181.16 6,870.65
31104 LAMINA REFLECTIVA ALTA INTENS. AMARILLA P2 15.80 188.00 2,970.40
31105 LAMINA REFLECTIVA ALTA INTENS VERDE P2 15.80 191.18 3,020.64
40000 ARENA FINA M3 152.54 2.03 309.66
40103 TIERRA AGRICOLA M3 8.47 1,110.00 9,401.70
50036 PIEDRA GRANDE M3 63.56 209.34 13,305.65
50104 ARENA GRUESA M3 131.36 333.25 43,775.72
50220 PIEDRA MEDIANA M3 63.56 34.90 2,218.24
50252 PIEDRA GRANDE DE 10" M3 63.56 22.63 1,438.36
50307 PIEDRA CHANCADA DE 1/2" Y 3/4" M3 139.83 323.83 45,281.15
53084 MATERIAL EXCAVADO ZARANDEADO M3 12.71 105.91 1,346.12
53310 BARROTES DE 2"X2"x3' UND 2.97 20.00 59.40
53329 BARROTES DE 3"X4"x2' UND 4.40 20.00 88.00
53330 PIE DERECHO 8"x8"x3' UND 35.25 16.00 564.00
53331 SOLERA DE 8"X8"x16' UND 101.69 4.00 406.76
53332 SOLERA DE 6"X4"x19' UND 83.72 10.00 837.20
90139 ALCANTARILLA METALICA TMC D=24" E=1.8MM M 238.00 91.20 21,705.60
90140 ALCANTARILLA METALICA TMC D=36" E=2.0MM M 357.00 9.60 3,427.20
121227 FOLLETO DE OPERCION Y MANTENIMIENTO DE CARRETE UND 7.50 200.00 1,500.00
170000 LADRILLO ARCILLA CORRIENTE REX 6x12x25 CM UND 0.64 472.00 302.08
172010 ENSAYO DE DENSIDAD DE CAMPO IN SITU UND 42.37 230.00 9,745.10
172011 ENSAYO DE CBR PARA SUBRAZANTE UND 254.24 20.00 5,084.80
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 17.40 4,284.73 74,554.30
270006 MECHA O GUIA P 1.10 40,760.14 44,836.15
270211 FULMINANTE UND 1.19 39,788.39 47,348.18
280022 DINAMITA KG 14.83 8,640.61 128,140.25
280105 ANFO KG 2.37 404.90 959.61
290410 CINTA SEÑALADORA AMARILLA PZA 88.50 15.00 1,327.50
290491 CINTA SEÑALADORA ROJA PZA 88.50 15.00 1,327.50
292201 CORDEL M 1.36 18.30 24.89
297203 MATERIALES DIVERSOS PARA TALLER UND 350.00 8.00 2,800.00
297204 MATERIALES DE ESCRITORIO UND 750.00 1.00 750.00
300191 DESMOLDADOR PARA ENCOFRADO GLN 30.50 2.50 76.25
300201 YESO DE 28 Kg BOL 6.78 126.91 860.45
300810 BARRENO 5' X 7/8" UND 207.63 528.27 109,684.70
304703 SOLDADURA CELLOCORD P 3/16" KG 11.44 23.40 267.70
306521 NEOPRENE SHORE DE 0.4 X 0.35 X 0.05 M 650.00 4.00 2,600.00
309919 LIJA UND 1.50 42.22 63.33
309932 ROTURA DE PROBETA DE CONCRETO UND 25.42 30.00 762.60
309980 WINCHA UND 93.22 0.59 55.00
320059 FLETE TERRESTRE DEMATERIALES DIVERSOS GLB 17,218.75 1.00 17,218.75
320060 FLETE TERRESTRE DE EXPLOSIVOS DESDE LIMA A APAC TON 27,088.75 1.00 27,088.75
329703 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS VARIOS GLB 39,563.33 1.00 39,563.33
370125 BROCHA DE 4" UND 16.50 9.80 161.70
379072 RODILLO PARA PINTAR PZA 13.56 2.00 27.12
390100 LIJA PARA PARED PLG 1.86 8.00 14.88
390235 HOJA DE SIERRA UND 4.66 9.80 45.67
390500 AGUA M3 3.00 8,961.90 26,885.70
391505 PRUEBAS PROCTOR MODIFICADO DE CAMPO UND 169.49 6.00 1,016.94
391506 DISEÑO DE MEZCLA PARA CONCRETO UND 296.49 3.00 889.47
391507 PRUEBAS DE DETERMINACION DE MAXIMA DENSIDAD SE UND 42.37 42.00 1,779.54
391508 PRUEBAS DE CLASIFICACION DE SUELOS UND 180.00 10.00 1,800.00
399025 AVISOS Y SEÑALES DE SEGURIDAD GLB 118.64 25.00 2,966.00
436708 TABLA DE 2"X8"X19' UND 55.76 4.00 223.04
436711 TABLA DE 2"X8"X17' UND 50.85 24.00 1,220.40
436712 TABLA DE 2"X10"X19' UND 69.49 4.00 277.96
440100 ESTACA DE MADERA P2 2.80 2,098.46 5,875.69
440210 TRIPLAY DE 4' X 8' X 19 MM PLN 93.22 8.69 810.08
440323 TRIPLAY DE 4'x8'x 8 mm PLN 55.08 300.00 16,524.00
450101 MADERA TORNILLO INC.CORTE P/ENCOFRADO P2 3.22 5,230.04 16,840.73
511354 PLATINA DE FIERRO 3/16" x 3" x 3 1/2" UND 16.95 36.00 610.20
520452 PLATINA DE FIERRO 5/8"x8"x8" PZA 25.42 18.00 457.56
530327 THINER GLN 15.20 3.58 54.42
540115 IMPRIMANTE GLN 20.34 6.02 122.45
540242 PINTURA ESMALTE SINTETICO GLN 39.60 30.80 1,219.68
540500 PINTURA AL OLEO MATE GLN 39.60 2.32 91.87
542101 PINTURA ANTICORROSIVA GLN 38.14 21.97 837.94
560198 CALAMINAS GALVANIZADAS 1.83mX1.085mx 0.3mm UND 27.54 420.00 11,566.80
560214 PLANCHA ACERO 2.0mm x 1.30m x 0.60m PLN 30.51 5.00 152.55
560215 PLANCHA DE ACERO 2.5mm x2.40m x1.35m PLN 63.56 4.00 254.24
562285 PLANCHA DE ACERO DE 7" x 1/2" M 122.00 9.45 1,152.90
562287 FIERRO DE ANGULO DE 4"x4"x3/8"' M 85.80 18.90 1,621.62
610012 PLANCHA MET. 1/16"x0.60x0.60 SEG. DISEÑO C/SOPORTE PZA 18.50 47.00 869.50
650058 TUBO Fo.GALV. DE 2" M 14.83 10.00 148.30
652501 POSTES DE 1.2 M. UND 6.80 30.00 204.00
720296 TUBO DE FIERRO NEGRO 2.5 mm x 3" M 19.06 68.70 1,309.42
720297 TUBO DE FIERRO NEGRO 2.5 mm x 2" M 13.56 145.70 1,975.69
720298 TUBO PVC SAP 3" C-10 M 7.80 3.12 24.34

781,637.72
EQUIPOS
50137 CASACA TERMICA UND 67.79 40.00 2,711.60
270016 GRUPO ELECTROGENO 6000 WATS, INCL. COMBUSTIBLE HE 655.50 32.00 20,976.00
370119 BOTAS DE JEBE PAR 15.63 40.00 625.20
370159 CORREA DE SEGURIDAD UND 22.03 4.00 88.12
370524 ZAPATOS DE SEGURIDAD PAR 72.03 40.00 2,881.20
375401 MIRAS Y JALONES HM 7.29 257.67 1,878.41
375707 GUANTES DE JEBE PAR 13.56 30.00 406.80
376040 GUANTES DE CUERO PAR 7.20 40.00 288.00
376205 CASCOS TIPO JOCKEY CON TAFILETE PZA 12.71 45.00 571.95
376237 LENTES DE SEGURIDAD PZA 6.36 45.00 286.20
376238 PONCHO IMPERMEABLE PZA 33.89 45.00 1,525.05
376239 MAMELUCO PZA 42.37 45.00 1,906.65
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 84.75 266.23 22,562.99
480437 CAMION VOLQUETE 6x4 330 HP 15 M3. INCL. COMBUSTIBL HM 152.54 1,071.76 163,486.27
481294 CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. INCL. COMBUST HM 144.07 701.54 101,070.87
489605 CIZALLA P/CORTE DE FIERRO HM 16.95 41.01 695.12
490294 COMPRESORA NEUMATICA 196 HP 600-750 PCM INCL. CO HM 135.59 1,324.96 179,651.33
490301 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 38.14 26.20 999.27
490374 RODILLO LISO VIBR AUTOP 101-135HP 10-12T INCL. COMB HM 139.83 852.3 119,177.11
490492 TRACTOR DE ORUGAS DE 190-240 HP INCL. COMBUSTIBL HM 254.24 2,094.34 532,465.00
490495 EXCAVADORA SOBRE ORUGA 180 HP INCL. COMBUSTIBLE HM 279.66 1,003.42 280,616.44
490498 CARGADOR FRONTAL 150 - 180 HP, 2.5 - 2.75 YD3 INCL. CO HM 156.78 921.44 144,463.36
490604 MARTILLO NEUMATICO DE 25 Kg. HM 21.18 4,396.87 93,125.71
490704 VIBRADOR DE CONCRETO 4 HP 2" HM 13.13 132.45 1,739.07
490750 MOTOSOLDADORA DE 250 AMP. HM 110.17 12.06 1,328.65
490912 MOTONIVELADORA DE 125 HP INCL. COMBUSTIBLE HM 144.06 963.75 138,837.83
491494 ZARANDA METALICA CON PARANTES HE 10.59 541.14 5,730.67
491615 TALADRO A PERCUSION 3/4" DOS VELOC. UND 38.14 0.51 19.45
491901 TEODOLITO HM 14.4 257.67 3,710.45
498802 NIVEL TOPOGRAFICO HM 8.05 234.24 1,885.63

1,825,710.39

SUB-TOTAL 3,230,475.87
INSUMOS COMODIN
EQUIPOS
370101 HERRAMIENTAS MANUALES %MO

SUB-TOTAL 0

TOTAL 3,230,475.87
MONTO PARTIDAS ESTIMADAS

La columna parcial es el producto del precio por la cantidad requerida; y en la última columna se muestra el Monto Real que se está util
izando
ANALISIS DE FLETE TERRESTRE
PROYECTO : "CONST. Y MEJORAMIENTO DE LA CARRETERA PILCOCANCHA-ATAYLLAMA-CHAYNAPAMPA-ACORIA
DISTRITO DE ACORIA, PROVINCIA Y DEPARTAMENTO DE HUANCAVELICA”
DEPART. : HUANCAVELICA
PROVINCIA : HUANCAVELICA
DISTRITOS : ACORIA
LUGAR : PILCOCANCHA, ATAYLLAMA, CHAYNAPAMPA, ACORIA
FECHA : FEBRERO DEL 2013

TRASPORTADOS EN
N° DESCRIPCION DE LOS MATERIALES UND CANTIDAD PESO UNIT.(KG)
CAMION (KG)
1 ALAMBRE NEGRO RECOCIDO # 8 KG 891 1 891.47
2 CLAVOS PARA MADERA C/C 3" KG 676 1 676.38
3 CLAVOS KG 105 1 105.26
4 PERNOS 1/4" X 2 1/2" PZA 94 1 94.00
5 PERNOS 3/8" X 2 1/2" PZA 36 1 36.00
6 PERNOS 5/8" X 14" PZA 72 0.25 18.00
7 FIERRO CO. FY=4200 KG/CM2 KG 2181 1.5 3,271.74
8 LAMINA REFLECTIVA ALTA INTENS. AMARILLA P2 188 1 188.00
9 LAMINA REFLECTIVA ALTA INTENS VERDE P2 191 0.1 19.12
10 ARENA FINA M3 2 0.1 0.20
11 BARROTES DE 3"X4"x2' UND 20 3 60.00
12 PIE DERECHO 8"x8"x3' UND 16 4 64.00
13 SOLERA DE 8"X8"x16' UND 4 6 24.00
14 SOLERA DE 6"X4"x19' UND 10 15 150.00
15 ALCANTARILLA METALICA TMC D=24" E=1.8MM M 91 12.5 1,140.00
16 ALCANTARILLA METALICA TMC D=36" E=2.0MM M 10 36.69 352.22
17 FOLLETO DE OPERCION Y MANTENIMIENTO DE CARRETER UND 200 56.014 11,202.80
18 LADRILLO ARCILLA CORRIENTE REX 6x12x25 CM UND 472 56.14 26,498.08
19 ENSAYO DE DENSIDAD DE CAMPO IN SITU UND 230 3.5 805.00
20 CEMENTO PORTLAND TIPO I (42.5KG) BOL 4285 42.5 182,101.03
21 CINTA SEÑALADORA ROJA PZA 15 15 225.00
22 CORDEL M 18 15 274.50
23 YESO DE 28 Kg BOL 127 4 507.64
24 SOLDADURA CELLOCORD P 3/16" KG 23 10 234.00
25 NEOPRENE SHORE DE 0.4 X 0.35 X 0.05 M 4 1 4.00
26 LIJA UND 42 4 168.88
27 TABLA DE 2"X8"X19' UND 4 15 60.00
28 TABLA DE 2"X8"X17' UND 24 12 288.00
29 TABLA DE 2"X10"X19' UND 4 18 72.00
30 TRIPLAY DE 4' X 8' X 19 MM PLN 9 7.5 65.18
31 TRIPLAY DE 4'x8'x 8 mm PLN 300 4.5 1,350.00
32 MADERA TORNILLO INC.CORTE P/ENCOFRADO P2 5230 0.5 2,615.02
33 PLATINA DE FIERRO 3/16" x 3" x 3 1/2" UND 36 3 108.00
34 PLATINA DE FIERRO 5/8"x8"x8" PZA 18 5 90.00
35 PINTURA ESMALTE SINTETICO GLN 31 4 123.20
36 CALAMINAS GALVANIZADAS 1.83mX1.085mx 0.3mm UND 420 4 1,680.00
37 PLANCHA ACERO 2.0mm x 1.30m x 0.60m PLN 5 2.5 12.50
38 PLANCHA DE ACERO 2.5mm x2.40m x1.35m PLN 4 15 60.00
39 PLANCHA DE ACERO DE 7" x 1/2" M 9 2.5 23.63
40 FIERRO DE ANGULO DE 4"x4"x3/8"' M 19 3.8 71.82
41 PLANCHA MET. 1/16"x0.60x0.60 SEG. DISEÑO C/SOPORTE ME PZA 47 1.75 82.25
42 TUBO Fo.GALV. DE 2" M 10 5 50.00
43 POSTES DE 1.2 M. UND 30 3 90.00
44 TUBO DE FIERRO NEGRO 2.5 mm x 3" M 69 5.5 377.85
45 TUBO DE FIERRO NEGRO 2.5 mm x 2" M 146 4.5 655.65
46 MATERIALES VARIOS KG 4,500.00 1 4,500.00
PESO TOTAL DE LOS MATERIALES (KG) = 241,486.41

NUMERO DE VIAJES = PESO TOTAL DE MATERIAL 241,486.41 24.1


PESO CARGA CAMION 10,000.00
NUMERO DE VIAJES = 24 + 1 25
ANALISIS DE FLETE TERRESTRE
PROYECTO : "CONST. Y MEJORAMIENTO DE LA CARRETERA PILCOCANCHA-ATAYLLAMA-CHAYNAPAMPA-ACORIA
DISTRITO DE ACORIA, PROVINCIA Y DEPARTAMENTO DE HUANCAVELICA”
DEPART. : HUANCAVELICA
PROVINCIA : HUANCAVELICA
DISTRITOS : ACORIA
TRANSPORTE DE MATERIALES

TIEMPO
N° DESCRIPCION TIPO DE CARRETERA LONGITUD (Km) VELOCIDAD
(HORAS)

1 Hyo - Izcuchaca Carretera asfaltada 75.00 30.00 2.50


2 Izcuchaca - Pilcocancha Carretera afirmada 55.00 20.00 2.75

TIEMPO TOTAL DE MOVILIZACION POR VIAJE 5.25


COSTO DE ALQUILER HORARIO DE CAMION CARAGA DE 10 TN. S/. 120.00
NUMERO DE VIAJES REQUERIDOS POR PESO Y VOLUMEN 25.00
CALCULO DE COSTO DE TRANSPORTE DE MATERIALES S/. = 15,750.00

MOVILIZACION DE RETORNO DEL CAMION DE CARGA


TIEMPO
N° DESCRIPCION TIPO DE CARRETERA LONGITUD (Km) VELOCIDAD
(HORAS)
1 Hyo - Izcuchaca Carretera asfaltada 75.00 30.00 2.50
2 Izcuchaca - Pilcocancha Carretera afirmada 55.00 25.00 2.20

TIEMPO TOTAL DE MOVILIZACION POR VIAJE 4.70


COSTO DE OPERACIÓN HORARIA S/. 12.50
NUMERO DE VIAJES DE RETORNO () 25.00
COSTO MOVILIZACION DE RETORNO DE LOS CAMIONES S/. = 1,468.75

COSTO DE TRANSPORTE DE MATERIALES (HYO - PILCOCANCHA) S/. = 17,218.75


FLETE DE EXPLOSIVOS

PROYECTO : "CONST. Y MEJORAMIENTO DE LA CARRETERA PILCOCANCHA-ATAYLLAMA-CHAYNAPAMPA-ACORIA


DISTRITO DE ACORIA, PROVINCIA Y DEPARTAMENTO DE HUANCAVELICA”
DEPARTAMEN : HUANCAVELICA
PROVINCIA : HUANCAVELICA
DISTRITOS : ACORIA
LUGAR : PILCOCANCHA, ATAYLLAMA, CHAYNAPAMPA, ACORIA
FECHA : FEBRERO DEL 2013

MATERIALES UNIDAD CANTIDAD PESO UNIT. SUBTOTAL


MECHA O GUIA M 40,760.14 0.10 4,076.01
FULMINANTE UND 39,788.39 0.05 1,989.42
DINAMITA KG 8,640.61 1.00 8,640.61
ANFO KG 404.90 1.00 404.90

TOTAL (KG) 15,110.94

FLETE TERRESTRE

COSTO FLETE POR KG (LIMA-PILCOCANCHA) S/. 0.800


FLETE TOTAL ( S/. ) 12,088.75

NUMERO DE VIAJES 5

COSTO x COSTO SUB


TIPO DE CUSTODIA PARA EL TRASLADO CANTIDAD COSTO TOTAL
PERSONAL TOTAL

CUSATODIA CON EFECTIVOS POLICIALES 4 750 3,000.00 15,000.00

COSTO TOTAL FLETE EXPLOSIVOS ( S/. ) 27,088.75