OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
EJE TRAMO SENT LARGO ANCHO ALTO (+) LARGO ANCHO ALTO -) O)
A VIVIENDA DOS NIVELES
001 PREELIMINARES
PRE. 01.010 TRAZO Y NIVELACION CON EQUIPO 1-9 A-O 25.00 11.30 1.00 282.50

002 EXCAVACION
EXCAVACION A MANO EN CEPAS C 9-3 7.33 0.80 0.75 4.40 4.40
DE MATERIAL II DE 0-2 mtrs DE E 3-1 4.78 0.80 0.75 2.87 2.87
PROFUNDIDAD
EYF 9-8 2.08 0.80 0.75 2 2.49 2.49
G 8-3 6.125 0.80 0.75 3.68 3.68
H 3-1 4.78 0.80 0.75 2.87 2.87
J 3-2 3.2 0.80 0.75 1.92 1.92
KYO 9-1 11.3 0.80 0.75 2 13.56 13.56
M 9-2 9.075 0.08 0.75 0.5445 0.54
9 B-C 0.875 0.80 0.75 0.525 0.53
9Y8 C-E 1.375 0.80 0.75 2 1.65 1.65
9Y8 E-F 0.6 0.80 0.75 2 0.72 0.72
9 F-K 4.9 0.80 0.75 2.94 0.72
9 K-M 4.125 0.80 0.75 2 4.95 4.95
9 M-O 4.725 0.80 0.75 2.835 2.84
8 F-G 0.025 0.80 0.75 0.015 0.01
8 G-K 2.75 0.8 0.75 2 3.3 3.30
3 C-E 1.38 0.80 0.75 0.83 0.83
3 E-G 2.075 0.80 0.75 1.245 1.25
3 G-H 0.575 0.80 0.75 0.345 0.35
3Y2 H-J 0.45 0.80 0.75 2 0.54 0.54
3Y2 J-K 0.125 0.80 0.75 2 0.15 0.54
1 A-C 5.95 0.80 0.75 3.57 3.57
1 C-E 1.375 0.80 0.75 0.825 0.83
1 E-H 3.45 0.80 0.75 2.07 2.07
1 H-K 1.375 0.80 0.75 0.825 0.15
1 K-O 9.725 0.80 0.75 5.835 5.835
0
TER. 41 0.11 AFINE DE TALUDES C 9-3 7.33 0.75 2 10.99 10.99
E 3-1 4.78 0.75 2 7.16 7.16
EYF 9-8 2.08 0.75 4 6.23 6.23
G 8-3 6.125 0.75 2 9.19 9.19
H 3-1 4.78 0.75 2 7.16 7.16
J 3-2 3.2 0.75 2 4.80 4.80
KYO 9-1 11.3 0.75 4 33.90 33.90
M 9-2 9.075 0.75 2 13.61 13.61
9 B-C 0.875 0.75 2 1.31 1.31
9Y8 C-E 1.375 0.75 4 4.13 4.13
9Y8 E-F 0.6 0.75 4 1.80 1.80
9 F-K 4.9 0.75 2 7.35 7.35
9 K-M 4.125 0.75 4 12.38 12.38
9 M-O 4.725 0.75 2 7.09 7.09
8 F-G 0.025 0.75 2 0.04 0.04
8 G-K 2.75 0.75 4 8.25 8.25
3 C-E 1.38 0.75 2 2.06 2.06

:
Página 2 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
3 E-G 2.075 0.75 2 (+)
3.11 -) O)
3.11
3 G-H 0.575 0.75 2 0.86 0.86
3Y2 H-J 0.45 0.75 4 1.35 1.35
3Y2 J-K 0.125 0.75 4 0.38 0.38
1 A-C 5.95 0.75 2 8.93 8.93
1 C-E 1.375 0.75 2 2.06 2.06
1 E-H 3.45 0.75 2 5.18 5.18
1 H-K 1.375 0.75 2 2.06 2.06
1 K-O 9.725 0.75 2 14.59 14.59

TER. 41 0.12 AFINE DE FONDOS DE EXCAVACION C 9-3 7.33 0.80 5.86 5.86
E 3-1 4.78 0.80 3.82 3.82
EYF 9-8 2.08 0.80 2 3.32 3.32
G 8-3 6.125 0.80 4.90 4.90
H 3-1 4.78 0.80 3.82 3.82
J 3-2 3.2 0.80 2.56 2.56
KYO 9-1 11.3 0.80 2 18.08 18.08
M 9-2 9.075 0.08 0.73 0.73
9 B-C 0.875 0.80 0.70 0.70
9Y8 C-E 1.375 0.80 2 2.20 2.20
9Y8 E-F 0.6 0.80 2 0.96 0.96
9 F-K 4.9 0.80 3.92 3.92
9 K-M 4.125 0.80 2 6.60 6.60
9 M-O 4.725 0.80 3.78 3.78
8 F-G 0.025 0.80 0.02 0.02
8 G-K 2.75 0.8 2 4.40 4.40
3 C-E 1.38 0.80 1.10 1.10
3 E-G 2.075 0.80 1.66 1.66
3 G-H 0.575 0.80 0.46 0.46
3Y2 H-J 0.45 0.80 2 0.72 0.72
3Y2 J-K 0.125 0.80 2 0.20 0.20
1 A-C 5.95 0.80 4.76 4.76
1 C-E 1.375 0.80 1.10 1.10
1 E-H 3.45 0.80 2.76 2.76
1 H-K 1.375 0.80 1.10 1.10
1 K-O 9.725 0.80 7.78 7.78

TER. 41 0.13 TRASPALEO EN CARRETILLA VOLUMEN DE EXCAVASION ABUND.


62.97 1.30 81.87

ACAR. 25 1.26 ACARREO EN CARRETILLA EXCAVACION MAS ABUNDAMIENTO

ACAR. 24 1.27 ACARREO EN CAMION FUERA DE MATERIAL PRODUCTO DE EXCAVASION MAS DESPERDICIO 81.87 81.87
OBRA DESPERDICIO 81.87 81.87

CIMENTACION

:
Página 3 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
CIM. 02 25 PLANTILLA DE CIMENTACION DE C 9-3 7.33 0.8 (+)
5.86 -) O)
5.86
5cms DE ESPESOR, CON PEDACERIA E 3-1 4.78 0.8 3.82 3.82
DE TABIQUE Y MORTERO
CEMENTO-ARENA 1:5 EYF 9-8 2.08 0.8 2 3.32 3.32
G 8-3 6.125 0.8 4.90 4.90
H 3-1 4.78 0.8 3.82 3.82
J 3-2 3.2 0.8 2.56 2.56
KYO 9-1 11.3 0.8 2 18.08 18.08
M 9-2 9.075 0.8 7.26 7.26
9 B-C 0.875 0.8 0.70 0.70
9Y8 C-E 1.375 0.8 2 2.20 2.20
9Y8 E-F 0.6 0.8 2 0.96 0.96
9 F-K 4.9 0.8 3.92 3.92
9 K-M 4.125 0.8 3.30 3.30
9 M-O 4.725 0.8 3.78 3.78
8 F-G 0.025 0.8 0.02 0.02
8 G-K 2.75 0.8 2.20 2.20
3 C-E 1.38 0.8 1.10 1.10
3 E-G 2.075 0.8 1.66 1.66
3 G-H 0.575 0.8 0.46 0.46
3Y2 H-J 0.45 0.8 2 0.72 0.72
3Y2 J-K 0.125 0.8 2 0.20 0.20
1 A-C 5.95 0.8 4.76 4.76
1 C-E 1.375 0.8 1.10 1.10
1 E-H 3.45 0.8 2.76 2.76
1 H-K 1.375 0.8 1.10 1.10
1 K-O 9.725 0.8 7.78 7.78

AREA
CIM. 02 26 CIMENTACION DE MAMPOSTERIA C 9-3 7.33 0.34 2.47 2.47
DE PIEDRA DE LA REGION JUNTADA E 3-1 4.78 0.34 1.61 1.61
EYF 9-8 2.08 0.34 2 1.40 1.40
G 8-3 6.125 0.34 2.07 2.07
H 3-1 4.78 0.34 1.61 1.61
J 3-2 3.2 0.34 1.08 1.08
KYO 9-1 11.3 0.34 2 7.63 7.63
M 9-2 9.075 0.34 3.06 3.06
9 B-C 0.875 0.34 0.30 0.30
9Y8 C-E 1.375 0.34 2 0.93 0.93
9Y8 E-F 0.6 0.34 2 0.41 0.41
9 F-K 4.9 0.34 1.65 1.65
9 K-M 4.125 0.34 1.39 1.39
9 M-O 4.725 0.34 1.59 1.59
8 F-G 0.025 0.34 0.01 0.01
8 G-K 2.75 0.34 0.93 0.93
3 C-E 1.38 0.34 0.46 0.46
3 E-G 2.075 0.34 0.70 0.70
3 G-H 0.575 0.34 0.19 0.19
3Y2 H-J 0.45 0.34 2 0.30 0.30
3Y2 J-K 0.125 0.34 2 0.08 0.08

:
Página 4 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
1 A-C 5.95 0.34 (+)
2.01 -) O)
2.01
1 C-E 1.375 0.34 0.46 0.46
1 E-H 3.45 0.34 1.16 1.16
1 H-K 1.375 0.34 0.46 0.46
1 K-O 9.725 0.34 3.28 3.28

CIM. 02 27 RELLENO DE CEPAS CON MATERIAL (+) VOLUMEN DE LA EXCAVASION 62.97 37.11
DE BANCO (+) VOLUMEN DE BASE DE FIRME 15.82
(-) VOLUMEN DE LA MAMPOSTERIA 37.27
(-) VOUMEN DE LA PLANTILLA DE CIMENTACION 4.42

CIM. 02 28 RELLENO COMPACTADO PARA BASE 5.10 4.90 0.13 3.25 3.25
DE FIRME 1.85 2.35 0.13 0.57 0.57
1.85 1.25 0.13 0.30 0.30
5.20 0.50 0.13 0.34 0.34
8.85 4.85 0,13 #VALUE! #VALUE!
4.05 1.35 0.13 0.71 0.71
4.05 3.60 0.13 1.90 1.90
3.90 4.10 0.13 2.08 2.08
2.25 1.10 0.13 2 0.64 0.64
2.35 1.50 0.13 0.46 0.46

CIM. 02 29 CADENA DE CIMENTACION CD1 8 C-K 9.40 9.40 9.40


CON ARMEX 15*20 -4 INLCUYE 9 C-O 19.13 19.13 19.13
SIMBRA, COLADO, DESCIMBRADO,
CONCRETO F´C 200 KG/CM2 6 I-K 1.00 1.00 1.00
5 K-M 4.77 2.00 9.54 9.54
4 G-K 3.98 3.98 3.98
3 D-K 7.98 7.98 7.98
2-3 J-K 1.10 1.10 1.10
2 H-K 2.35 2.35 2.35
1 E-O 16.63 16.63 16.63
C 2-3 1.78 1.78 1.78
C 3-8 5.18 5.18 5.18
8-9 E-F 1.25 1.25 1.25
E 9-8 1.85 3.00 5.55 5.55
H 1-3 3.81 3.81 3.81
J 2-3 2.25 3.81 3.81
K 8-1 9.08 9.08 9.08
0 1-9 11.15 11.15 11.15
9 B-C 0.83 0.83 0.83
I-K 6-8 0.65 0.65 0.65
0.00 0.00
0.00
CIM 02 30 CADENA DE CIMENTACION CD2 M 2-9 8.93 8.93 8.93
CON ARMEX 15*30 -4 INLCUYE 3 C-D 2.10 2.10 2.10
SIMBRA, COLADO, DESCIMBRADO,
CONCRETO F´C 200 KG/CM2 E 1-3 3.83 3.83 3.83
G 3-8 5.10 5.10 5.10

:
Página 5 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
CADENA DE CIMENTACION CD2
PERIODO: OCTUBRE
CON ARMEX20 15*30
A FEBRERO DE 2020
-4 INLCUYE
SIMBRA, COLADO, DESCIMBRADO, NUMEROS GENERADORES
CONCRETO F´C 200 KG/CM2
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
1 D-E 1.23 (+)
1.23 -) O)
1.23
0.00

CIM. 02 31 FIRME DE CONCRETO 7 cms 8-9 C-E 1.78 2.35 1.00 4.17 4.17
ACABADO DE APLANADO PULIDO 8-9 E-F 1.78 1.25 1.00 2.22 2.22
8-9 F-K 1.78 5.2 1.00 9.23 9.23
5-9 K-M 4.33 4.85 1.00 20.98 20.98
3-8 C-G 5.10 4.90 1.00 24.99 24.99
4-8 G-K 3.60 4.05 1.00 14.58 14.58
3-4 G-K 1.35 4.05 1.00 5.47 5.47
2-5 K-M 4.30 4.85 1.00 20.86 20.86
1-3 E-H 3.83 4.10 1.00 15.68 15.68
2-3 H-J 2.25 1.10 2.00 4.95 4.95
1-2 H-K 1.43 2.35 1.00 3.35 3.35

PREL 1- 01 REGISTRO SANITARIO CON TAPA,


60*40 Y PULIDO INTERIOR S/E 4

PREL 1 - 02 TENDIDO DE TUBERIA DEDRENAJE 1 1.70 1 1.70


DE PVC DE 4" 2 1.20 1 1.20
3 12.00 1 12.00
4 9.00 1 9.00
5 3.85 1 3.85
6 5.20 1 5.20
7 1.35 1 1.35
8 1.00 1 1.00
0.00
0.00
PREL 1-03 1 1.00 1 1.00
TENDIDO DE TUBERIA DE DRENAJE 2 1.00 1 1.00
DE PVC DE 2" 3 1.35 2 1.35
5 1.00 1 1.00

CAST. 01 015
CASTILLO K1 CON ARMEX 15X20-4 f 3.60 45 162.00
´c=150 kg/cm2
0.00
0.00
CAST. 01 016 CASTILLO K2 CON ARMEX 15X20-4 f 3.60 16 57.60
´c=150 kg/cm2
0.00
0.00
COL, O2 013
COLUMNAS DE SECCION 30X30
CON 8 VARILLAS DE 1/2 Y ESTRIBOS
DEL NO.2 A CADA 12 Cm, INCLUYE
CIMBRA, ACABADO COMUN.

:
Página 6 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
(+) -) O)
ALB. 10 006 C 8-9 1.70 3.60 1 6.12 0.30 2.00 1.00 0.60 5.52
MURO DE LADRILLO ROJO
RECOCIDO 6X12X24, ACABADO E 9-8 1.78 3.60 1 6.39 0.00 6.39
COMUN 0.50 0.18 1.00 0.09
F 8-9 1.70 3.60 1.00 6.12 4.56
0.70 2.10 1.00 1.47
G 8-9 0.60 3.60 1.00 2.16 0.00 2.16
K 4-9 5.30 3.60 1.00 19.08 1.05 2.10 1.00 2.21 16.88
M 2-9 8.40 3.60 1.00 30.24 2.00 2.20 2.00 8.80 21.44
1.52 1.20 1.00 1.82
G 3-8 3.23 3.60 1.00 11.61 7.69
1.00 2.10 1.00 2.10
E 1-3 3.68 3.60 1.00 13.23 2.00 2.30 1.00 4.60 8.63
H 1-4 5.33 3.60 1.00 1.00 2.10 1.00 2.10
19.17 15.81
0.70 1.80 1.00 1.26
J 2-3 2.40 3.60 1.00 8.64 0.00 8.64
0.49 0.50 1.00 0.25
K 1-3 3.83 3.60 1.00 13.77 12.81
1.43 0.50 1.00 0.72
9 C-E 2.35 3.60 1.00 8.46 0.00 8.46
9 E-F 1.25 3.60 1.00 4.50 0.00 4.50
9 F-K 5.20 3.60 1.00 18.72 0.00 18.72
9 K-M 4.78 3.60 1.00 17.19 0.00 17.19
9 M-O 4.50 2.50 1.00 11.25 0.00 11.25
8 C-E 2.28 3.60 1.00 8.19 0.70 2.10 1.00 1.47 6.72
8 E-F 1.25 3.60 1.00 4.50 0.00 4.50
8 F-G 0.93 3.60 1.00 3.33 1.00 2.10 1.00 2.10 1.23
1.50 1.30 1.00 1.95
8 G-K 3.98 3.60 1.00 14.31 10.26
1.00 2.10 1.00 2.10
4 G-K 4.05 3.60 1.00 14.58 14.58
3 C-E 2.05 3.60 1.00 7.38 7.38
3 H-E 4.03 3.60 1.00 14.49 0.95 2.10 1.00 2.00 12.50
3 J-K 1.10 3.60 1.00 3.96 0.70 2.10 1.00 1.47 2.49
2-3 J-K 0.40 0.90 2.00 0.72 0.00 0.72
2 H-J 1.10 3.60 2.00 7.92 0.00 7.92
2 K-M 4.78 3.60 1.00 17.19 2.00 1.50 1.00 3.00 14.19
1 D-E 1.00 3.60 1.00 3.60 3.60
1 E-H 4.03 3.60 1.00 14.49 14.49
1 H-K 2.35 1.96 1.00 4.61 4.61
1 K-O 9.58 2.50 1.00 23.94 23.94
O 1-9 11.00 2.50 1.00 27.50 27.50
7-8 I-K 0.70 1.00 1.00 0.70 0.70
6 I-K 0.70 3.60 1.00 2.52 2.52

:
Página 7 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
(+) -) O)

:
Página 8 de 17

OBRA: CONSTRUCCION VIVIENDA DE DOS NIVELES


FRENTE: LOTE 10 SAN LORENZO
PERIODO: OCTUBRE 20 A FEBRERO DE 2020
NUMEROS GENERADORES
LOCALIZACION DIMENSIONES (+) PZAS SUB TOTAL DIMENSIONES (-) PZAS SUB TOTAL ( DIFERENCIA (J-
CÓDIGO CONCEPTO
(+) -) O)

:
Página 9 de 17

###

CANTIDAD TOTAL UNIDAD

282.50 m2

62.97 m3

175.95 m2

:
Página 10 de 17

###

CANTIDAD TOTAL UNIDAD

87.31 m2

81.87 m3

81.87 m3

163.73 m3

:
Página 11 de 17

###

CANTIDAD TOTAL UNIDAD


88.34 m2

37.27 m3

:
Página 12 de 17

###

CANTIDAD TOTAL UNIDAD

48.24 m3

15.82 m3

112.40 ml

21.18 ml

:
Página 13 de 17

###

CANTIDAD TOTAL UNIDAD

126.47 m2

4 pza

30.10 mtrs

4.35 mtrs

162.00 ml

57.60 ml

:
Página 14 de 17

###

CANTIDAD TOTAL UNIDAD


330.48 m2

:
Página 15 de 17

###

CANTIDAD TOTAL UNIDAD

:
Página 16 de 17

###

CANTIDAD TOTAL UNIDAD

:
Generadores de acero
OBRA: CORTIJO SAN LORENZO.
FRENTE: CONSTRUCCION 12 VIVIENDAS 64 M2 INTERES MEDIO
PERIODO: ENERO 2015 - JUNIO 2015 (SEIS MESES)

ESTRIBO para COLUMNA DE 40X40 ARMADA CON 4Ø #6 + 16Ø # 5/8" ESTR, 3/8"
Extremo Superior 20@ 7, 7@ 10 en Extremo Inferior, resto @20 CMS. CONCRETO
APARENTE DE F'C= 200 KGR/CM2 DE 4.00 MTS DE ALTURA, EN PRIMER NIVEL.
INCLUYE MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO

C O N C E P T O LOCALIZ. A R M A D O LONGITUDES / CALIBRES


Dirección
CVE DESCRIPCION EJE TRAMO TIPO # LARGO PZAS REPET. TOTAL Cal 18 #2 #2.5 #3 #4 #5 #6 #8 #12

Alambre 8 B Amarre Estribo 1 18 0.350 20.00 1 7.00 7.00

Estribo Tipo 1 54.4x54.4 3 2.28 1.00 1 2.28 2.28


Estribo Tipo 2 34.4x54.4 3 1.88 1.00 2 3.75 3.75
Estribo Tipo 3 14.9x54.4 3 1.49 1.00 2 2.97 2.97
suma 9.00 por los 3 estribos

diametro 18.00 1/4" 5/16" 3/8" 1/2" 5/8" 3/4" 1" 1 1/2"
TRASLAPES 40 Ø diametro 0.64 0.79 0.95 1.27 1.59 1.91 2.54 3.81
Suma ml 7.00 0.00 0.00 9.00 0.00 0.00 0.00 0.00 0.00
POR LO TANTO Peso ( kgr/ml) 0.0143 0.251 0.384 0.557 0.996 1.560 2.250 3.975 8.938
Alambre 0.110 Total peso (kgr/ml) 0.100 0.00 0.00 5.01 0.00 0.00 0.00 0.00 0.00
1000 20.42 kg de Alambre / Ton de
Varilla Estribo 5.39 Varilla Estribo % Ganchos 0.0433 0.000 0.217 0.000 0.000 0.000 0.000 0.000
% Traslape 0.0126 0.000 0.063 0.000 0.000 0.000 0.000 0.000
0.110 1 20.42 kg de Alambre / Ton de % Desperdicio 0.0200 0.000 0.00 0.10 0.00 0.00 0.00 0.00 0.00
0.0054 Varilla Estribo % Desperdicio 0.1000 0.010
total ( kgr) 0.11 0.00 0.00 5.39 0.00 0.00 0.00 0.00 0.00
TONELADAS 0.0001 0.0000 0.0000 0.0054 0.0000 0.0000 0.0000 0.0000 0.0000
P.UNITARIO $ 15.00 $ 18.00 $ 12,000.00 $ 12,000.00 $ 12,000.00 $ 12,000.00 $ 12,000.00 $ 12,000.00 $ 12,000.00
TOTAL $ 1.65 $ - $ - $ 64.72 $ - $ - $ - $ - $ -
COSTO TOTAL $ 66.37

ANALISIS DE COSTO POR ESTRIBOS TIPO (5) POR TON

Estribo de Varilla #3 Ton


Cve Concepto U.M. Cant P. U. IMPORTE
Varilla # 3 p/Estribo Ton 0.0054 $ 12,000.00 $ 64.72
Alambre Cal 18 kg 0.02042 $ 15.00 $ 0.31
$ -
$ 65.03