CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

PROYECTO :"MEJORAMIENTO DEL ORNATO PUBLICO EN EL CASERIO DE SHUMAY, DISTRITO DE MARCARA - PROVINCIA DE CARHUAZ - DEPARTAMENTO DE ANCASH"
DISTRITO : MARCARA
PROVINCIA : CARHUAZ
DEPARTAMENTO : ANCASH
¤ MESES
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) TOTAL
1° 2° 3°
0 01 OBRAS PRELIMINARES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 82,854.50 75,359.38 6,656.72 838.40 82,854.50
0 01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 51,248.93 43,753.81 6,656.72 838.40 51,248.93
0 01.01.01 CONSTRUCCIONES PRELIMINARES 13,332.34 13,332.34 0.00 0.00 13,332.34
0 01.01.01.01 ALMACEN Y CASETA DE VIGILANCIA m2 50.00 60.78 3,039.00 3,039.00 3039.00
0 01.01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA 3.60x2.40 glb 1.00 833.10 833.10 833.10 833.10
0 01.01.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y glb 1.00 7,000.00 7,000.00 7,000.00 7000.00
0 01.01.01.04 CERCO PERIMETRICO PROVISIONAL DE OBRA m2 102.00 24.12 2,460.24 2,460.24 2460.24
0 01.01.02 TRABAJOS PRELIMINARES 1,235.20 1,235.20 0.00 0.00 1,235.20
0 01.01.02.01 LIMPIEZA DEL TERRENO MANUAL m2 640.00 1.93 1,235.20 1,235.20 1235.20
0 01.01.03 TRAZO, NIVELACION Y REPLANTEO 1,676.80 838.40 0.00 838.40 1,676.80
0 01.01.03.01 TRAZO, NIVELACION Y REPLANTEO (ANTES DEL PRO m2 640.00 1.31 838.40 838.40 838.40
0 01.01.03.02 TRAZO, NIVELACION Y REPLANTEO (DURANTE EL PR m2 640.00 1.31 838.40 838.40 838.40
0 01.01.04 MOVIMIENTO DE TIERRAS 35,004.59 28,347.87 6,656.72 0.00 35,004.59
0 01.01.04.01 DEMOLICIÓN DE ESTRUCTURAS EXISTENTES m3 105.88 154.40 16,347.87 16,347.87 16347.87
0 01.01.04.02 EXCAVACIÓN MANUAL CONGLOMERADO m3 160.00 26.37 4,219.20 2,000.00 2,219.20 4219.20
0 01.01.04.03 NIVELACIÓN INTERIOR APISONADO m2 640.00 8.01 5,126.40 3,000.00 2,126.40 5126.40
0 01.01.04.04 ELIMINACIÓN DE DESMONTE m3 265.88 35.02 9,311.12 7,000.00 2,311.12 9311.12
0 01.02 SEGURIDAD Y SALUD 31,605.57 31,605.57 0.00 0.00 31,605.57
0 01.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y 31,605.57 31,605.57 0.00 0.00 31,605.57
0 01.02.01.01 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 20,478.00 20,478.00 20,478.00 20478.00
0 01.02.01.02 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 3,500.00 3,500.00 3,500.00 3500.00
0 01.02.01.03 RECURSOS PARA LA RESPUESTA ANTE EMERGENCI glb 1.00 1,750.00 1,750.00 1,750.00 1750.00
0 01.02.01.04 PROTOCOLO PARA LA VIGILANCIA, PREVENCION Y C mes 3.00 1,959.19 5,877.57 5,877.57 5877.57
0 02 ORNATO PUBLICO EN EL CASERIO DE SHUMAY 189,209.46 1,374.35 136,492.93 51,342.18 189,209.46
0 02.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 2,912.00 0.00 2,912.00 0.00 2,912.00
0 02.01.01 TRABAJOS PRELIMINARES 1,235.20 0.00 1,235.20 0.00 1,235.20
0 02.01.01.01 LIMPIEZA DEL TERRENO MANUAL m2 640.00 1.93 1,235.20 1,235.20 1235.20
0 02.01.02 TRAZO, NIVELACION Y REPLANTEO 1,676.80 0.00 1,676.80 0.00 1,676.80
0 02.01.02.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 640.00 1.31 838.40 838.40 838.40
0 02.01.02.02 REPLANTEO DURANTE EL PROCESO m2 640.00 1.31 838.40 838.40 838.40
0 02.02 ESTRUCTURAS 42,331.84 1,374.35 40,957.49 0.00 42,331.84
0 02.02.01 MOVIMIENTO DE TIERRAS 2,068.49 1,374.35 694.14 0.00 2,068.49
0 02.02.01.01 EXCAVACIONES Y CORTES 1,312.43 1,312.43 0.00 0.00 1,312.43
0 02.02.01.01.0 EXCAVACIÓN MANUAL DE ZANJAS P/ZAPATA m3 60.93 21.54 1,312.43 1,312.43 1312.43
0 02.02.01.02 RELLENOS 61.92 61.92 0.00 0.00 61.92
0 02.02.01.02.0 RELLENO COMPACTADO CON MATERIAL PROPIO, m3 1.80 34.40 61.92 61.92 61.92
0 02.02.01.03 ELIMINACION DEL MATERIAL EXCEDENTE 694.14 0.00 694.14 0.00 694.14
0 02.02.01.03.0 ELIMINACION DE MAT. EXCED. C/VOLQUETE DE m3 76.87 9.03 694.14 694.14 694.14
0 02.02.02 OBRAS DE CONCRETO SIMPLE 6,589.49 0.00 6,589.49 0.00 6,589.49
0 02.02.02.01 SOLADOS 6,589.49 0.00 6,589.49 0.00 6,589.49
0 02.02.02.01.0 SOLADOS PARA ZAPATAS DE 2" MEZCLA 1:12 C:H m2 9.53 20.83 198.51 198.51 198.51
0 02.02.02.01.0 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIEN m2 178.27 35.85 6,390.98 6,390.98 6390.98
0 02.02.03 OBRAS DE CONCRETO ARMADO 33,673.86 0.00 33,673.86 0.00 33,673.86
0 02.02.03.01 PILETA 2,751.72 0.00 2,751.72 0.00 2,751.72
0 02.02.03.01.0 CONCRETO EN PILETA f´c=210 kg/cm2 m3 3.74 325.98 1,219.17 1,219.17 1219.17
0 02.02.03.01.0 ENCOFRADO Y DESENCOFRADO EN PILETA m2 17.60 70.33 1,237.81 1,237.81 1237.81
0 02.02.03.01.0 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 65.79 4.48 294.74 294.74 294.74
0 02.02.03.02 SARDINELES 16,699.93 0.00 16,699.93 0.00 16,699.93
0 02.02.03.02.0 CONCRETO f'c= 175 kg/cm2 m3 43.86 273.50 11,995.71 11,995.71 11995.71
0 02.02.03.02.0 ACERO DE REFUERZO FY=4200 KG/CM2 EN SARDIN kg 1,050.05 4.48 4,704.22 4,704.22 4704.22
0 02.02.03.03 BANCAS 2,416.56 0.00 2,416.56 0.00 2,416.56
0 02.02.03.03.0 CONCRETO BANCAS f'c=210 kg/cm2 m3 1.69 340.58 575.58 575.58 575.58
0 02.02.03.03.0 ENCOFRADO Y DESENCOFRADO NORMAL EN BANC m2 19.80 70.33 1,392.53 1,392.53 1392.53
0 02.02.03.03.0 ACERO DE REFUERZO FY=4200 KG/CM2 EN BANCAS kg 100.10 4.48 448.45 448.45 448.45
0 02.02.03.04 CISTERNA 8,156.83 0.00 8,156.83 0.00 8,156.83
0 02.02.03.04.0 CONCRETO CISTERNA f'c=210 kg/cm2 m3 5.69 340.58 1,937.90 1,937.90 1937.90
0 02.02.03.04.0 ENCOFRADO Y DESENCOFRADO NORMAL EN CIST m2 51.36 70.33 3,612.15 3,612.15 3612.15
0 02.02.03.04.0 ACERO DE REFUERZO FY=4200 KG/CM2 EN CISTER kg 581.87 4.48 2,606.78 2,606.78 2606.78
0 02.02.03.05 COLUMNAS 2,081.39 0.00 2,081.39 0.00 2,081.39
0 02.02.03.05.0 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.38 333.99 460.91 460.91 460.91
0 02.02.03.05.0 ENCOFRADO Y DESENCOFRADO NORMAL EN COL m2 17.04 53.23 907.04 907.04 907.04
0 02.02.03.05.0 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUM kg 159.25 4.48 713.44 713.44 713.44
0 02.02.03.06 VIGAS 1,567.43 0.00 1,567.43 0.00 1,567.43
0 02.02.03.06.0 CONCRETO VIGAS f'c=210 kg/cm2 m3 0.91 340.58 309.93 309.93 309.93
0 02.02.03.06.0 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGASm2 10.48 70.33 737.06 737.06 737.06
0 02.02.03.06.0 ACERO DE REFUERZO FY=4200 KG/CM2 EN VIGAS kg 116.17 4.48 520.44 520.44 520.44
0 02.03 ARQUITECTURA 136,485.09 0.00 92,623.44 43,861.65 136,485.09
0 02.03.01 REVOQUES Y REVESTIMIENTOS 3,623.72 0.00 3,623.72 0.00 3,623.72
0 02.03.01.01 TARRAJEO EN EXTERIORES E INTERIORES (MORTEROm2 169.65 21.36 3,623.72 3,623.72 3623.72
0 02.03.02 COBERTURAS 64.26 0.00 64.26 0.00 64.26
0 02.03.02.01 COBERTURA CON TEJA ANDINA m2 0.79 81.34 64.26 64.26 64.26
0 02.03.03 PISOS Y PAVIMENTOS 132,797.11 0.00 88,935.46 43,861.65 132,797.11
0 02.03.03.01 ACABADO DE CERAMICO EN PISOS 18,571.22 0.00 18,571.22 0.00 18,571.22
0 02.03.03.01.0 LOSETA VENECIANA PARA PISOS m2 177.63 57.66 10,242.15 10,242.15 10242.15
0 02.03.03.01.0 ADOQUINES DE CONCRETO m2 177.63 46.89 8,329.07 8,329.07 8329.07
0 02.03.03.02 VEREDAS 25,028.24 0.00 25,028.24 0.00 25,028.24
0 02.03.03.02.0 ENCOFRADO Y DESENCOFRADO PARA VEREDAS m2 25.80 61.11 1,576.64 1,576.64 1576.64
0 02.03.03.02.0 CONCRETO f'c= 175 kg/cm2 PARA VEREDA m3 83.61 274.04 22,912.48 22,912.48 22912.48
0 02.03.03.02.0 JUNTAS ASFALTICAS EN VEREDAS m 92.00 5.86 539.12 539.12 539.12
0 02.03.03.03 PILETA DE AGUA 45,336.00 0.00 45,336.00 0.00 45,336.00
0 02.03.03.03.0 PILETA DE AGUA DE PIEDRA DE H= 3.5 M und 1.00 45,336.00 45,336.00 45,336.00 45336.00
0 02.03.03.04 CARPINTERIA METALICA Y HERRERIA 35,779.38 0.00 0.00 35,779.38 35,779.38
0 02.03.03.04.0 TACHOS METALICOS PARA BASURA und 9.00 413.18 3,718.62 3,718.62 3718.62
0 02.03.03.04.0 POSTES ORNAMENTALES DE FIERRO FUNDIDO Y L und 8.00 1,085.70 8,685.60 8,685.60 8685.60
0 02.03.03.04.0 BANCAS ORNAMENTALES DE FIERRO FUNDIDO Y und 10.00 1,192.96 11,929.60 11,929.60 11929.60
0 02.03.03.04.0 PERGOLA DE ACERO und 2.00 5,495.70 10,991.40 10,991.40 10991.40
0 02.03.03.04.0 TAPA METALICA ESTRIADA 0.60x0.60, e=1/8" und 2.00 227.08 454.16 454.16 454.16
0 02.03.03.05 JARDINERIA 8,082.27 0.00 0.00 8,082.27 8,082.27
0 02.03.03.05.0 SUMINISTRO E INCORPORACION DE TIERRA DE CH m3 53.96 34.72 1,873.49 1,873.49 1873.49
0 02.03.03.05.0 SEMBRADO DE CESPED EN JARDINES m2 155.17 15.97 2,478.06 2,478.06 2478.06
0 02.03.03.05.0 SEMBRADO DE PLANTAS ORNAMENTALES glb 1.00 3,730.72 3,730.72 3,730.72 3730.72
0 02.04 INSTALACIONES SANITARIAS 2,958.26 2,958.26 2,958.26
0 02.04.01 SISTEMA DE AGUA FRIA 2,958.26 0.00 0.00 2,958.26 2,958.26
0 02.04.01.01 SALIDA DE AGUA FRIA 767.76 0.00 0.00 767.76 767.76
0 02.04.01.01.0 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/ pto 8.00 95.97 767.76 767.76 767.76
0 02.04.01.02 RED DE DISTRIBUCION 2,146.58 0.00 0.00 2,146.58 2,146.58
0 02.04.01.02.0 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 47.80 19.24 919.67 919.67 919.67
0 02.04.01.02.0 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 21.50 23.58 506.97 506.97 506.97
0 02.04.01.02.0 RED DE DISTRIBUCION TUBERIA DE 2" PVC-SAP m 22.40 32.14 719.94 719.94 719.94
0 02.04.01.03 VALVULAS 43.92 0.00 0.00 43.92 43.92
0 02.04.01.03.0 VALVULA COMPUERTA DE BRONCE DE UNION ROSCund 1.00 43.92 43.92 43.92 43.92
0 02.04.02 SISTEMA DE DRENAJE PLUVIAL
0 02.05 INSTALACIONES ELECTRICAS 4,522.27 0.00 0.00 4,522.27 4,522.27
0 02.05.01 CONECCION A LA RED EXTERNA DE MEDIDORES glb 1.00 99.08 99.08 99.08 99.08
0 02.05.02 SALIDA PARA ALUMBRADO, TOMACORRIENTES, FUERZA Y SEÑALES DEBILES 4,105.55 0.00 0.00 4105.55 4105.55
0 02.05.02.01 SALIDA 798.46 0.00 0.00 798.46 798.46
0 02.05.02.01.0 CAJAS DE PASO PARA PERGOLA 100x100x100 MM pto 2.00 39.47 78.94 78.94 78.94
0 02.05.02.01.0 CAJAS DE PASO PARA FAROS ORNAMENTALES 150 pto 16.00 44.97 719.52 719.52 719.52
0 02.05.02.02 CANALIZACIONES CONDUCTORES O TUBERIAS TUBERIAS 1,312.37 0.00 0.00 1,312.37 1,312.37
0 02.05.02.02.0 TUBERIAS PVC SAP (ELECTRICAS) D=3/4". m 182.40 6.35 1,158.24 1,158.24 1158.24
0 02.05.02.02.0 TUBERIAS PVC SAP (ELECTRICAS) D=1" m 15.20 10.14 154.13 154.13 154.13
0 02.05.02.03 CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS 1,994.72 0.00 0.00 1,994.72 1,994.72
0 02.05.02.03.0 CABLE ELECTRICO TW AWG # 10 m 421.00 3.91 1,646.11 1,646.11 1646.11
0 02.05.02.03.0 CABLE ELECTRICO TW AWG # 12 - 4 MM2 m 94.22 3.70 348.61 348.61 348.61
0 02.05.03 ARTEFACTOS 317.64 317.64 317.64
0 02.05.03.01 BOMBAS DE AGUA 317.64 0.00 0.00 317.64 317.64
0 02.05.03.01.0 ELECTROBOMBA DE 2 HP und 1.00 317.64 317.64 317.64 317.64
0 03 FLETE 13,538.78 13,538.78 0.00 0.00 13,538.78
0 03.01 FLETE TERRESTRE glb 1.00 13,538.78 13,538.78 13,538.78 13538.78

COSTO DIRECTO S/ 285,602.74 S/ 90,272.51 S/ 143,149.65 S/ 52,180.58 S/ 285,602.74

GASTOS GENERALES (17.615%) ### S/ 50,308.92 S/ 15,901.50 S/ 25,215.81 S/ 9,191.61 S/ 50,308.92


UTILIDAD (10.0%) ### S/ 28,560.27 S/ 9,027.25 S/ 14,314.97 S/ 5,218.06 S/ 28,560.28
SUB TOTAL S/ 364,471.93 S/ 115,201.26 S/ 182,680.43 S/ 66,590.25 S/ 364,471.94

IMPUESTO GENERAL A LAS VENTAS (18.00 %) 18% S/ 65,604.95 S/ 20,736.23 S/ 32,882.48 S/ 11,986.25 S/ 65,604.96

TOTAL DEL PRESUPUESTO S/ 430,076.88 S/ 135,937.49 S/ 215,562.91 S/ 78,576.50 S/ 430,076.90

AVANCE MENSUAL PROGRAMADO 32.00% 50.00% 18.00% 100%


AVANCE ACUMULADO PROGRAMADO 32.00% 82.00% 100.00%