Está en la página 1de 1

CALENDARIO DE AVANCE DE OBRA VALORIZADO

PROYECTO: " MEJORAMIENTO DEL LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE RAQUEL EN LA APV. PUCUTUPAMPA, DEL DISTRITO DE SANTIAGO, CUSCO-CUSCO "
UBICACIÓN: SANTIAGO DE CUSCO
TIEMPO: 2 MESES
Fecha: 7-Jan-21
AVANCE % POR SEMANA
ITEM DESCRIPCION MONTO 1 2 3 4 5 6 7 8
1 SUMINISTRO DE MATERIALES
CABLES Y CONDUCTORES PARA RED DE DISTRIBUCION EN B.T. Y ALUMBRADO PUBLICO 73,202.33 36,601.16 36,601.16 100.00
CONECTORES Y KIT DE EMPALMES DE CABLES ELECTRICOS 1,200.00 600.00 600.00 100.00
TUBERIA ELECTRICA DE PVC y ACCESORIOS 32,101.88 16,050.94 16,050.94 100.00
DUCTOS EN CRUCE DE VIAS 46.24 23.12 23.12 100.00
PUESTA TIERRA 992.00 496.00 496.00 100.00
BUZON DE CºSº PARA CONEXIONES ELECTRICAS 5,218.35 2,609.17 2,609.17 100.00
ALUMBRADO PUBLICO 86,850.04 43,425.02 43,425.02 100.00
ACOMETIDAS DOMICILIARIAS 6,714.47 3,357.23 3,357.23 100.00
OTROS ACCESORIOS 3,582.20 1,791.10 1,791.10 100.00
SUB TOTAL ACUMULADO SUMINISTRO DE MATERIALES 209,907.49 - 36,601.16 103,162.65 68,352.58 1,791.10 - - 100.00
2 MONTAJE Y DESMONTAJE ELECTROMECANICO
OBRAS PRELIMINARES 115.27 38.42 38.42 38.42 100.00
EXCAVACION Y MOVIMIENTO DE TIERRAS 105,349.80 35,116.60 35,116.60 35,116.60 100.00
INSTALACION DE TUBERIA ELECTRICA DE PVC Y ACCESORIOS 35,375.93 11,791.98 11,791.98 11,791.98 100.00
INSTALACION DE DUCTOS EN CRUCE DE VIAS 110.85 36.95 36.95 36.95 100.00
CONSTRUCCION DE CAJA DE CºSº PARA CONEXIONES 8,494.68 8,494.68 100.00
INSTALACION DE CABLES Y CONDUCTORES 299,946.66 299,946.66 100.00
INSTALACION DE KIT DE EMPALMES 2,726.40 2,726.40 100.00
INSTALACION DE PUESTAS A TIERRA 284.60 142.30 142.30 100.00
INSTALACION DE ALUMBRADO PUBLICO 2,154.48 2,154.48 100.00
INSTALACION DE ACOMETIDAS DOMICILIARIAS 2,220.66 2,220.66 100.00
DESMONTAJE Y CONEXION A RED DE ENERGIA EXISTENTE 1,299.16 1,299.16 100.00
PRUEBAS Y PUESTA EN SERVICIO 24,088.60 24,088.60 100.00
SUB TOTAL ACUMULADO MONTAJE ELECTROMECANICO 482,167.09 46,947.00 46,947.00 46,983.95 311,346.99 179.25 - 5,674.30 24,088.60 100.00

TRANSPORTE 2,099.07 262.38 262.38 262.38 262.38 262.38 262.38 262.38 262.38
SUB TOTAL ACUMULADO TRANSPORTE 2,099.07 262.38 262.38 262.38 262.38 262.38 262.38 262.38 262.38 100.00

SUB TOTAL COSTO DIRECTO 694,173.66 47,209.38 83,810.55 150,408.98 379,961.96 2,232.73 262.38 5,936.68 24,350.99
694,173.66 47,209.38 83,810.55 150,408.98 379,961.96 2,232.73 262.38 5,936.68 24,350.99 100.00

8.89% GASTOS GENERALES 61,712.04 4,196.91 7,450.76 13,371.36 33,778.62 198.49 23.33 527.77 2,164.80 100.00
2.19% GASTOS DE SUPERVISION 15,202.40 1,033.89 1,835.45 3,293.96 8,321.17 48.90 5.75 130.01 533.29 100.00
1.14% GASTOS DE EXPEDIENTE TECNICO 7,913.58 538.19 955.44 1,714.66 4,331.57 25.45 2.99 67.68 277.60 100.00
0.62% GASTOS DE LIQUIDACION 4,303.88 292.70 519.63 932.54 2,355.76 13.84 1.63 36.81 150.98 100.00
TOTAL GENERAL SIN IGV S/. 783,305.56 53,271.07 94,571.82 169,721.49 428,749.08 2,519.42 296.07 6,698.95 27,477.65 100.00

IMPUESTO GENERAL A LAS VENTAS (18%) 140,995.00 9,588.79 17,022.93 30,549.87 77,174.83 453.50 53.29 1,205.81 4,945.98 100.00

TOTAL GENERAL ACUMULADO EN NUEVOS SOLES 924,300.56 62,859.86 111,594.75 200,271.36 505,923.91 2,972.91 349.37 7,904.77 32,423.63 100.00