CRONOGRAMA RESUMEN DE VALORIZACION DE EJECUCION DE OBRA

PROYECTO : "MANTENIMIENTO PERIÓDICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE CHIMBOTE –
PROVINCIA DEL SANTA – DEPARTAMENTO DE ANCASH – SEGUNDA CONVOCATORIA"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DEL SANTA
FECHA : NOVIEMBRE- 2020
DIAS : 40 DIAS
RESIDENTE : ING. LUIS ENRIQUE ROMERO PRADO - CIP N° 178184

PERIODO DE OBRA
ITEM UND. PARCIAL NOVIEMBRE DICIEMBRE
SEM. 02 SEM. 03 SEM. 04 SEM. 01 SEM. 02 SEM. 03 SEM. 04

01 TRAMO I GLB 1,432,259.19 393,871.28 1,038,387.91


02 TRAMO II GLB 267,107.36 73,454.52 193,652.84
03 TRAMO III GLB 191,622.47 52,696.18 138,926.29
04 TRAMO IV GLB 205,927.73 56,630.13 149,297.60
05 TRAMO V GLB 129,758.05 35,683.46 94,074.58
06 TRAMO VI GLB 203,456.29 55,950.48 147,505.81
07 TRAMO VII GLB 338,703.15 93,143.37 245,559.79
08 TRAMO VIII GLB 236,354.02 64,997.35 171,356.66
09 TRAMO IX GLB 43,791.14 12,042.56 31,748.58
10 TRAMO X GLB 673,963.10 185,339.85 488,623.25
11 TRAMO XI GLB 331,537.77 91,172.89 240,364.88

05 COSTO DIRECTO 4,054,480.27 1,114,982.07 2,939,498.19


06 GASTO GENERALES 8.00% 324,358.42 89,198.57 235,159.86
07 UTILIDAD 5.00% 202,724.01 55,749.10 146,974.91
08 SUB TOTAL 4,581,562.70 1,259,929.74 3,321,632.96
09 IGV 18% 18.00% 824,681.29 226,787.35 597,893.93

PRESUPUESTO DE OBRA TOTAL


10 5,406,243.99 1,486,717.10 3,919,526.89
(1)
PORCENTAJE DEL MES 100.00% 27.50% 72.50%
PORCENTAJE ACUMULADO 100.00% 27.50% 100.00%
CRONOGRAMA RESUMEN DE VALORIZACION DE EJECUCION DE SERVICIO

PROYECTO : "MANTENIMIENTO PERIÓDICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE CHIMBOTE –
PROVINCIA DEL SANTA – DEPARTAMENTO DE ANCASH – SEGUNDA CONVOCATORIA"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DEL SANTA
FECHA : NOVIEMBRE- 2020
INSPECTOR ING. HELMER LAVANDERA GONZALES
RESIDENTE : ING. LUIS ENRIQUE ROMERO PRADO - CIP N° 178184

PERIODO DEL SERVICIO


ITEM UND. PARCIAL MARZO ABRIL
SEM. 02 SEM. 02 SEM. 03 SEM. 04 SEM. 01 SEM. 02 SEM. 03 SEM. 04

01 TRAMO I GLB 1,432,259.19 146,000.00 197,400.00


02 TRAMO II GLB 267,107.36 0.00 86,772.98
03 TRAMO III GLB 191,622.47 33,500.00 58,009.42
04 TRAMO IV GLB 205,927.73 0.00 87,641.53
05 TRAMO V GLB 129,758.05 0.00 39,540.76
06 TRAMO VI GLB 203,456.29 0.00 6,000.00
07 TRAMO VII GLB 338,703.15 23,000.00 171,498.55
08 TRAMO VIII GLB 236,354.02 80,324.11 25,149.02
09 TRAMO IX GLB 43,791.14 0.00 0.00
10 TRAMO X GLB 673,963.10 0.00 296,440.18
11 TRAMO XI GLB 331,537.79 0.00 123,853.10

05 COSTO DIRECTO 4,054,480.29 282,824.11 1,092,305.53


06 GASTO GENERALES 8.00% 324,358.42 22,625.93 87,384.44
07 UTILIDAD 5.00% 202,724.01 14,141.21 54,615.28
08 SUB TOTAL 4,581,562.72 319,591.24 1,234,305.25
09 IGV 18% 18.00% 824,681.29 57,526.42 222,174.94

PRESUPUESTO DE OBRA TOTAL


10 5,406,244.01 377,117.67 1,456,480.19
(1)

PORCENTAJE DEL MES 100.00% 6.98% 26.94%


PORCENTAJE ACUMULADO 100.00% 6.98% 33.92%
CRONOGRAMA VALORIZADO

PROYECTO : "MANTENIMIENTO PERIÓDICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE CHIMBOTE – PROVINCIA DEL SANTA – DEPARTAMENTO DE ANCASH – SEGUNDA
ENTIDAD CONVOCATORIA"
: MUNICIPALIDAD PROVINCIAL DEL SANTA
FECHA : 01/01/2021
DIAS : 40 DIAS
RESIDENTE : ING. LUIS ENRIQUE ROMERO PRADO - CIP N° 178184
INSPECTOR Ing. HELMER LAVANDERA GONZALES
AMPLIACION DE PLAZO N°02 50 DIAS CONSENTIDO
TERMINO 2/17/2021
SERVICIO
1 MES 2 MES 1 MES 2 MES 1 MES 2 MES 1 MES 2 MES 1 MES 2 MES
ITEM DESCRIPCION UND METRADO PRECIO PARCIAL 01-03-2021 01-04-2021
01-01-2021 AL 01-02-2021 AL
20/11/20 - 30/11/20 01/12/20 - 29/12/20 % % % % AL 31-03- AL 30-04-
30-01-2021 17-02-2021
2021 2021
01 TRAMO I 1,432,259.19 253,511.22 1,178,747.98 17.70% 82.30% 340,724.08 671,763.33 23.79% 46.90% 146000.00 197400.00
1 OBRAS PRELIMINARES 22,032.78 6,247.65 15,785.13 2,500.00 3,474.19 2000.00
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 2,475.00 6,525.00 27.50% 72.50% 2,000.00 2,500.00 22.22% 27.78% 0.00 2000.00
1.02 TRAZO Y REPLANTEO km 34.39 378.97 13,032.78 3,772.65 9,260.13 28.95% 71.05% 500.00 974.19 3.84% 7.47% 0.00 0.00
2 PAVIMENTOS 1,012,537.88 157,152.82 855,385.06 283,000.00 517,749.13 101000.00 153400.00
2.01 CAPA NIVELANTE E=0.05M m3 2,063.69 39.74 82,011.04 17,573.79 64,437.25 21.43% 78.57% 10,000.00 12,401.04 12.19% 15.12% 1000.00 3400.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 20,637.10 45.09 930,526.84 139,579.03 790,947.81 15.00% 85.00% 273,000.00 505,348.09 29.34% 54.31% 100000.00 150000.00
3 TRANSPORTE 287,872.65 89,886.29 197,986.37 55,224.08 56,879.60 30000.00 18000.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 287.00 3.13 898.31 320.83 577.49 35.71% 64.29% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 27,221.76 8.00 217,774.08 60,492.80 157,281.28 27.78% 72.22% 47,774.08 50,000.00 21.94% 22.96% 30000.00 15000.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 917.15 3.13 2,870.66 1,435.33 1,435.33 50.00% 50.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 8,291.20 8.00 66,329.60 27,637.33 38,692.27 41.67% 58.33% 7,450.00 6,879.60 11.23% 10.37% 0.00 3000.00
4 OBRAS DE ARTE Y DRENAJE 87,462.07 0.00 87,462.07 0.00 87,462.07 15000.00 24000.00
4.01 RECONFORMACIÓN DE CUNETAS ml 24,028.04 3.64 87,462.07 0.00 87,462.07 0.00% 100.00% 0.00 87,462.07 0.00% 100.00% 15000.00 24000.00
5 SEÑALIZACIÓN 3,918.75 0.00 3,918.75 0.00 3,918.75 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 35.00 59.69 2,089.15 0.00 2,089.15 0.00% 100.00% 0.00 2,089.15 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 10.00 119.78 1,197.80 0.00 1,197.80 0.00% 100.00% 0.00 1,197.80 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 17,618.84 0.00 17,618.84 0.00 2,279.59 0.00 0.00
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 3.79 4,652.22 17,618.84 0.00 17,618.84 0.00% 100.00% 0.00 2,279.59 0.00% 12.94% 0.00 0.00
7 EMERGENCIA SANITARIA 816.22 224.46 591.76 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 224.46 591.76 27.50% 72.50% 0.00 0.00 0.00% 0.00% 0.00 0.00

02 TRAMO II 267,107.36 1,686.43 265,420.92 0.63% 99.37% 80,644.34 161,662.43 30.19% 60.52% 0.00 86772.98
1 OBRAS PRELIMINARES 11,353.57 1,577.60 9,775.97 1,567.52 3,770.00 0.00 1567.52
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 1,241.38 7,758.62 13.79% 86.21% 1,230.00 3,270.00 13.67% 36.33% 0.00 1230.00
1.02 TRAZO Y REPLANTEO km 6.21 378.97 2,353.57 336.22 2,017.35 14.29% 85.71% 337.52 500.00 14.34% 21.24% 0.00 337.52
2 PAVIMENTOS 182,776.32 0.00 182,776.32 67,972.38 114,803.94 0.00 74972.38
2.01 CAPA NIVELANTE E=0.05M m3 372.52 39.74 14,803.94 0.00 14,803.94 0.00% 100.00% 0.00 14,803.94 0.00% 100.00% 0.00 7000.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 3,725.27 45.09 167,972.38 0.00 167,972.38 0.00% 100.00% 67,972.38 100,000.00 40.47% 59.53% 0.00 67972.38
3 TRANSPORTE 51,979.88 0.00 51,979.88 9,000.00 25,942.00 0.00 9000.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 52.00 3.13 162.76 0.00 162.76 0.00% 100.00% 0.00 131.46 0.00% 80.77% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 4,915.04 8.00 39,320.32 0.00 39,320.32 0.00% 100.00% 7,000.00 20,320.32 17.80% 51.68% 0.00 7000.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 166.34 3.13 520.64 0.00 520.64 0.00% 100.00% 0.00 314.06 0.00% 60.32% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,497.02 8.00 11,976.16 0.00 11,976.16 0.00% 100.00% 2,000.00 5,176.16 16.70% 43.22% 0.00 2000.00
4 OBRAS DE ARTE Y DRENAJE 15,728.66 0.00 15,728.66 0.00 15,728.66 0.00 0.00
4.01 RECONFORMACIÓN DE CUNETAS ml 4,321.06 3.64 15,728.66 0.00 15,728.66 0.00% 100.00% 0.00 15,728.66 0.00% 100.00% 0.00 0.00
5 SEÑALIZACIÓN 1,289.19 0.00 1,289.19 871.36 417.83 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 7.00 59.69 417.83 0.00 417.83 0.00% 100.00% 0.00 417.83 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 2.00 119.78 239.56 0.00 239.56 0.00% 100.00% 239.56 0.00 100.00% 0.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 210.60 0.00 100.00% 0.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 421.20 0.00 100.00% 0.00% 0.00 0.00
6 IMPACTO AMBIENTAL 3,163.51 0.00 3,163.51 1,233.07 1,000.00 0.00 1233.07
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.68 4,652.22 3,163.51 0.00 3,163.51 0.00% 100.00% 1,233.07 1,000.00 38.98% 31.61% 0.00 1233.07
7 EMERGENCIA SANITARIA 816.22 108.83 707.39 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 108.83 707.39 13.33% 86.67% 0.00 0.00 0.00% 0.00% 0.00 0.00

03 TRAMO III 191,622.47 1,587.34 190,035.15 0.83% 99.17% 69,020.57 104,509.66 36.02% 54.54% 33500.00 58009.42
1 OBRAS PRELIMINARES 10,659.89 1,478.51 9,181.38 1,478.98 2,644.00 0.00 1478.98
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 1,241.38 7,758.62 13.79% 86.21% 1,241.00 2,359.00 13.79% 26.21% 0.00 1241.00
1.02 TRAZO Y REPLANTEO km 4.38 378.97 1,659.89 237.13 1,422.76 14.29% 85.71% 237.98 285.00 14.34% 17.17% 0.00 237.98
2 PAVIMENTOS 129,068.51 0.00 129,068.51 55,300.00 73,768.51 33500.00 38500.00
2.01 CAPA NIVELANTE E=0.05M m3 263.05 39.74 10,453.61 0.00 10,453.61 0.00% 100.00% 5,300.00 5,153.61 50.70% 49.30% 3500.00 3500.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 2,630.63 45.09 118,614.90 0.00 118,614.90 0.00% 100.00% 50,000.00 68,614.90 42.15% 57.85% 30000.00 35000.00
3 TRANSPORTE 36,704.92 0.00 36,704.92 11,311.15 15,957.27 0.00 11100.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 36.44 3.13 114.07 0.00 114.07 0.00% 100.00% 0.00 114.07 0.00% 100.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 3,470.77 8.00 27,766.16 0.00 27,766.16 0.00% 100.00% 10,000.00 13,766.16 36.02% 49.58% 0.00 10000.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 117.46 3.13 367.65 0.00 367.65 0.00% 100.00% 211.15 0.00 57.43% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,057.13 8.00 8,457.04 0.00 8,457.04 0.00% 100.00% 1,100.00 2,077.04 13.01% 24.56% 0.00 1100.00
4 OBRAS DE ARTE Y DRENAJE 11,149.54 0.00 11,149.54 0.00 11,149.54 0.00 6000.00
4.01 RECONFORMACIÓN DE CUNETAS ml 3,063.06 3.64 11,149.54 0.00 11,149.54 0.00% 100.00% 0.00 11,149.54 0.00% 100.00% 0.00 6000.00
5 SEÑALIZACIÓN 990.34 0.00 990.34 0.00 990.34 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 4.00 59.69 238.76 0.00 238.76 0.00% 100.00% 0.00 238.76 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 1.00 119.78 119.78 0.00 119.78 0.00% 100.00% 0.00 119.78 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 2,233.07 0.00 2,233.07 930.44 0.00 0.00 930.44
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.48 4,652.22 2,233.07 0.00 2,233.07 0.00% 100.00% 930.44 0.00 41.67% 0.00% 0.00 930.44
7 EMERGENCIA SANITARIA 816.22 108.83 707.39 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 108.83 707.39 13.33% 86.67% 0.00 0.00 0.00% 0.00% 0.00 0.00

04 TRAMO IV 205,927.73 1,338.94 204,588.80 0.65% 99.35% 75,263.42 97,164.66 36.55% 47.18% 0.00 87641.53
1 OBRAS PRELIMINARES 9,011.48 1,251.88 7,759.60 2,553.54 2,100.00 0.00 2153.54
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.08 90,000.00 7,200.00 993.10 6,206.90 13.79% 86.21% 2,000.00 1,600.00 27.78% 22.22% 0.00 1600.00
1.02 TRAZO Y REPLANTEO km 4.78 378.97 1,811.48 258.78 1,552.70 14.29% 85.71% 553.54 500.00 30.56% 27.60% 0.00 553.54
2 PAVIMENTOS 140,597.40 0.00 140,597.40 65,597.40 75,000.00 0.00 66209.90
2.01 CAPA NIVELANTE E=0.05M m3 286.55 39.74 11,387.50 0.00 11,387.50 0.00% 100.00% 5,387.50 6,000.00 47.31% 52.69% 0.00 6000.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 2,865.60 45.09 129,209.90 0.00 129,209.90 0.00% 100.00% 60,209.90 69,000.00 46.60% 53.40% 0.00 60209.90
3 TRANSPORTE 39,984.56 0.00 39,984.56 6,412.48 6,246.40 0.00 6412.48
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 40.00 3.13 125.20 0.00 125.20 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 3,780.80 8.00 30,246.40 0.00 30,246.40 0.00% 100.00% 5,000.00 5,246.40 16.53% 17.35% 0.00 5000.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 127.95 3.13 400.48 0.00 400.48 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,151.56 8.00 9,212.48 0.00 9,212.48 0.00% 100.00% 1,412.48 1,000.00 15.33% 10.85% 0.00 1412.48
4 OBRAS DE ARTE Y DRENAJE 12,165.61 0.00 12,165.61 0.00 12,165.61 0.00 12165.61
4.01 RECONFORMACIÓN DE CUNETAS ml 3,342.20 3.64 12,165.61 0.00 12,165.61 0.00% 100.00% 0.00 12,165.61 0.00% 100.00% 0.00 12165.61
5 SEÑALIZACIÓN 1,050.03 0.00 1,050.03 0.00 1,050.03 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 5.00 59.69 298.45 0.00 298.45 0.00% 100.00% 0.00 298.45 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 1.00 119.78 119.78 0.00 119.78 0.00% 100.00% 0.00 119.78 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 2,465.68 0.00 2,465.68 700.00 602.62 0.00 700.00
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.53 4,652.22 2,465.68 0.00 2,465.68 0.00% 100.00% 700.00 602.62 28.39% 24.44% 0.00 700.00
7 EMERGENCIA SANITARIA 652.98 87.06 565.92 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.08 8,162.19 652.98 87.06 565.92 13.33% 86.67% 0.00 0.00 0.00% 0.00% 0.00 0.00

05 TRAMO V 129,758.05 30,449.31 99,308.72 23.47% 76.53% 36,530.17 84,130.65 28.15% 64.84% 0.00 39540.76
1 OBRAS PRELIMINARES 6,529.33 1,135.54 5,393.79 1,896.39 1,175.00 0.00 1896.39
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.06 90,000.00 5,400.00 939.13 4,460.87 17.39% 82.61% 1,700.00 1,000.00 31.48% 18.52% 0.00 1700.00
1.02 TRAZO Y REPLANTEO km 2.98 378.97 1,129.33 196.41 932.92 17.39% 82.61% 196.39 175.00 17.39% 15.50% 0.00 196.39
2 PAVIMENTOS 87,732.69 19,941.89 67,790.80 19,941.89 67,790.80 0.00 21718.36
2.01 CAPA NIVELANTE E=0.05M m3 178.81 39.74 7,105.91 2,664.72 4,441.19 37.50% 62.50% 2,664.72 4,441.19 37.50% 62.50% 0.00 4441.19
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 1,788.13 45.09 80,626.78 17,277.17 63,349.61 21.43% 78.57% 17,277.17 63,349.61 21.43% 78.57% 0.00 17277.17
3 TRANSPORTE 24,950.34 9,293.52 15,656.82 14,087.10 6,644.14 0.00 7731.24
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 24.96 3.13 78.12 34.72 43.40 44.44% 55.55% 25.00 21.82 32.00% 27.93% 0.00 46.82
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 2,359.22 8.00 18,873.76 5,807.31 13,066.45 30.77% 69.23% 13,000.00 5,873.76 68.88% 31.12% 0.00 5873.76
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 79.84 3.13 249.90 166.60 83.30 66.67% 33.33% 62.10 0.00 24.85% 0.00% 0.00 62.10
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 718.57 8.00 5,748.56 3,284.89 2,463.67 57.14% 42.86% 1,000.00 748.56 17.40% 13.02% 0.00 1748.56
4 OBRAS DE ARTE Y DRENAJE 7,589.98 0.00 7,589.98 0.00 7,589.98 0.00 7589.98
4.01 RECONFORMACIÓN DE CUNETAS ml 2,085.16 3.64 7,589.98 0.00 7,589.98 0.00% 100.00% 0.00 7,589.98 0.00% 100.00% 0.00 7589.98
5 SEÑALIZACIÓN 930.73 0.00 930.73 0.00 930.73 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 3.00 59.72 179.15 0.00 179.15 0.00% 100.00% 0.00 179.15 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 1.00 119.78 119.78 0.00 119.78 0.00% 100.00% 0.00 119.78 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 1,535.23 0.00 1,535.23 604.79 0.00 0.00 604.79
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.33 4,652.22 1,535.23 0.00 1,535.23 0.00% 100.00% 604.79 0.00 39.39% 0.00% 0.00 604.79
7 EMERGENCIA SANITARIA 489.73 78.36 411.37 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.06 8,162.19 489.73 78.36 411.37 16.00% 84.00% 0.00 0.00 0.00% 0.00% 0.00 0.00

06 TRAMO VI 203,456.29 1,603.04 201,853.26 0.79% 99.21% 112,752.83 36,557.94 55.42% 17.97% 0.00 6000.00
1 OBRAS PRELIMINARES 10,769.79 1,494.21 9,275.58 3,752.83 1,126.14 0.00 0.00
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 1,241.38 7,758.62 13.79% 86.21% 3,500.00 1,000.00 38.89% 11.11% 0.00 0.00
1.02 TRAZO Y REPLANTEO km 4.67 378.97 1,769.79 252.83 1,516.96 14.29% 85.71% 252.83 126.14 14.29% 7.13% 0.00 0.00
2 PAVIMENTOS 137,504.57 0.00 137,504.57 103,000.00 28,543.57 0.00 0.00
2.01 CAPA NIVELANTE E=0.05M m3 280.25 39.74 11,137.14 0.00 11,137.14 0.00% 100.00% 3,000.00 2,176.14 26.94% 19.54% 0.00 0.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 2,802.56 45.09 126,367.43 0.00 126,367.43 0.00% 100.00% 100,000.00 26,367.43 79.13% 20.87% 0.00 0.00
3 TRANSPORTE 39,104.85 0.00 39,104.86 0.00 0.00 0.00 0.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 39.12 3.13 122.45 0.00 122.45 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 3,697.62 8.00 29,580.96 0.00 29,580.96 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 125.14 3.13 391.69 0.00 391.69 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,126.22 8.00 9,009.76 0.00 9,009.76 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
4 OBRAS DE ARTE Y DRENAJE 11,897.78 0.00 11,897.78 6,000.00 5,897.78 0.00 6000.00
4.01 RECONFORMACIÓN DE CUNETAS ml 3,268.62 3.64 11,897.78 0.00 11,897.78 0.00% 100.00% 6,000.00 5,897.78 50.43% 49.57% 0.00 6000.00
5 SEÑALIZACIÓN 990.45 0.00 990.45 0.00 990.46 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 4.00 59.69 238.76 0.00 238.76 0.00% 100.00% 0.00 238.76 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 1.00 119.89 119.89 0.00 119.89 0.00% 100.00% 0.00 119.89 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.61 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 2,372.63 0.00 2,372.63 0.00 0.00 0.00 0.00
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.51 4,652.22 2,372.63 0.00 2,372.63 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
7 EMERGENCIA SANITARIA 816.22 108.83 707.39 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 108.83 707.39 13.33% 86.67% 0.00 0.00 0.00% 0.00% 0.00 0.00

07 TRAMO VII 338,703.15 60,204.88 278,498.30 17.78% 82.22% 157,826.15 103,668.42 46.60% 30.61% 23000.00 171498.55
1 OBRAS PRELIMINARES 8,443.13 2,365.91 6,077.22 1,790.34 400.00 0.00 2190.34
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.06 90,000.00 5,400.00 1,485.00 3,915.00 27.50% 72.50% 1,400.00 400.00 25.93% 7.41% 0.00 1800.00
1.02 TRAZO Y REPLANTEO km 8.03 378.97 3,043.13 880.91 2,162.22 28.95% 71.05% 390.34 0.00 12.83% 0.00% 0.00 390.34
2 PAVIMENTOS 236,484.98 36,704.07 199,780.92 140,151.89 96,331.09 23000.00 147370.88
2.01 CAPA NIVELANTE E=0.05M m3 481.98 39.74 19,153.89 4,104.41 15,049.49 21.43% 78.57% 15,151.89 4,000.00 79.11% 20.88% 3000.00 8205.89
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 4,819.94 45.09 217,331.09 32,599.66 184,731.43 15.00% 85.00% 125,000.00 92,331.09 57.52% 42.48% 20000.00 139164.99
3 TRANSPORTE 67,254.03 21,000.22 46,253.83 0.00 0.00 0.00 0.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 67.28 3.13 210.59 75.21 135.38 35.71% 64.29% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 6,359.31 8.00 50,874.48 14,131.80 36,742.68 27.78% 72.22% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 215.21 3.13 673.61 336.81 336.81 50.00% 50.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,936.92 8.00 15,495.36 6,456.40 9,038.96 41.67% 58.33% 0.00 0.00 0.00% 0.00% 0.00 0.00
4 OBRAS DE ARTE Y DRENAJE 20,468.67 0.00 20,468.67 15,000.00 5,468.67 0.00 20468.67
4.01 RECONFORMACIÓN DE CUNETAS ml 5,623.26 3.64 20,468.67 0.00 20,468.67 0.00% 100.00% 15,000.00 5,468.67 73.28% 26.72% 0.00 20468.67
5 SEÑALIZACIÓN 1,468.66 0.00 1,468.66 0.00 1,468.66 0.00 1468.66
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 8.00 59.69 477.52 0.00 477.52 0.00% 100.00% 0.00 477.52 0.00% 100.00% 0.00 477.52
5.02 SEÑALES PREVENTIVAS und 3.00 119.78 359.34 0.00 359.34 0.00% 100.00% 0.00 359.34 0.00% 100.00% 0.00 359.34
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 210.60
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 421.20
6 IMPACTO AMBIENTAL 4,093.95 0.00 4,093.95 883.92 0.00 0.00 0.00
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.88 4,652.22 4,093.95 0.00 4,093.95 0.00% 100.00% 883.92 0.00 21.59% 0.00% 0.00 0.00
7 EMERGENCIA SANITARIA 489.73 134.68 355.05 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.06 8,162.19 489.73 134.68 355.05 27.50% 72.50% 0.00 0.00 0.00% 0.00% 0.00 0.00

08 TRAMO VIII 236,354.02 1,645.81 234,708.10 0.70% 99.30% 127,955.44 54,163.76 54.14% 22.92% 80324.11 25149.02
1 OBRAS PRELIMINARES 11,069.18 1,536.98 9,532.20 4,000.00 1,256.00 5257.94 0.00
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 1,241.38 7,758.62 13.79% 86.21% 3,500.00 1,000.00 38.89% 11.11% 4500.00 0.00
1.02 TRAZO Y REPLANTEO km 5.46 378.97 2,069.18 295.60 1,773.58 14.29% 85.71% 500.00 256.00 24.16% 12.37% 757.94 0.00
2 PAVIMENTOS 160,843.46 0.00 160,843.46 113,025.00 47,816.29 75066.17 10057.55
2.01 CAPA NIVELANTE E=0.05M m3 327.81 39.74 13,027.17 0.00 13,027.17 0.00% 100.00% 13,025.00 0.00 99.98% 0.00% 7066.17 0.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 3,278.25 45.09 147,816.29 0.00 147,816.29 0.00% 100.00% 100,000.00 47,816.29 67.65% 32.35% 68000.00 10057.55
3 TRANSPORTE 45,742.36 0.00 45,742.36 0.00 0.00 0.00 0.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 45.76 3.13 143.23 0.00 143.23 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 4,325.24 8.00 34,601.92 0.00 34,601.92 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 146.38 3.13 458.17 0.00 458.17 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,317.38 8.00 10,539.04 0.00 10,539.04 0.00% 100.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
4 OBRAS DE ARTE Y DRENAJE 13,921.58 0.00 13,921.58 10,000.00 3,921.58 0.00 13921.58
4.01 RECONFORMACIÓN DE CUNETAS ml 3,824.61 3.64 13,921.58 0.00 13,921.58 0.00% 100.00% 10,000.00 3,921.58 71.83% 28.17% 0.00 13921.58
5 SEÑALIZACIÓN 1,169.89 0.00 1,169.89 0.00 1,169.89 0.00 1169.89
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 5.00 59.69 298.45 0.00 298.45 0.00% 100.00% 0.00 298.45 0.00% 100.00% 0.00 298.45
5.02 SEÑALES PREVENTIVAS und 2.00 119.78 239.56 0.00 239.56 0.00% 100.00% 0.00 239.56 0.00% 100.00% 0.00 239.56
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 210.60
5.04 SEÑALES INFORMATIVAS und 2.00 210.64 421.28 0.00 421.28 0.00% 100.00% 0.00 421.28 0.00% 100.00% 0.00 421.28
6 IMPACTO AMBIENTAL 2,791.33 0.00 2,791.33 930.44 0.00 0.00 0.00
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.60 4,652.22 2,791.33 0.00 2,791.33 0.00% 100.00% 930.44 0.00 33.33% 0.00% 0.00 0.00
7 EMERGENCIA SANITARIA 816.22 108.83 707.28 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 108.83 707.28 13.33% 86.65% 0.00 0.00 0.00% 0.00% 0.00 0.00

09 TRAMO IX 43,791.14 6,543.92 37,247.27 14.94% 85.06% 29,425.10 1,870.96 67.19% 4.27% 0.00 0.00
1 OBRAS PRELIMINARES 9,303.18 2,664.72 6,638.46 3,575.79 1,000.00 0.00 0.00
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 2,571.43 6,428.57 28.57% 71.43% 3,500.00 1,000.00 38.89% 11.11% 0.00 0.00
1.02 TRAZO Y REPLANTEO km 0.80 378.97 303.18 93.29 209.89 30.77% 69.23% 75.79 0.00 25.00% 0.00% 0.00 0.00
2 PAVIMENTOS 23,620.31 0.00 23,620.31 23,618.81 0.00 0.00 0.00
2.01 CAPA NIVELANTE E=0.05M m3 48.14 39.74 1,913.08 0.00 1,913.08 0.00% 100.00% 1,913.08 0.00 100.00% 0.00% 0.00 0.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 481.42 45.09 21,707.23 0.00 21,707.23 0.00% 100.00% 21,705.73 0.00 99.99% 0.00% 0.00 0.00
3 TRANSPORTE 6,717.37 3,661.54 3,055.83 0.00 0.00 0.00 0.00
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 6.72 3.13 21.03 14.02 7.01 66.66% 33.33% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 635.17 8.00 5,081.36 2,032.54 3,048.82 40.00% 60.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 21.50 3.13 67.30 67.30 0.00 100.01% 0.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 193.46 8.00 1,547.68 1,547.68 0.00 100.00% 0.00% 0.00 0.00 0.00% 0.00% 0.00 0.00
4 OBRAS DE ARTE Y DRENAJE 2,044.41 0.00 2,044.41 2,044.41 0.00 0.00 0.00
4.01 RECONFORMACIÓN DE CUNETAS ml 561.65 3.64 2,044.41 0.00 2,044.41 0.00% 100.00% 2,044.41 0.00 100.00% 0.00% 0.00 0.00
5 SEÑALIZACIÓN 870.96 0.00 870.96 0.00 870.96 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 2.00 59.69 119.38 0.00 119.38 0.00% 100.00% 0.00 119.38 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 1.00 119.78 119.78 0.00 119.78 0.00% 100.00% 0.00 119.78 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 418.70 0.00 418.70 186.09 0.00 0.00 0.00
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.09 4,652.22 418.70 0.00 418.70 0.00% 100.00% 186.09 0.00 44.44% 0.00% 0.00 0.00
7 EMERGENCIA SANITARIA 816.22 217.66 598.60 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 217.66 598.60 26.67% 73.34% 0.00 0.00 0.00% 0.00% 0.00 0.00

10 TRAMO X 673,963.10 119,731.48 554,231.64 17.77% 82.23% 368,500.99 235,181.30 54.68% 34.90% 0.00 296440.18
1 OBRAS PRELIMINARES 15,082.47 4,235.72 10,846.76 5,900.00 1,413.80 0.00 1413.80
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 2,475.00 6,525.00 27.50% 72.50% 4,400.00 1,000.00 48.89% 11.11% 0.00 1000.00
1.02 TRAZO Y REPLANTEO km 16.05 378.97 6,082.47 1,760.72 4,321.76 28.95% 71.05% 1,500.00 413.80 24.66% 6.80% 0.00 413.80
2 PAVIMENTOS 472,407.53 73,320.84 399,086.70 259,459.53 205,000.00 0.00 239145.46
2.01 CAPA NIVELANTE E=0.05M m3 962.81 39.74 38,262.07 8,199.02 30,063.06 21.43% 78.57% 25,314.07 5,000.00 66.16% 13.07% 0.00 5000.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 9,628.42 45.09 434,145.46 65,121.82 369,023.64 15.00% 85.00% 234,145.46 200,000.00 53.93% 46.07% 0.00 234145.46
3 TRANSPORTE 134,348.05 41,950.46 92,397.59 58,670.79 26,581.76 0.00 32298.71
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 134.40 3.13 420.67 150.24 270.43 35.71% 64.29% 264.17 0.00 62.80% 0.00% 0.00 264.17
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 12,703.49 8.00 101,627.92 28,229.98 73,397.94 27.78% 72.22% 50,000.00 23,627.92 49.20% 23.25% 0.00 23627.92
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 429.91 3.13 1,345.62 672.81 672.81 50.00% 50.00% 406.62 0.00 30.22% 0.00% 0.00 406.62
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 3,869.23 8.00 30,953.84 12,897.43 18,056.41 41.67% 58.33% 8,000.00 2,953.84 25.84% 9.54% 0.00 8000.00
4 OBRAS DE ARTE Y DRENAJE 40,888.67 0.00 40,888.67 40,888.67 0.00 0.00 20000.00
4.01 RECONFORMACIÓN DE CUNETAS ml 11,233.15 3.64 40,888.67 0.00 40,888.67 0.00% 100.00% 40,888.67 0.00 100.00% 0.00% 0.00 20000.00
5 SEÑALIZACIÓN 2,185.74 0.00 2,185.74 0.00 2,185.74 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 16.00 59.69 955.04 0.00 955.04 0.00% 100.00% 0.00 955.04 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 5.00 119.78 598.90 0.00 598.90 0.00% 100.00% 0.00 598.90 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 8,234.43 0.00 8,234.43 3,582.00 0.00 0.00 3582.21
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 1.77 4,652.22 8,234.43 0.00 8,234.43 0.00% 100.00% 3,582.00 0.00 43.50% 0.00% 0.00 3582.21
7 EMERGENCIA SANITARIA 816.22 224.46 591.76 0.00 0.00 0.00 0.00
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 224.46 591.76 27.50% 72.50% 0.00 0.00 0.00% 0.00% 0.00 0.00

11 TRAMO XI 331,537.79 59,334.93 272,202.84 17.90% 82.10% 183,594.10 109,979.52 55.38% 33.17% 0.00 123853.10
1 OBRAS PRELIMINARES 11,944.60 3,327.38 8,617.22 4,700.00 1,086.66 0.00 1086.66
1.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO glb 0.10 90,000.00 9,000.00 2,475.00 6,525.00 27.50% 72.50% 3,000.00 600.00 33.33% 6.67% 0.00 600.00
1.02 TRAZO Y REPLANTEO km 7.77 378.97 2,944.60 852.38 2,092.22 28.95% 71.05% 1,700.00 486.66 57.73% 16.53% 0.00 486.66
2 PAVIMENTOS 228,611.56 35,482.06 193,129.50 135,095.50 93,516.06 0.00 100000.00
2.01 CAPA NIVELANTE E=0.05M m3 465.93 39.74 18,516.06 3,967.73 14,548.33 21.43% 78.57% 15,000.00 3,516.06 81.01% 18.99% 0.00 10000.00
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15M m3 4,659.47 45.09 210,095.50 31,514.33 178,581.18 15.00% 85.00% 120,095.50 90,000.00 57.16% 42.84% 0.00 90000.00
3 TRANSPORTE 65,014.85 20,301.03 44,713.83 26,460.23 9,180.64 0.00 15640.87
3.01 TRANSPORTE MATERIAL GRANULAR HASTA 1KM m3k 65.04 3.13 203.58 72.71 130.87 35.72% 64.29% 99.10 0.00 48.68% 0.00% 0.00 99.10
3.02 TRANSPORTE MATERIAL GRANULAR MAYOR A 1KM m3k 6,147.58 8.00 49,180.64 13,661.29 35,519.35 27.78% 72.22% 20,000.00 9,180.64 40.67% 18.67% 0.00 9180.64
3.03 TRANSPORTE MATERIAL EXCEDENTE HASTA 1KM m3k 208.05 3.13 651.20 325.60 325.60 50.00% 50.00% 181.70 0.00 27.90% 0.00% 0.00 181.70
3.04 TRANSPORTE MATERIAL EXCEDENTE MAYOR A 1KM m3k 1,872.43 8.00 14,979.44 6,241.43 8,738.01 41.67% 58.33% 6,179.44 0.00 41.25% 0.00% 0.00 6179.44
4 OBRAS DE ARTE Y DRENAJE 19,787.19 0.00 19,787.19 15,000.00 4,787.19 0.00 4787.19
4.01 RECONFORMACIÓN DE CUNETAS ml 5,436.04 3.64 19,787.19 0.00 19,787.19 0.00% 100.00% 15,000.00 4,787.19 75.81% 24.19% 0.00 4787.19
5 SEÑALIZACIÓN 1,408.98 0.00 1,408.97 0.00 1,408.97 0.00 0.00
5.01 INSTALACIÓN DE POSTES KILOMÉTRICOS und 7.00 59.69 417.83 0.00 417.83 0.00% 100.00% 0.00 417.83 0.00% 100.00% 0.00 0.00
5.02 SEÑALES PREVENTIVAS und 3.00 119.78 359.35 0.00 359.34 0.00% 100.00% 0.00 359.34 0.00% 100.00% 0.00 0.00
5.03 SEÑALES REGLAMENTARIAS und 1.00 210.60 210.60 0.00 210.60 0.00% 100.00% 0.00 210.60 0.00% 100.00% 0.00 0.00
5.04 SEÑALES INFORMATIVAS und 2.00 210.60 421.20 0.00 421.20 0.00% 100.00% 0.00 421.20 0.00% 100.00% 0.00 0.00
6 IMPACTO AMBIENTAL 3,954.39 0.00 3,954.39 2,093.50 0.00 0.00 2093.50
6.01 RECUPERACIÓN AMBIENTAL DE ÁREAS OCUPADAS ha 0.85 4,652.22 3,954.39 0.00 3,954.39 0.00% 100.00% 2,093.50 0.00 52.94% 0.00% 0.00 2093.50
7 EMERGENCIA SANITARIA 816.22 224.46 591.76 244.87 0.00 0.00 244.87
7.01 EMERGENCIA SANITARIA COVID 19 glb 0.10 8,162.19 816.22 224.46 591.76 27.50% 72.50% 244.87 0.00 30.00% 0.00% 0.00 244.87
COSTO DIRECTO 4,054,480.29 537,637.30 3,516,842.98 1,582,237.19 1,660,652.63 282824.11 1092305.53
GASTOS GENERALES 8.0% 324,358.42 43,010.98 281,347.44 126,578.98 132,852.21 22625.93 87384.44
UTILIDAD 5.0% 202,724.01 26,881.87 175,842.15 79,111.86 83,032.63 14141.21 54615.28
SUBTOTAL 4,581,562.72 607,530.15 3,974,032.57 1,787,928.03 1,876,537.47 319591.25 1234305.25
Impuesto (IGV ) 18.0% 824,681.29 109,355.43 715,325.86 321,827.05 337,776.74 57526.43 222174.95
TOTAL PRESUPUESTO 5,406,244.01 716,885.58 4,689,358.43 2,109,755.08 2,214,314.21 377117.68 1456480.20
PORCENTAJE DE AVANCE PARCIAL(%) 13.26% 86.74% 48.79% 51.21% 6.98% 26.94%
PORCENTAJE DE AVANCE ACUMULADO(%) 13.26% 100.00% 48.79% 100.00%
3 MES 1 MES 2 MES 3 MES
01-05-2021
AL 31-05- % % %
2021
211304.52 10.19% 13.78% 14.75%

3974.19
2500.00 0.00% 80.81% 38.31%
1474.19 0.00% 0.00% 15.92%
167965.03
4092.04 1.22% 19.35% 6.35%
163872.99 10.75% 107.47% 20.72%
16104.48
0.00 0.00% 0.00% 0.00%
12774.88 13.78% 24.80% 8.12%
0.00 0.00% 0.00% 0.00%
3329.60 0.00% 10.85% 8.61%
19342.07
19342.07 17.15% 27.44% 22.11%
3918.75
2089.15 0.00% 0.00% 100.00%
1197.80 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

155533.79 0.00% 32.49% 58.23%


3770.00
3270.00 0.00% 13.67% 42.15%
500.00 0.00% 14.34% 24.78%
107803.94
7803.94 0.00% 47.28% 52.72%
100000.00 0.00% 40.47% 59.53%
25942.00
131.46 0.00% 0.00% 80.77%
20320.32 0.00% 17.80% 51.68%
314.06 0.00% 0.00% 60.32%
5176.16 0.00% 16.70% 43.22%
15728.66
15728.66 0.00% 0.00% 100.00%
1289.19
417.83 0.00% 0.00% 100.00%
239.56 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
1000.00
1000.00 0.00% 38.98% 31.61%
0.00
0.00 0.00% 0.00% 0.00%

82020.81 17.48% 30.27% 42.80%


2644.00
2359.00 0.00% 13.79% 30.40%
285.00 0.00% 14.34% 20.03%
57068.51
3453.61 33.48% 33.48% 33.04%
53614.90 25.29% 29.51% 45.20%
16168.42
114.07 0.00% 0.00% 100.00%
13766.16 0.00% 36.02% 49.58%
211.15 0.00% 0.00% 57.43%
2077.04 0.00% 13.01% 24.56%
5149.54
5149.54 0.00% 53.81% 46.19%
990.34
238.76 0.00% 0.00% 100.00%
119.78 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 41.67% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

84786.55 0.00% 42.56% 41.17%


2500.00
2000.00 0.00% 22.22% 32.22%
500.00 0.00% 30.56% 32.20%
74387.50
5387.50 0.00% 52.69% 47.31%
69000.00 0.00% 46.60% 53.40%
6246.40
0.00 0.00% 0.00% 0.00%
5246.40 0.00% 16.53% 17.35%
0.00 0.00% 0.00% 0.00%
1000.00 0.00% 15.33% 10.85%
0.00
0.00 0.00% 100.00% 0.00%
1050.03
298.45 0.00% 0.00% 100.00%
119.78 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
602.62
602.62 0.00% 28.39% 24.44%
0.00
0.00 0.00% 0.00% 0.00%

81120.06 0.00% 30.47% 62.52%


1175.00
1000.00 0.00% 31.48% 22.42%
175.00 0.00% 17.39% 18.76%
66014.33
2664.72 0.00% 62.50% 60.00%
63349.61 0.00% 21.43% 100.00%
13000.00
0.00 0.00% 59.93% 0.00%
13000.00 0.00% 31.12% 99.49%
0.00 0.00% 24.85% 0.00%
0.00 0.00% 30.42% 0.00%
0.00
0.00 0.00% 100.00% 0.00%
930.73
179.15 0.00% 0.00% 100.00%
119.78 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 39.39% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

6888.23 0.00% 2.95% 3.39%


0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
5897.78
5897.78 0.00% 50.43% 49.57%
990.46
238.76 0.00% 0.00% 100.00%
119.89 0.00% 0.00% 100.00%
210.61 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%

0.00 6.79% 50.63% 0.00%


0.00
0.00 0.00% 33.33% 0.00%
0.00 0.00% 12.83% 0.00%
0.00
0.00 15.66% 42.84% 0.00%
0.00 9.20% 64.03% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 100.00% 0.00%
0.00
0.00 0.00% 100.00% 0.00%
0.00 0.00% 100.00% 0.00%
0.00 0.00% 100.00% 0.00%
0.00 0.00% 100.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

0.00 33.98% 10.64% 0.00%


0.00
0.00 50.00% 0.00% 0.00%
0.00 36.63% 0.00% 0.00%
0.00
0.00 54.24% 0.00% 0.00%
0.00 46.00% 6.80% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 100.00% 0.00%
0.00
0.00 0.00% 100.00% 0.00%
0.00 0.00% 100.00% 0.00%
0.00 0.00% 100.00% 0.00%
0.00 0.00% 100.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

870.96 0.00% 0.00% 1.99%


0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%
870.96
119.38 0.00% 0.00% 100.00%
119.78 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 0.00% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

307242.32 0.00% 43.98% 45.59%


5900.00
4400.00 0.00% 11.11% 67.43%
1500.00 0.00% 6.80% 34.71%
225314.07
25314.07 0.00% 13.07% 84.20%
200000.00 0.00% 53.93% 54.20%
52953.84
0.00 0.00% 62.80% 0.00%
50000.00 0.00% 23.25% 68.12%
0.00 0.00% 30.22% 0.00%
2953.84 0.00% 25.84% 16.36%
20888.67
20888.67 0.00% 48.91% 51.09%
2185.74
955.04 0.00% 0.00% 100.00%
598.90 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 43.50% 0.00%
0.00
0.00 0.00% 0.00% 0.00%

169720.53 0.00% 37.36% 51.19%


4700.00
3000.00 0.00% 6.67% 45.98%
1700.00 0.00% 16.53% 81.25%
128611.56
8516.06 0.00% 54.01% 58.54%
120095.50 0.00% 42.84% 67.25%
20000.00
0.00 0.00% 48.68% 0.00%
20000.00 0.00% 18.67% 56.31%
0.00 0.00% 27.90% 0.00%
0.00 0.00% 41.25% 0.00%
15000.00
15000.00 0.00% 24.19% 75.81%
1408.97
417.83 0.00% 0.00% 100.00%
359.34 0.00% 0.00% 100.00%
210.60 0.00% 0.00% 100.00%
421.20 0.00% 0.00% 100.00%
0.00
0.00 0.00% 52.94% 0.00%
0.00
0.00 0.00% 30.00% 0.00%
1099487.77
87959.02
54974.39
1242421.18
223635.81
1466057.00
27.12%