- TERRAPLEN DELANTERO

MANO DE OBRA UNIDAD CANTIDAD P.U. PARCIAL


BORDERA CON LADRILLO M2 12.00 30.00 360.00
RELLENO PROPIO M3 18.00 15.00 270.00
FALSO PISO M2 15.00 20.00 300.00
CONTRAPISO M2 15.00 15.00 225.00
ARMADO DE MADERA M2 15.00 30.00 450.00
COBERTURA DE CALAMINA M2 15.00 20.00 300.00
ESCALINATAS UND 3.00 100.00 300.00
2205.00
MATERIALES UNIDAD CANTIDAD P.U. PARCIAL
LADRILLO CEMENTO MACISO MILLAR 0.50 1500.00 750.00
ARENA GRUESA M3 6.00 70.00 420.00
TIERRA RELLENO M3 21.00 45.00 945.00
HORMIGON M3 3.00 70.00 210.00
CEMENTO BLS 56.00 28.00 1568.00
PILARES DE MADERA 4"x4"X4 m UND 4.00 110.00 440.00
VIGAS DE MADERA 4"*2"*4 m UND 8.00 70.00 560.00
CORREAS DE MADERA 2"*2"*4m UND 12.00 45.00 540.00
CANALETAS METALICAS ML 8.00 25.00 200.00
TUBO 4 PULGADAS UND 2.00 25.00 50.00
CALAMINA TRANSPARENTE PLANCHAS 13.00 30.00 390.00
CLAVOS 4 y 5 " KG 3.00 7.00 21.00
CLAVO CALAMINAS KG 1.00 10.00 10.00
BARANDAS CON MADERA 2" 3" EN TERRAPLEN ML 10.00 30.00 300.00
6404.00
TOTAL 1 8609.00

2.- PARRA DE UVA 6 m x 4 m


TUBOS DE 4" UND 12.00 25.00 300.00
TIERRA MEJORADA M3 2.00 100.00 200.00
ALAMBRE GALVANIZADO # 4 KG 5.00 20.00 100.00
MANO OBRA GLOBAL 150.00

TOTAL 2 750.00

3.- BARANDAS METALICAS


BARANDAS EN ESCALERAS Y DUCTO A 2DO PISO ML 23.00 70.00 1610.00
BARANDA EN MUROS EN 2DO PISO ML 24.00 35.00 840.00
CABLEADO ELECTRICO #14 RLLS 2.00 205.00 410.00
TOTAL 3 2860.00

4.- VEREDAS PERIMETRALES 0.60 ancho; e=0.15 m; L= 45 m

HORMIGON M3 7 70 490.00
ARENA GRUESA M3 4 70 280.00
CEMENTO BLS 38 27 1026.00
MANO OBRA ML 45 25 1125.00
TOTAL 4 2921.00

5.- POZO SEPTICO: 2 m x 2 m x 2m

LADRILLO 18 HUECOS MILLAR 0.5 1500 750.00


CEMENTO BLS 40 27 1080.00
PIEDRA CHANCADA M3 2 100 200.00
HORMIGON M3 1.5 70 105.00
ARENA GRUESA M3 1 70 70.00
TABLAS 1" x 10" x 3m UND 8 25 200.00
LISTONES 4" x 2" x 3m UND 4 20 80.00
FIERRO 1/2" VARILLAS 14 40 560.00
ALAMBRE # 16 KG 2 9 18.00
CAJA REGISTRO UND 2 150 300.00
TUBO 4" UND 8 25 200.00
TUBO 2" UND 8 18 144.00
TEE 4x4 UND 4 7 28.00
CODO 4" x 90° UND 4 7 28.00
LLAVE 2" COMPLETO UND 1 70 70.00
MANO OBRA UND 1 1500 1500.00
TOTAL 5 5333.00

6.- TANQUE ELEVADO: ROTOPLAST 1100 LITROS

MATERIALES 5466.00
FIERRO 1/2" VARILLAS 14.00 40.00 560.00
FIERRO 3/8" VARILLAS 9.00 28.00 252.00
ALAMBRE # 16 KG 10.00 10.00 100.00
CEMENTO BLS 48.00 27.00 1296.00
HORMIGON M3 6.00 70.00 420.00
TUBO 2" UND 8.00 18.00 144.00
TUBO 1" UND 10.00 25.00 250.00
TUBO 1/2" UND 12.00 14.00 168.00
CODO 1" UND 6.00 6.00 36.00
CODO 1/2" UND 6.00 2.00 12.00
TEE 1/2" UND 6.00 2.00 12.00
TUBO 3/4" LUZ UND 15.00 8.00 120.00
CURVAS 3/4" LUZ UND 12.00 3.00 36.00
CODO 2" DESAGUE UND 5.00 7.00 35.00
LLAVE PASO 1/2" UND 1.00 40.00 40.00
VALVULLA CHECK 1/2" UND 2.00 40.00 80.00
ESCALERA Y TECHO SOBRE TANQUE GLOBAL 1.00 500.00 500.00
TANQUE ROTOPLAST 1100 L UND 1.00 600.00 600.00
BOMBA SUMERGIBLE 1 HP, 15 m ALTURA UND 1.00 400.00 400.00
CONTROL DE NIVEL UND 2.00 100.00 200.00
CABLE # 14 ROLLO 1.00 205.00 205.00

MANO OBRA 0.00 1950.00


COLUMNAS 25 x 25 UND 3.00 250.00 750.00
VIGAS 25 x 25 UND 3.00 200.00 600.00
LOSA SUPERIOR e=10 cm UND 1.00 300.00 300.00
INSTALACION DE TANQUE Y TUBERIAS Y BOMBA GLOBAL 1.00 300.00 300.00

TOTAL 6 7416.00

ACABADOS :
PISO 2: MATERIALES:
PISO EN BANOS M2 12.4 30 372
PARED EN BAÑOS M2 52.2 30 1566
PEGAMENTO x 25 kg BLS 35 12 420
SANITARIOS BAÑO COMPLETO UNIDAD 2 600 1200
ACCESORIOS/MANIJAS,JABONERAS, UNIDAD 2 75 150
LLAVE LAVATORIO UNIDAD 2 50 100
MANGUERAS DE ACOPLE EN LAV, WATER UNIDAD 4 25 100
PISO EN DORMITORIOS M2 25 30 750
PISO EN STAR Y PASADIZOS M2 32 30 960
ZOCALOS ML 34 15 510
CORTINA EN BAÑO UNIDAD 2 75 150
CIELO RASO CON DRAYWALL M2 0
PUERTA ALUMINIO UND 2 0
VENTANA VIDRIO 8 mm M2 0
VENTANA CON MALLA METALICA/MADERA M2 0

PISO 2: MANO DE OBRA:


PISOS Y PAREDES/ZOCALOS M2 126.7 25 3167.5
INSTALACION SANITARIOS EN BAÑOS UND 2 150 300
CIELO RASO M2 80 50 4000 2.88
0
0
0
0
0
0
0
0
0

PISO 1: MATERIALES:
PISO EN BAÑO M2 2 30 60
PARED EN BAÑO M2 8 30 240
PEGAMENTO x 25 kg BLS 14 12 168
SANITARIOS BAÑO COMPLETO UNIDAD 1 600 600
ACCESORIOS/MANIJAS,JABONERAS, UNIDAD 1 75 75
LLAVE LAVATORIO UNIDAD 1 50 50
MANGUERAS DE ACOPLE EN LAV, WATER UNIDAD 2 25 50
PISO EN SALA M2 41 30 1230
ZOCALO ML 23 15 345
PUERTA ALUMINIO EN BAÑO UNIDAD 1 0
PUERTA MADERA UNIDAD 2 0
0
0
0
PISO 1: MANO DE OBRA:
PISOS Y PAREDES/ZOCALOS M2 54.45 20 1089
INSTALACION SANITARIOS EN BAÑOS UND 2 150 300
CIELO RASO M2 0
VENTANA CON MALLA METALICA M2 0

Nota: se gasto por instalacion de luz electrica, desde el vecino. 700.00


Compra compartida de cable 450.00
compra individual de medidor digital+15 m de cable # 10 y 2 llaves de 32 AM 250.00

TOTAL GENERAL 28589.00


ENCHAPADOS CON CERAMICA EN: 3 BAÑOS, 2 DORMITORIOS, PASADIZOS Y SALA EN EL PRIMER PISO.

ACABADOS : PISO 2 8917.50


MATERIALES: 5400.00
CERAMICA EN PISO EN BANOS M2 12.4 30 372
CERAMICA EN PARED EN BAÑOS M2 62.2 30 1866
PEGAMENTO x 25 kg BLS 35 18 630
CERAMICA EN PISO EN DORMITORIOS M2 25 30 750
CERAMICA EN PISO EN STAR Y PASADIZ M2 36 30 1080
ZOCALOS ML 34 15 510
FRAGUA KG 16 12 192
PISO 2: MANO DE OBRA: 3517.50
PISOS Y PAREDES/ZOCALOS M2 140.7 25 3517.5

ACABADOS: PISO 1: 3560.25


MATERIALES: 2199.00
CERAMICA EN PISO EN BAÑO M2 2 30 60
CERAMICA EN PARED EN BAÑO M2 8 30 240
PEGAMENTO x 25 kg BLS 14 18 252
CERAMICA EN PISO EN SALA M2 41 30 1230
ZOCALOS ML 23 15 345
FRAGUA KG 6 12 72
PISO 1: MANO DE OBRA:
PISOS Y PAREDES/ZOCALOS M2 54.45 25 1361.25 1361.25

ACABADOS: SANITARIOS EN BAÑOS 4200.00


MATERIALES: 3600.00
BAÑO COMPLETO, WATER-TANQUE-LAVUNIDAD 3 850 2550
ACCESORIOS POR BAÑO UNIDAD 3 200 600
LLAVE EN LAVATORIOS UNIDAD 3 150 450

MANO DE OBRA:
INSTALACION EN BAÑOS UNIDAD 3 200 600 600.00

TANQUE ELEVADO: ROTOPLAST 1100 LITROS 6638.00

MATERIALES 4988.00
FIERRO 1/2" VARILLAS 14.00 45.00 630.00
FIERRO 3/8" VARILLAS 9.00 28.00 252.00
ALAMBRE # 16 KG 5.00 10.00 50.00
CEMENTO BLS 22.00 27.00 594.00
HORMIGON M3 4.00 70.00 280.00
TUBO 2" UND 8.00 18.00 144.00
TUBO 1" UND 8.00 25.00 200.00
TUBO 1/2" UND 8.00 14.00 112.00
CODO 1" UND 6.00 6.00 36.00
CODO 1/2" UND 6.00 2.00 12.00
TEE 1/2" UND 6.00 2.00 12.00
TUBO 3/4" LUZ UND 15.00 8.00 120.00
CURVAS 3/4" LUZ UND 12.00 3.00 36.00
CODO 2" DESAGUE UND 5.00 7.00 35.00
LLAVE PASO 1/2" UND 1.00 40.00 40.00
VALVULLA CHECK 1/2" UND 2.00 40.00 80.00
ESCALERA Y TECHO SOBRE TANQUE GLOBAL 1.00 950.00 950.00
TANQUE ROTOPLAST 1100 L UND 1.00 600.00 600.00
BOMBA SUMERGIBLE 1 HP, 15 m ALTURUND 1.00 400.00 400.00
CONTROL DE NIVEL UND 2.00 100.00 200.00
CABLE # 14 ROLLO 1.00 205.00 205.00

MANO OBRA 1650.00


COLUMNAS 25 x 25 UND 3.00 250.00 750.00
VIGAS 25 x 25 UND 2.00 150.00 300.00
LOSA SUPERIOR e=10 cm UND 1.00 300.00 300.00
INSTALACION DE TANQUE Y TUBERIAS GLOBAL 1.00 300.00 300.00
PUERTAS: Dimensiones area(m2) 8037.15
P1-1 1.00 x 2.63 2.63 500 1315
P1-2 1.00 x 2.64 2.64 500 1320
P1-B1 0.70 x 2.17 1.519 500 759.5
P2-1 0.90 x 2.16 1.944 500 972
P2-B1 0.81 x 2.16 1.7496 500 874.8
P2-2 0.90 x 2.16 1.944 500 972
P2-B2 0.81 x 2.17 1.7577 500 878.85
P2-3 0.70 x 2.70 1.89 500 945

VENTANAS: Dimensiones area(m2) 7706.895


V1-1 1.47 x 1.80 2.65 150 396.9
V1-2 2.59 x 1.80 4.66 150 699.3
V1-3 2.44 x 1.90 4.64 150 695.4
V1-4 2.48 x 1.91 4.74 150 710.52
V1-5 0.40 x 1.80 0.72 150 108
V2-1 2.87 x 1.92 5.51 150 826.56
V2-B1 0.84 x 0.53 0.45 150 66.78
V2-2 2.76 x 1.95 5.38 150 807.3
V2-B2 0.90 x 0.51 0.46 150 68.85
V2-3 2.70 x 1.87 5.05 150 757.35
V2-4 2.82 x 1.87 5.27 150 791.01
V2-5 2.60 x 1.84 4.78 150 717.6
MP 2.65 x 2.67 7.08 150 1061.325

CIELORAZO I AREA 64
CIELORAZO EAREA 36
area 1 area 2 area 3 area 4 area total
piso cuato 1 0.27 10.07 10.34
piso cuarto 2 0.285 10.07 10.355
piso baño 1 1.0192 3.264 4.2832
pared baño 1 9.18 6.28 15.46
piso baño 2 1.0192 3.264 4.2832
pared baño 2 9.18 6.28 15.46
piso valcon y sala star 11.685 8.7135 3.135 3.08 26.6135
piso y contra piso escalera 1 28.5 1.21 29.71
piso y contra piso esaclera 2 6.65 0.9025 7.5525
piso sala 1er piso 33.4284 33.4284
piso baño 1er psio 1.776 1.776
pared baño 1er piso 6.6 6.6
pared ducha 1 6.28 6.28
pared ducha 2 6.28 6.28

piso pared
area cuartos 20.695 CISTERNA 13.5
area baños 10.3424 50.08 PISO 2DO 26.6
piso 2do piso 26.6135 PISO 1ER 33.4
piso 1er piso 33.4284 ESCALERA 37.26

piso total 91.0793


pared total 50.08
7550 7700 150

55.8749
78

1365.6

134.4

18 243 1215.6
10 266 509
10 334 843
10 372.6 1215.6
1.- TERRAPLEN DELANTERO

MANO DE OBRA UNIDAD CANTIDAD P.U. PARCIAL


BORDERA CON LADRILLO M2 12.00 30.00 360.00
RELLENO PROPIO M3 18.00 15.00 270.00
FALSO PISO M2 15.00 20.00 300.00
CONTRAPISO M2 15.00 15.00 225.00
ARMADO DE MADERA M2 15.00 30.00 450.00
COBERTURA DE CALAMINA M2 15.00 20.00 300.00
ESCALINATAS UND 3.00 100.00 300.00
2205.00
MATERIALES UNIDAD CANTIDAD P.U. PARCIAL
LADRILLO CEMENTO MACISO MILLAR 0.50 1500.00 750.00
ARENA GRUESA M3 6.00 70.00 420.00
TIERRA RELLENO M3 21.00 45.00 945.00
HORMIGON M3 3.00 70.00 210.00
CEMENTO BLS 56.00 28.00 1568.00
PILARES DE MADERA 4"x4"X4 m UND 4.00 110.00 440.00
VIGAS DE MADERA 4"*2"*4 m UND 8.00 70.00 560.00
CORREAS DE MADERA 2"*2"*4m UND 12.00 45.00 540.00
CANALETAS METALICAS ML 8.00 25.00 200.00
TUBO 4 PULGADAS UND 2.00 25.00 50.00
CALAMINA TRANSPARENTE PLANCHAS 13.00 30.00 390.00
CLAVOS 4 y 5 " KG 3.00 7.00 21.00
CLAVO CALAMINAS KG 1.00 10.00 10.00
BARANDAS CON MADERA 2" 3" EN TEML 10.00 30.00 300.00
6404.00
TOTAL 1 8609.00

2.- PARRA DE UVA 6 m x 4 m


TUBOS DE 4" UND 12.00 25.00 300.00
TIERRA MEJORADA M3 2.00 100.00 200.00
ALAMBRE GALVANIZADO # 4 KG 5.00 20.00 100.00
MANO OBRA GLOBAL 150.00

TOTAL 2 750.00

3.- BARANDAS METALICAS


BARANDAS EN ESCALERAS Y DUCTO A ML 23.00 70.00 1610.00
BARANDA EN MUROS EN 2DO PISO ML 24.00 35.00 840.00
CABLEADO ELECTRICO #14 RLLS 2.00 205.00 410.00
TOTAL 3 2860.00
4.- VEREDAS PERIMETRALES 0.60 ancho; e=0.15 m; L= 45 m

HORMIGON M3 7 70 490.00
ARENA GRUESA M3 4 70 280.00
CEMENTO BLS 38 27 1026.00
MANO OBRA ML 45 25 1125.00
TOTAL 4 2921.00

5.- POZO SEPTICO: 2 m x 2 m x 2m

LADRILLO 18 HUECOS MILLAR 0.5 1500 750.00


CEMENTO BLS 40 27 1080.00
PIEDRA CHANCADA M3 2 100 200.00
HORMIGON 38 1.5 70 105.00
ARENA GRUESA M3 1 70 70.00
TABLAS 1" x 10" x 3m UND 8 25 200.00
LISTONES 4" x 2" x 3m UND 4 20 80.00
FIERRO 1/2" VARILLAS 14 40 560.00
ALAMBRE # 16 KG 2 9 18.00
CAJA REGISTRO UND 2 150 300.00
TUBO 4" UND 8 25 200.00
TUBO 2" UND 8 18 144.00
TEE 4x4 UND 4 7 28.00
CODO 4" x 90° UND 4 7 28.00
LLAVE 2" COMPLETO UND 1 70 70.00
MANO OBRA UND 1 1500 1500.00
TOTAL 5 5333.00

Nota: se gasto por instalacion de luz electrica, desde el vecino. 700.00


Compra compartida de cable 450.00
compra individual de medidor digital+15 m de cable # 10 y 2 ll 250.00

TOTAL GENERAL 21173.00