Está en la página 1de 3

CALENDARIO DE AVANCE DE OBRA VALORIZADO

OBRA “REHABILITACION DEL CANAL HUARCOS, EN EL SECTOR HUARCOS (PROGRESIVA TRAMO 1), DISTRITO DE MORO, PROVINCIA SANTA, DEPARTAMENTO DE ANCASH”

Dec-20 Jan-21 Feb-21 Mar-21


Item Descripción Und. Metrado Precio S/. Parcial S/.
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9

01 CONSTRUCCION DE CANAL HUARCOS

01.01 OBRAS PROVISIONALES

100.00%
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 4.80 M (GIGANTOGRAFIA) und 1.00 1,045.00 1,045.00
S/1,045.00

100.00%
01.01.02 CAMPAMEMNTO PROSIONAL DE LA OBRA und 1.00 4,500.00 4,500.00
S/4,500.00

30.00% 30.00% 25.00% 15.00%


01.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIA GLB 2.00 12,000.00 24,000.00
S/7,200.00 S/7,200.00 S/6,000.00 S/3,600.00

100.00%
01.01.04 CAMINO DE ACCESO Y HABILITACION m2 1,119.26 8.83 9,883.07
S/9,883.07

01.02 MOVIMIENTO DE TIERRAS

100.00%
01.02.01 NIVELACION DE TERRENO m2 11.40 12.87 146.72
S/146.72

50.00% 50.00%
01.02.02 PROTECCION - DEFENSA m3 3,200.00 8.86 28,352.00
S/14,176.00 S/14,176.00

01.03 CAPTACION

01.03.01 TRABAJOS PRELIMINARES

100.00%
01.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 11.40 3.78 43.09
S/43.09

100.00%
01.03.01.02 TRAZO Y REPLANTEO m2 11.40 8.23 93.82
S/93.82

100.00%
01.03.01.03 DESVIO DE CAUCE TEMPORAL m 40.00 14.94 597.60
S/597.60

01.03.02 MOVIMIENTO DE TIERRAS

100.00%
01.03.02.01 EXCAVACION MANUAL DE TERRENO NORMAL m3 4.95 68.87 340.91
S/340.91

100.00%
01.03.02.02 NIVELACION DE TERRENO m2 11.40 12.87 146.72
S/146.72

100.00%
01.03.02.03 COLOCACION Y COMPACTACION DE MATERIAL GRANULAR m3 2.38 105.03 249.97
S/249.97

100.00%
01.03.02.04 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M ) m3 6.44 32.55 209.62
S/209.62

01.03.03 OBRAS DE CONCRETO

100.00%
01.03.03.01 SOLADO E=10CM CEMENTO. HORMIGON 1:10 m2 11.40 126.51 1,442.21
S/1,442.21

100.00%
01.03.03.02 CONCRETO F´C=175 KG/CM2 m3 4.87 449.43 2,188.72
S/2,188.72

100.00%
01.03.03.03 ENCOFRADO Y DESENCOFRADO m2 23.44 48.40 1,134.50
S/1,134.50

100.00%
01.03.03.04 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 494.60 6.09 3,012.11
S/3,012.11

01.04 DESARENADOR

01.04.01 TRABAJOS PRELIMINARES

100.00%
01.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 15.08 3.78 57.00
S/57.00

100.00%
01.04.01.02 TRAZO Y REPLANTEO m2 15.08 8.23 124.11
S/124.11

01.04.02 MOVIMIENTO DE TIERRAS

100.00%
01.04.02.01 EXCAVACION MANUAL DE TERRENO NORMAL m3 12.87 68.87 886.36
S/886.36

100.00%
01.04.02.02 NIVELACION DE TERRENO m2 14.30 12.87 184.04
S/184.04

100.00%
01.04.02.03 COLOCACION Y COMPACTACION DE MATERIAL GRANULAR m3 3.43 105.03 360.25
S/360.25

100.00%
01.04.02.04 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M ) m3 16.73 32.55 544.56
S/544.56
01.04.03 OBRAS DE CONCRETO

100.00%
01.04.03.01 SOLADO E=10CM CEMENTO. HORMIGON 1:10 m2 14.30 126.51 1,809.09
S/1,809.09

100.00%
01.04.03.02 CONCRETO F´C=175 KG/CM2 m3 6.87 449.43 3,087.58
S/3,087.58

100.00%
01.04.03.03 ENCOFRADO Y DESENCOFRADO m2 44.60 48.40 2,158.64
S/2,158.64

100.00%
01.04.03.04 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 274.48 6.09 1,671.58
S/1,671.58

01.04.04 VARIOS

100.00%
01.04.04.01 COMPUERTA METALICA TIPO I und 2.00 825.39 1,650.78
S/1,650.78

01.05 CANAL RECTANGULAR DE CONCRETO

01.05.01 TRABAJOS PRELIMINARES

100.00%
01.05.01.01 TRAZO Y REPLANTEO m2 0.56 8.23 4.61
S/4.61

100.00%
01.05.01.02 DESBROCE Y LIMPIEZA PARA CANAL m2 3,355.80 5.06 16,980.35
S/16,980.35

100.00%
01.05.01.03 DESVIO DE CAUCE TEMPORAL m 559.30 14.94 8,355.94
S/8,355.94

01.05.02 MOVIMIENTO DE TIERRAS

10.00% 55.00% 35.00%


01.05.02.01 EXCAVACION MANUAL DE TERRENO NORMAL m3 1,072.10 68.87 73,835.53
S/7,383.55 S/40,609.54 S/25,842.43

100.00%
01.05.02.02 EXCAVACION MANUAL EN TERRENO SEMIROCOSO m3 20.15 130.19 2,623.33
S/2,623.33

10.00% 40.00% 50.00%


01.05.02.03 RELLENO CON MATERIAL PROPIO EN CAJA HIDRAULICA DE CANAL m3 658.36 38.61 25,419.28
S/2,541.93 S/10,167.71 S/12,709.64

20.00% 40.00% 40.00%


01.05.02.04 PERFILADO DE CANAL EN TERRENO NORMAL m2 1,230.40 10.95 13,472.88
S/2,694.58 S/5,389.15 S/5,389.15

25.00% 75.00%
01.05.02.05 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 98.12 274.48 26,931.98
S/6,732.99 S/20,198.98

10.00% 40.00% 50.00%


01.05.02.06 ACARREO MANUAL EXDENTE D. PROM. 100M m3 910.29 52.08 47,407.90
S/4,740.79 S/18,963.16 S/23,703.95

10.00% 50.00% 40.00%


01.05.02.07 ELIMINACION DE MATERIAL EXCEDENTE m3 910.29 24.47 22,274.80
S/2,227.48 S/11,137.40 S/8,909.92

01.05.03 MEJORAMIENTO DE SUELO

50.00% 40.00% 10.00%


01.05.03.01 COLOCACION Y COMPACTACION DE MATERIAL GRANULAR m3 44.80 105.03 4,705.34
S/2,352.67 S/1,882.14 S/470.53

01.05.04 OBRAS DE CONCRETO

60.00% 30.00% 10.00%


01.05.04.01 CONCRETO F´C=175 KG/CM2 m3 128.71 449.43 57,846.14
S/34,707.68 S/17,353.84 S/5,784.61

60.00% 25.00% 15.00%


01.05.04.02 ENCOFRADO Y DESENCOFRADO m2 671.55 48.40 32,503.02
S/19,501.81 S/8,125.76 S/4,875.45

20.00% 80.00%
01.05.04.03 SOLAQUEADO m2 1,231.18 13.39 16,485.50
S/3,297.10 S/13,188.40

01.05.05 JUNTAS

10.00% 90.00%
01.05.05.01 JUNTAS DE DILATACION m 373.09 34.73 12,957.42
S/1,295.74 S/11,661.67

01.05.06 TOMA LATERAL (Toma Predial) 4.00 UND.

01.05.06.01 PLACAS DE C° A° PARA COMPUERTA

100.00%
01.05.06.01.01 CONCRETO F´C=175 KG/CM2 m3 1.96 449.43 880.88
S/880.88
50.00% 50.00%
01.05.06.01.02 ENCOFRADO Y DESENCOFRADO m2 15.09 48.40 730.36
S/365.18 S/365.18

100.00%
01.05.06.01.03 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 118.28 6.09 720.33
S/720.33

100.00%
01.05.06.01.04 SOLAQUEADO m2 16.28 13.39 217.99
S/217.99

01.05.06.02 VARIOS

100.00%
01.05.06.02.01 COMPUERTA METALICA TIPO I und 8.00 825.39 6,603.12
S/6,603.12

01.06 REPARTIDOR (Empalma a otro canal) 1.00 UND.

01.06.01 PLACAS DE C° A° PARA COMPUERTA

100.00%
01.06.01.01 CONCRETO F´C=175 KG/CM2 m3 0.49 449.43 220.22
S/220.22

100.00%
01.06.01.02 ENCOFRADO Y DESENCOFRADO m2 1.89 48.40 91.48
S/91.48

100.00%
01.06.01.03 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 29.57 6.09 180.08
S/180.08

100.00%
01.06.01.04 SOLAQUEADO m2 4.07 13.39 54.50
S/54.50

01.06.02 VARIOS

100.00%
01.06.02.01 COMPUERTA METALICA TIPO I und 2.00 825.39 1,650.78
S/1,650.78

1.07 FLETE

20.00% 40.00% 30.00% 10.00%


FLETE TERRESTRE
01.07.01 GLB 1.00 11,511.81 11,511.81
S/2,302.36 S/4,604.72 S/3,453.54 S/1,151.18

20.00% 40.00% 30.00% 10.00%


01.07.02 FLETE RURAL ACARREO DE MATERIALES GLB 1.00 64,871.83 64,871.83
S/12,974.37 S/25,948.73 S/19,461.55 S/6,487.18

Costo Directo 539,457.45 106,513.06 225,683.46 160,041.88 47,219.04

Gastos Generales (10%) 53,945.75 10,651.31 22,568.35 16,004.19 4,721.90

Utilidades (10%) 53,945.75 10,651.31 22,568.35 16,004.19 4,721.90

Sub Total 647,348.95 127,815.67 270,820.15 192,050.26 56,662.85

Impuesto (18%) 116,522.81 23,006.82 48,747.63 34,569.05 10,199.31

Total Presupusto 763,871.76 150,822.49 319,567.78 226,619.30 66,862.16

PORCENTAJE DE AVANCE PARCIAL 100.00% 19.74% 41.84% 29.67% 8.75%

PORCENTAJE DE AVANCE ACUMULADO 100.00% 19.74% 61.58% 91.25% 100.00%