Está en la página 1de 6

CRONOGRAMA VALORIZADO POR PARTIDAS DE EJECUCIÓN DE OBRA

ACTUALIZACION DEL EXPEDIENTE TECNICO: “MEJORAMIENTO DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN LAS AVENIDAS VICTORIA, PROGRESO, CALLE NUEVA Y UNION, PROLONGACIONES ANDRES
MUNICIPALIDAD RAZURI, ERNESTO VELIT Y MARISCAL SUCRE, CALLES Y PASAJES DEL CC.PP. BALCONCITO SECTOR 1, PASAJES. CON SALIDAS A CALLE ROSARIO, AV. PROGRESO, PROLONG. ANDRES RAZURI Y A LA AVENIDA VICTORIA
PROVINCIAL DE EN EL SECTOR 02 DEL DISTRITO DE CHINCHA ALTA, PROVINCIA DE CHINCHA – ICA”
DIST. : CHINCHA ALTA CHINCHA.
PROV. : CHINCHA JUNIO - 2020
DPTO. : ICA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

ITEM PARTIDA UND CANT. PRECIO TOTAL


CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/.

01 RED DE DISTRIBUCION DE AGUA POTABLE 1,310,247.82 0.00 0.00 104,068.10 429,542.82 507,590.54 269,046.36
01.01 TRABAJOS PROVISIONALES 80,956.44 0.00 0.00 18,229.19 24,082.77 23,186.69 15,457.79
01.01.01 CINTA Y MALLA PLASTICA SEÑALIZADORA DE PELIGRO (INC. POSTES) m 14,528.00 5.32 77,288.96 0% 0.00 0% 0.00 20% 15,457.79 30% 23,186.69 30% 23,186.69 20% 15,457.79
01.01.02 PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA (PROV. DURANTE OBRA) und 4.00 468.83 1,875.32 0% 0.00 0% 0.00 100% 1,875.32 0% 0.00 0% 0.00 0% 0.00
01.01.03 PIQUES DE EXPLORACION EN REDES EXISTENTES und 23.00 77.92 1,792.16 0% 0.00 0% 0.00 50% 896.08 50% 896.08 0% 0.00 0% 0.00
01.02 TRABAJOS PRELIMINARES 59,731.93 0.00 0% 0.00 36,054.77 12,552.03 6,766.73 4,358.40
01.02.01 LIMPIEZA DE TERRENO MANUAL m 7,264.00 1.03 7,481.92 0% 0.00 0% 0.00 50% 3,740.96 50% 3,740.96 0% 0.00 0% 0.00
01.02.02 TRAZO, NIVELACION Y REPLANTEO DE OBRA INICIAL m 7,264.00 1.53 11,113.92 0% 0.00 0% 0.00 50% 5,556.96 50% 5,556.96 0% 0.00 0% 0.00
01.02.03 REPLANTEO FINAL DE OBRA m 7,264.00 0.60 4,358.40 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 4,358.40
01.02.04 CORTE Y ROTURA DE VEREDA DE CONCRETO m2 577.81 16.73 9,666.76 0% 0.00 0% 0.00 0% 0.00 30% 2,900.03 70% 6,766.73 0% 0.00
01.02.05 CORTE Y ROTURA PAVIMENTO FLEXIBLE C/MAQ. m2 2,288.36 10.30 23,570.11 0% 0.00 0% 0.00 100% 23,570.11 0% 0.00 0% 0.00 0% 0.00
01.02.06 CORTE Y ROTURA PAVIMENTO RIGIDO C/MAQ. m2 256.21 13.82 3,540.82 0% 0.00 0% 0.00 90% 3,186.74 10% 354.08 0% 0.00 0% 0.00
01.03 MOVIMIENTO DE TIERRAS 264,938.87 0.00 0.00 32,319.61 109,308.84 88,606.53 34,703.89
01.03.01 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=1.20m m 7,264.00 7.31 53,099.84 0% 0.00 0% 0.00 30% 15,929.95 70% 37,169.89 0% 0.00 0% 0.00
01.03.02 REFINE Y CONFORMACION DE FONDO DE ZANJA m 7,264.00 2.42 17,578.88 0% 0.00 0% 0.00 20% 3,515.78 60% 10,547.33 20% 3,515.78 0% 0.00
01.03.03 COLOCACION DE CAMA DE ARENA (h=0.10m) Y RECUB (h=0.20m) C/MAT. PROPIO ZARANDEADO m3 2,430.74 9.88 24,015.71 0% 0.00 0% 0.00 20% 4,803.14 60% 14,409.43 20% 4,803.14 0% 0.00
01.03.04 RELLENO Y COMPACTADO DE ZANJA C/MAT. PROPIO ZARAND. Hprom=1.00MT DE PROF. m3 5,677.43 22.87 129,842.82 0% 0.00 0% 0.00 0% 0.00 20% 25,968.56 60% 77,905.69 20% 25,968.56
01.03.05 DESMONTAJE DE TUBERIA Y MANTENIMIENTO DE SERVICIO AGUA POTABLE m 5,136.57 4.31 22,138.62 0% 0.00 0% 0.00 30% 6,641.59 70% 15,497.03 0% 0.00 0% 0.00
01.03.06 ACARREO DE MATERIAL EXCEDENTE m3 489.10 19.48 9,527.67 0% 0.00 0% 0.00 15% 1,429.15 60% 5,716.60 25% 2,381.92 0% 0.00
01.03.07 ELIMINACION DE MATERIAL EXCEDENTE m3 489.10 17.86 8,735.33 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 8,735.33
01.04 SUMINISTRO E INSTALACION DE TUBERIAS UF 147,574.35 0.00 0.00 17,464.53 130,109.82 0.00 0.00
01.04.01 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø63mm AGUA POTABLE NTP ISO 1452 m 2,110.25 7.43 15,679.16 0% 0.00 0% 0.00 100% 15,679.16 0% 0.00 0% 0.00 0% 0.00
01.04.02 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø75mm AGUA POTABLE NTP ISO 1452 m 189.03 7.45 1,408.27 0% 0.00 0% 0.00 100% 1,408.27 0% 0.00 0% 0.00 0% 0.00
01.04.03 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø90mm AGUA POTABLE NTP ISO 1452 m 30.00 12.57 377.10 0% 0.00 0% 0.00 100% 377.10 0% 0.00 0% 0.00 0% 0.00
01.04.04 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø110mm AGUA POTABLE NTP ISO 1452 m 2,894.84 14.90 43,133.12 0% 0.00 0% 0.00 0% 0.00 100% 43,133.12 0% 0.00 0% 0.00
01.04.05 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø160mm AGUA POTABLE NTP ISO 1452 m 495.97 29.77 14,765.03 0% 0.00 0% 0.00 0% 0.00 100% 14,765.03 0% 0.00 0% 0.00
01.04.06 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø200mm AGUA POTABLE NTP ISO 1452 m 1,487.22 45.80 68,114.68 0% 0.00 0% 0.00 0% 0.00 100% 68,114.68 0% 0.00 0% 0.00
01.04.07 SUMINITRO E INSTALACION DE TUBERIA PVC UF C-7.5 Ø250mm AGUA POTABLE NTP ISO 1452 m 56.69 72.27 4,096.99 0% 0.00 0% 0.00 0% 0.00 100% 4,096.99 0% 0.00 0% 0.00
01.05 PRUEBA HIDRAULICA Y DESINFECCION DE REDES 16,822.42 0.00 0.00 0.00 16,822.42 0.00 0.00
01.05.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 63mm m 2,110.25 1.78 3,756.25 0% 0.00 0% 0.00 0% 0.00 100% 3,756.25 0% 0.00 0% 0.00
01.05.02 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 75mm m 189.03 1.93 364.83 0% 0.00 0% 0.00 0% 0.00 100% 364.83 0% 0.00 0% 0.00
01.05.03 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 90mm m 30.00 2.16 64.80 0% 0.00 0% 0.00 0% 0.00 100% 64.80 0% 0.00 0% 0.00
01.05.04 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 110mm m 2,894.84 2.45 7,092.36 0% 0.00 0% 0.00 0% 0.00 100% 7,092.36 0% 0.00 0% 0.00
01.05.05 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 160mm m 495.97 2.37 1,175.45 0% 0.00 0% 0.00 0% 0.00 100% 1,175.45 0% 0.00 0% 0.00
01.05.06 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 200mm m 1,487.22 2.79 4,149.34 0% 0.00 0% 0.00 0% 0.00 100% 4,149.34 0% 0.00 0% 0.00
01.05.07 DOBLE PRUEBA HIDRAULICA Y DESINFECCION TUBERIA PVC UF, 250mm m 56.69 3.87 219.39 0% 0.00 0% 0.00 0% 0.00 100% 219.39 0% 0.00 0% 0.00
01.06 SUMINISTRO E INSTALACION DE ACCESORIOS 29,997.79 0.00 0.00 0.00 29,997.79 0.00 0.00
01.06.01 TAPON PVC, UF, Ø63mm und 5.00 33.01 165.05 0% 0.00 0% 0.00 0% 0.00 100% 165.05 0% 0.00 0% 0.00
01.06.02 TAPON PVC, UF, Ø75mm und 1.00 47.29 47.29 0% 0.00 0% 0.00 0% 0.00 100% 47.29 0% 0.00 0% 0.00
01.06.03 TAPON PVC, UF, Ø110mm und 1.00 82.95 82.95 0% 0.00 0% 0.00 0% 0.00 100% 82.95 0% 0.00 0% 0.00
01.06.04 TAPON PVC, UF, Ø160mm und 1.00 125.87 125.87 0% 0.00 0% 0.00 0% 0.00 100% 125.87 0% 0.00 0% 0.00
01.06.05 TAPON PVC, UF, Ø200mm und 2.00 192.04 384.08 0% 0.00 0% 0.00 0% 0.00 100% 384.08 0% 0.00 0% 0.00
01.06.06 TAPON PVC, UF, Ø250mm und 1.00 249.17 249.17 0% 0.00 0% 0.00 0% 0.00 100% 249.17 0% 0.00 0% 0.00
01.06.07 TEE PVC, UF, 63x63mm und 6.00 58.64 351.84 0% 0.00 0% 0.00 0% 0.00 100% 351.84 0% 0.00 0% 0.00
01.06.08 TEE PVC, UF, 110x110mm und 35.00 58.81 2,058.35 0% 0.00 0% 0.00 0% 0.00 100% 2,058.35 0% 0.00 0% 0.00
01.06.09 TEE PVC, UF, 160x160mm und 5.00 308.84 1,544.20 0% 0.00 0% 0.00 0% 0.00 100% 1,544.20 0% 0.00 0% 0.00
01.06.10 TEE PVC, UF, 200x200mm und 19.00 517.19 9,826.61 0% 0.00 0% 0.00 0% 0.00 100% 9,826.61 0% 0.00 0% 0.00
01.06.11 TEE PVC, UF, 250x250mm und 4.00 1,066.15 4,264.60 0% 0.00 0% 0.00 0% 0.00 100% 4,264.60 0% 0.00 0% 0.00
01.06.12 CURVA PVC, UF, 63mm.x11°30' und 1.00 43.65 43.65 0% 0.00 0% 0.00 0% 0.00 100% 43.65 0% 0.00 0% 0.00
01.06.13 CURVA PVC, UF, 63mm.x22°30' und 5.00 47.25 236.25 0% 0.00 0% 0.00 0% 0.00 100% 236.25 0% 0.00 0% 0.00
01.06.14 CURVA PVC, UF, 63mm.x45° und 1.00 51.65 51.65 0% 0.00 0% 0.00 0% 0.00 100% 51.65 0% 0.00 0% 0.00
01.06.15 CURVA PVC, UF, 63mm.x90° und 6.00 58.25 349.50 0% 0.00 0% 0.00 0% 0.00 100% 349.50 0% 0.00 0% 0.00
01.06.16 CURVA PVC, UF, 75mm.x90° und 2.00 98.06 196.12 0% 0.00 0% 0.00 0% 0.00 100% 196.12 0% 0.00 0% 0.00
CRONOGRAMA VALORIZADO POR PARTIDAS DE EJECUCIÓN DE OBRA

ACTUALIZACION DEL EXPEDIENTE TECNICO: “MEJORAMIENTO DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN LAS AVENIDAS VICTORIA, PROGRESO, CALLE NUEVA Y UNION, PROLONGACIONES ANDRES
MUNICIPALIDAD RAZURI, ERNESTO VELIT Y MARISCAL SUCRE, CALLES Y PASAJES DEL CC.PP. BALCONCITO SECTOR 1, PASAJES. CON SALIDAS A CALLE ROSARIO, AV. PROGRESO, PROLONG. ANDRES RAZURI Y A LA AVENIDA VICTORIA
PROVINCIAL DE EN EL SECTOR 02 DEL DISTRITO DE CHINCHA ALTA, PROVINCIA DE CHINCHA – ICA”
DIST. : CHINCHA ALTA CHINCHA.
PROV. : CHINCHA JUNIO - 2020
DPTO. : ICA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

ITEM PARTIDA UND CANT. PRECIO TOTAL


CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/.

01.06.17 CURVA PVC, UF, 110mm.x11.30° und 4.00 62.72 250.88 0% 0.00 0% 0.00 0% 0.00 100% 250.88 0% 0.00 0% 0.00
01.06.18 CURVA PVC, UF, 110mm.x22.30° und 11.00 64.01 704.11 0% 0.00 0% 0.00 0% 0.00 100% 704.11 0% 0.00 0% 0.00
01.06.19 CURVA PVC, UF, 110mm.x45° und 8.00 75.37 602.96 0% 0.00 0% 0.00 0% 0.00 100% 602.96 0% 0.00 0% 0.00
01.06.20 CURVA PVC, UF, 110mm.x90° und 7.00 82.11 574.77 0% 0.00 0% 0.00 0% 0.00 100% 574.77 0% 0.00 0% 0.00
01.06.21 CURVA PVC, UF, 160mm.x11°30' und 1.00 133.82 133.82 0% 0.00 0% 0.00 0% 0.00 100% 133.82 0% 0.00 0% 0.00
01.06.22 CURVA PVC, UF, 160mm.x22,30° und 3.00 145.77 437.31 0% 0.00 0% 0.00 0% 0.00 100% 437.31 0% 0.00 0% 0.00
01.06.23 CURVA PVC, UF, 160mm.x90° und 1.00 181.75 181.75 0% 0.00 0% 0.00 0% 0.00 100% 181.75 0% 0.00 0% 0.00
01.06.24 CURVA PVC, UF, 200mm.x22°30' und 2.00 303.87 607.74 0% 0.00 0% 0.00 0% 0.00 100% 607.74 0% 0.00 0% 0.00
01.06.25 CURVA PVC, UF, 250mm.x90° und 1.00 530.39 530.39 0% 0.00 0% 0.00 0% 0.00 100% 530.39 0% 0.00 0% 0.00
01.06.26 REDUCCION PVC-UF, Ø110X63mm und 10.00 50.00 500.00 0% 0.00 0% 0.00 0% 0.00 100% 500.00 0% 0.00 0% 0.00
01.06.27 REDUCCION PVC-UF, Ø110X75mm und 3.00 51.42 154.26 0% 0.00 0% 0.00 0% 0.00 100% 154.26 0% 0.00 0% 0.00
01.06.28 REDUCCION PVC-UF, Ø110X90mm und 4.00 68.68 274.72 0% 0.00 0% 0.00 0% 0.00 100% 274.72 0% 0.00 0% 0.00
01.06.29 REDUCCION PVC-UF, Ø160X110mm und 3.00 77.72 233.16 0% 0.00 0% 0.00 0% 0.00 100% 233.16 0% 0.00 0% 0.00
01.06.30 REDUCCION PVC-UF, Ø200X63mm und 4.00 121.14 484.56 0% 0.00 0% 0.00 0% 0.00 100% 484.56 0% 0.00 0% 0.00
01.06.31 REDUCCION PVC-UF, Ø200X110mm und 4.00 150.26 601.04 0% 0.00 0% 0.00 0% 0.00 100% 601.04 0% 0.00 0% 0.00
01.06.32 REDUCCION PVC-UF, Ø200X160mm und 2.00 139.75 279.50 0% 0.00 0% 0.00 0% 0.00 100% 279.50 0% 0.00 0% 0.00
01.06.33 REDUCCION PVC-UF, Ø250X200mm und 2.00 228.85 457.70 0% 0.00 0% 0.00 0% 0.00 100% 457.70 0% 0.00 0% 0.00
01.06.34 EMPALME EN TUBERIA Ø110mm CON ACOPLE METALICO DE AMPLIO RANGO und 1.00 150.91 150.91 0% 0.00 0% 0.00 0% 0.00 100% 150.91 0% 0.00 0% 0.00
01.06.35 EMPALME EN TUBERIA Ø200mm CON ACOPLE METALICO DE AMPLIO RANGO und 2.00 349.20 698.40 0% 0.00 0% 0.00 0% 0.00 100% 698.40 0% 0.00 0% 0.00
01.06.36 EMPALME EN TUBERIA Ø63mm CON UNION DE REPARACION DE PVC-UF und 23.00 32.47 746.81 0% 0.00 0% 0.00 0% 0.00 100% 746.81 0% 0.00 0% 0.00
01.06.37 EMPALME EN TUBERIA Ø90mm CON UNION DE REPARACION DE PVC-UF und 4.00 38.26 153.04 0% 0.00 0% 0.00 0% 0.00 100% 153.04 0% 0.00 0% 0.00
01.06.38 EMPALME EN TUBERIA Ø110mm CON UNION DE REPARACION DE PVC-UF und 6.00 46.36 278.16 0% 0.00 0% 0.00 0% 0.00 100% 278.16 0% 0.00 0% 0.00
01.06.39 EMPALME EN TUBERIA Ø160mm CON UNION DE REPARACION DE PVC-UF und 3.00 104.46 313.38 0% 0.00 0% 0.00 0% 0.00 100% 313.38 0% 0.00 0% 0.00
01.06.40 EMPALME EN TUBERIA Ø200mm CON UNION DE REPARACION DE PVC-UF und 2.00 140.69 281.38 0% 0.00 0% 0.00 0% 0.00 100% 281.38 0% 0.00 0% 0.00
01.06.41 EMPALME EN TUBERIA Ø250mm CON UNION DE REPARACION DE PVC-UF und 2.00 194.93 389.86 0% 0.00 0% 0.00 0% 0.00 100% 389.86 0% 0.00 0% 0.00
01.07 VALVULAS 51,045.80 0.00 0.00 0.00 0.00 46,866.09 4,179.71
01.07.01 VALVULA COMPUERTA H.D. Ø63mm ENTRADA TIPO LUFLEX ISO 7259 und 18.00 321.18 5,781.24 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 5,781.24 0% 0.00
01.07.02 VALVULA COMPUERTA H.D. Ø90mm ENTRADA TIPO LUFLEX ISO 7259 und 3.00 395.97 1,187.91 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 1,187.91 0% 0.00
01.07.03 VALVULA COMPUERTA H.D. Ø110mm ENTRADA TIPO LUFLEX ISO 7259 und 22.00 429.13 9,440.86 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 9,440.86 0% 0.00
01.07.04 VALVULA COMPUERTA H.D. Ø160mm ENTRADA TIPO LUFLEX ISO 7259 und 1.00 634.72 634.72 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 634.72 0% 0.00
01.07.05 VALVULA COMPUERTA H.D. Ø200mm ENTRADA TIPO LUFLEX ISO 7259 und 5.00 976.79 4,883.95 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 4,883.95 0% 0.00
01.07.06 SUMINISTRO E INSTALACION DE VALVULA DE PURGA DN 50mm und 2.00 2,168.02 4,336.04 0% 0.00 0% 0.00 0% 0.00 0% 0.00 80% 3,468.83 20% 867.21
01.07.07 SUMINISTRO E INSTALACION DE VALVULA DE AIRE DN 50mm EN TUBERIA DE 160mm und 1.00 3,312.50 3,312.50 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 3,312.50
01.07.08 SUMINISTRO E INSTALACION DE VALVULA DE AIRE DN 50mm EN TUBERIA DE 200mm und 1.00 4,165.50 4,165.50 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 4,165.50 0% 0.00
01.07.09 CAMARA TIPO CIRCULAR Di=1.50m P/VALVULA PURGA INC. EXCAV. und 2.00 4,588.64 9,177.28 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 9,177.28 0% 0.00
01.07.10 CAMARA TIPO CIRCULAR Di=1.50m P/VALVULA AIRE INC. EXCAV. und 2.00 4,062.90 8,125.80 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 8,125.80 0% 0.00
01.08 CONEXION DOMICILIARIA DE AGUA Ø 1/2" 428,431.94 0.00 0.00 0.00 85,538.75 326,296.15 16,597.04
01.08.01 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=1.50M, INC. EXCAVAC. Y RELLENO und 156.00 290.97 45,391.32 0% 0.00 0% 0.00 0% 0.00 20% 9,078.26 60% 27,234.79 20% 9,078.26
01.08.02 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=2.50M, INC. EXCAVAC. Y RELLENO und 469.00 321.13 150,609.97 0% 0.00 0% 0.00 0% 0.00 20% 30,121.99 80% 120,487.98 0% 0.00
01.08.03 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=4.00M, INC. EXCAVAC. Y RELLENO und 296.00 366.36 108,442.56 0% 0.00 0% 0.00 0% 0.00 20% 21,688.51 80% 86,754.05 0% 0.00
01.08.04 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=5.50M, INC. EXCAVAC. Y RELLENO und 81.00 411.61 33,340.41 0% 0.00 0% 0.00 0% 0.00 20% 6,668.08 60% 20,004.25 20% 6,668.08
01.08.05 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=7.00M, INC. EXCAVAC. Y RELLENO und 64.00 456.84 29,237.76 0% 0.00 0% 0.00 0% 0.00 20% 5,847.55 80% 23,390.21 0% 0.00
01.08.06 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=8.50M, INC. EXCAVAC. Y RELLENO und 28.00 502.09 14,058.52 0% 0.00 0% 0.00 0% 0.00 20% 2,811.70 80% 11,246.82 0% 0.00
01.08.07 CONEXION DOMICILIARIA AGUA Ø1/2", DN.15, Lprom=10.00M, INC. EXCAVAC. Y RELLENO und 54.00 547.32 29,555.28 0% 0.00 0% 0.00 0% 0.00 20% 5,911.06 80% 23,644.22 0% 0.00
01.08.08 CONEXION DOMICILIARIA AGUA Ø3/4", DN.20, Lprom=2.50M, INC. EXCAVAC. Y RELLENO und 7.00 358.29 2,508.03 0% 0.00 0% 0.00 0% 0.00 20% 501.61 80% 2,006.42 0% 0.00
01.08.09 CONEXION DOMICILIARIA AGUA Ø3/4", DN.20, Lprom=4.00M, INC. EXCAVAC. Y RELLENO und 4.00 404.13 1,616.52 0% 0.00 0% 0.00 0% 0.00 20% 323.30 80% 1,293.22 0% 0.00
01.08.10 CONEXION DOMICILIARIA AGUA Ø3/4", DN.20, Lprom=5.50M, INC. EXCAVAC. Y RELLENO und 3.00 450.00 1,350.00 0% 0.00 0% 0.00 0% 0.00 20% 270.00 80% 1,080.00 0% 0.00
01.08.11 CONEXION DOMICILIARIA AGUA Ø3/4", DN.20, Lprom=7.00M, INC. EXCAVAC. Y RELLENO und 1.00 495.84 495.84 0% 0.00 0% 0.00 0% 0.00 20% 99.17 80% 396.67 0% 0.00
01.08.12 CONEXION DOMICILIARIA AGUA Ø3/4", DN.20, Lprom=8.50M, INC. EXCAVAC. Y RELLENO und 1.00 541.71 541.71 0% 0.00 0% 0.00 0% 0.00 20% 108.34 80% 433.37 0% 0.00
01.08.13 CONEXION DOMICILIARIA AGUA Ø1", DN.25, Lprom=2.50M, INC. EXCAVAC. Y RELLENO und 3.00 657.03 1,971.09 0% 0.00 0% 0.00 0% 0.00 0.00 80% 1,576.87 20% 394.22
01.08.14 CONEXION DOMICILIARIA AGUA Ø1", DN.25, Lprom=4.00M, INC. EXCAVAC. Y RELLENO und 1.00 708.90 708.90 0% 0.00 0% 0.00 0% 0.00 0.00 80% 567.12 20% 141.78
01.08.15 CONEXION DOMICILIARIA AGUA Ø1", DN.25, Lprom=5.50M, INC. EXCAVAC. Y RELLENO und 1.00 760.80 760.80 0% 0.00 0% 0.00 0% 0.00 0.00 80% 608.64 20% 152.16
01.08.16 CONEXION DOMICILIARIA AGUA Ø1", DN.25, Lprom=7.00M, INC. EXCAVAC. Y RELLENO und 1.00 812.67 812.67 0% 0.00 0% 0.00 0% 0.00 0.00 80% 650.14 20% 162.53
CRONOGRAMA VALORIZADO POR PARTIDAS DE EJECUCIÓN DE OBRA

ACTUALIZACION DEL EXPEDIENTE TECNICO: “MEJORAMIENTO DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN LAS AVENIDAS VICTORIA, PROGRESO, CALLE NUEVA Y UNION, PROLONGACIONES ANDRES
MUNICIPALIDAD RAZURI, ERNESTO VELIT Y MARISCAL SUCRE, CALLES Y PASAJES DEL CC.PP. BALCONCITO SECTOR 1, PASAJES. CON SALIDAS A CALLE ROSARIO, AV. PROGRESO, PROLONG. ANDRES RAZURI Y A LA AVENIDA VICTORIA
PROVINCIAL DE EN EL SECTOR 02 DEL DISTRITO DE CHINCHA ALTA, PROVINCIA DE CHINCHA – ICA”
DIST. : CHINCHA ALTA CHINCHA.
PROV. : CHINCHA JUNIO - 2020
DPTO. : ICA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

ITEM PARTIDA UND CANT. PRECIO TOTAL


CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/.

01.08.17 DESMONTAJE DE CONEXION DOMICILIARIA DE AGUA POTABLE (INC. ACOPIO) und 604.00 11.64 7,030.56 0% 0.00 0% 0.00 0% 0.00 30% 2,109.17 70% 4,921.39 0% 0.00
01.09 OTROS 34,172.48 0.00 0.00 0.00 21,130.40 13,042.08 0.00
01.09.01 BLOQUE DE CONCRETO PARA ANCLAJE DN 63-110mm und 191.00 76.40 14,592.40 0% 0.00 0% 0.00 0% 0.00 100% 14,592.40 0% 0.00 0% 0.00
01.09.02 BLOQUE DE CONCRETO PARA ANCLAJE DN 160-200mm und 52.00 102.05 5,306.60 0% 0.00 0% 0.00 0% 0.00 100% 5,306.60 0% 0.00 0% 0.00
01.09.03 BLOQUE DE CONCRETO PARA ANCLAJE DN 250-315mm und 10.00 123.14 1,231.40 0% 0.00 0% 0.00 0% 0.00 100% 1,231.40 0% 0.00 0% 0.00
01.09.04 SUMINISTRO E INSTALACION DE GRIFO C/INCENDIO Ho DUCTIL 2 BOCAS TIPO POSTE CUERPO SECO NTP.350.102:2001 und 9.00 1,449.12 13,042.08 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 13,042.08 0% 0.00
01.10 REPOSICION DE PAVIMENTO CON MATERIAL GRANULAR 28,262.70 0.00 0.00 0.00 0.00 2,826.27 25,436.43
01.10.01 PERFILADO Y COMPACTADO MANUAL DE SUELO m2 2,544.56 4.31 10,967.05 0% 0.00 0% 0.00 0% 0.00 0% 0.00 10% 1,096.71 90% 9,870.35
01.10.02 BASE GRANULAR e=0.10m m3 254.46 67.97 17,295.65 0% 0.00 0% 0.00 0% 0.00 0% 0.00 10% 1,729.57 90% 15,566.09
01.11 REPOSICION DE CARPETA ASFALTICA EN CALIENTE 111,146.39 0.00 0.00 0.00 0.00 0.00 111,146.39
01.11.01 IMPRIMACION ASFALTICA A PULSO m2 2,544.56 8.12 20,661.83 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 20,661.83
01.11.02 CARPETA ASFALTICA EN CALIENTE DE 2"(PARCHADO) m2 2,544.56 35.26 89,721.19 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 89,721.19
01.11.03 SELLO DE ARENA m2 2,544.56 0.30 763.37 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 763.37
01.12 REPOSICION DE CONCRETO 57,166.71 0.00 0.00 0.00 0.00 0.00 57,166.71
01.12.01 PERFILADO Y COMPACTADO MANUAL DE SUELO m2 1,016.96 4.31 4,383.10 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 4,383.10
01.12.02 BASE GRANULAR e=0.10m m3 101.70 67.97 6,912.55 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 6,912.55
01.12.03 CONCRETO F'C=140 KG/CM2 EN VEREDAS m3 101.70 334.49 34,017.63 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 34,017.63
01.12.04 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 268.42 44.16 11,853.43 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 11,853.43
01 CONSTRUCCION DE SISTEMA DE ALCANTARILLADO 1,694,266.21 240,091.88 520,565.81 477,994.06 266,662.93 70,116.00 118,835.53
01.01 OBRAS PROVISIONALES 56,707.06 36,939.21 3,488.45 3,488.45 3,488.45 4,651.26 4,651.26
01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 7,500.00 7,500.00 100% 7,500.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.01.02 SEÑALIZACION DE DESVIOS DE TRÁNSITO mes 6.00 3,876.05 23,256.30 15% 3,488.45 15% 3,488.45 15% 3,488.45 15% 3,488.45 20% 4,651.26 20% 4,651.26
01.01.03 CONSTRUCCION CAMPAMENTO, OFICINAS Y ALMACEN PARA OBRA und 1.00 16,696.20 16,696.20 100% 16,696.20 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.01.04 CARTEL DE IDENTIFICACION DE LA OBRA DE 8.50 x 3.60 M und 1.00 3,254.56 3,254.56 100% 3,254.56 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.01.05 FLETE TERRESTRE glb 1.00 6,000.00 6,000.00 100% 6,000.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.02 TRABAJOS PRELIMINARES 171,405.65 23,388.25 48,297.80 83,003.45 14,061.04 2,655.11 0.00
01.02.01 TRAZO, NIVELACION Y REPLANTEO DE OBRA INICIAL m 4,425.19 1.53 6,770.54 25% 1,692.64 25% 1,692.64 25% 1,692.64 25% 1,692.64 0% 0.00 0% 0.00
01.02.02 REPLANTEO FINAL DE OBRA m 4,425.19 0.60 2,655.11 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 2,655.11 0% 0.00
01.02.03 MALLA Y CINTA PLASTICA SEÑALIZADORA DE PELIGRO INC. POSTES m 8,850.38 5.59 49,473.62 25% 12,368.41 25% 12,368.41 25% 12,368.41 25% 12,368.41 0% 0.00 0% 0.00
01.02.04 PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA (PROV. DURANTE OBRA) und 5.00 468.83 2,344.15 100% 2,344.15 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.02.05 CORTE Y ROTURA PAVIMENTO FLEXIBLE C/MAQ. m2 879.70 11.34 9,975.80 70% 6,983.06 30% 2,992.74 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.02.06 CORTE Y ROTURA PAVIMENTO RIGIDO C/MAQ. m2 357.82 15.62 5,589.15 0% 0.00 100% 5,589.15 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.02.07 CORTE Y ROTURA DE VEREDA DE CONCRETO m2 542.80 16.73 9,081.04 0% 0.00 0% 0.00 100% 9,081.04 0% 0.00 0% 0.00 0% 0.00
01.02.08 DESVIO DE AGUAS SERVIDAS INCL. BOMBEO Y ALQUILER DE TUBO P/MANTENIMIENTO. SERVICIO DN 200-250mm mes 4.00 21,379.06 85,516.24 0% 0.00 30% 25,654.87 70% 59,861.37 0% 0.00 0% 0.00 0% 0.00
01.03 MOVIMIENTO DE TIERRAS 409,801.86 50,837.42 271,953.75 87,010.69 0.00 0.00 0.00
01.03.01 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=1.20m m 234.86 7.31 1,716.83 100% 1,716.83 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.02 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=1.50m m 993.24 11.75 11,670.57 100% 11,670.57 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.03 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=2.00m m 2,091.16 13.44 28,105.19 50% 14,052.60 50% 14,052.60 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.04 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=2.50m m 714.49 15.48 11,060.31 20% 2,212.06 80% 8,848.25 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.05 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=3.00m m 143.25 19.64 2,813.43 0% 0.00 100% 2,813.43 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.06 EXCAVACION DE ZANJA EN TERRENO ARENOSO-LIMOSO CON PROF. PROM H=3.50m m 248.19 22.47 5,576.83 0% 0.00 100% 5,576.83 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.07 REFINE Y CONFORMACION DE FONDO DE ZANJA PARA TODA PROFUNDIDAD m 4,112.55 1.94 7,978.35 40% 3,191.34 60% 4,787.01 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.08 COLOCACION DE CAMA DE ARENA (h=0.10) Y RECUB (h=0.20) C/MAT. PROPIO ZARANDEADO m3 2,365.82 9.88 23,374.30 40% 9,349.72 60% 14,024.58 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.09 ENTIBADO METALICO TIPO CAJON (BOX), ZANJAS DE 1.50 A 2.50m. DE PROF.(INCL. INSTALACION, MANTENIMIENTO RETIRO) m 2,668.04 16.69 44,529.59 0% 0.00 30% 13,358.88 70% 31,170.71 0% 0.00 0% 0.00 0% 0.00
01.03.10 ENTIBADO METALICO TIPO CAJON (BOX), ZANJAS DE 2.51 A 3.50m. DE PROF.(INCL. INSTALACION, MANTENIMIENTO RETIRO) m 388.24 25.36 9,845.77 0% 0.00 30% 2,953.73 70% 6,892.04 0% 0.00 0% 0.00 0% 0.00
01.03.11 RELLENO Y COMPACTADO DE ZANJAS C/MAT. PROPIO ZARAND. Hprom=1.00 MT DE PROF. m3 1,562.26 23.19 36,228.81 0% 0.00 70% 25,360.17 30% 10,868.64 0% 0.00 0% 0.00 0% 0.00
01.03.12 RELLENO Y COMPACTADO DE ZANJAS C/MAT. PROPIO ZARAND. Hprom=1.50 MT DE PROF. m3 4,309.97 24.24 104,473.67 0% 0.00 100% 104,473.67 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.13 RELLENO Y COMPACTADO DE ZANJAS C/MAT. PROPIO ZARAND. Hprom=2.00 MT DE PROF. m3 2,143.47 25.37 54,379.83 0% 0.00 100% 54,379.83 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.14 RELLENO Y COMPACTADO DE ZANJAS C/MAT. PROPIO ZARAND. Hprom=2.50 MT DE PROF. m3 525.49 26.62 13,988.54 0% 0.00 30% 4,196.56 70% 9,791.98 0% 0.00 0% 0.00 0% 0.00
01.03.15 RELLENO Y COMPACTADO DE ZANJAS C/MAT. PROPIO ZARAND. Hprom=3.00 MT DE PROF. m3 1,075.90 28.02 30,146.72 0% 0.00 30% 9,044.02 70% 21,102.70 0% 0.00 0% 0.00 0% 0.00
01.03.16 DESMONTAJE Y RETIRO DE TUBERIA m 3,342.73 4.31 14,407.17 60% 8,644.30 40% 5,762.87 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.03.17 ACARREO DE MATERIAL EXCEDENTE m3 238.33 19.48 4,642.67 0% 0.00 50% 2,321.34 50% 2,321.34 0% 0.00 0% 0.00 0% 0.00
01.03.18 ELIMINACION DE MATERIAL EXCEDENTE m3 272.30 17.86 4,863.28 0% 0.00 0% 0.00 100% 4,863.28 0% 0.00 0% 0.00 0% 0.00
CRONOGRAMA VALORIZADO POR PARTIDAS DE EJECUCIÓN DE OBRA

ACTUALIZACION DEL EXPEDIENTE TECNICO: “MEJORAMIENTO DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN LAS AVENIDAS VICTORIA, PROGRESO, CALLE NUEVA Y UNION, PROLONGACIONES ANDRES
MUNICIPALIDAD RAZURI, ERNESTO VELIT Y MARISCAL SUCRE, CALLES Y PASAJES DEL CC.PP. BALCONCITO SECTOR 1, PASAJES. CON SALIDAS A CALLE ROSARIO, AV. PROGRESO, PROLONG. ANDRES RAZURI Y A LA AVENIDA VICTORIA
PROVINCIAL DE EN EL SECTOR 02 DEL DISTRITO DE CHINCHA ALTA, PROVINCIA DE CHINCHA – ICA”
DIST. : CHINCHA ALTA CHINCHA.
PROV. : CHINCHA JUNIO - 2020
DPTO. : ICA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

ITEM PARTIDA UND CANT. PRECIO TOTAL


CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/.

01.04 BUZONES 279,044.29 49,970.50 100,617.19 88,369.76 40,086.84 0.00 0.00


01.04.01 DEMOLICION DE BUZON EN MAL ESTADO DE 1.20 A 1.50m. DE PROFUNDIDAD (INC. ACOMODO DEL DESMONTE PARA SU ELIMINAC und 16.00 441.90 7,070.40 100% 7,070.40 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.02 DEMOLICION DE BUZON EN MAL ESTADO DE 1.51 A 2.00m. DE PROFUNDIDAD (INC. ACOMODO DEL DESMONTE PARA SU ELIMINAC und 23.00 552.37 12,704.51 100% 12,704.51 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.03 DEMOLICION DE BUZON EN MAL ESTADO DE 2.01 A 2.50m. DE PROFUNDIDAD (INC. ACOMODO DEL DESMONTE PARA SU ELIMINAC und 9.00 736.50 6,628.50 100% 6,628.50 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.04 DEMOLICION DE BUZON EN MAL ESTADO DE 2.51 A 3.00m. DE PROFUNDIDAD (INC. ACOMODO DEL DESMONTE PARA SU ELIMINAC und 5.00 883.79 4,418.95 100% 4,418.95 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.05 DEMOLICION DE BUZON EN MAL ESTADO DE 3.01 A 3.50m. DE PROFUNDIDAD (INC. ACOMODO DEL DESMONTE PARA SU ELIMINAC und 4.00 1,104.74 4,418.96 100% 4,418.96 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.06 CAJA DE REGISTRO CONDOMINIAL HASTA 1.20 M DE PROFUNDIDAD INC. EXCAV. und 9.00 499.07 4,491.63 0% 0.00 100% 4,491.63 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.07 BUZONETAS HASTA 1.00 M DE PROFUNDIDAD INC. EXCAV. und 1.00 1,744.24 1,744.24 100% 1,744.24 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.08 REPOSICION DE BUZON HASTA 1.20 M DE PROFUNDIDAD INC. EXCAV. und 1.00 1,770.22 1,770.22 100% 1,770.22 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.09 REPOSICION DE BUZON HASTA 1.21-1.50 M DE PROFUNDIDAD INC. EXCAV. und 6.00 1,869.12 11,214.72 100% 11,214.72 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.04.10 REPOSICION DE BUZON HASTA 1.51-2.00 M DE PROFUNDIDAD INC. EXCAV. und 21.00 2,211.27 46,436.67 0% 0.00 80% 37,149.34 20% 9,287.33 0% 0.00 0% 0.00 0% 0.00
01.04.11 REPOSICION DE BUZON HASTA 2.01-2.50 M DE PROFUNDIDAD INC. EXCAV. und 9.00 2,600.00 23,400.00 0% 0.00 80% 18,720.00 20% 4,680.00 0% 0.00 0% 0.00 0% 0.00
01.04.12 REPOSICION DE BUZON HASTA 2.51-3.00 M DE PROFUNDIDAD INC. EXCAV. und 5.00 3,021.95 15,109.75 0% 0.00 80% 12,087.80 20% 3,021.95 0% 0.00 0% 0.00 0% 0.00
01.04.13 REPOSICION DE BUZON HASTA 3.01-3.50 M DE PROFUNDIDAD INC. EXCAV. und 4.00 4,530.94 18,123.76 0% 0.00 80% 14,499.01 20% 3,624.75 0% 0.00 0% 0.00 0% 0.00
01.04.14 BUZON HASTA 1.20 M DE PROFUNDIDAD INC. ECAV. und 9.00 1,898.53 17,086.77 0% 0.00 80% 13,669.42 20% 3,417.35 0% 0.00 0% 0.00 0% 0.00
01.04.15 BUZON DE 1.21-1.50 M DE PROFUNDIDAD INC. ECAV. und 11.00 2,010.26 22,112.86 0% 0.00 0% 0.00 80% 17,690.29 20% 4,422.57 0% 0.00 0% 0.00
01.04.16 BUZON DE 1.51-2.00 M DE PROFUNDIDAD INC. ECAV. und 15.00 2,386.62 35,799.30 0% 0.00 0% 0.00 80% 28,639.44 20% 7,159.86 0% 0.00 0% 0.00
01.04.17 BUZON DE 2.01-2.50 M DE PROFUNDIDAD INC. ECAV. und 8.00 2,813.85 22,510.80 0% 0.00 0% 0.00 80% 18,008.64 20% 4,502.16 0% 0.00 0% 0.00
01.04.18 REVESTIMIENTO INTERIOR DE BUZONES DE 1.20m DE PROFUNDIDAD C/IMPERM+CONFORMACION DE MEDIA CAÑA und 6.00 391.51 2,349.06 0% 0.00 0% 0.00 0% 0.00 100% 2,349.06 0% 0.00 0% 0.00
01.04.19 REVESTIMIENTO INTERIOR DE BUZONES DE 1.21-1.50m DE PROFUNDIDAD C/IMPERM+CONFORMACION DE MEDIA CAÑA und 5.00 439.36 2,196.80 0% 0.00 0% 0.00 0% 0.00 100% 2,196.80 0% 0.00 0% 0.00
01.04.20 REVESTIMIENTO INTERIOR DE BUZONES DE 1.51-2.00m DE PROFUNDIDAD C/IMPERM+CONFORMACION DE MEDIA CAÑA und 14.00 582.91 8,160.74 0% 0.00 0% 0.00 0% 0.00 100% 8,160.74 0% 0.00 0% 0.00
01.04.21 REVESTIMIENTO INTERIOR DE BUZONES DE 2.01-2.50m DE PROFUNDIDAD C/IMPERM+CONFORMACION DE MEDIA CAÑA und 14.00 742.41 10,393.74 0% 0.00 0% 0.00 0% 0.00 100% 10,393.74 0% 0.00 0% 0.00
01.04.22 REVESTIMIENTO INTERIOR DE BUZONES DE 2.51-3.00m DE PROFUNDIDAD C/IMPERM+CONFORMACION DE MEDIA CAÑA und 1.00 901.91 901.91 0% 0.00 0% 0.00 0% 0.00 100% 901.91 0% 0.00 0% 0.00
01.05 SUMINISTRO E INSTALACION DE TUBERIAS 141,950.30 72,462.57 69,487.73 0.00 0.00 0.00 0.00
01.05.01 SUMINISTRO E INSTALACION TUBERIA PVC UF Ø160mm NTP ISO4435, SN 4 S-20 m 98.52 21.28 2,096.51 100% 2,096.51 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.05.02 SUMINISTRO E INSTALACION TUBERIA PVC UF Ø200mm NTP ISO4435, SN 4 S-20 m 3,694.92 31.74 117,276.76 60% 70,366.06 40% 46,910.70 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.05.03 SUMINISTRO E INSTALACION TUBERIA PVC UF Ø315mm NTP ISO4435, SN 4 S-20 m 319.11 70.75 22,577.03 0% 0.00 100% 22,577.03 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.06 PRUEBA HIDRAULICA 17,272.33 0.00 16,441.05 831.28 0.00 0.00 0.00
01.06.01 PRUEBA HIDRAULICA DE TUBERIA P/DESAGUE Ø160mm. m 98.52 3.55 349.75 0% 0.00 100% 349.75 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.06.02 PRUEBA HIDRAULICA DE TUBERIA P/DESAGUE Ø200mm. m 3,694.92 4.13 15,260.02 0% 0.00 100% 15,260.02 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.06.03 PRUEBA HIDRAULICA DE TUBERIA P/DESAGUE Ø315mm. m 319.11 5.21 1,662.56 0% 0.00 50% 831.28 50% 831.28 0% 0.00 0% 0.00 0% 0.00
01.07 CONEXIONES DOMICILIARIAS 482,181.54 0.00 501.77 212,592.55 209,026.60 60,060.63 0.00
01.07.01 CONEXION DOMICILIARIA Lprom=1.0m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 165.00 371.22 61,251.30 0% 0.00 0% 0.00 40% 24,500.52 40% 24,500.52 20% 12,250.26 0% 0.00
01.07.02 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø160 INC. EXCAV. Y RELLENO und 4.00 433.33 1,733.32 0% 0.00 0% 0.00 70% 1,213.32 30% 520.00 0% 0.00 0% 0.00
01.07.03 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 177.00 436.75 77,304.75 0% 0.00 0% 0.00 100% 77,304.75 0% 0.00 0% 0.00 0% 0.00
01.07.04 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO und 9.00 469.09 4,221.81 0% 0.00 0% 0.00 100% 4,221.81 0% 0.00 0% 0.00 0% 0.00
01.07.05 CONEXION DOMICILIARIA Lprom=4.0m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 136.00 589.08 80,114.88 0% 0.00 0% 0.00 80% 64,091.90 20% 16,022.98 0% 0.00 0% 0.00
01.07.06 CONEXION DOMICILIARIA Lprom=4.0m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO und 45.00 534.60 24,057.00 0% 0.00 0% 0.00 80% 19,245.60 20% 4,811.40 0% 0.00 0% 0.00
01.07.07 CONEXION DOMICILIARIA Lprom=5.5m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 102.00 578.67 59,024.34 0% 0.00 0% 0.00 20% 11,804.87 80% 47,219.47 0% 0.00 0% 0.00
01.07.08 CONEXION DOMICILIARIA Lprom=5.5m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO und 25.00 600.13 15,003.25 0% 0.00 0% 0.00 20% 3,000.65 80% 12,002.60 0% 0.00 0% 0.00
01.07.09 CONEXION DOMICILIARIA Lprom=7.0m EN TUB PVC UF Ø160 INC. EXCAV. Y RELLENO und 1.00 629.88 629.88 0% 0.00 0% 0.00 0% 0.00 100% 629.88 0% 0.00 0% 0.00
01.07.10 CONEXION DOMICILIARIA Lprom=7.0m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 60.00 633.30 37,998.00 0% 0.00 0% 0.00 0% 0.00 100% 37,998.00 0% 0.00 0% 0.00
01.07.11 CONEXION DOMICILIARIA Lprom=7.0m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO und 3.00 665.64 1,996.92 0% 0.00 0% 0.00 0% 0.00 100% 1,996.92 0% 0.00 0% 0.00
01.07.12 CONEXION DOMICILIARIA Lprom=8.5m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 12.00 698.83 8,385.96 0% 0.00 0% 0.00 0% 0.00 100% 8,385.96 0% 0.00 0% 0.00
01.07.13 CONEXION DOMICILIARIA Lprom=10.0m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO und 5.00 764.34 3,821.70 0% 0.00 0% 0.00 0% 0.00 100% 3,821.70 0% 0.00 0% 0.00
01.07.14 CONEXION DOMICILIARIA Lprom=1.0m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 4.00 424.90 1,699.60 0% 0.00 0% 0.00 0% 0.00 100% 1,699.60 0% 0.00 0% 0.00
01.07.15 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø160 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 20.00 433.33 8,666.60 0% 0.00 0% 0.00 0% 0.00 100% 8,666.60 0% 0.00 0% 0.00
01.07.16 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 22.00 436.75 9,608.50 0% 0.00 0% 0.00 0% 0.00 100% 9,608.50 0% 0.00 0% 0.00
01.07.17 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 1.00 469.09 469.09 0% 0.00 0% 0.00 0% 0.00 100% 469.09 0% 0.00 0% 0.00
01.07.18 CONEXION DOMICILIARIA Lprom=2.5m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 3.00 490.43 1,471.29 0% 0.00 0% 0.00 0% 0.00 100% 1,471.29 0% 0.00 0% 0.00
01.07.19 CONEXION DOMICILIARIA Lprom=4.0m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 5.00 589.08 2,945.40 0% 0.00 0% 0.00 0% 0.00 100% 2,945.40 0% 0.00 0% 0.00
01.07.20 CONEXION DOMICILIARIA Lprom=4.0m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 10.00 534.60 5,346.00 0% 0.00 0% 0.00 0% 0.00 100% 5,346.00 0% 0.00 0% 0.00
01.07.21 CONEXION DOMICILIARIA Lprom=4.0m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 12.00 555.94 6,671.28 0% 0.00 0% 0.00 0% 0.00 100% 6,671.28 0% 0.00 0% 0.00
CRONOGRAMA VALORIZADO POR PARTIDAS DE EJECUCIÓN DE OBRA

ACTUALIZACION DEL EXPEDIENTE TECNICO: “MEJORAMIENTO DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN LAS AVENIDAS VICTORIA, PROGRESO, CALLE NUEVA Y UNION, PROLONGACIONES ANDRES
MUNICIPALIDAD RAZURI, ERNESTO VELIT Y MARISCAL SUCRE, CALLES Y PASAJES DEL CC.PP. BALCONCITO SECTOR 1, PASAJES. CON SALIDAS A CALLE ROSARIO, AV. PROGRESO, PROLONG. ANDRES RAZURI Y A LA AVENIDA VICTORIA
PROVINCIAL DE EN EL SECTOR 02 DEL DISTRITO DE CHINCHA ALTA, PROVINCIA DE CHINCHA – ICA”
DIST. : CHINCHA ALTA CHINCHA.
PROV. : CHINCHA JUNIO - 2020
DPTO. : ICA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

ITEM PARTIDA UND CANT. PRECIO TOTAL


CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/.

01.07.22 CONEXION DOMICILIARIA Lprom=5.5m EN TUB PVC UF Ø160 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 1.00 564.37 564.37 0% 0.00 0% 0.00 0% 0.00 80% 451.50 20% 112.87 0% 0.00
01.07.23 CONEXION DOMICILIARIA Lprom=5.5m EN TUB PVC UF Ø200 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 2.00 578.67 1,157.34 0% 0.00 0% 0.00 0% 0.00 80% 925.87 20% 231.47 0% 0.00
01.07.24 CONEXION DOMICILIARIA Lprom=5.5m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 17.00 600.13 10,202.21 0% 0.00 0% 0.00 0% 0.00 80% 8,161.77 20% 2,040.44 0% 0.00
01.07.25 CONEXION DOMICILIARIA Lprom=5.5m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 30.00 621.47 18,644.10 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 18,644.10 0% 0.00
01.07.26 CONEXION DOMICILIARIA Lprom=7.0m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 10.00 665.64 6,656.40 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 6,656.40 0% 0.00
01.07.27 CONEXION DOMICILIARIA Lprom=7.0m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 8.00 686.98 5,495.84 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 5,495.84 0% 0.00
01.07.28 CONEXION DOMICILIARIA Lprom=8.5m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 9.00 731.17 6,580.53 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 6,580.53 0% 0.00
01.07.29 CONEXION DOMICILIARIA Lprom=8.5m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 2.00 752.51 1,505.02 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 1,505.02 0% 0.00
01.07.30 CONEXION DOMICILIARIA Lprom=10.0m EN TUB PVC UF Ø315 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 1.00 796.68 796.68 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 796.68 0% 0.00
01.07.31 CONEXION DOMICILIARIA Lprom=10.0m EN TUB PVC UF Ø355 INC. EXCAV. Y RELLENO (EN TUB. EXIST.) und 1.00 818.02 818.02 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 818.02 0% 0.00
01.07.32 DESMONTAJE DE CONEXION DOMICILIARIA DESAGUE (INC. ACOPIO) und 276.00 18.18 5,017.68 0% 0.00 10% 501.77 70% 3,512.38 20% 1,003.54 0% 0.00 0% 0.00
01.07.33 PRUEBA HIDRAULICA EN CONEXIONES DOMICILIARIAS (DN 160) m 3,404.00 3.62 12,322.48 0% 0.00 0% 0.00 30% 3,696.74 30% 3,696.74 40% 4,928.99 0% 0.00
01.08 OTROS 18,969.91 6,493.94 9,778.07 2,697.89 0.00 0.00 0.00
01.08.01 CAIDA EN BUZONES und 5.00 377.23 1,886.15 0% 0.00 0% 0.00 100% 1,886.15 0% 0.00 0% 0.00 0% 0.00
01.08.02 DADO DE CONCRETO F'C=210KG/CM2 EN BUZONES und 222.00 73.13 16,234.86 40% 6,493.94 55% 8,929.17 5% 811.74 0% 0.00 0% 0.00 0% 0.00
01.08.03 EMPALME TUBERIA PVC PROYECTADA DN 200mm A TUBERIA CNS EXISTENTE 8" und 5.00 131.76 658.80 0% 0.00 100% 658.80 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.08.04 EMPALME TUBERIA PVC PROYECTADA DN 200mm A TUBERIA PVC EXISTENTE DN 200mm und 2.00 95.05 190.10 0% 0.00 100% 190.10 0% 0.00 0% 0.00 0% 0.00 0% 0.00
01.09 REPOSICION DE PAVIMENTO CON MATERIAL GRANULAR 13,745.00 0.00 0.00 0.00 0.00 2,749.00 10,996.00
01.09.01 PERFILADO Y COMPACTADO MANUAL DE SUELO m2 1,237.52 4.31 5,333.71 0% 0.00 0% 0.00 0% 0.00 0% 0.00 20% 1,066.74 80% 4,266.97
01.09.02 BASE GRANULAR e=0.10m m3 123.75 67.97 8,411.29 0% 0.00 0% 0.00 0% 0.00 0% 0.00 20% 1,682.26 80% 6,729.03
01.10 REPOSICION DE CARPETA ASFALTICA EN CALIENTE 54,054.88 0.00 0.00 0.00 0.00 0.00 54,054.88
01.10.01 IMPRIMACION ASFALTICA A PULSO m2 1,237.52 8.12 10,048.66 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 10,048.66
01.10.02 CARPETA ASFALTICA EN CALIENTE DE 2"(PARCHADO) m2 1,237.52 35.26 43,634.96 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 43,634.96
01.10.03 SELLO DE ARENA m2 1,237.52 0.30 371.26 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 371.26
01.11 REPOSICION DE CONCRETO 49,133.39 0.00 0.00 0.00 0.00 0.00 49,133.39
01.11.01 PERFILADO Y COMPACTADO MANUAL DE SUELO m2 858.81 4.31 3,701.47 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 3,701.47
01.11.02 BASE GRANULAR e=0.10m m3 85.88 67.97 5,837.26 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 5,837.26
01.11.03 CONCRETO F'C= 140 KG/CM2 EN VEREDAS m3 85.88 334.49 28,726.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 28,726.00
01.11.04 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 246.12 44.16 10,868.66 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 10,868.66
02 MONITOREO ARQUEOLOGICO, AMBIENTAL, SEGURIDAD Y SALUD 65,283.38 31,898.85 7,337.92 7,337.92 7,337.92 7,337.92 4,032.87
02.01 SEÑALIZACION AMBIENTAL 1,733.36 1,733.36 0.00 0.00 0.00 0.00 0.00
02.01.01 CARTELES DE INSTALACIONES TEMPORALES und 8.00 216.67 1,733.36 100% 1,733.36 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
02.02 SEGURIDAD E HIGIENE OCUPACIONAL 39,436.11 6,415.49 7,337.92 7,337.92 7,337.92 7,337.92 3,668.96
02.02.01 EQUIPOS DE PROTECCION PERSONAL (EPPS) mes 6.00 4,347.40 26,084.40 10% 2,608.44 20% 5,216.88 20% 5,216.88 20% 5,216.88 20% 5,216.88 10% 2,608.44
02.02.02 SS.HH. PORTATIL (INC. MNMTO) mes 6.00 1,767.53 10,605.18 10% 1,060.52 20% 2,121.04 20% 2,121.04 20% 2,121.04 20% 2,121.04 10% 1,060.52
02.02.03 EQUIPO DE CONTINGENCIA EN SEGURIDAD Y SALUD glb 3.00 915.51 2,746.53 100% 2,746.53 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
02.03 PROGRAMA DE ABANDONO DE OBRA 363.91 0.00 0.00 0.00 0.00 0.00 363.91
02.03.01 REACONDICIONAMIENTO DE INSTALACIONES TEMPORALES HA 0.10 3,639.08 363.91 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 100% 363.91
02.04 ARQUEOLOGIA 17,000.00 17,000.00 0.00 0.00 0.00 0.00 0.00
02.04.01 ELABORACION DEL PLAN DE MONITOREO Y SEGUIMIENTO ARQUEOLOGICO glb 1.00 5,000.00 5,000.00 100% 5,000.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
02.04.02 MONITOREO ARQUEOLOGICO-MINISTERIO CULTURA mes 6.00 2,000.00 12,000.00 100% 12,000.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
02.05 PROGRAMA DE EDUCACION SANITARIA 6,750.00 6,750.00 0.00 0.00 0.00 0.00 0.00
02.05.01 EDUCACION SANITARIA PARA POBLADORES und 1.00 2,250.00 2,250.00 100% 2,250.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
02.05.02 EDUCACION SANITARIA PARA TRABAJADORES und 2.00 2,250.00 4,500.00 100% 4,500.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
03 PLAN PARA LA VIGILANCIA, PREVENCIÓN Y CONTROL DEL COVID-19 EN EL TRABAJO 152,987.69 30,355.95 24,526.35 24,526.35 24,526.35 24,526.35 24,526.35
ACTIVIDADES DE PREVENCION DEL COVID-19
03.01 113,546.89 23,782.48 17,952.88 17,952.88 17,952.88 17,952.88 17,952.88
ELABORACION DEL PLAN PARA VIGILANCIA, PREVENCION Y CONTROL DEL COVID-19
03.01.01 glb 1.00 1,230.00 1,230.00 100% 1,230.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
03.01.02 LIMPIEZA Y DESINFECCION EN OBRA mes 6.00 2,578.20 15,469.20 17% 2,578.20 17% 2,578.20 17% 2,578.20 17% 2,578.20 17% 2,578.20 17% 2,578.20
03.01.03 EVALUACION DE LA CONDICION DE SALUD DEL TRABAJADOR und 120.00 38.33 4,599.60 100% 4,599.60 0% 0.00 0% 0.00 0% 0.00 0% 0.00 0% 0.00
03.01.04 LAVADO Y DESINFECCION DE MANOS (OBLIGATORIO) mes 6.00 403.20 2,419.20 17% 403.20 17% 403.20 17% 403.20 17% 403.20 17% 403.20 17% 403.20
03.01.05 SENSIBILIZACION DE LA PREVENCION DEL CONTAGIO COVID-19 EN OBRA mes 6.00 1,184.00 7,104.00 17% 1,184.00 17% 1,184.00 17% 1,184.00 17% 1,184.00 17% 1,184.00 17% 1,184.00
03.01.06 MEDIDAS PREVENTIVAS COLECTIVAS glb 1.00 4,202.89 4,202.89 17% 700.48 17% 700.48 17% 700.48 17% 700.48 17% 700.48 17% 700.48
03.01.07 MEDIDAS DE PROTECCION PERSONAL mes 6.00 10,255.00 61,530.00 17% 10,255.00 66% 10,255.00 66% 10,255.00 66% 10,255.00 66% 10,255.00 66% 10,255.00
CRONOGRAMA VALORIZADO POR PARTIDAS DE EJECUCIÓN DE OBRA

ACTUALIZACION DEL EXPEDIENTE TECNICO: “MEJORAMIENTO DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN LAS AVENIDAS VICTORIA, PROGRESO, CALLE NUEVA Y UNION, PROLONGACIONES ANDRES
MUNICIPALIDAD RAZURI, ERNESTO VELIT Y MARISCAL SUCRE, CALLES Y PASAJES DEL CC.PP. BALCONCITO SECTOR 1, PASAJES. CON SALIDAS A CALLE ROSARIO, AV. PROGRESO, PROLONG. ANDRES RAZURI Y A LA AVENIDA VICTORIA
PROVINCIAL DE EN EL SECTOR 02 DEL DISTRITO DE CHINCHA ALTA, PROVINCIA DE CHINCHA – ICA”
DIST. : CHINCHA ALTA CHINCHA.
PROV. : CHINCHA JUNIO - 2020
DPTO. : ICA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

ITEM PARTIDA UND CANT. PRECIO TOTAL


CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/. CANT. COSTO S/.

03.01.08 IDENTIFICACION DE SINTOMATOLOGIA COVID-19 AL INGRESO A LA OBRA und 60.00 212.40 12,744.00 17% 2,124.00 17% 2,124.00 17% 2,124.00 17% 2,124.00 17% 2,124.00 17% 2,124.00
03.01.09 VIGILANCIA DE LA SALUD DEL TRABAJADOR EN EL CONTEXTO DEL COVID-19 und 60.00 70.80 4,248.00 17% 708.00 17% 708.00 17% 708.00 17% 708.00 17% 708.00 17% 708.00
EQUIPAMIENTO Y PERSONAL DE SEGURIDAD Y SALUD EN EL TRABAJO
03.02 39,440.80 6,573.47 6,573.47 6,573.47 6,573.47 6,573.47 6,573.47
03.02.01 EQUIPAMIENTO PARA LA VIGILANCIA DE LA SALUD glb 1.00 5,531.20 5,531.20 17% 921.87 17% 921.87 17% 921.87 17% 921.87 17% 921.87 17% 921.87
03.02.02 PROFESIONALES DE SEGURIDAD Y SALUD OCUPACIONAL mes 6.00 5,651.60 33,909.60 17% 5,651.60 37% 5,651.60 37% 5,651.60 37% 5,651.60 37% 5,651.60 37% 5,651.60

COSTO DIRECTO TOTAL DE EJECUCIÓN DEL PROYECTO 3,222,785.10 302,346.680 552,430.075 613,926.423 728,070.013 609,570.800 416,441.108
CRONOGRAMA MENSUAL DE DESEMBOLSOS
ITEM INICIO DE OBRA MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
% COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/. % COSTO S/.
A.- VALORIZACIÓN BRUTA PROGRAMADA M. Contrato 3,222,785.10 M. Valoriz. 302,346.68 M. Valoriz. 552,430.08 M. Valoriz. 613,926.42 M. Valoriz. 728,070.01 M. Valoriz. 609,570.80 M. Valoriz. 416,441.11
B.- ADELANTO DIRECTO S/. 10% 322,278.51 -10.00% -30,234.67 -10.00% -55,243.01 -10.00% -61,392.64 -10.00% -72,807.00 -10.00% -60,957.08 -10.00% -41,644.11
C.- ADELANTO POR MATERIALES S/. 20% 644,557.02 -20.00% -60,469.34 -20.00% -110,486.02 -20.00% -122,785.28 -20.00% -145,614.00 -20.00% -121,914.16 -20.00% -83,288.22
E.- VALORIZACIÓN NETA PROGRAMADA S/. 211,642.68 386,701.05 429,748.50 509,649.01 426,699.56 291,508.78

F.- MONTO ENTREGADO S/. 966,835.53 211,642.68 386,701.05 429,748.50 509,649.01 426,699.56 291,508.78
G.- GASTOS GENERALES (10%) S/. 96,683.55 21,164.27 38,670.11 42,974.85 50,964.90 42,669.96 29,150.88
H.- UTILIDADES (8%) S/. 77,346.84 16,931.41 30,936.08 34,379.88 40,771.92 34,135.96 23,320.70
I.- SUB TOTAL S/. 1,140,865.93 249,738.36 456,307.24 507,103.23 601,385.83 503,505.48 343,980.36
J- IGV(18%) S/. 205,355.87 44,952.90 82,135.30 91,278.58 108,249.45 90,630.99 61,916.46
K.- DESEMBOLSOS PROYECTADO S/. 1,346,221.79 294,691.26 538,442.55 598,381.81 709,635.28 594,136.47 405,896.82