CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01 09 ALCANTARILLA TIPICA DE 1.20 M X 1.00 M (OLIVA, ZARATE, PALOMINO, UGARTE, S/ 86,870.58
PUMA, PEÑA, CANDELARIA, OSVALDO LEZAMA, CAMASCA)
01.01 OBRAS PROVISIONALES S/ 10,832.16
01.01.01 TRANSPORTE A OBRA DE EQUIPOS Y HERRAMIENTAS glb S/ 1.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00 S/ - S/ - S/ - S/ 4,500.00
01.01.02 GUARDIANIAS und S/ 6.00 S/ 535.36 S/ 3,212.16 S/ 3,212.16 S/ - S/ - S/ - S/ 3,212.16
01.01.03 DESVIO DE CAUDALES und S/ 6.00 S/ 520.00 S/ 3,120.00 S/ 3,120.00 S/ - S/ - S/ - S/ 3,120.00
01.02 OBRAS PRELIMINARES S/ 1,134.00
01.02.01 TRAZO, NIVEL Y REPLANTEO m2 S/ 162.00 S/ 7.00 S/ 1,134.00 S/ 1,134.00 S/ - S/ - S/ - S/ 1,134.00
01.03 MOVIMIENTO DE TIERRAS S/ 15,031.83
01.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 153.47 S/ 52.52 S/ 8,060.24 S/ 8,060.24 S/ - S/ - S/ - S/ 8,060.24
01.03.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 S/ 114.12 S/ 61.09 S/ 6,971.59 S/ 6,971.59 S/ - S/ - S/ - S/ 6,971.59
01.04 CONCRETO SIMPLE S/ 6,849.49
01.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 35.10 S/ 87.80 S/ 3,081.78 S/ 1,216.43 S/ 1,865.35 S/ - S/ - S/ 3,081.78
01.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 25% P.M. m3 S/ 16.29 S/ 231.29 S/ 3,767.71 S/ - S/ 3,767.71 S/ - S/ - S/ 3,767.71
01.05 CONCRETO ARMADO S/ 53,023.10
01.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 35.98 S/ 448.62 S/ 16,141.35 S/ - S/ 16,141.35 S/ - S/ - S/ 16,141.35
01.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 281.52 S/ 67.77 S/ 19,078.61 S/ 7,040.34 S/ 12,038.27 S/ - S/ - S/ 19,078.61
01.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 2,536.06 S/ 7.02 S/ 17,803.14 S/ 17,803.14 S/ - S/ - S/ - S/ 17,803.14
02 ALCANTARILLA ZARATE S/ 9,842.93
02.01 OBRAS PROVISIONALES S/ 1,393.36
02.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ - S/ 480.00
02.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ 393.36 S/ - S/ - S/ - S/ 393.36
02.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ - S/ 520.00
02.02 OBRAS PRELIMINARES S/ 126.00
02.02.01 TRAZO Y REPLANTEO m2 S/ 18.00 S/ 7.00 S/ 126.00 S/ 126.00 S/ - S/ - S/ - S/ 126.00
02.03 MOVIMIENTO DE TIERRAS S/ 1,670.09
02.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 17.05 S/ 52.52 S/ 895.47 S/ 895.47 S/ - S/ - S/ - S/ 895.47
02.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 12.68 S/ 61.09 S/ 774.62 S/ 774.62 S/ - S/ - S/ - S/ 774.62
02.04 CONCRETO SIMPLE S/ 761.05
02.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ 342.42 S/ - S/ - S/ - S/ 342.42
02.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 1.81 S/ 231.29 S/ 418.63 S/ 418.63 S/ - S/ - S/ - S/ 418.63
02.05 CONCRETO ARMADO S/ 5,892.43
02.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 4.00 S/ 448.62 S/ 1,794.48 S/ 1,794.48 S/ - S/ - S/ - S/ 1,794.48
02.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 31.28 S/ 67.77 S/ 2,119.85 S/ 2,119.85 S/ - S/ - S/ - S/ 2,119.85
02.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 281.78 S/ 7.02 S/ 1,978.10 S/ 1,978.10 S/ - S/ - S/ - S/ 1,978.10
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
03 09 ALCANTARILLA
ALCANTARILLA TIPICA DE 1.20 M X 1.00 M (OLIVA, ZARATE, PALOMINO, UGARTE,
BOZA S/ 86,870.58
29,856.81
03.01 PUMA, PEÑA,
OBRAS CANDELARIA, OSVALDO LEZAMA, CAMASCA)
PROVISIONALES S/ 1,393.36
03.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ - S/ 480.00
03.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ 393.36 S/ - S/ - S/ - S/ 393.36
03.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ - S/ 520.00
03.02 OBRAS PRELIMINARES S/ 237.30
03.02.01 TRAZO Y REPLANTEO m2 S/ 33.90 S/ 7.00 S/ 237.30 S/ 237.30 S/ - S/ - S/ - S/ 237.30
03.03 MOVIMIENTO DE TIERRAS S/ 13,318.04
03.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 110.94 S/ 52.52 S/ 5,826.57 S/ 1,942.19 S/ 3,884.38 S/ - S/ - S/ 5,826.57
03.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 122.63 S/ 61.09 S/ 7,491.47 S/ - S/ 7,491.47 S/ - S/ - S/ 7,491.47
03.04 CONCRETO SIMPLE S/ 1,221.32
03.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ 342.42 S/ - S/ - S/ 342.42
03.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 3.80 S/ 231.29 S/ 878.90 S/ - S/ 878.90 S/ - S/ - S/ 878.90
03.05 CONCRETO ARMADO S/ 13,686.79
03.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 9.76 S/ 448.62 S/ 4,378.53 S/ - S/ 4,378.53 S/ - S/ - S/ 4,378.53
03.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 75.68 S/ 67.77 S/ 5,128.83 S/ - S/ 5,128.83 S/ - S/ - S/ 5,128.83
03.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 595.36 S/ 7.02 S/ 4,179.43 S/ - S/ 4,179.43 S/ - S/ - S/ 4,179.43
04 ALCANTARILLA CHUCHON S/ 13,521.73
04.01 OBRAS PROVISIONALES S/ 1,393.36
04.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ 480.00 S/ - S/ - S/ 480.00
04.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ 393.36 S/ - S/ - S/ 393.36
04.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ 520.00 S/ - S/ - S/ 520.00
04.02 OBRAS PRELIMINARES S/ 126.00
04.02.01 TRAZO Y REPLANTEO m2 S/ 18.00 S/ 7.00 S/ 126.00 S/ - S/ 126.00 S/ - S/ - S/ 126.00
04.03 MOVIMIENTO DE TIERRAS S/ 4,387.20
04.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 37.03 S/ 52.52 S/ 1,944.82 S/ - S/ 1,944.82 S/ - S/ - S/ 1,944.82
04.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 39.98 S/ 61.09 S/ 2,442.38 S/ - S/ 2,442.38 S/ - S/ - S/ 2,442.38
04.04 CONCRETO SIMPLE S/ 761.05
04.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ 342.42 S/ - S/ - S/ 342.42
04.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 1.81 S/ 231.29 S/ 418.63 S/ - S/ 418.63 S/ - S/ - S/ 418.63
04.05 CONCRETO ARMADO S/ 6,854.12
04.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 4.64 S/ 448.62 S/ 2,081.60 S/ - S/ 2,081.60 S/ - S/ - S/ 2,081.60
04.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 39.88 S/ 67.77 S/ 2,702.67 S/ - S/ 2,702.67 S/ - S/ - S/ 2,702.67
04.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 294.85 S/ 7.02 S/ 2,069.85 S/ - S/ 2,069.85 S/ - S/ - S/ 2,069.85
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
05 09 ALCANTARILLA
ALCANTARILLA TIPICA DE 1.20 M X 1.00 M (OLIVA, ZARATE, PALOMINO, UGARTE,
GARCIA S/ 86,870.58
12,497.63
05.01 PUMA, PEÑA,
OBRAS CANDELARIA, OSVALDO LEZAMA, CAMASCA)
PROVISIONALES S/ 1,393.36
05.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ 240.00 S/ 240.00 S/ - S/ 480.00
05.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ 196.68 S/ 196.68 S/ - S/ 393.36
05.01.03 DESVIO DE CANALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ 260.00 S/ 260.00 S/ - S/ 520.00
05.02 OBRAS PRELIMINARES S/ 163.80
05.02.01 TRAZO Y REPLANTEO m2 S/ 23.40 S/ 7.00 S/ 163.80 S/ - S/ - S/ 163.80 S/ - S/ 163.80
05.03 MOVIMIENTO DE TIERRAS S/ 1,614.31
05.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 14.22 S/ 52.52 S/ 746.83 S/ - S/ - S/ 746.83 S/ - S/ 746.83
05.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 14.20 S/ 61.09 S/ 867.48 S/ - S/ - S/ 867.48 S/ - S/ 867.48
05.04 CONCRETO SIMPLE S/ 934.52
05.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ - S/ 342.42 S/ - S/ 342.42
05.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 2.56 S/ 231.29 S/ 592.10 S/ - S/ - S/ 592.10 S/ - S/ 592.10
05.05 CONCRETO ARMADO S/ 8,391.64
05.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 6.69 S/ 448.62 S/ 3,001.27 S/ - S/ - S/ 3,001.27 S/ - S/ 3,001.27
05.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 45.88 S/ 67.77 S/ 3,109.29 S/ - S/ - S/ 3,109.29 S/ - S/ 3,109.29
05.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 324.94 S/ 7.02 S/ 2,281.08 S/ - S/ - S/ 2,281.08 S/ - S/ 2,281.08
06 ALCANTARILLA PAULA PEÑA S/ 12,497.63
06.01 OBRAS PROVISIONALES S/ 1,393.36
06.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ 480.00 S/ - S/ 480.00
06.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ - S/ 393.36 S/ - S/ 393.36
06.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ 520.00 S/ - S/ 520.00
06.02 OBRAS PRELIMINARES S/ 163.80
06.02.01 TRAZO Y REPLANTEO m2 S/ 23.40 S/ 7.00 S/ 163.80 S/ - S/ - S/ 163.80 S/ - S/ 163.80
06.03 MOVIMIENTO DE TIERRAS S/ 1,614.31
06.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 14.22 S/ 52.52 S/ 746.83 S/ - S/ - S/ 746.83 S/ - S/ 746.83
06.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 14.20 S/ 61.09 S/ 867.48 S/ - S/ - S/ 867.48 S/ - S/ 867.48
06.04 CONCRETO SIMPLE S/ 934.52
06.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ - S/ 342.42 S/ - S/ 342.42
06.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 2.56 S/ 231.29 S/ 592.10 S/ - S/ - S/ 592.10 S/ - S/ 592.10
06.05 CONCRETO ARMADO S/ 8,391.64
06.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 6.69 S/ 448.62 S/ 3,001.27 S/ - S/ - S/ 3,001.27 S/ - S/ 3,001.27
06.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 45.88 S/ 67.77 S/ 3,109.29 S/ - S/ - S/ 3,109.29 S/ - S/ 3,109.29
06.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 324.94 S/ 7.02 S/ 2,281.08 S/ - S/ - S/ 2,281.08 S/ - S/ 2,281.08
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
07 09 ALCANTARILLA
ALCANTARILLA TIPICA DE KALY
MARGARITA 1.20 M X 1.00 M (OLIVA, ZARATE, PALOMINO, UGARTE, S/ 86,870.58
12,497.63
07.01 PUMA, PEÑA,
OBRAS CANDELARIA, OSVALDO LEZAMA, CAMASCA)
PROVISIONALES S/ 1,393.36
07.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ 480.00 S/ - S/ 480.00
07.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ - S/ 393.36 S/ - S/ 393.36
07.01.03 DESVIO DE CANALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ 520.00 S/ - S/ 520.00
07.02 OBRAS PRELIMINARES S/ 163.80
07.02.01 TRAZO Y REPLANTEO m2 S/ 23.40 S/ 7.00 S/ 163.80 S/ - S/ - S/ 163.80 S/ - S/ 163.80
07.03 MOVIMIENTO DE TIERRAS S/ 1,614.31
07.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 14.22 S/ 52.52 S/ 746.83 S/ - S/ - S/ - S/ 746.83 S/ 746.83
07.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 14.20 S/ 61.09 S/ 867.48 S/ - S/ - S/ 277.80 S/ 589.68 S/ 867.48
07.04 CONCRETO SIMPLE S/ 934.52
07.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ - S/ - S/ 342.42 S/ 342.42
07.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 2.56 S/ 231.29 S/ 592.10 S/ - S/ - S/ - S/ 592.10 S/ 592.10
07.05 CONCRETO ARMADO S/ 8,391.64
07.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 6.69 S/ 448.62 S/ 3,001.27 S/ - S/ - S/ - S/ 3,001.27 S/ 3,001.27
07.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 45.88 S/ 67.77 S/ 3,109.29 S/ - S/ - S/ - S/ 3,109.29 S/ 3,109.29
07.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 324.94 S/ 7.02 S/ 2,281.08 S/ - S/ - S/ - S/ 2,281.08 S/ 2,281.08
08 ALCANTARILLA YOLANDA ROJAS S/ 22,829.57
08.01 OBRAS PROVISIONALES S/ 1,393.36
08.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ - S/ 480.00 S/ 480.00
08.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ - S/ - S/ 393.36 S/ 393.36
08.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ - S/ 520.00 S/ 520.00
08.02 OBRAS PRELIMINARES S/ 268.80
08.02.01 TRAZO Y REPLANTEO m2 S/ 38.40 S/ 7.00 S/ 268.80 S/ - S/ - S/ - S/ 268.80 S/ 268.80
08.03 MOVIMIENTO DE TIERRAS S/ 2,648.69
08.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 23.33 S/ 52.52 S/ 1,225.29 S/ - S/ - S/ - S/ 1,225.29 S/ 1,225.29
08.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 23.30 S/ 61.09 S/ 1,423.40 S/ - S/ - S/ - S/ 1,423.40 S/ 1,423.40
08.04 CONCRETO SIMPLE S/ 1,975.33
08.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ - S/ - S/ 342.42 S/ 342.42
08.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 7.06 S/ 231.29 S/ 1,632.91 S/ - S/ - S/ - S/ 1,632.91 S/ 1,632.91
08.05 CONCRETO ARMADO S/ 16,543.39
08.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 10.23 S/ 448.62 S/ 4,589.38 S/ - S/ - S/ - S/ 4,589.38 S/ 4,589.38
08.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 102.76 S/ 67.77 S/ 6,964.05 S/ - S/ - S/ - S/ 6,964.05 S/ 6,964.05
08.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 710.82 S/ 7.02 S/ 4,989.96 S/ - S/ - S/ - S/ 4,989.96 S/ 4,989.96
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
09 609ALCANTARILLA
ALCANTARILLATIPICA
TIPICADEDE0.90
1.20MMX X0.80
1.00MM(MARTIN
(OLIVA,HERNANDEZ,
ZARATE, PALOMINO, UGARTE,
PORTILLO, TAYPE, S/ 86,870.58
39,830.57
PUMA,ROMERO,
ELIAS PEÑA, CANDELARIA, OSVALDO LEZAMA, CAMASCA)
CIPRIANO RAMOS)
09.01 OBRAS PROVISIONALES S/ 8,480.16
09.01.01 FLETE TRANSPORTE DE EQUIPO LIVIANO Y HERRAMIENTAS glb S/ 1.00 S/ 3,000.00 S/ 3,000.00 S/ - S/ 3,000.00 S/ - S/ - S/ 3,000.00
09.01.02 DESVIO DE CAUDALES und S/ 6.00 S/ 520.00 S/ 3,120.00 S/ - S/ 3,120.00 S/ - S/ - S/ 3,120.00
09.01.03 GUARDIANIA und S/ 6.00 S/ 393.36 S/ 2,360.16 S/ - S/ 2,360.16 S/ - S/ - S/ 2,360.16
09.02 OBRAS PRELIMINARES S/ 756.00
09.02.01 TRAZO Y REPLANTEO m2 S/ 108.00 S/ 7.00 S/ 756.00 S/ - S/ 756.00 S/ - S/ - S/ 756.00
09.03 MOVIMIENTO DE TIERRAS S/ 2,088.59
09.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 30.66 S/ 52.52 S/ 1,610.26 S/ - S/ 1,610.26 S/ - S/ - S/ 1,610.26
09.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 7.83 S/ 61.09 S/ 478.33 S/ - S/ 478.33 S/ - S/ - S/ 478.33
09.04 CONCRETO SIMPLE S/ 4,082.60
09.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 38.28 S/ 87.80 S/ 3,360.98 S/ - S/ 3,360.98 S/ - S/ - S/ 3,360.98
09.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 3.12 S/ 231.29 S/ 721.62 S/ - S/ 721.62 S/ - S/ - S/ 721.62
09.05 CONCRETO ARMADO S/ 24,423.22
09.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 17.82 S/ 448.62 S/ 7,994.41 S/ - S/ 7,994.41 S/ - S/ - S/ 7,994.41
09.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 121.23 S/ 67.77 S/ 8,215.76 S/ - S/ 8,215.76 S/ - S/ - S/ 8,215.76
09.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 1,169.95 S/ 7.02 S/ 8,213.05 S/ - S/ 8,213.05 S/ - S/ - S/ 8,213.05
10 ALCANTARILLA 0.90 M X 0.80 M ( MALDONADO) S/ 10,060.40
10.01 OBRAS PROVISIONALES S/ 1,393.36
10.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ 480.00 S/ - S/ - S/ 480.00
10.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ 393.36 S/ - S/ - S/ 393.36
10.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ 520.00 S/ - S/ - S/ 520.00
10.02 OBRAS PRELIMINARES S/ 163.80
10.02.01 TRAZO Y REPLANTEO m2 S/ 23.40 S/ 7.00 S/ 163.80 S/ - S/ 163.80 S/ - S/ - S/ 163.80
10.03 MOVIMIENTO DE TIERRAS S/ 2,088.59
10.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 30.66 S/ 52.52 S/ 1,610.26 S/ - S/ 1,610.26 S/ - S/ - S/ 1,610.26
10.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 7.83 S/ 61.09 S/ 478.33 S/ - S/ 478.33 S/ - S/ - S/ 478.33
10.04 CONCRETO SIMPLE S/ 680.43
10.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 6.38 S/ 87.80 S/ 560.16 S/ - S/ - S/ 560.16 S/ - S/ 560.16
10.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 0.52 S/ 231.29 S/ 120.27 S/ - S/ - S/ 120.27 S/ - S/ 120.27
10.05 CONCRETO ARMADO S/ 5,734.22
10.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 4.46 S/ 448.62 S/ 2,000.85 S/ - S/ - S/ 2,000.85 S/ - S/ 2,000.85
10.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 29.96 S/ 67.77 S/ 2,030.39 S/ - S/ - S/ 2,030.39 S/ - S/ 2,030.39
10.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 242.59 S/ 7.02 S/ 1,702.98 S/ - S/ 355.89 S/ 1,347.09 S/ - S/ 1,702.98
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
11 09 ALCANTARILLA
ALCANTARILLA TIPICA DE 1.20
PESCADORES M X DE
(BOCA 1.00SALINAS)
M (OLIVA, ZARATE, PALOMINO, UGARTE, S/ 86,870.58
13,521.73
11.01 PUMA, PEÑA,
OBRAS CANDELARIA, OSVALDO LEZAMA, CAMASCA)
PROVISIONALES S/ 1,393.36
11.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ 480.00 S/ - S/ 480.00
11.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ - S/ 393.36 S/ - S/ 393.36
11.01.03 DESVIO DE CANALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ 520.00 S/ - S/ 520.00
11.02 OBRAS PRELIMINARES S/ 126.00
11.02.01 TRAZO Y REPLANTEO m2 S/ 18.00 S/ 7.00 S/ 126.00 S/ - S/ - S/ 126.00 S/ - S/ 126.00
11.03 MOVIMIENTO DE TIERRAS S/ 4,387.20
11.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 37.03 S/ 52.52 S/ 1,944.82 S/ - S/ - S/ 1,944.82 S/ - S/ 1,944.82
11.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 39.98 S/ 61.09 S/ 2,442.38 S/ - S/ - S/ 2,442.38 S/ - S/ 2,442.38
11.04 CONCRETO SIMPLE S/ 761.05
11.04.01 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 3.90 S/ 87.80 S/ 342.42 S/ - S/ - S/ 342.42 S/ - S/ 342.42
11.04.02 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 1.81 S/ 231.29 S/ 418.63 S/ - S/ - S/ 418.63 S/ - S/ 418.63
11.05 CONCRETO ARMADO S/ 6,854.12
11.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 4.64 S/ 448.62 S/ 2,081.60 S/ - S/ - S/ 2,081.60 S/ - S/ 2,081.60
11.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 39.88 S/ 67.77 S/ 2,702.67 S/ - S/ - S/ 2,702.67 S/ - S/ 2,702.67
11.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 294.85 S/ 7.02 S/ 2,069.85 S/ - S/ - S/ 2,069.85 S/ - S/ 2,069.85
12 PUENTE HUACA BLANCA S/ 32,610.18
12.01 OBRAS PROVISIONALES S/ 1,393.36
12.01.01 TRANSPORTE glb S/ 1.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ 480.00 S/ - S/ 480.00
12.01.02 GUARDIANIA glb S/ 1.00 S/ 393.36 S/ 393.36 S/ - S/ - S/ 393.36 S/ - S/ 393.36
12.01.03 DESVIO DE CAUDALES glb S/ 1.00 S/ 520.00 S/ 520.00 S/ - S/ - S/ 520.00 S/ - S/ 520.00
12.02 OBRAS PRELIMINARES S/ 280.00
12.02.01 TRAZO Y REPLANTEO m2 S/ 40.00 S/ 7.00 S/ 280.00 S/ - S/ - S/ 280.00 S/ - S/ 280.00
12.03 MOVIMIENTO DE TIERRAS S/ 4,680.19
12.03.01 EXCAVACION Y PERFILADO DE TERRENO m3 S/ 43.33 S/ 52.52 S/ 2,275.69 S/ - S/ - S/ 2,275.69 S/ - S/ 2,275.69
12.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/ 39.36 S/ 61.09 S/ 2,404.50 S/ - S/ - S/ 2,404.50 S/ - S/ 2,404.50
12.04 CONCRETO SIMPLE EN ESTRIBOS Y ALEROS S/ 21,422.45
12.04.01 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 S/ 65.65 S/ 231.29 S/ 15,184.19 S/ - S/ - S/ 1,345.61 S/ 13,838.58 S/ 15,184.19
12.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 S/ 94.00 S/ 45.61 S/ 4,287.34 S/ - S/ - S/ 4,287.34 S/ - S/ 4,287.34
12.04.03 EMBOQUILLADO DE PIEDRA EN CAUCE DE CANAL E=25 CM m2 S/ 22.22 S/ 87.80 S/ 1,950.92 S/ - S/ - S/ - S/ 1,950.92 S/ 1,950.92
12.05 CONCRETO ARMADO EN LOSA S/ 4,834.18
12.05.01 CONCRETO f'c=210 kg/cm2 m3 S/ 4.24 S/ 448.62 S/ 1,902.15 S/ - S/ - S/ - S/ 1,902.15 S/ 1,902.15
12.05.02 ENCOFRADO Y DESENCOFRADO m2 S/ 15.46 S/ 67.77 S/ 1,047.72 S/ - S/ - S/ - S/ 1,047.72 S/ 1,047.72
12.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 268.42 S/ 7.02 S/ 1,884.31 S/ - S/ - S/ 393.79 S/ 1,490.52 S/ 1,884.31
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
13 809COMPUERTAS
ALCANTARILLA TIPICA
TIPICA DE DE
1.001.20 M X 1.00
M SEGUN M (OLIVA,
DISEÑO ZARATE,
(ISLA PALOMINO,
JOYA, YOLANDA UGARTE,
ROJAS, S/ 86,870.58
30,461.53
PUMA, PEÑA,
ISABEL CANDELARIA,
QUISPE, OSVALDO
RICARDO QUISPE, LEZAMA, CAMASCA)
POLVADERA, AÑANKA, OSVALDO LEZAMA, HABEL
FERNANDEZ)

13.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 9.60 S/ 38.24 S/ 367.10 S/ - S/ - S/ - S/ 367.10 S/ 367.10
13.02 SUMINISTRO E INSTALACION COMPUERTA INCLUIDO ACCESORIOS A= 1.00 M glb S/ 8.00 S/ 3,291.53 S/ 26,332.24 S/ - S/ - S/ - S/ 26,332.24 S/ 26,332.24
13.03 CONCRETO f'c=210 kg/cm2 m3 S/ 6.00 S/ 448.62 S/ 2,691.72 S/ - S/ - S/ - S/ 2,691.72 S/ 2,691.72
13.04 ENCOFRADO Y DESENCOFRADO m2 S/ 5.52 S/ 67.77 S/ 374.09 S/ - S/ - S/ - S/ 374.09 S/ 374.09
13.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 99.20 S/ 7.02 S/ 696.38 S/ - S/ - S/ - S/ 696.38 S/ 696.38
14 6 COMPUERTAS TIPICA DE 0.80 M SEGUN DISEÑO (SAMUDIO, GRADOS, CHUCHON, S/ 21,639.78
MARGARITA KALI, HF-1, JUAN QUISPE)
14.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 8.06 S/ 38.24 S/ 308.21 S/ - S/ - S/ - S/ 308.21 S/ 308.21
14.02 SUMINISTRO E INSTALACION DE COMPUERTA INCLUIDO ACCESORIOS A= 0.80 M glb S/ 6.00 S/ 3,092.37 S/ 18,554.22 S/ - S/ - S/ - S/ 18,554.22 S/ 18,554.22
14.03 CONCRETO f'c=210 kg/cm2 m3 S/ 5.10 S/ 448.62 S/ 2,287.96 S/ - S/ - S/ - S/ 2,287.96 S/ 2,287.96
14.04 ENCOFRADO Y DESENCOFRADO m2 S/ 4.76 S/ 67.77 S/ 322.59 S/ - S/ - S/ - S/ 322.59 S/ 322.59
14.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 23.76 S/ 7.02 S/ 166.80 S/ - S/ - S/ - S/ 166.80 S/ 166.80
15 1 COMPUERTAS TIPICA DE 1.20 M SEGUN DISEÑO (FAJARDO) S/ 4,728.29
15.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.73 S/ 38.24 S/ 66.16 S/ - S/ - S/ - S/ 66.16 S/ 66.16
15.02 SUMINISTRO E INSTALACION DE COMPUERTA INCLUIDO ACCESORIOS A=1.20 M glb S/ 1.00 S/ 3,728.81 S/ 3,728.81 S/ - S/ - S/ - S/ 3,728.81 S/ 3,728.81
15.03 CONCRETO f'c=210 kg/cm2 m3 S/ 1.07 S/ 448.62 S/ 480.02 S/ - S/ - S/ - S/ 480.02 S/ 480.02
15.04 ENCOFRADO Y DESENCOFRADO m2 S/ 5.28 S/ 67.77 S/ 357.83 S/ - S/ - S/ - S/ 357.83 S/ 357.83
15.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 13.60 S/ 7.02 S/ 95.47 S/ - S/ - S/ - S/ 95.47 S/ 95.47
16 1 COMPUERTAS TIPICA DE 1.00 M SEGUN DISEÑO (TOMA MAGALENA) S/ 4,365.65
16.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.92 S/ 38.24 S/ 73.42 S/ - S/ - S/ - S/ 73.42 S/ 73.42
16.02 SUMINISTRO E INSTALACION DE COMPUERTA INCLUIDO ACCESORIOS A=1.00 M glb S/ 1.00 S/ 3,291.53 S/ 3,291.53 S/ - S/ - S/ - S/ 3,291.53 S/ 3,291.53
16.03 CONCRETO f'c=210 kg/cm2 m3 S/ 1.10 S/ 448.62 S/ 493.48 S/ - S/ - S/ - S/ 493.48 S/ 493.48
16.04 ENCOFRADO Y DESENCOFRADO m2 S/ 6.20 S/ 67.77 S/ 420.17 S/ - S/ - S/ - S/ 420.17 S/ 420.17
16.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 12.40 S/ 7.02 S/ 87.05 S/ - S/ - S/ - S/ 87.05 S/ 87.05
17 1 COMPUERTAS TIPICA DE 0.98 M SEGUN DISEÑO (RETENCION MAGALENA) S/ 4,461.21
17.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.44 S/ 38.24 S/ 55.07 S/ - S/ - S/ - S/ 55.07 S/ 55.07
17.02 SUMINISTRO E INSTALACION COMPUERTAS INCLUIDO ACCESORIOS A=0.80 M glb S/ 1.00 S/ 3,490.68 S/ 3,490.68 S/ - S/ - S/ - S/ 3,490.68 S/ 3,490.68
17.03 CONCRETO f'c=210 kg/cm2 m3 S/ 0.91 S/ 448.62 S/ 408.24 S/ - S/ - S/ - S/ 408.24 S/ 408.24
17.04 ENCOFRADO Y DESENCOFRADO m2 S/ 6.20 S/ 67.77 S/ 420.17 S/ - S/ - S/ - S/ 420.17 S/ 420.17
17.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 12.40 S/ 7.02 S/ 87.05 S/ - S/ - S/ - S/ 87.05 S/ 87.05
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
18 109COMPUERTAS
ALCANTARILLA TIPICA
TIPICA DE DE
0.901.20 M X 1.00
M SEGUN M (OLIVA,
DISEÑO ZARATE, PALOMINO,
(RETENCION YUCA) UGARTE, S/ 86,870.58
4,325.69
18.01 PUMA, PEÑA, CANDELARIA,
EXCAVACION OSVALDO
MANUAL DE ZANJAS LEZAMA,
PARA CAMASCA)
CANALETAS m3 S/ 1.49 S/ 38.24 S/ 56.98 S/ - S/ - S/ - S/ 56.98 S/ 56.98
18.02 SUMINISTRO E INSTALACION COMPUERTAS INCLUIDO ACCESORIOS A=0.90 M glb S/ 1.00 S/ 3,371.19 S/ 3,371.19 S/ - S/ - S/ - S/ 3,371.19 S/ 3,371.19
18.03 CONCRETO f'c=210 kg/cm2 m3 S/ 0.87 S/ 448.62 S/ 390.30 S/ - S/ - S/ - S/ 390.30 S/ 390.30
18.04 ENCOFRADO Y DESENCOFRADO m2 S/ 6.20 S/ 67.77 S/ 420.17 S/ - S/ - S/ - S/ 420.17 S/ 420.17
18.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 12.40 S/ 7.02 S/ 87.05 S/ - S/ - S/ - S/ 87.05 S/ 87.05
19 1 COMPUERTAS TIPICA DE 0.82 M SEGUN DISEÑO (PASO BARRIOS) S/ 4,009.07
19.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.18 S/ 38.24 S/ 45.12 S/ - S/ - S/ - S/ 45.12 S/ 45.12
19.02 SUMINISTRO E INSTALACION COMPUERTAS INCLUIDO ACCESORIOS A=0.82 M glb S/ 1.00 S/ 3,112.71 S/ 3,112.71 S/ - S/ - S/ - S/ 3,112.71 S/ 3,112.71
19.03 CONCRETO f'c=210 kg/cm2 m3 S/ 0.84 S/ 448.62 S/ 376.84 S/ - S/ - S/ - S/ 376.84 S/ 376.84
19.04 ENCOFRADO Y DESENCOFRADO m2 S/ 5.84 S/ 67.77 S/ 395.78 S/ - S/ - S/ - S/ 395.78 S/ 395.78
19.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 11.20 S/ 7.02 S/ 78.62 S/ - S/ - S/ - S/ 78.62 S/ 78.62
20 1 COMPUERTAS TIPICA DE 0.50 M SEGUN DISEÑO (PASO HUAMAN) S/ 3,810.72
20.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.49 S/ 38.24 S/ 56.98 S/ - S/ - S/ - S/ 56.98 S/ 56.98
20.02 SUMINISTRO E INSTALACION COMPUERTAS INCLUIDO ACCESORIOS A=0.50 M glb S/ 1.00 S/ 2,894.07 S/ 2,894.07 S/ - S/ - S/ - S/ 2,894.07 S/ 2,894.07
20.03 CONCRETO f'c=210 kg/cm2 m3 S/ 0.84 S/ 448.62 S/ 376.84 S/ - S/ - S/ - S/ 376.84 S/ 376.84
20.04 ENCOFRADO Y DESENCOFRADO m2 S/ 5.84 S/ 67.77 S/ 395.78 S/ - S/ - S/ - S/ 395.78 S/ 395.78
20.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 12.40 S/ 7.02 S/ 87.05 S/ - S/ - S/ - S/ 87.05 S/ 87.05
21 1 COMPUERTAS TIPICA DE 1.90 M SEGUN DISEÑO (BOTADOR CAMACHO) S/ 5,377.04
21.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.44 S/ 38.24 S/ 55.07 S/ - S/ - S/ - S/ 55.07 S/ 55.07
21.02 SUMINISTRO E INSTALACION COMPUERTAS INCLUIDO ACCESORIOS A=1.90 M glb S/ 1.00 S/ 4,186.44 S/ 4,186.44 S/ - S/ - S/ - S/ 4,186.44 S/ 4,186.44
21.03 CONCRETO f'c=210 kg/cm2 m3 S/ 1.00 S/ 448.62 S/ 448.62 S/ - S/ - S/ - S/ 448.62 S/ 448.62
21.04 ENCOFRADO Y DESENCOFRADO m2 S/ 9.10 S/ 67.77 S/ 616.71 S/ - S/ - S/ - S/ 616.71 S/ 616.71
21.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 10.00 S/ 7.02 S/ 70.20 S/ - S/ - S/ - S/ 70.20 S/ 70.20
22 1 COMPUERTAS TIPICA DE 0.85 M SEGUN DISEÑO (BOTADOR CAMACHO CENTRO) S/ 4,184.38
22.01 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS m3 S/ 1.51 S/ 38.24 S/ 57.74 S/ - S/ - S/ - S/ 57.74 S/ 57.74
22.02 SUMINISTRO E INSTALACION COMPUERTAS INCLUIDO ACCESORIOS A=0.85 M glb S/ 1.00 S/ 3,311.02 S/ 3,311.02 S/ - S/ - S/ - S/ 3,311.02 S/ 3,311.02
22.03 CONCRETO f'c=210 kg/cm2 m3 S/ 0.91 S/ 448.62 S/ 408.24 S/ - S/ - S/ - S/ 408.24 S/ 408.24
22.04 ENCOFRADO Y DESENCOFRADO m2 S/ 4.82 S/ 67.77 S/ 326.65 S/ - S/ - S/ - S/ 326.65 S/ 326.65
22.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg S/ 11.50 S/ 7.02 S/ 80.73 S/ - S/ - S/ - S/ 80.73 S/ 80.73
23 CARTEL DE OBRA Y ENSAYOS DE LABORATORIO S/ 2,100.00
23.01 CARTEL DE OBRA und S/ 1.00 S/ 850.00 S/ 850.00 S/ - S/ 850.00 S/ - S/ - S/ 850.00
23.02 PRUEBAS DE CALIDAD (ENSAYO DE COMPRENCION) glb S/ 1.00 S/ 1,250.00 S/ 1,250.00 S/ - S/ 1,250.00 S/ - S/ - S/ 1,250.00
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y CAUCATO DEL DISTRITO DE SAN CLEMENTE -
PROVINCIA DE PISCO - DEPARTAMENTO DE ICA
Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE
Lugar ICA - PISCO - SAN CLEMENTE
PRESUPUESTO DEL PROYECTO CRONOGRAMA VALORIZADO MENSUAL
Item Descripción Und. Metrado Precio S/. MONTO S/. JUNIO JULIO AGOSTO SETIEMBRE PARCIAL S/.
01
24 09 ALCANTARILLA
EQUIPAMIENTO TIPICA DE 1.20ANTE
DE PROTECCION M X 1.00 M (OLIVA, ZARATE, PALOMINO, UGARTE,
COVID S/ 86,870.58
35,709.76
24.01 PUMA,
KIT DEPEÑA, CANDELARIA,
LIMPIEZA OSVALDO
Y DESINFECCIÓN LEZAMA, CAMASCA)
PERSONAL mes S/ 4.00 S/ 3,377.60 S/ 13,510.40 S/ 7,030.76 S/ 2,231.88 S/ 2,231.88 S/ 2,015.89 S/ 13,510.41
24.02 DESINFECCIÓN DE ÁREAS COMUNES mes S/ 4.00 S/ 488.89 S/ 1,955.56 -S/ 200.13 -S/ 213.93 -S/ 213.93 S/ 2,583.54 S/ 1,955.55
24.03 CONTROLES ADMINISTRATIVOS mes S/ 4.00 S/ 2,908.95 S/ 11,635.80 S/ 6,947.59 S/ 1,614.83 S/ 1,614.83 S/ 1,458.55 S/ 11,635.80
24.04 EQUIPAMIENTO DE PROTECCION PERSONAL mes S/ 4.00 S/ 152.00 S/ 608.00 S/ 1,427.23 -S/ 282.18 -S/ 282.18 -S/ 254.87 S/ 608.00
24.05 ELABORACIÓN Y SEGUIMIENTO DE IMPLEMENTACIÓN DEL PLAN COVID mes S/ 4.00 S/ 2,000.00 S/ 8,000.00 S/ 8,000.00 S/ - S/ - S/ - S/ 8,000.00

COSTO DIRECTO S/ 412,596.92 S/ 89,679.13 S/ 123,597.86 S/ 61,444.92 S/ 146,888.60 S/ 421,610.51

GASTOS GENERALES 8% S/ 33,007.75 S/ 7,174.33 S/ 9,887.83 S/ 4,915.59 S/ 11,751.09 S/ 33,728.84


UTILIDAD 7% S/ 28,881.78 S/ 6,277.54 S/ 8,651.85 S/ 4,301.14 S/ 10,282.20 S/ 29,512.74

SUBTOTAL S/ 474,486.46 S/ 103,131.00 S/ 142,137.54 S/ 70,661.66 S/ 168,921.89 S/ 484,852.09


IMPUESTO (IGV 18%) S/ 85,407.56 S/ 18,563.58 S/ 25,584.76 S/ 12,719.10 S/ 30,405.94 S/ 87,273.38

TOTAL PRESUPUESTO S/ 559,894.01 S/ 121,694.58 S/ 167,722.30 S/ 83,380.76 S/ 199,327.84 S/ 572,125.47