ANEXO N° 1

PRESUPUESTO DE OBRA

Obra: FECHA:
CONSTRUCCION PRIMER FASE DE LA OBRA NUEVA IPS LOURDES
FEBRERO 24- 2016

CODIGO DESCRIPCION UNIDAD CANTIDAD VR. UNITARIO VR. TOTAL


1 DEMOLICION EDIFICACION EXISTENTE
10101 CORTE ARBOL MAS RETIRO(INCL.RAICES)H>3.0 UND 2.00 88,180.00 176,360.00
61211 DESMONTE LUMINARIAS UND 45.00 22,350.00 1,005,750.00
100501 DESM.APARATO SANITARIO UND 11.00 18,510.00 203,610.00
100404 DESM.CIELO FALSO ESTRUCIELO M2 244.00 3,280.00 800,320.00
100505 DESM.CUBIERTA ASBESTO CEMENTO M2 106.00 3,720.00 394,320.00
100537 DESM. NAVE METALICA EXISTENTE M2 20.00 6,770.00 135,400.00
100513 DESM.LAVADERO PREFABRICAD UND 1.00 14,810.00 14,810.00
100515 DESM.MARCO + NAVE SENCILLA UND 20.00 13,150.00 263,000.00
100519 DESM.REJA METALICA M2 20.00 9,510.00 190,200.00
100528 DESM.VENTANA - LUCETA EXISTENTE UND 3.00 9,750.00 29,250.00
100521 DESM.VIDRIO M2 42.00 1,960.00 82,320.00
100314 DEMOL.MURO LAD. SOGA M2 540.00 3,650.00 1,971,000.00
100407 DEMOL.PISO BALDOSA+MORTERO M2 197.00 2,020.00 397,940.00
100405 DEMOL.ANDEN/CONTRAPISO CONCRETO E=<7.5CM M2 197.00 2,030.00 399,910.00
100312 DEMOL.MESON CONCRETO M2 10.00 20,000.00 200,000.00
100204 DEMOL.COLUMNA CONCRETO AMARRE ML 48.00 4,620.00 221,760.00
100214 DEMOL.VIGA AMARRE MURO ML 60.00 4,620.00 277,200.00
100206 DEMOL.ESCALERA M2 4.80 31,030.00 148,944.00
100201 DEMOL.CIMIENTO CONCRETO (CR) M3 3.75 101,030.00 378,862.50
100607 RETIRO ESCOMBROS MANUAL-VOLQUETA <=10KM. M3 184.35 15,690.00 2,892,451.50

SUBTOTAL DEMOLICION
10,183,408.00
EDIFICACION EXISTENTE

2 PRELIMINARES
CAMPAMENTO TABLA 54 M2 INCLUYE OBRAS
APU UND 1.00 7,780,378.00 7,780,378.00
HIDROSANITARIAS Y ELECTRICAS
100106 CERRAMIENTO LAMINA GALVANIZADA M2 228.00 21,350.00 4,867,800.00
100113 LOCALIZACION-REPLANTEO OBRA ARQUITECTONICA M2 355.00 2,800.00 994,000.00
SUBTOTAL
13,642,178.00
PRELIMINARES

3 EXCAVACIONES
10203 EXCAVACION A MAQUINA SIN RETIRO M3 1,519.70 2,640.00 4,012,008.00
10207 RELLENO ROCA MUERTA COMPACTADO-CILINDRO M3 292.45 30,470.00 8,910,951.50

SUBTOTAL
MAMPOSTERIA Y 12,922,959.50
REPELLOS

4 CIMENTACION

EXCAVACION, ARMADO DE ACERO, IZAJE Y FUNDICION,


APU ML 80.00 67,216.00 5,377,280.00
PILOTE 40 CM, INCLUYE RETIRO DE MATERIAL SOBRANTE

EXCAVACION, ARMADO DE ACERO, IZAJE Y FUNDICION,


APU ML 50.00 86,900.00 4,345,000.00
PILOTE 50 CM, INCLUYE RETIRO DE MATERIAL SOBRANTE.

EXCAVACION, ARMADO DE ACERO, IZAJE Y FUNDICION,


APU ML 90.00 168,864.00 15,197,760.00
PILOTE 80 CM, INCLUYE RETIRO DE MATERIAL SOBRANTE.

EXCAVACION, ARMADO DE ACERO, IZAJE Y FUNDICION,


PANTALLAS COLADAS, INCLUYE VIGA GUIA, INCLUYE
M3 110.16 437,000.00 48,139,920.00
RETIRO DE MATERIAL SOBRANTE. ESPESOR 0,40 M
LONGITUD 6,0 M

CONSTRUCCION DE VIGA DE AMARRE MUROS COLADOS


APU SECCCION 0,40 M X 0,60 M. NO INCLUYE SUMIISTRO DE M3 14.69 380,000.00 5,582,200.00
MATERIALES

CONSTRUCCION DE CABEZAL CONCRETO 3000 PSI M3 22.15 465,000.00 10,299,750.00

120304 VIGAS DE AMARRE DE CIMENTACION M3 17.09 468,940.00 8,014,184.60

130912 CONCRETO 4000 PSI PARA MURO COLADO M3 110.16 529,710.00 58,352,853.60

SUBTOTAL CIMENTACION 155,308,948.20


5 ESTRUCTURA METALICA
ACERO ESTRUCTURAL A.S.T,M,A-572 GRADO 50 y/o A.S.T.M.
130801 KLS 30,295.26 7,570.00 229,335,115.93
A-36 FABRICACION MONTAJE E INSTALACION
120102 ACERO REFUERZO FLEJADO 37000 PSI 280Mpa KLS 14,407.49 2,940.00 42,358,005.90

SUBTOTAL ESTRUCTURA METALICA 271,693,121.83


6 CONCRETO LOSAS Y PUNTO FIJO
120220 PILOTES EN CONCRETO M3 74.88 459,180.00 34,381,561.68
APU LOSA MACIZA ENTREPISO (ESPESOR=0,10M) M2 391.11 98,000.00 38,328,780.00
APU CONCRETO RELLENO COLUMNAS TIPO H M3 0.85 465,000.00 395,250.00
130912 PANTALLA EN CONCRETO 4000 PSI E=10-30CMS M3 18.20 529,710.00 9,640,722.00
SUBTOTAL CONCRETO LOSAS Y PUNTO FIJO 82,746,313.68

7 BASES - PLACAS - ANDENES


CONTRAPISO E=10cm 3000 PSI+ ALLANADO MECANICO +
APU M2 203.77 50,548.00 10,300,165.96
SIKA ENDURECEDOR

RAMPA EN CONCRETO 3000PSI E=10CM.ESTRIADO Y


APU M2 88.68 67,831.00 6,015,253.08
ESCOBILLADO
APU DILATACIONES CON CORTE SOBRE CONTRAPISOS ML 90.00 5,950.00 535,500.00
130702 LOSA PARA DESCANSOS EN CONCRETO MACIZA E=10CM M2 2.70 62,980.00 170,046.00
200108 ALISTADO PISO 5 CM M2 391.11 25,950.00 10,149,304.50

SUBTOTAL BASES -
27,170,269.54
PLACAS - ANDENES

8 MAMPOSTERIA Y REPELLOS
MURO ESTRUCTURAL EN BLOQUE DE ARCILLA DE
APU M2 65.70 52,004.00 3,416,662.80
12X24X6CM
190109 REPELLO MURO 1:3 M2 131.40 16,550.00 2,174,670.00
190108 REPELLO MURO 1:3 LINEAL ML 24.00 11,070.00 265,680.00
131214 CONCRETO MURO-DOVELAS 3100PSI-420MPA M3 1.50 299,620.00 449,430.00

SUBTOTAL
MAMPOSTERIA Y 6,306,442.80
REPELLOS

9 INSTALACIONES ELECTRICAS - VOZ Y DATOS - AA


170131 CABLE COBRE THWN# 6 ML 9.00 10,880.00 97,920.00
170133 CABLE COBRE THWN# 10 ML 19.23 5,550.00 106,726.50
170134 CABLE COBRE THWN# 12 ML 4,084.59 3,750.00 15,317,212.50
170135 CABLE COBRE THWN# 14 ML 12.00 2,800.00 33,600.00
APU TUBO EMT 3MT X1/2" ML 52.61 8,965.00 471,648.65
APU TUBO EMT 3MT X1" ML 0.00 14,940.00 -
APU TUBO EMT 3MT X2" ML 32.45 24,611.00 798,626.95
APU ACOMETIDA E. 2F (3X#8+1X#10) 1"EMT ML 57.36 41,522.00 2,381,701.92
APU CAJAS DE PASO 25 X 25 UND 64.00 35,832.00 2,293,248.00
APU UNION 1/2" EMT" UND 194.00 1,664.00 322,816.00
APU UNION 1" EMT" UND 0.00 1,956.00 -
APU UNION 2" EMT" UND 14.00 3,056.00 42,784.00
APU CURVA EMT MET 1/2" UND 5.00 2,306.00 11,530.00
APU CURVA EMT MET 2" UND 3.00 13,056.00 39,168.00
APU DIGITURNO UND 1.00 458,820.00 458,820.00
APU SAL SWITCHE SC RAYOS X UND 2.00 45,000.00 90,000.00
APU SAL TOMA 1F (C/T/A:2#12+1#14/TOMA) UND 32.00 64,336.00 2,058,752.00
51012 SAL TOMA 1F (C/T/A/TO:REGULADO P&S) UND 10.00 65,080.00 650,800.00
APU SAL TOMA 1F (C/T/A:3#12/TOMA)ZONA HUMEDA UND 6.00 94,840.00 569,040.00
APU SAL SWITCHE S1 (C/T/A:2#12/S1) UND 12.00 63,089.00 757,068.00
APU SAL SWITCHE S2 (C/T/A:3#12/S2) UND 11.00 81,927.00 901,197.00
APU SAL SWITCHE S3 (C/T/A:4#12/S3) UND 1.00 99,953.00 99,953.00
APU SAL SWITCHE SC (C/T/A:3#12/SC) UND 2.00 79,706.00 159,412.00
APU MARCO METALICO LAMPARA UND 8.00 15,718.00 125,744.00
APU SAL LAMP (C/T/A:2#12+1#14)Ó3/4"EMT UND 59.00 72,915.00 4,301,985.00

APU LAMPARA PANEL LED DE EMPOTRAR 60X60X11 CUADRADA UND 8.00 341,708.00 2,733,664.00

APU LAMPARA CIRCULAR DE EMPORTRAR D=20CM UND 10.00 161,751.00 1,617,510.00


APU LAMPARA LED LONGITUDINAL DE EMPOTRAR UND 41.00 318,986.00 13,078,426.00
APU TABLERO DE BREAKERS AQD 24 CIRCUITOS UND 4.00 425,000.00 1,700,000.00
APU TABLERO DE BREAKERS AQD 12 CIRCUITOS UND 4.00 315,000.00 1,260,000.00
170813 BREAKER 1F DESDE 15 HASTA 60 AMP UND 29.00 33,150.00 961,350.00
170802 BREAKER 2F DESDE 15 HASTA 60 AMP UND 15.00 75,540.00 1,133,100.00
170824 BREAKER 3F DESDE 15 HASTA 60 AMP UND 1.00 63,290.00 63,290.00
APU BANDEJA PORTA CABLES 25CM ML 27.72 78,444.00 2,174,467.68
APU ABRAZADERA RIEL CHANEL UND 27.00 8,549.00 230,823.00
APU ANCLAJE SOPORTE VARILLA ROSCADA 3/8" UND 54.00 14,805.00 799,470.00
APU CABLE UTP CAT 7 ML 294.32 7,226.00 2,126,756.32
APU FACE PLATE UND 8.00 7,939.00 63,512.00
APU JACK RJ45 CAT 7 UND 16.00 27,563.00 441,008.00
APU PATCH CORD UND 16.00 11,129.00 178,064.00
APU CERTIFICACION PUNTO RED CAT 7 UND 16.00 15,078.00 241,248.00
APU PATCH PANEL 24 10/100/1000 CAT 7 UND 1.00 1,023,750.00 1,023,750.00
APU SWITCHE 24 PUERTOS CAT 7 UND 1.00 2,457,263.00 2,457,263.00
APU RACK 60X 80 X 45 UND 1.00 778,680.00 778,680.00
160727 ABRAZADERA GALVANIZADA .1/2" UND 52.00 2,110.00 109,720.00
160729 ABRAZADERA GALVANIZADA 1" UND 0.00 2,440.00 -
160732 ABRAZADERA GALVANIZADA 2" UND 32.00 3,030.00 96,960.00
APU UPS 10000 VA UND 1.00 3,154,200.00 3,154,200.00
APU TABLERO GENERAL UND 1.00 3,447,000.00 3,447,000.00
APU MALLA A TIERRA 3 VARILLAS-PERNADA UND 1.00 1,301,974.00 1,301,974.00
APU MEDIDOR 220 3F UND 1.00 1,624,200.00 1,624,200.00
SUBTOTAL INST
74,886,189.52
ELECTRICAS

10 REDES SANITARIAS
Suministro, transporte e instalacion de tuberia PVC Sanitaria ( Incluye soldadura y limpiador PVC), en los siguientes diametros :
110303 Tubería PVC Sanitaria, 4" ML 300.00 22,520.00 6,756,000.00
APU UNION SANITARIA PVC CC-4" UND 32.00 9,792.00 313,344.00
150104 Suministro Tubería PVC Sanitaria, 2" ML 32.00 12,580.00 402,560.00
150105 Suministro Tubería PVC Ventilación, 2" ML 16.00 9,490.00 151,840.00
160733 ANCLAJE - SOPORTE TUBERIA UND 16.00 22,210.00 355,360.00
APU ACCESORIOS 2" PVC-S UND 30.00 8,063.06 241,891.93
APU ACCESORIOS 4" PVC-S UND 12.00 15,837.50 190,050.05
APU CAJA 100X100 UND 4.00 316,693.22 1,266,772.87
APU REJILLA SOTANO ML 9.00 125,000.00 1,125,000.00
APU CAMARA TIPO B 1.0 UND 1.00 1,350,000.00 1,350,000.00
APU TUBERIA ALCANTARILLADO 6" ML 15.70 46,825.35 735,158.03
APU TUBERIA ALCANTARILLADO 4" ML 17.00 25,435.97 432,411.44
APU BOMBA SUGERGIBLE 2 HP - ADT 5 M UND 1.00 1,429,819.07 1,429,819.07
Suministro, transporte e instalacion de Puntos sanitarios en tuberia PVC Sanitaria ( Incluye niples de tuberia, codos, soldadura, limpiador ), en los
siguientes diametros :
150506 Punto sanitario , 4" UND 6.00 48,910.00 293,460.00
150502 Punto sanitario , 2" UND 13.00 22,930.00 298,090.00
150323 Punto sanitario sifon de piso , 2" UND 5.00 6,180.00 30,900.00
160733 ANCLAJE - SOPORTE TUBERIA VERTICAL UND 4.00 22,210.00 88,840.00
Suministro, transporte e instalacion de tuberia PVC Sanitaria para recoleccion de aguas lluvias provenientes de las cubiertas. (Incluye soldadura y
limpiador) en los siguientes diametros :
APU Tubería PVC Sanitaria, 4" aguas lluvias- BALL-4 ML 12.00 35,353.85 424,246.19
APU ACCESORIOS SANITARIO PVC -S4" UND 8.00 15,837.50 126,700.03
APU Tubería PVC Sanitaria, 6" -aguas lluvias ML 10.00 67,699.06 676,990.56
APU ACCESORIOS SANITARIO PVC -S6" UND 8.00 78,159.10 625,272.77
APU ANCLAJE - SOPORTE TUBERIA UND 4.00 24,013.00 96,052.00
APU CAJA DE 100X100 UND 1.00 316,693.22 316,693.22
PUNTOS SANITARIOS: Suministro, transporte e instalacion de Punto sanitario para AGUAS LLUVIAS en tuberia PVC Sanitaria ( Incluye niples de tuberia,
codo, soldadura, limpiador y sifon )
150506 Punto sanitario , 4" UND 8.00 48,910.00 391,280.00
APU Punto sanitario , 6" UND 6.00 78,159.10 468,954.58
APU TAPA CAJA MARCO ANGULO 1,00X1,00 UND 5.00 121,700.00 608,500.00
11 INSTALACIONES RED CONTRA INCENDIOS
160410 EXTINTOR ABC-10 LB UND 6.00 78,770.00 472,620.00
160409 EXTINTOR CO2-10 LB UND 2.00 942,370.00 1,884,740.00

SUBTOTAL INST
21,553,546.75
HIDROSANITARIO

12 INSTALACIONES HIDRAULICAS
Suministro, transporte e instalacion de tuberia PVC Presion E.L RDE 21 (Incluye accesorios PVC, soldadura, limpiador), en los siguientes diametros :
APU 2" TUBERIA PVC- UZ RDE-21 ML 16.00 22,895.86 366,333.74
160516 1.1/2" TUBERIA PVC- UZ RDE-21 ML 19.00 11,110.00 211,090.00
APU 1" TUBERIA PVC- UZ RDE-21 ML 14.00 7,492.35 104,892.85
APU 3/4" TUBERIA PVC- UZ RDE-21 ML 21.00 5,417.71 113,771.99
APU 1/2" TUBERIA PVC- UZ RDE-9 ML 120.00 4,740.47 568,856.45
10106 LOCALIZACION-REPLANTEO ML 70.00 1,380.00 96,600.00
60810 EXCAVACION A MANO M3 12.00 9,880.00 118,560.00
100612 RELLENO ARENA FINA TUBERIA ML 8.00 34,830.00 278,640.00
100618 RELLENO MATERIAL SITIO COMPACATADO-SALTARIN ML 2.00 11,330.00 22,660.00
100622 RETIRO DE SALDOS EN SITIO M3 14.00 5,300.00 74,200.00
160413 ANCLAJE - SOPORTE TUBERIA UND 32.00 22,210.00 710,720.00
160801 PUNTO HIDRAULICO 1/2" UND 25.00 29,050.00 726,250.00
160803 PUNTO HIDRAULICO 1" UND 5.00 34,080.00 170,400.00
160802 PUNTO HIDRAULICO 3/4" UND 3.00 31,730.00 95,190.00
APU ANCLAJE - SOPORTE TUBERIA VERICAL UND 8.00 29,508.60 236,068.80
APU VALVULA DE PASO RED - WHITE 1 1/2" UND 2.00 101,863.93 203,727.86
APU VALVULA DE PASO RED - WHITE 1" UND 4.00 68,336.53 273,346.13
APU VALVULA DE PASO RED - WHITE 1/2" UND 13.00 36,516.00 474,708.00
40701 PRUEBA HIDRAULICA A TUBERIA PVC PRESION ML 190.00 1,920.00 364,800.00
60810 EXCAVACION A MANO M3 17.00 9,880.00 167,960.00
APU RELLENO CON MATERIAL DE SITIO TANQUE M3 1.00 12,333.84 12,333.84
131304 MURO CONCRETO TANQUE SUBTERRANEO 4000PSI M3 14.40 642,260.00 9,248,544.00
APU LOSA M3 1.80 268,186.00 482,734.80
APU ACERO DE REFUERZO KG 850.00 3,520.00 2,992,000.00
APU TAPAS EN ALFAJOR 80X80 UND 2.00 250,045.00 500,090.00
APU POLLOS EN CONCRETO PARA BOMBAS 1.0X1.0 UND 2.00 45,527.00 91,054.00
APU PASES EN MUROS ACERO INOX EQUIPO DE BOMBEO UND 2.00 92,100.00 184,200.00
APU BOMBAS PRESION 40-60 Q= 40 GPM Y E INSTALACION GLB 2.00 5,500,000.00 11,000,000.00
APU CAJA MEDIDOR + MEDIDOR 1" UND 1.00 1,157,688.12 1,157,688.12
APU ACOMETIDA 1" UND 1.00 562,868.64 562,868.64
APU REJA ESLABONADA M2 12.00 25,950.00 311,400.00
IMPERMEABILIZACION EPOXICO MURO TANQUE AGUA
APU M2 27.00 120,000.00 3,240,000.00
POTABLE

SUBTOTAL
INSTALACIONES 35,161,689.21
HIDRAULICAS

13 DIVISIONES
240419 MURO 1-BOARD 8MM 1-BOARD 8MM M2 229.40 62,580.00 14,355,852.00
240432 MURO 1-BOARD 10MM 1-CARA M2 25.55 36,410.00 930,156.80
240437 ESTRUC.MURO BOARD [CANAL-PARAL] 89MM C20 M2 229.40 37,520.00 8,607,088.00
240402 MURO CARTERA SUPERBOARD 10 MM ML 23.25 20,670.00 480,577.50
240444 ESTRUCT.DINTEL BOARD[OMEGA-ANG]92MM C20 ML 23.25 23,520.00 546,840.00

SUBTOTAL DIVISIONES 24,920,514.30

14 ESTUCOS Y PINTURAS
290109 ESTUCO MUROS PLASTICO M2 875.51 5,330.00 4,666,468.30
290112 ESTUCO MUROS PLASTICO LINEAL ML 65.12 4,350.00 283,278.00
APU PINTURA HIDRORREPELENTE COLOR BLANCO [2M] M2 918.60 4,856.00 4,460,721.60
290210 URETANO SIKA MUROS M2 191.00 24,840.00 4,744,439.52
290213 URETANO SIKA CIELOS M3 61.50 26,660.00 1,639,651.48
290619 PINTURA KORAZA [3M] M2 827.25 7,190.00 5,947,935.00
PINTURA REFLECTIVA COLOR BLANCO SEÑALIZACION
APU ML 65.00 1,658.00 107,770.00
PARQUEADEROS

SUBTOTAL
ESTUCOS Y 21,850,263.90
PINTURAS

15 REVESTIMIENTOS ESPECIALES

REVESTIMIENTO SCREEN PANEL PERFORADO HUNTER


APU DOUGLAS O SIMILAR. INCLUYE ESTRUCTURA, M2 77.40 617,539.00 47,797,518.60
TRANSPORTE, FABRICACION E INSTALACION.
MESON POLICUARZO A=0.50-0.60 M E=1CM. INCLUYE
APU ML 4.85 397,666.00 1,928,680.10
ESTRUCTURA DE SOPORTE

SUBTOTAL
REVESTIMIENTOS 49,726,198.70
ESPECIALES

16 PISOS Y ENCHAPES
200421 PISO PAÑOS DE GRANITO PULIDO #2. M2 35.00 66,300.00 2,320,500.00
200440 BALDOSA GRANO # 4-5 40X40 M2 441.00 83,470.00 36,810,270.00
APU DILATACIONES EN ALUMINIO PARA PISO ML 120.00 6,976.00 837,120.00
200819 GUARDAESCOBA GRANITO 1/2 C + DIL. PLAST. ML 191.50 28,140.00 5,388,810.00
200414 CENEFA GRANITO PULIDO #2. A<=60CM ML 18.75 31,130.00 583,687.50
APU SIKAFLEX 1CSL A=8-10MM H=10MM ML 85.33 10,840.00 925,013.33
ENCHAPE PARED TIPO EGEO BLANCO DE 30X60CM H:
APU M2 91.80 55,342.00 5,080,395.60
2,40M
APU MURO PLOMADO 2MM M2 19.98 378,400.00 7,560,432.00
260120 VIDRIO PLOMADO BLINDADO 24 MM (20*30) UND 1.00 643,450.00 643,450.00
SUBTOTAL PISOS Y
60,149,678.43
ENCHAPES

17 CUBIERTAS E IMPERMEABILIZACIONES
JARDIN PARA ODONTOLOGIA INC. SISTEMA DE RIEGO POR
APU M2 12.00 100,116.00 1,201,392.00
ASPERSION EJECUTABLE.
180310 IMPERM.MANTO 500XT-FOIL ALUMINIO M2 25,330.00 -

LUCARNAS SEGUN DISEÑO ARQUITECTÓNICO DE ANCHO


PROM: 1.0.M Y H: 1.80M. EN CONCRETO PARTE SUPERIOR
APU UND 1,185,090.00 -
Y BOARD 10MM DESCOLGADO INCL. ESTRUCTURA Y
VIDRIO. ACABADO EN PINTURA KORAZA

180919 LAMINA POLICARBONATO ALVEOLAR 10MM M2 32.00 84,130.00 2,692,160.00


190304 PEND.IMPERMEAB. 5 CM MORT 1:3 M2 0.00 25,510.00 -

SUBTOTAL CUBIERTAS E
3,893,552.00
IMPERMEABILIZACIONES

18 CIELO FALSO
180410 C.F.PANEL YESO 12.7MM S.JUNTA+VINILO M2 274.00 39,200.00 10,740,800.00
APU ESTRUCTURA CIELO M2 274.00 21,000.00 5,754,000.00
180405 CARTERA PANEL YESO 12.7MM S.JUNTA+VINILO ML 64.27 33,430.00 2,148,546.10
APU MOLDURAS MEDIA CAÑA EN YESO PARA CIELOS ML 95.75 40,852.00 3,911,579.00
SUBTOTAL CIELO FALSO 22,554,925.10

119 CARPINTERIA DE ALUMINIO

PUERTA P1 PUERTA EN ALUMINIO INCL. ZOCALO EN


ALUMINIO ANODIZADO NATURAL - VIDRIO TEMPLADO
APU M2 7.83 389,296.00 3,048,187.68
OPALIZADO ESPESOR 10MM, MANIJA TIPO ROMA DE 0.30 X
3/4" PIVOTE EN PISO Y TECHO

APU PUERTA P2. CORTAFUEGO PRESURIZADA M2 3.00 765,300.00 2,295,900.00

PUERTA P3 DOBLE ZOCALO EN ALUMINIO ANODIZADO


NATURAL VIDRIO TEMPLADO Y OPALIZADO, ESPESOR
APU M2 7.00 393,002.00 2,751,014.00
10MM, MANIJA HORIZONTAL DEL ANCHO DE LA PUERTA
TIPO ROMA DE 3/4" PIVOTE EN PISO TECHO

PUERTA P4 UNA NAVE ZOCALO EN ALUMINIO ANODIZADO


NATURAL VIDRIO TEMPLADO Y OPALIZADO, ESPESOR
APU M2 7.00 405,497.00 2,838,479.00
10MM, MANIJA HORIZONTAL DEL ANCHO DE LA PUERTA
TIPO ROMA DE 3/4" PIVOTE EN PISO TECHO

PUERTA P5 UNA NAVE ZOCALO EN ALUMINIO ANODIZADO


NATURAL VIDRIO TEMPLADO Y OPALIZADO, ESPESOR
APU M2 10.00 405,497.00 4,054,970.00
10MM, MANIJA HORIZONTAL DEL ANCHO DE LA PUERTA
TIPO ROMA DE 3/4" PIVOTE EN PISO TECHO

PUERTA P6 CORREDERA DOBLE ZOCALO EN ALUMINIO


ANODIZADO NATURAL VIDRIO TEMPLADO ESPESOR 10MM
APU M2 7.00 449,124.00 3,143,868.00
+ VINILICO LAVABLE, MANIJA TIPO ROMA DE 0.30M X 3/4"
GUIA SUPERIOR EN ALUMINIO

VENTANA V1 - V2. VIDRIO TEMPLADO 10MM A JUNTA


PERDIDA + ESTRUCTURA SOPORTE PISO A TECHO
APU M2 60.00 441,690.00 26,501,400.00
TUBULARES 3X2" DE ALUMINIO NATURAL + ACCESORIO EN
ACERO INOX. CUERPO CENTRAL BASCULANTE H: 0.60

APU DIV.ALUMINIO - VIDRIO CORREDIZA M2 7.00 253,397.00 1,773,779.00

SUBTOTAL CARPINTERIA
46,407,597.68
DE ALUMINIO

20 CARPINTERIA MADERA
PUERTA PLEGABLE PVC HOGGAN COLOR MILANO NOGAL
18,1 M2 4.50 242,575.00 1,091,587.50
ANCHO: 0.60-1.00M Y ALTURA:2.0M.

VIGAS DE REFUERZOS EN MADERA CHANUL PARA


18,2 ML 30.00 10,309.00 309,270.00
SOPORTE EN MUROS DE BOARD
SUBTOTAL CARPINTERIA
1,400,857.50
MADERA

21 BARANDAS
PASAMANOS EN ACERO INOXIDABLE DE 3" ANCLAJE A
APU ML 11.00 377,178.00 4,148,958.00
MURO

PASAMANOS TIPO B-01. EN ACERO INOXIDABLE DE 3". CAL.


18 + VIDRIO TEMPLADO CRISTAL CLARO DE 10MM +
PELICULA DE SEGURIDAD, EMPATES ENTRE VIDRIO A
APU ML 839,784.00 -
JUNTA PERDIDA. TUBULAR VERTICAL DE ACERO INOX. DE
3" + SOPORTES Y DILATADORES DE ACERO INOX. +
PLATINA EN U DE SOPORTE DEL VIDRIO ANCLADA A PISO

BARRA EN ACERO INOXIDABLE ∅11/2 PARA


DISCAPACITADOS FIJADA A PISO Y PARED, EN ACERO
APU INOXIDABLE SATINADO, CON TORNILLOS ESCONDIDOS, JGO 1.00 504,161.00 504,161.00
PARA INSTALAR DERECHA O IZQUIERDA MARCA
ACCESORIOS Y ACABADOS O SIMILAR

SUBTOTAL BARANDAS 4,653,119.00

22 DOTACIONES
SANITARIO LINEA INSTITUCIONAL COLOR BLANCO REF.
APU JGO 4.00 760,748.00 3,042,992.00
ERIE DE CORONA O SIMILAR + VALVULA ANTIVANDALICA.

LAVAMANOS LINEA INSTITUCIONAL COLOR BLANCO TIPO


APU FREE ANTIBACTERIAL REF. 00389A001 DE CORONA O UND 10.00 296,050.00 2,960,500.00
SIMILAR

250530 GRIFO LAVAMANOS PUSH PARED - DOCOL UND 10.00 146,120.00 1,461,200.00
250419 ORINAL COLBY PLUS MEDIANO - ALFA UND 0.00 162,350.00 -
APU GRIFO PUSH ORINAL COMPLETA UND 0.00 184,630.00 -
SECADORES MANOS LIBRES SENSOR ABS CROMADO TIPO
APU UND 10.00 510,740.00 5,107,400.00
AC-CS400X LOSDI O SIMILAR

DISPENSADOR DE TOALLAS DE PAPEL EN ACERO


APU INOXIDABLE 304, CON LLAVE CAPACIDAD 1 PAQUETE TIPO UND 10.00 152,652.00 1,526,520.00
BRADLEY O SIMILAR

DISPENSADOR DE PAPEL HIGIENICO EN ACERO INOX. 304.


APU UND 4.00 126,153.00 504,612.00
200M CON LLAVEREF. AC-DP200 BRADLEY O SIMILAR

DISPENSADOR DE JABON LIQUIDO EN ACERO INOX. TIPO


APU UND 10.00 95,229.00 952,290.00
AC-6542 CON LLAVE BRADLEY O SIMILAR
250503 DUCHA MEZCLADORA GRIV L PRISMA-GALAX (M) UND 1.00 90,460.00 90,460.00
DUCHA CROMADA MONOCONTROL REF. AC-2675501 PARA
APU UND 1.00 435,110.00 435,110.00
PMR
250515 LLAVE AUTOMATICA MESA - CROMO UND 1.00 124,870.00 124,870.00
APU LAVAMANOS A.INOX. 50X 60CM UND 1.00 97,480.00 97,480.00
LAVAMANOS EN ACERO INOX. TIPO 304 CON SISTEMA DE
APU UND 1.00 2,286,421.00 2,286,421.00
RODILLA 400X295X220MM
APU LAVATRAPEADOR LADRILLO - ENCHAPADO UND 1.00 244,979.00 244,979.00

SUBTOTAL DOTACIONES 18,834,834.00

23 PAVIMENTO CONCRETO RIGIDO


080207 SUB-BASE COMPACT.MAT.SELECC.(TIPO INVIAS) M3 91.20 72,250.00 6,589,200.00
080301 PAV.CONCR MR=36 E=0.15,INC.JUNTA M2 228.00 57,300.00 13,064,400.00
080521 SARDINEL EN CONCRETO 40X15 TRAPEZOIDAL ML 45.00 42,480.00 1,911,600.00

SUBTOTAL PAVIMENTO
21,565,200.00
CONCRETO RIGIDO

24 OBRAS COMPLEMENTARIAS
TOPELLANTAS DE CONCRETO PREFABRICADOS 0,70 0,20,
APU UND 12.00 37,102.00 445,224.00
h= 15 cm

ALCORQUE CUADRADO/CIRCULAR CONTENEDOR DE


APU UND 1.00 95,149.00 95,149.00
RAICES PREFABRICADO

REJILLA PARA CANAL ANGULO 1X1/ 8-PLAT 1X3/16.


APU ML 6.00 135,429.00 812,574.00
ACABADO PINTURA ELECTROSTÁTICA GRIS

REJILLA MARCO TUBULAR 3X2" LAMINA CAL.20 Y


APU TUBULARES REDONDOS DE 1/2". INCLUYE ANTICORROSIVO ML 5.66 397,126.00 2,248,368.56
Y ACABADO POLIURETANO BLANCO SEMIMATE. A:1.00M

SUBTOTAL OBRAS
3,601,315.56
COMPLEMENTARIAS

25 ZONAS VERDES
APU VEGETACION TIPO BAMBUSA UND 60.00 28,329.00 1,699,740.00
100617 RELLENO GRAVA TRITURADA-POLVILLO [S.COM] M3 14.00 47,440.00 664,160.00
APU ARBOL TIPO ALMENDRO PORTE MEDIO UND 3.00 49,029.00 147,087.00
SUMINISTRO E INSTALACION TIERRA AGRICOLA PARA
300220 M3 28.00 51,320.00 1,436,960.00
JARDIN SECO
SUBTOTAL ZONAS
3,947,947.00
VERDES

26 MUEBLES PREFABRICADOS

PUESTO PARA CONSULTORIO DE 1.20X0.60M


CONFORMADO POR SUPERFICIE DE TRABAJO 1.20X0.60M,
APU ARCHIVADOR PEDESTAL 2X1 ELABORADO EN LAMINA UND 8.00 484,299.00 3,874,392.00
COLD ROLLED, SOPORTE DOBLE TUBO CON ACABADO EN
PINTURA ELECTROSTÁTICA.

MODULO DE RECEPCION Y CONTROL PARA DOS


USUARIOS DE 3.40X1.50M DE FONDO CONFORMADO POR
FRENTE DE RECEPCION ENTAMBORADO CON ENCHAPE EN
FORMICA Y DILATADORES EN ALUMINIO, AREA DE
ATENCIÓN ELABOADA EN TABLEX DE 30MM CON ENCHAPE
APU EN FÓRMICA Y BORDE EN PVC, SUPERFICIE DE TRABAJO UND 1.00 4,543,600.00 4,543,600.00
EN TABLEX 30MM CON ENCHAPE EN FORMICA Y BORDE EN
PVC, DOS CAJONEROS 2X1 ELABORADO EN LAMINA COLD
ROLLED CON ACABADO EN PINTURA ELECTROSTÁTICA,
DOS PUERTAS DE ACCESO CON CHAPA DE SEGURIDAD DE
0.90X1.00M DE ALTURA.

PUESTO MICRO DE 1.50X1.50M CONFORMADO POR


SUPERFICIE DE TRABAJO MICRO DE 1.50X0.90M,
APU SUPERFICIE DE 0.60X0.60. ARCHIVADOR PEDESTAL 2X1 EN UND 3.00 609,079.00 1,827,237.00
LAMINA COLD ROLLED, SOPORTES DOBLE TUBO CON
ACABADO PINTURA ELECTROSTÁTICA

MODULO DE DIVISION DE 1.50X1.35M, ESTRUCTURA EN


LAMINA COLD ROLLED CON ACABADO EN PINTURA
ELECTROSTATICA, ZOCALO INFERIOR QUE PERMITE EL
APU UND 3.00 419,017.00 1,257,051.00
PASO DE CABLEADO ELECTRICO DE VOZ Y DATOS,
PANELES ENTAMBORADOS TAPIZADOS EN PROQUINAL Y
MARCO VIDRIOS SUPERIORES CON VIDRIO CLARO 4MM.

ESTACIÓN DE TOMA DE MUESTRAS, CONFORMADO POR


CUATRO SUPERF. EN TABLEX 30MM CON ENCHAPE EN
FÓRMICA Y BORDE EN PVC, CINCO SOPORTES
APU UND 1.00 1,168,568.00 1,168,568.00
ENTAMBORADOS EN LÁMINA COLD ROLLED ACABADO EN
PINTURA ELECTROSTÁTICA, TRES SEPARADORES EN
VIDRIO TEMPLADO INCL. ACCESORIOS EN ACERO INOX.
SUBTOTAL MUEBLES
12,670,848.00
PREFABRICADOS

COSTOS INDIRECTOS

TOTAL COSTOS DIRECTOS 1,007,751,918

ADMINISTRACION 20.00% 201,550,384

IMPREVISTOS -
UTILIDAD 9.00% 90,697,673
TOTAL AIU 29.00% 292,248,056
IVA SOBRE LA
UTILIDAD

VALOR TOTAL
PRESUPUESTO 1,299,999,974
ANEXO N° 1- A
PRESUPUESTO DE OBRA

FECHA:
Obra: CONSTRUCCION PRIMER FASE DE LA OBRA NUEVA IPS LOURDES
1-Apr-2016

27 ESTRUCTURA METALICA

13080 ACERO ESTRUCTURAL A.S.T,M,A-572 KLS 21,541.10 7,570.00 163,066,099.75


1 GRADO 50 y/o A.S.T.M. A-36
FABRICACION MONTAJE E
INSTALACION
SUBTOTAL ESTRUCTURA METALICA 163,066,099.75

28 CONCRETO LOSAS Y PUNTO FIJO

APU LOSA MACIZA ENTREPISO M2 288.45 98,000.00 28,268,100.00


(ESPESOR=0,10M) TERCER PISO
12010 ACERO REFUERZO FLEJADO 37000 KLS 1,200.00 2,940.00 3,528,000.00
2 PSI 280Mpa
SUBTOTAL CONCRETO LOSAS 31,796,100.00

29 AIRES ACONDICIONADO

APU Sistema de Aire Acondicionado TONELADAS 12.00 8,500,000 102,000,000.00


refrigeracion Variable de 12 TR. Incluye
Equipos, mano de obra, izada de
equipos, materiales (Tuberia, cableado
de control, ducteria, soldadura etc.)
30 AIRES ACONDICIONADO 102,000,000.00
31 EXCAVACIONES

10060 RETIRO SOBRANTES MAQUINA M3 515.00 14,820.00 7,632,300.00


8 <=10KM.
SUBTOTAL EXCAVACION 7,632,300

32 REDES SANITARIAS

15050 Punto sanitario , 4" UND 9.00 48,910.00 440,190.00


6
15050 Punto sanitario , 2" UND 19.00 22,930.00 435,670.00
2
15032 Punto sanitario sifon de piso , 2" UND 7.00 6,180.00 43,260.00
3
11030 Tubería PVC Sanitaria, 4" ML 150.00 22,520.00 3,378,000.00
3
15010 Suministro Tubería PVC Sanitaria, 2" ML 30.00 12,580.00 377,400.00
4
15010 Suministro Tubería PVC Ventilación, 2" ML 8.00 9,490.00 75,920.00
5
16073 ANCLAJE - SOPORTE TUBERIA UND 8.00 22,210.00 177,680.00
3
16051 1.1/2" TUBERIA PVC- UZ RDE-21 ML 19.00 11,110.00 211,090.00
6
SUBTOTAL INST HIDROSANITARIO 5,139,210.00

33 ESTUCOS Y PINTURAS

29010 ESTUCO CIELOS PLASTICO M2 166.70 6,150.00 1,025,205.00


6
SUBTOTAL ESTUCOS Y PINTURAS 1,025,205.00

COSTOS INDIRECTOS

TOTAL COSTOS DIRECTOS 310,658,915

ADMINISTRACION 20.00% 62,131,783

IMPREVISTOS

UTILIDAD 9.00% 27,959,302

TOTAL AIU 29.00% 90,091,085

IVA SOBRE LA UTILIDAD

VALOR TOTAL
PRESUPUESTO $400,750,000°°
GRAN TOTAL PRESUPUESTO: $ 1.700.749.974°°