ITEM DESCRIPCION UNIDADMETRADO PRECIO (S.) PARCIAL (S.) MES 1 MES 2 MES 3 TOTAL
01.01.04 SERVICIOS HIGIENICOS DE OBRA (CONTENEDORES) mes 3.00 6,100.00 18,300.00 S18,300.00 S18,300.00
01.02.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA, EQUIPO Y HERRAMIENT glb 1.00 11,932.54 11,932.54 S11,932.54 S11,932.54
01.02.04 TRAZO Y REPLANTEO DURANTE EL PROCESO mes 1,540.00 8.68 13,367.20 S13,367.20 S13,367.20
01.02.05 CARTEL DE IDENTIFICACION DE OBRA: 3.60x2.40m und 2.00 495.78 991.56 S991.56 S991.56
01.03.01 CORTE DE TERRENO CON MAQUINARIA m3 806.60 6.15 4,960.59 S4,960.59 S4,960.59
01.03.02 CORTE Y EXCAVACION EN FORMA MANUAL m3 57.00 40.72 2,321.04 S2,321.04 S2,321.04
01.03.04 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 1,012.00 4.02 4,068.24 S4,068.24 S4,068.24
01.04.01 EXTRACCION Y APILONAMIENTO DE MATERIAL DE SUBRASANTE m3 506.00 36.94 18,691.64 S18,691.64 S18,691.64
01.05.01 EXTRACCION Y APILONAMIENTO DE MATERIAL PARA SUB BASE m3 379.50 37.27 14,143.97 S14,143.97 S14,143.97
01.05.04 CONFORMACION DE SUB BASE CON EQUIPO m3 379.50 10.45 3,965.78 S3,965.78 S3,965.78
01.06.01 CONEXION ENTRE LOSAS RIGIDAS (PAVIMENTO) S/D und 672.00 15.36 10,321.92 S10,321.92 S10,321.92
01.06.02 ENCOFRADO Y DESENCOFRADO PAVIMENTO RIGIDO m2 49.68 44.74 2,222.68 S2,222.68 S2,222.68
01.06.03 LOSAS MACISAS - CONCRETO f'c=210 kg/cm2 m2 1,012.00 104.00 105,248.00 S105,248.00 S105,248.00
01.06.04 JUNTA DEDILATACION CON TECKNOPOR e=1", Hmax=25 CMS m2 264.05 18.71 4,940.38 S4,940.38 S4,940.38
01.06.05 JUNTAS CON ASFALTO, e=1" m 257.60 11.64 2,998.46 S2,998.46 S2,998.46
02.02.01 EXCAVACION SUPERFICIAL PARA VEREDAS H=0.30M m3 158.40 40.72 6,450.05 S6,450.05 S6,450.05
02.02.03 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3 198.00 32.58 6,450.84 S6,450.84 S6,450.84
02.02.04 RELLENO COMPACTADO C/MAT, PRESTAMO, CON PLANCHA COMP m2 132.00 8.12 1,071.84 S1,071.84 S1,071.84
02.03.02 VEREDA - CONCRETO f'c=175 kg/cm E=0.10M m2 528.00 102.19 53,956.32 S53,956.32 S53,956.32
02.03.03 VEREDA - ACAB. FROT. PISO C/ MORTERO 1:2x1.5CM DE ESPESOR m2 528.00 1.00 528.00 S528.00 S528.00
02.03.05 VEREDAS, JUNTA ASFALTICA, e=1" m 67.20 11.64 782.21 S782.21 S782.21
02.03.06 SARDINELS - ENCOFRADO Y DESENCOFRADO (H=0.20M) m 105.60 44.74 4,724.54 S4,724.54 S4,724.54
03.01.02 ELIMINACIÓN DE MATERIAL PROVENIENTE DE LAS DEMOLICIONES m3 33.54 40.96 1,373.80 S1,373.80 S1,373.80
03.02.01 CORTE DE TERRENO CON MAQUINARIA m3 20.64 6.15 126.94 S126.94 S126.94
03.02.03 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 25.80 4.02 103.72 S103.72 S103.72
03.03.01 EXTRACCION Y APILONAMIENTO DE MATERIAL DE SUBRASANTE m3 12.90 36.94 476.53 S476.53 S476.53
03.04.01 EXTRACCION Y APILONAMIENTO DE MATERIAL PARA SUB BASE m3 9.68 37.27 360.77 S360.77 S360.77
03.04.02 TRANSPORTE DE MATERIAL SELECCIONADO m3 9.68 28.57 276.56 S276.56 S276.56
03.04.04 CONFORMACION DE SUB BASE CON EQUIPO m3 9.68 10.45 101.16 S101.16 S101.16
03.05.01 CONEXION ENTRE LOSAS RIGIDAS (PAVIMENTO) S/D und 18.00 15.36 276.48 S276.48 S276.48
03.05.02 ENCOFRADO Y DESENCOFRADO PAVIMENTO RIGIDO m2 1.94 44.74 86.80 S86.80 S86.80
03.05.03 LOSAS MACISAS - CONCRETO f'c=210 kg/cm2 m2 25.80 104.00 2,683.20 S2,683.20 S2,683.20
03.05.04 JUNTA DEDILATACION CON TECKNOPOR e=1", Hmax=25 CMS m2 18.45 18.71 345.20 S345.20 S345.20
03.05.05 JUNTAS CON ASFALTO, e=1" m 18.45 11.64 214.76 S214.76 S214.76
04.01.01 ELABORACION IMPLEMENTACION Y ADMINISTRACION DE PLAN DE SEGURIDA glb 1.00 4,500.00 4,500.00 S4,500.00 S4,500.00
04.01.02 EQUIPAMIENTO DE PROTECCIÓN PERSONAL glb 1.00 18,191.85 18,191.85 S15,000.00 S1,595.93 S1,595.93 S18,191.85
04.01.03 EQUIPO DE PROTECCION COLECTIVA glb 1.00 4,189.00 4,189.00 S1,396.33 S1,396.33 S1,396.33 S4,189.00
04.01.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 4,598.65 4,598.65 S1,532.88 S1,532.88 S1,532.88 S4,598.65
04.01.05 CAPACITACION EN SEGURIDAD Y SALUD mes 3.00 1,755.00 5,265.00 S1,755.00 S1,755.00 S1,755.00 S5,265.00
04.01.06 RECURSOS DE RESPUESTA ANTE EMERGENCIAS mes 3.00 1,298.41 3,895.23 S1,298.41 S1,298.41 S1,298.41 S3,895.23
04.02.01 MANEJO DE RESIDUOS SOLIDOS Y MEDIO AMBIENTE 7,773.67 S2,591.23 S2,743.68 S2,438.77 S7,773.68
04.02.01.01 DISPOSICIÓN DE RESIDUOS SÓLIDOS glb 1.00 2,358.84 2,358.84 S786.28 S864.91 S707.65 S2,358.84
04.02.01.02 DEPOSITOS DE MATERIAL RELLENADO glb 1.00 2,214.83 2,214.83 S738.28 S812.10 S664.45 S2,214.83
04.02.01.03 CHARLAS DE SOCIABILIZACIÓN DEL PROYECTO A USUARIOS glb 1.00 3,200.00 3,200.00 S1,066.67 S1,066.67 S1,066.67 S3,200.01
04.02.02.01 CHARLAS DE CAPACITACION AL PERSONAL DE OBRA Y POBLACION glb 1.00 6,000.00 6,000.00 S2,000.00 S2,200.00 S1,800.00 S6,000.00
05.02 PLAN DE MONITOREO ARQUEOLOGICO mes 3.00 8,203.80 24,611.40 S8,203.80 S8,203.80 S8,203.80 S24,611.40