Está en la página 1de 3

CRONOGRAMA VALORIZADO DE OBRA

ITEM DESCRIPCION UNIDADMETRADO PRECIO (S.) PARCIAL (S.) MES 1 MES 2 MES 3 TOTAL

01 PAVIMENTACION 280,186.56 S154,455.12 S125,731.44 S280,186.56

01.01 OBRAS PROVISIONALES 24,683.84 S24,683.84 S24,683.84

01.01.01 OFICINAS m2 12.00 126.76 1,521.12 S1,521.12 S1,521.12

01.01.02 ALMACEN m2 35.00 126.76 4,436.60 S4,436.60 S4,436.60

01.01.03 GUARDIANIA m2 4.00 106.53 426.12 S426.12 S426.12

01.01.04 SERVICIOS HIGIENICOS DE OBRA (CONTENEDORES) mes 3.00 6,100.00 18,300.00 S18,300.00 S18,300.00

01.02 TRABAJOS PROVISIONALES 33,344.50 S33,344.50 S33,344.50

01.02.01 DESBROCE Y LIMPIEZA DE TERRENO m2 1,540.00 0.27 415.80 S415.80 S415.80

01.02.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA, EQUIPO Y HERRAMIENT glb 1.00 11,932.54 11,932.54 S11,932.54 S11,932.54

01.02.03 TRAZO Y REPLANTEO INICAL m2 1,540.00 4.31 6,637.40 S6,637.40 S6,637.40

01.02.04 TRAZO Y REPLANTEO DURANTE EL PROCESO mes 1,540.00 8.68 13,367.20 S13,367.20 S13,367.20

01.02.05 CARTEL DE IDENTIFICACION DE OBRA: 3.60x2.40m und 2.00 495.78 991.56 S991.56 S991.56

01.03 MOVIMIENTO DE TIERRAS 22,442.35 S22,442.35 S22,442.35

01.03.01 CORTE DE TERRENO CON MAQUINARIA m3 806.60 6.15 4,960.59 S4,960.59 S4,960.59

01.03.02 CORTE Y EXCAVACION EN FORMA MANUAL m3 57.00 40.72 2,321.04 S2,321.04 S2,321.04

01.03.03 TRANSPORTE DE MATERIAL EXCEDENTE m3 1,083.25 10.24 11,092.48 S11,092.48 S11,092.48

01.03.04 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 1,012.00 4.02 4,068.24 S4,068.24 S4,068.24

01.04 MEJORAMIENTO DE SUBRASANTE 42,064.29 S42,064.29 S42,064.29

01.04.01 EXTRACCION Y APILONAMIENTO DE MATERIAL DE SUBRASANTE m3 506.00 36.94 18,691.64 S18,691.64 S18,691.64

01.04.02 TRANSPORTE DE MATERIAL SELECCIONADO m3 506.00 28.57 14,456.42 S14,456.42 S14,456.42

01.04.03 RIEGO PARA COMPACTACION m3 50.60 78.21 3,957.43 S3,957.43 S3,957.43

01.04.04 CONFORMACION DE SUBRASANTE m3 506.00 9.80 4,958.80 S4,958.80 S4,958.80

01.05 SUB BASE GRANULAR 31,920.14 S31,920.14 S31,920.14

01.05.01 EXTRACCION Y APILONAMIENTO DE MATERIAL PARA SUB BASE m3 379.50 37.27 14,143.97 S14,143.97 S14,143.97

01.05.02 TRANSPORTE DE MATERIAL SELECCIONADO m3 379.50 28.57 10,842.32 S10,842.32 S10,842.32

01.05.03 RIEGO PARA COMPACTACION m3 37.95 78.21 2,968.07 S2,968.07 S2,968.07

01.05.04 CONFORMACION DE SUB BASE CON EQUIPO m3 379.50 10.45 3,965.78 S3,965.78 S3,965.78

01.06 LOSA DE RODADURA 125,731.44 S125,731.44 S125,731.44

01.06.01 CONEXION ENTRE LOSAS RIGIDAS (PAVIMENTO) S/D und 672.00 15.36 10,321.92 S10,321.92 S10,321.92

01.06.02 ENCOFRADO Y DESENCOFRADO PAVIMENTO RIGIDO m2 49.68 44.74 2,222.68 S2,222.68 S2,222.68

01.06.03 LOSAS MACISAS - CONCRETO f'c=210 kg/cm2 m2 1,012.00 104.00 105,248.00 S105,248.00 S105,248.00

01.06.04 JUNTA DEDILATACION CON TECKNOPOR e=1", Hmax=25 CMS m2 264.05 18.71 4,940.38 S4,940.38 S4,940.38
01.06.05 JUNTAS CON ASFALTO, e=1" m 257.60 11.64 2,998.46 S2,998.46 S2,998.46

02 VEREDAS Y SARDINELES 97,553.12 S88,678.96 S8,874.16 S97,553.12

02.01 TRABAJOS PRELIMINARES 4,583.04 S4,583.04 S4,583.04

02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 528.00 8.68 4,583.04 S4,583.04 S4,583.04

02.02 MOVIMIENTO DE TIERRAS 18,580.19 S18,580.19 S18,580.19

02.02.01 EXCAVACION SUPERFICIAL PARA VEREDAS H=0.30M m3 158.40 40.72 6,450.05 S6,450.05 S6,450.05

02.02.02 ACARREO DE MATERIAL EXCEDENTE m3 198.00 23.27 4,607.46 S4,607.46 S4,607.46

02.02.03 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3 198.00 32.58 6,450.84 S6,450.84 S6,450.84

02.02.04 RELLENO COMPACTADO C/MAT, PRESTAMO, CON PLANCHA COMP m2 132.00 8.12 1,071.84 S1,071.84 S1,071.84

02.03 OBRAS DE CONCRETO Y MAMPOSTERIA 70,544.29 S65,515.73 S5,028.56 S70,544.29

02.03.01 VEREDA ENCOFRADO Y DESENCOFRADO m2 100.96 44.74 4,516.95 S4,516.95 S4,516.95

02.03.02 VEREDA - CONCRETO f'c=175 kg/cm E=0.10M m2 528.00 102.19 53,956.32 S53,956.32 S53,956.32

02.03.03 VEREDA - ACAB. FROT. PISO C/ MORTERO 1:2x1.5CM DE ESPESOR m2 528.00 1.00 528.00 S528.00 S528.00

02.03.04 VEREDAS, BRUÑAS DE 1 X 1.5 cm m 264.00 6.78 1,789.92 S1,789.92 S1,789.92

02.03.05 VEREDAS, JUNTA ASFALTICA, e=1" m 67.20 11.64 782.21 S782.21 S782.21

02.03.06 SARDINELS - ENCOFRADO Y DESENCOFRADO (H=0.20M) m 105.60 44.74 4,724.54 S4,724.54 S4,724.54

02.03.07 SARDINELS - ECONCRETO F´c=175KG/CM2 m3 8.80 482.54 4,246.35 S4,246.35 S4,246.35

02.04 PINTURAS 3,845.60 S3,845.60 S3,845.60

02.04.01 PINTURA EN SARDINELES m 440.00 8.74 3,845.60 S3,845.60 S3,845.60

03 REHABILITACION DE LA CUADRA 4 DEL JIRON HUALGAYOC 9,504.26 S4,744.66 S4,759.60 S9,504.26

03.01 TRABAJOS PRELIMINARES 3,516.23 S3,516.23 S3,516.23

03.01.01 DEMOLICION DE LOSA EXISTENTE m2 25.80 83.04 2,142.43 S2,142.43 S2,142.43

03.01.02 ELIMINACIÓN DE MATERIAL PROVENIENTE DE LAS DEMOLICIONES m3 33.54 40.96 1,373.80 S1,373.80 S1,373.80

03.02 MOVIMIENTO DE TIERRAS 494.85 S391.13 S103.72 S494.85

03.02.01 CORTE DE TERRENO CON MAQUINARIA m3 20.64 6.15 126.94 S126.94 S126.94

03.02.02 TRANSPORTE DE MATERIAL EXCEDENTE m3 25.80 10.24 264.19 S264.19 S264.19

03.02.03 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 25.80 4.02 103.72 S103.72 S103.72

03.03 MEJORAMIENTO DE SUBRASANTE 1,072.39 S476.53 S595.86 S1,072.39

03.03.01 EXTRACCION Y APILONAMIENTO DE MATERIAL DE SUBRASANTE m3 12.90 36.94 476.53 S476.53 S476.53

03.03.02 TRANSPORTE DE MATERIAL SELECCIONADO m3 12.90 28.57 368.55 S368.55 S368.55

03.03.03 RIEGO PARA COMPACTACION m3 1.29 78.21 100.89 S100.89 S100.89

03.03.04 CONFORMACION DE SUBRASANTE m3 12.90 9.80 126.42 S126.42 S126.42

03.04 SUB BASE GRANULAR 814.35 S360.77 S453.58 S814.35

03.04.01 EXTRACCION Y APILONAMIENTO DE MATERIAL PARA SUB BASE m3 9.68 37.27 360.77 S360.77 S360.77
03.04.02 TRANSPORTE DE MATERIAL SELECCIONADO m3 9.68 28.57 276.56 S276.56 S276.56

03.04.03 RIEGO PARA COMPACTACION m3 0.97 78.21 75.86 S75.86 S75.86

03.04.04 CONFORMACION DE SUB BASE CON EQUIPO m3 9.68 10.45 101.16 S101.16 S101.16

03.05 LOSA DE RODADURA 3,606.44 S3,606.44 S3,606.44

03.05.01 CONEXION ENTRE LOSAS RIGIDAS (PAVIMENTO) S/D und 18.00 15.36 276.48 S276.48 S276.48

03.05.02 ENCOFRADO Y DESENCOFRADO PAVIMENTO RIGIDO m2 1.94 44.74 86.80 S86.80 S86.80

03.05.03 LOSAS MACISAS - CONCRETO f'c=210 kg/cm2 m2 25.80 104.00 2,683.20 S2,683.20 S2,683.20

03.05.04 JUNTA DEDILATACION CON TECKNOPOR e=1", Hmax=25 CMS m2 18.45 18.71 345.20 S345.20 S345.20

03.05.05 JUNTAS CON ASFALTO, e=1" m 18.45 11.64 214.76 S214.76 S214.76

04 SEGURIDAD, SALUD Y MEDIO AMBIENTE 61,312.92 S30,073.86 S16,921.75 S14,317.32 S61,312.93

04.01 SEGURIDAD Y SALUD 40,639.73 S25,482.63 S7,578.55 S7,578.55 S40,639.73

04.01.01 ELABORACION IMPLEMENTACION Y ADMINISTRACION DE PLAN DE SEGURIDA glb 1.00 4,500.00 4,500.00 S4,500.00 S4,500.00

04.01.02 EQUIPAMIENTO DE PROTECCIÓN PERSONAL glb 1.00 18,191.85 18,191.85 S15,000.00 S1,595.93 S1,595.93 S18,191.85

04.01.03 EQUIPO DE PROTECCION COLECTIVA glb 1.00 4,189.00 4,189.00 S1,396.33 S1,396.33 S1,396.33 S4,189.00

04.01.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 4,598.65 4,598.65 S1,532.88 S1,532.88 S1,532.88 S4,598.65

04.01.05 CAPACITACION EN SEGURIDAD Y SALUD mes 3.00 1,755.00 5,265.00 S1,755.00 S1,755.00 S1,755.00 S5,265.00

04.01.06 RECURSOS DE RESPUESTA ANTE EMERGENCIAS mes 3.00 1,298.41 3,895.23 S1,298.41 S1,298.41 S1,298.41 S3,895.23

04.02 MEDIO AMBIENTE 20,673.19 S4,591.23 S9,343.20 S6,738.77 S20,673.20

04.02.01 MANEJO DE RESIDUOS SOLIDOS Y MEDIO AMBIENTE 7,773.67 S2,591.23 S2,743.68 S2,438.77 S7,773.68

04.02.01.01 DISPOSICIÓN DE RESIDUOS SÓLIDOS glb 1.00 2,358.84 2,358.84 S786.28 S864.91 S707.65 S2,358.84

04.02.01.02 DEPOSITOS DE MATERIAL RELLENADO glb 1.00 2,214.83 2,214.83 S738.28 S812.10 S664.45 S2,214.83

04.02.01.03 CHARLAS DE SOCIABILIZACIÓN DEL PROYECTO A USUARIOS glb 1.00 3,200.00 3,200.00 S1,066.67 S1,066.67 S1,066.67 S3,200.01

04.02.02 EDUCACIÓN Y CAPACITACIÓN 6,000.00 S2,000.00 S2,200.00 S1,800.00 S6,000.00

04.02.02.01 CHARLAS DE CAPACITACION AL PERSONAL DE OBRA Y POBLACION glb 1.00 6,000.00 6,000.00 S2,000.00 S2,200.00 S1,800.00 S6,000.00

04.02.03 PROGRAMA DE ABANDONO 6,899.52 S4,399.52 S2,500.00 S6,899.52

04.02.03.01 CIERRE DE CAMPAMENTO glb 1.00 2,500.00 2,500.00 S2,500.00 S2,500.00

04.02.03.02 CIERRE DE CANTERAS glb 1.00 4,399.52 4,399.52 S4,399.52 S4,399.52

05 VARIOS 39,611.40 S23,203.80 8203.8 8203.8 S39,611.40

05.01 FLETE TERRESTRE glb 1.00 15,000.00 15,000.00 S15,000.00 S15,000.00

05.02 PLAN DE MONITOREO ARQUEOLOGICO mes 3.00 8,203.80 24,611.40 S8,203.80 S8,203.80 S8,203.80 S24,611.40

COSTO DIRECTO 488,168.26 212477.44 244295.55 31395.28


GASTOS GENERALES (10%) 48816.83
UTILIDAD (5%) 24408.41
SUB TOTAL 561,393.50
IGV(18%) 101050.83
VALOR REFERENCIAL 662,444.33
EXPEDIENTE TECNICO 10866.68
GASTOS DE SUPERVISION (5%) 33122.22
PRESUPUESTO TOTAL 706,433.23