CRONOGRAMA CISTERNA DEL 05/07/18-13/07/18

7/5/2018 7/6/2018 7/7/2018 7/8/2018 7/9/2018 7/10/2018 7/11/2018 7/12/2018 7/13/2018 7/14/2018 7/15/2018 7/16/2018 7/17/2018
1.0 CISTERNA 13% 13% 13% 13% 13% 13% 13% 13%
2.0 ELIMACION MATERIAL 33% 33% 33%
3.0 EXCAVACION CON MAQUINA CISTERNA v=325m3 50% 50%
4.0 EXCAVACION Y PERFILADO MANUAL CISTERNA (ZAPATAS) V= 30m3 50% 50%
5.0 TRAZO DE EJES Y NIVELES 14% 14% 14% 14% 14% 14% 14% 14%
6.0 VACIADO DE SOLADO F'C 100 ZAPATA CISTERNA V=15M3 50% 50%
7.0 INSTALACION DE ACERO EN ZAPATA (CISTERNA) 50% 50%
8.0 INSTALACION DE ACERO EN PLACAS Y COLUMNAS CISTERNA 50% 50%
9.0 ENCOFRADO DE ZAPATA y LOSA CISTERNA 100%
10.0 I. ELECTRICAS 50% 50%
11.0 I. SANITARIAS 50% 50%
12.0 VACIADO DE ZAPATA CISTERNA F'C 280 Y LOSA CISTERNA v=50m3 100%
13.0 ENCOFRADO DE PLACAS Y COLUMNAS CISTERNA 100% 100%
14.0 VACIADO DE MUROS CISTERNA 100%
15.0 DESENCOFRADO DE MUROS CISTERNA 100%
16.0 HABILITADO ACERO ZAPATAS Y COLUMNAS SOTANO 3 50% 50%
17.0 HABILITADO ACERO VIGAS SOTANOS 25% 25% 25% 25%
18.0 RELLENO DE TERRENO DE NIVEL TECHO CISTERNA ENTERRADA CON EXCAVADORA 33% 33% 33%
19.0 EXCAVACION ZAPATAS COLUMNAS SOTANO 3 CON EXCAVADORA 50% 50%
20.0 ARMADO DE COLUMNAS CON EXCAVADORA 50% 50%
21.0 CAMBIO DE EXCAVADORA POR BODCAT 100%
22.0 TRABAJOS DE NIVELACIION DE PISO CON BODCAT 50% 50%
* rutas criticas color rojo
* Se recuperara en las partidas de nivelacion de piso para sotano 3, ya que se tendra unos dias mas la excavadora para que ayude en los trabajos de excavacion de zapatas, colocado de zapatas y columnas, y nivelacion de terreno