Está en la página 1de 3

CALENDARIO DE OBRA VALORIZADO DE MANTENIMIENTO PERIODICO

PROYECTO:
SERVICIO PARA LA EJECUCIÓN DEL MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO
VECINAL, TRAMO I Emp. PE-34B (Azángaro) - I.E.I Huayllacunca - Emp. PU-117 (Mercedes),
SEGÚN TÉRMINOS DE REFERENCIA.

FECHA: 9/1/2020
SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 TOTAL
MANTENIMIENTO PERIODICO
S/179,765.53 S/168,752.37 S/163,295.49 S/78,850.06 S/4,531.66 S/595,195.11
OBRAS PRELIMINARES S/24,540.72 S/6,811.08 S/5,297.51 S/36,649.31
MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
S/20,000.00 S/20,000.00
TRAZO, NIVELES Y REPLANTEO S/4,540.72 S/6,811.08 S/5,297.51 S/16,649.31
CONSERVACION DE CALZADA EN AFIRMADO S/54,095.93 S/86,976.71 S/86,976.71 S/38,656.32 S/266,705.67
CAPA NIVELANTE E=0.05CM S/15,439.61 S/15,439.61
MATERIAL GRANULAR DE CANTERA PARA
ESTABILIZADO E=0.15 M S/38,656.32 S/86,976.71 S/86,976.71 S/38,656.32 S/251,266.06
TRANSPORTES S/52,547.69 S/71,503.04 S/67,559.73 S/23,892.50 S/215,502.96
TRANSPORTE DE MATERIAL GRANULAR HASTA
1KM S/23,892.50 S/53,758.13 S/53,758.13 S/23,892.50 S/155,301.26
TRANSPORTE DE MATERIAL GRANULAR MAYOR A
1KM S/7,886.63 S/17,744.91 S/13,801.60 S/39,433.14
TRANSPORTE DE MATERIAL EXEDENTE HASTA 1KM
S/18,724.10 S/18,724.10
TRANSPORTE DE MATERIAL EXEDENTE MAYOR A
1KM S/2,044.46 S/2,044.46
OBRAS DE ARTE Y DRENAJE S/46,273.50 S/46,273.50
RECONFORMACION DE CUNETAS S/46,273.50 S/46,273.50
SEÑALIZACION S/7,376.34 S/4,531.66 S/11,908.00
INSTALACION DE POSTES KILOMETRICOS S/3,012.24 S/3,012.24
SEÑALES PREVENTIVAS S/4,364.10 S/1,454.70 S/5,818.80
SEÑALES REGLAMENTARIAS S/1,927.26 S/1,927.26
SEÑALES INFORMATIVAS S/1,149.70 S/1,149.70
IMPACTO AMBIENTAL S/8,155.67 S/8,155.67
RECUPERACION AMBIENTAL DE AREA OCUPADAS
S/8,155.67 S/8,155.67
EMERGENCIA SANITARIA S/2,307.69 S/3,461.54 S/3,461.54 S/769.23 S/10,000.00
EMERGENCIA SANITARIA COVID-19 S/2,307.69 S/3,461.54 S/3,461.54 S/769.23 S/10,000.00
COSRO DIRECTO S/179,765.53 S/168,752.37 S/163,295.49 S/78,850.06 S/4,531.66 S/595,195.11
GASTOS GENERALES (4%) S/7,190.62 S/6,750.09 S/6,531.82 S/3,154.00 S/181.27 S/23,807.80
UTILIDAD (6%) S/10,785.93 S/10,125.14 S/9,797.73 S/4,731.00 S/271.90 S/35,711.71
SUBTOTAL S/197,742.08 S/185,627.61 S/179,625.04 S/86,735.07 S/4,984.83 S/654,714.62
IGV (18%) S/35,593.57 S/33,412.97 S/32,332.51 S/15,612.31 S/897.27 S/117,848.63
PRESUPUESTO TOTAL S/233,335.66 S/219,040.58 S/211,957.55 S/102,347.38 S/5,882.09 S/772,563.25
SON: SETECIENTOS SETENTA Y DOS MIL QUINIENTOS SESENTA Y TRES Y 25/100 NUEVOS SOLES
CALENDARIO DE AVANCE DE OBRA VALORIZADO

PRESUPUESTO SERVICIO PARA LA EJECUCIÓN DEL MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL TRAMO 16 PTE.
AZÁNGARO - EMP. PE-34B, SEGÚN TÉRMINOS DE REFERENCIA.

ENTIDAD MUNICIPALIDAD PROVINCIAL DE AZÁNGARO


INSPECTOR ING. ROGER HIPÒLITO HUALLPA APAZA
RESIDENTE ING. CESAR AUGUSTO DURAND COILA
LUGAR PUNO - AZANGARO - AZANGARO
PLAZO 9 DIAS CALENDARIOS

ÍTEM DESCRIPCION UNIDAD DICIEMBRE %

2 MANTENIMIENTO PERIODICO S/. 52,760.89 100.00%


A TRAMO 16 S/. 52,760.89 100.00%
1 OBRAS PRELIMINARES S/. 4,860.48 9.21%
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB S/. 4,000.00 7.58%
1.02 TRAZO Y REPLANTEO KM S/. 860.48 1.63%
2 PAVIMENTOS S/. 27,584.37 52.28%
2.01 CAPA NIVELANTE E=0.05 M M3
2.02 MATERIAL GRANULAR DE CANTERA E=0.15 M M3 S/. 27,584.37 52.28%
3 TRANSPORTE S/. 11,732.82 22.24%

3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K S/. 7,976.93 15.12%


TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1
3.02 M3K S/. 3,755.89 7.12%
KM

3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K

TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A


3.04 M3K
1KM
4 OBRAS DE ARTE Y DRENAJE S/. 2,238.70 4.24%
4.01 RECONFORMACION DE CUNETAS ML S/. 2,238.70 4.24%
5 SEÑALIZACION S/. 3,677.14 6.97%
5.01 INSTALACION DE POSTES KILOMETRICOS UND S/. 430.32 0.82%
5.02 SEÑALES PREVENTIVAS UND S/. 1,454.70 2.76%
5.03 SEÑALES REGLAMENTARIAS UND S/. 642.42 1.22%
5.04 SEÑALES INFORMATIVAS UND S/. 1,149.70 2.18%
6 IMPACTO AMBIENTAL S/. 1,665.03 3.16%

6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA S/. 1,665.03 3.16%

7 EMERGENCIA SANITARIA S/. 1,002.35 1.90%


7.01 EMERGENCIA SANITARIA COVID 19 GLB S/. 1,002.35 1.90%
% DE AVANCE 100.00%
MENSUAL
PROGRAMADO
% DE AVANCE 100.00%
ACUMULADO