PRESUPUESTO GENERAL NAVE COMERCIAL

DESCRIPCION UND CANT MONTO UNIT SUBTOTAL


Corte & Bote Retroexcavadora UND 1 $ 10,000.00 $ 10,000.00
Trazo, Nivel & replanteo UND 1 $ 15,000.00 $ 15,000.00
Enlates para Charrancha 1 x 4¨x 16¨- Pino Cepillado UND 30 $ 398.00 $ 11,940.00
Clavos dulces 2-1/2" LBS 100 $ 70.00 $ 7,000.00
Clavos Acero 2-1/2" LBS 100 $ 70.00 $ 7,000.00
Funda de cal 15 lbs UND 1 $ 60.00 $ 60.00
Alambre dulce picado LBS 120 $ 70.00 $ 8,400.00
Blocks 6" Semi - Industrial UND 3600 $ 40.00 $ 144,000.00
Arena Lavada M3 140 $ 1,700.00 $ 238,000.00
Arena Itabo M3 85 $ 1,100.00 $ 93,500.00
Grava M3 140 $ 1,300.00 $ 182,000.00
Varilla quintal 1/2 QUINT 46 $ 2,900.00 $ 133,400.00
Varilla quintal 3/8 QUINT 69 $ 2,700.00 $ 186,300.00
Varilla quintal 3/4 x 20 QUINT 46 $ 2,700.00 $ 124,200.00
Funda de cemento Titan UND 780 $ 370.00 $ 288,600.00

TOTAL MATERIALES RD$ $ 1,412,460.00


MANO DE OBRA,
GENERAL
Trazo, Nivel & replanteo 1 $ 25,000.00 $ 25,000.00
Terminacion Panete y mochetas 1 $ 195,000.00 $ 195,000.00
Habilitacion y colocacion de Varillas de acero, en estructura de concreto armado, Cuerpo Estructural 1 $ 85,000.00 $ 85,000.00
Columnas 40 x 40, concreto premezclado F*C=210Kg/cm2 Capacidad 3,000 PSI, Carpinteria 1 $ 45,000.00 $ 45,000.00
Vigas Amarre 40 x 40 estructura cisterna, concreto premezclado F*C=210Kg/cm2 Capacidad 3,000 PSI, Carpinteria 1 $ 75,000.00 $ 75,000.00
Encofrado General estructural Reforzada doble capa traslapada 1 $ 178,000.00 $ 178,000.00
Mamposteria Puesta + Mano de obra General 1 $ 250,000.00 $ 250,000.00
Electricidad - Plomeria 1 $ 195,000.00 $ 195,000.00
TOTAL OBRA RD$ $ 1,048,000.00

TOTAL GENERAL $ 2,460,460.00