Está en la página 1de 18

º

CONSORCIO AAA
FORMATO: CARTILLA DE ACERO DE REFUERZO

OBRA:

ITEM DIAGRAMA CANTIDAD PRODUCTO

2.6
0.2 0.2
0.2 0.2
4.8

1 0.2 0.2 32 #4
0.2 0.2

0.3

1 0.2 0.2 12 #4

0.2 0.2

2 0.2 0.2 44 #4

2.4
3 0.2 0.2 10 #4

1
3 0.2 0.2 30 #4

DESPERDICIO

TOTAL KG

KILOGRAMOS ALAMBRE NEGR


O AAA 30
ENCARGDO
INSPECTOR MARLON PEREZ CARRASQUILLA
FECHA:

SUB-TOTAL
LONG. (m) PESO (Kg/m) UBICACIÓN
PESO

5.6 0.994 178.12 LOSA


INFERIOR

caja de 4.9 0.2

2.7 0.2
LOSA
1.1 0.994 13.12
INFERIOR

2.4 0.994 104.97 MURO

2.8 0.994 27.83 CAJA TP

1.4 0.994 41.75 CAJA TP

SUB-TOTAL KG VARILLA 365.79

DESPERDICIO 2% 7.32

TOTAL KG VARILLA 373.11

KILOGRAMOS ALAMBRE NEGRO N° 18 25


TOTAL-KG 398.11
27

16
º

CONSORCIO AAA
FORMATO: CARTILLA DE ACERO DE REFUERZO

OBRA:

ITEM DIAGRAMA CANTIDAD PRODUCTO


1.5
0.2
1 0.6 0.2 0.2 34 #4

0.2
1.5

1 0.2 0.2 34 #4
0.2 0.2

5.6

1 0.2 18 #4
0.2

1.6

1 0.2 18 #4

0.2
6

1 2 #4

1.2

1 2 #4

0.3

1 0.2 0.2 12 #4

0.2 0.2

2 44 #4
2 0.2 0.2 44 #4

0.6
2 0.2 0.2 28 #4

1
2 0.2 72 #4

1.2
2 0.2 1 28 #4
0.2

4.8
2 1 8 #4
0.2

1
2 1 8 #4
0.2

1.6
3 0.2 0.2 20 #4

1
3 0.2 0.2 24 #4

2.4
3 0.2 0.2 10 #4

1
3 0.2 0.2 30 #4
DESPERDICIO

TOTAL KG

KILOGRAMOS ALAMBRE NEGR


O AAA 30
ENCARGDO
INSPECTOR MARLON PEREZ CARRASQUILLA
FECHA:

SUB-TOTAL
LONG. (m) PESO (Kg/m) UBICACIÓN
PESO

LOSA
2.9 0.994 98.01
INFERIOR

LOSA
2.3 0.994 77.73
INFERIOR

LOSA
6 0.994 107.35
INFERIOR

LOSA
2 0.994 35.78
INFERIOR

LOSA
6 0.994 11.93 INFERIOR

LOSA
1.2 0.994 2.39
INFERIOR

LOSA
1.1 0.994 13.12
INFERIOR

2.4 0.994 104.97 MURO


2.4 0.994 104.97 MURO

1 0.994 27.83 MURO

1.2 0.994 85.88 MURO

2.6 0.994 72.36 MURO

6 0.994 47.71 MURO

2.2 0.994 17.49 MURO

2 0.994 39.76 CAJA MURO

1.4 0.994 33.40 CAJA MURO

2.8 0.994 27.83 CAJA TP

1.4 0.994 41.75 CAJA TP

SUB-TOTAL KG VARILLA 845.30


DESPERDICIO 2% 16.91

TOTAL KG VARILLA 862.20

KILOGRAMOS ALAMBRE NEGRO N° 18 25

TOTAL-KG 887.20
º

CONSORCIO AAA 3
FORMATO: CARTILLA DE ACERO DE REFUERZO

OBRA:

ITEM DIAGRAMA CANTIDAD PRODUCTO


1.5
0.2
1 0.6 0.2 0.2 34 #4

0.2
1.5

1 0.2 0.2 34 #4
0.2 0.2

5.6

1 0.2 18 #4
0.2

1.6

1 0.2 18 #4

0.2
6

1 2 #4

1.2

1 2 #4

0.3

1 0.2 0.2 12 #4
1 12 #4

0.2 0.2

2.4

2 0.2 0.2 44 #4

1
2 0.2 0.2 28 #4

1.2
2 0.2 1 28 #4
0.2

4.8
2 1 8 #4
0.2

1
2 1 8 #4
0.2

1.6
3 0.2 0.2 20 #4

1
3 0.2 0.2 24 #4

2.4
3 0.2 0.2 10 #4

1
3 0.2 0.2 30 #4
DESPERDICIO

TOTAL KG VAR

KILOGRAMOS ALAMBRE NEGRO N


O AAA 30
ENCARGDO
INSPECTOR MARLON PEREZ CARRASQUILLA
FECHA:

SUB-TOTAL
LONG. (m) PESO (Kg/m) UBICACIÓN
PESO

LOSA
2.9 0.994 98.01
INFERIOR

LOSA
2.3 0.994 77.73
INFERIOR

LOSA
6 0.994 107.35 INFERIOR

LOSA
2 0.994 35.78
INFERIOR

LOSA
6 0.994 11.93
INFERIOR

LOSA
1.2 0.994 2.39
INFERIOR

LOSA
1.1 0.994 13.12
INFERIOR
LOSA
1.1 0.994 13.12
INFERIOR

2.8 0.994 122.46 MURO

1.4 0.994 38.96 MURO

2.6 0.994 72.36 MURO

6 0.994 47.71 MURO

2.2 0.994 17.49 MURO

2 0.994 39.76 CAJA MURO

1.4 0.994 33.40 CAJA MURO

2.8 0.994 27.83 CAJA TP

1.4 0.994 41.75 CAJA TP


SUB-TOTAL KG VARILLA 788.04 5.964
132.133333
DESPERDICIO 2% 15.76

TOTAL KG VARILLA 803.80

KILOGRAMOS ALAMBRE NEGRO N° 18 25

TOTAL-KG 828.80
CONCRETO
6.6 1.7 0.3 3.366
LOSA FONDO 3.96 3.96
6.6 0.3 0.3 0.594
7.3 2.2 0.3 4.818
1 1.2 0.3 0.36
MURO 4.53 4.53
1 1.2 0.3 0.36
2.8 1.2 0.3 1.008
LOSA SUPERIOR 3.4 1 0.3 1.02 1.02 1.02
SELLO DE TUBO 0.8 1.4 0.5 0.56 0.56 0.56
MURO 1 MUERO 2

EXCAVACION MURO1
2.2 2 1.4 6.16
2.2 2 1.5 6.6
2.4 2 0.6 2.88
TOTAL 15.64

EXCAVACION MURO2
2.2 2 1.8 7.92
2.2 2 1.6 7.04
2.4 2 0.6 2.88
TOTAL 17.84

FILTRO MURO 1
6.6 2 0.6 7.92

FILTRO MURO 2
6.6 2 0.6 7.92

SOLADO 2500psi MURO 1


6.6 2 0.1 1.32

SOLADO 2500psi MURO 2


6.6 2 0.1 1.32

MOTOBOMBA
fecha
DICIEMBRE ENERO
30 31 4 5 6
ENERO
8 10 11 13

También podría gustarte