Está en la página 1de 22

CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
01 OBRAS PROVISIONALES
01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 Alquiler de almacen de obra mes 6.00 423.73 2,542.38 2,542.38 ###
01.01.02 Cartel de Identificacion de Obra de 4.80m x 3.60 m und 1.00 1,695.93 1,695.93 1,695.93 ###
01.01.03 Servicios higienicos durante la ejecucion mes 6.00 254.24 1,525.44 1,525.44 ###
01.01.04 Cerco Provisional de Calamina m 205.27 49.65 10,191.66 10,191.66 ###
01.02 INSTALACIONES PROVISIONALES ###
01.02.01 Agua para la construcción glb 1.00 500.00 500.00 500.00 ###
01.02.02 Energia electrica para la construcción glb 1.00 2,000.00 2,000.00 2,000.00 ###
02 TRABAJOS PRELIMINARES ###
02.01 Limpieza de Terreno Manual m2 2,895.00 0.68 1,968.60 1,968.60 ###
02.02 Trazo, Niveles y Replanteo Preliminar m2 2,551.89 3.22 8,217.09 8,217.09 ###
02.03 Movilizacion y desmovilizacion de equipos y maquinarias glb 1.00 33,118.64 33,118.64 33,118.64 ###
02.04 DEMOLICIONES ###
02.04.01 Demolicion de muros de adobe m3 615.10 25.00 15,377.50 15,377.50 ###
02.04.02 Demolicion de falso piso de concreto con maquinaria m3 120.14 91.92 11,043.27 11,043.27 ###
02.04.03 Demolicion de cimentacion m3 90.01 216.08 19,449.36 19,449.36 ###
02.04.04 Desmontaje de puertas und 26.00 16.21 421.46 421.46 ###
02.04.05 Desmontaje de ventanas und 35.00 12.96 453.60 453.60 ###
02.04.06 Desmontaje de paredes prefabricadas und 8.00 42.05 336.40 336.40 ###
02.04.07 Desmontaje de barandas m2 17.00 28.03 476.51 476.51 ###
02.04.08 Desmontaje de aparatos sanitarios und 6.00 40.52 243.12 243.12 ###
02.04.09 Desmontaje de tijetales de madera und 72.00 45.92 3,306.24 3,306.24 ###
02.04.10 Desmontaje de coberturas m2 1,201.36 18.23 21,900.79 21,900.79 ###
02.04.11 Eliminacion de material excedente con Equipo (d=1 km) m3 1,072.82 21.03 22,561.40 22,561.40 ###
02.05 MOVIMIENTO DE TIERRAS ###
02.05.01 CORTES ###
02.05.01.01 Corte masivo de terreno narutal m3 1,820.52 11.78 21,445.73 21,445.73 ###
02.05.02 NIVELACION INTERIOR Y APISONADO ###
02.05.02.01 Nivelacion Interior y Apisonado m2 2,345.00 1.35 3,165.75 3,165.75 ###
02.05.03 RELLENO CON MATERIAL PROPIO ###
02.05.03.01 Relleno con material propio m3 650.23 15.31 9,955.02 9,955.02 ###
02.05.03.02 Eliminacion de material excedente con Equipo (d=1 km) m3 1,521.46 21.03 31,996.30 31,996.30 ###
03 SISTEMA DE DRENAJE ###
03.01 SISTEMA DE DRENAJE PLUVIAL SUPERFICIAL ###
03.01.01 Excavacion de zanja para drenaje pluvial superficial m3 34.08 41.28 1,406.82 1,406.82 ###
03.01.02 Eliminacion de material excedente con Equipo (d=1 km) m3 44.30 21.03 931.63 931.63 ###
03.01.03 Concreto f'c= 210 Kg/Cm2 m3 17.48 520.01 9,089.77 9,089.77 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
03.01.04 Encofrado y desencofrado m2 131.06 57.34 7,514.98 7,514.98 ###
03.01.05 Acabado y Revestimiento en drenaje m2 174.75 37.39 6,533.90 6,533.90 ###
03.01.06 Rejilla Metalica p/Canal Evac. Aguas pluv. m 218.44 101.59 22,191.32 22,191.32 ###
03.01.07 Caja de Registro de Drenaje pluvial 12" X 24" und 3.00 152.05 456.15 456.15 ###
04 SEGURIDAD Y SALUD ###
04.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO ###
04.01.01 Elaboracion, Implementacion y administracion del Plan de Seguridad y Salud en el Trabajo glb 1.00 847.45 847.45 847.45 ###
04.01.02 Equipos de Proteccion Individual und 30.00 299.20 8,976.00 8,976.00 ###
04.01.03 Equipos de Proteccion Colectiva glb 1.00 2,800.00 2,800.00 2,800.00 ###
04.01.04 Señalizacion Temporal de Seguridad glb 1.00 654.81 654.81 654.81 ###
04.01.05 Capacitacion en Seguridad y Salud und 1.00 1,400.00 1,400.00 1,400.00 ###
04.01.06 Recursos para Respuestas ante Emergencias en Seguridad y Salud durante el Trabajo glb 1.00 700.00 700.00 700.00 ###
04.02 CURADO Y PROTECCION DEL CONCRETO - -
04.02.01 Curado y proteccion del concreto en obra con aditivo m2 4,200.00 2.87 12,054.00 1,567.02 2,410.80 2,049.18 2,049.18 1,928.64 2,049.18
05 MODULO EDUCATIVO ###
05.01 ESTRUCTURAS ###
05.01.01 MOVIMIENTO DE TIERRAS ###
05.01.01.01 EXCAVACIONES ###
05.01.01.01.01 Excavacion de zapatas y muros m3 323.70 23.90 7,736.43 5,802.32 1,934.11 ###
05.01.01.01.02 Excavacion de cimientos m3 221.59 48.17 10,673.99 10,673.99 ###
05.01.01.02 RELLENO CON MATERIAL PROPIO ###
05.01.01.02.01 Relleno con material propio m3 210.50 15.31 3,222.76 3,222.76 ###
05.01.01.02.02 Eliminacion de material excedente con Equipo (d=1 km) m3 435.23 21.03 9,152.89 9,152.89 ###
05.01.01.03 NIVELACION DE TERRENO ###
05.01.01.03.01 Nivelacion Interior y Apisonado m2 728.78 1.35 983.85 983.85 ###
05.01.02 OBRAS DE CONCRETO SIMPLE ###
05.01.02.01 ZAPATAS ###
05.01.02.01.01 Solado - Concreto C:H 1:10, e=10CM m2 256.14 37.55 9,618.06 9,618.06 ###
05.01.02.01.02 falsa zapata - Concreto , e=30CM m3 45.74 298.32 13,645.16 13,645.16 ###
05.01.02.02 CIMIENTO CORRIDO ###
05.01.02.02.01 Cimiento Corrido - Concreto Ciclopeo C:H 1:10 + 30% PG m3 65.85 462.27 30,440.48 30,440.48 ###
05.01.02.02.02 Sobrecimiento-Concreto C:H 1:8+25%PM m3 29.10 365.57 10,638.09 10,638.09 ###
05.01.02.02.03 Sobrecimientos - Encofrado y Desencofrado m2 299.72 45.97 13,778.13 13,778.13 ###
05.01.02.03 PISO DE CONCRETO Y VEREDAS ###
05.01.02.03.01 PISOS INTERIORES ###
05.01.02.03.01 Falso piso en interiores-Concreto F'c 175 Kg/cm2 m2 663.28 45.96 30,484.35 30,484.35 ###
05.01.02.03.02 PISOS EXTERIORES ###
05.01.02.03.02 Piso de patio de formacion -Concreto F'c 175 Kg/cm2 m2 715.28 45.96 32,874.27 32,874.27 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.01.02.03.02 pisos exteriores-Concreto F'c 175 Kg/cm2 m2 354.36 45.96 16,286.39 16,286.39 ###
05.01.02.03.02 veredas-Concreto F'c 175 Kg/cm2 m2 443.50 45.96 20,383.26 20,383.26 ###
05.01.02.03.02 Encofrado y desencofrado m2 69.45 57.34 3,982.26 3,982.26 ###
05.01.02.03.02 juntas con asfalto exterior m 463.03 14.67 6,792.65 6,792.65 ###
05.01.03 OBRAS DE CONCRETO ARMADO ###
05.01.03.01 ZAPATAS ###
05.01.03.01.01 Zapatas - Concreto f'c=210 kg/cm2 m3 88.58 511.09 45,272.35 45,272.35 ###
05.01.03.01.02 Zapatas - Acero f'y=4200 kg/cm2 kg 1,832.79 4.95 9,072.31 9,072.31 ###
05.01.03.02 VIGAS DE CIMENTACION ###
05.01.03.02.01 VIGAS DE CIMENTACION - Concreto f'c=210 kg/cm2 m3 19.03 511.09 9,726.04 9,726.04 ###
05.01.03.02.02 VIGAS DE CIMENTACION - Acero f'y=4200 kg/cm2 kg 2,159.08 4.95 10,687.45 10,687.45 ###
05.01.03.03 COLUMNAS ###
05.01.03.03.01 Columnas - Concreto f'c=210 kg/cm2 m3 52.31 502.41 26,281.07 26,281.07 ###
05.01.03.03.02 Columnas - Encofrado y Desencofrado m2 529.26 71.29 37,730.95 37,730.95 ###
05.01.03.03.03 Columnas - Acero f'y=4200 kg/cm2 kg 7,020.08 4.92 34,538.79 34,538.79 ###
05.01.03.03.04 Columnetas de Concreto f'c= 175 kg/cm2 m3 8.78 473.74 4,159.44 4,159.44 ###
05.01.03.03.05 Columnetas - Encofrado y Desencofrado m2 116.48 50.65 5,899.71 5,899.71 ###
05.01.03.03.06 Columnetas - Acero f'y=4200 kg/cm2 kg 1,163.57 4.92 5,724.76 5,724.76 ###
05.01.03.04 VIGAS ###
05.01.03.04.01 Vigas - Concreto f'c= 210 Kg/Cm2 m3 76.97 462.27 35,580.92 35,580.92 ###
05.01.03.04.02 Vigas - Encofrado y Desencofrado m2 675.03 48.73 32,894.21 32,894.21 ###
05.01.03.04.03 Vigas - Acero fy=4200 kg/cm2 kg 8,535.91 4.92 41,996.68 41,996.68 ###
05.01.03.05 LOSA ALIGERADA ###
05.01.03.05.01 Losa Aligerada - Concreto f'c= 210 kg/cm2 m3 79.05 502.58 39,728.95 5,959.34 33,769.61 ###
05.01.03.05.02 Losa Aligerada - Encofrado y Desencofrado m2 1,044.85 40.02 41,814.90 6,272.24 35,542.67 ###
05.01.03.05.03 Losa Aligerada - Acero f'y= 4200 kg/cm2 kg 3,633.03 4.95 17,983.50 2,697.53 15,285.98 ###
05.01.03.05.04 Losa Aligerada - Ladrillo Hueco de Arcilla de 15x30x30 cm und 8,475.86 3.24 27,461.79 4,119.27 23,342.52 ###
05.01.03.06 ESCALERA ###
05.01.03.06.01 ESCALERA - Concreto f'c= 210 kg/cm2 m3 5.65 502.58 2,839.58 2,839.58 ###
05.01.03.06.02 ESCALERA - Encofrado y Desencofrado m2 23.11 40.02 924.86 924.86 ###
05.01.03.06.03 Escalera - Acero f'y= 4200 kg/cm2 kg 94.05 4.95 465.55 93.11 372.44 ###
05.01.03.07 RAMPA ###
05.01.03.07.01 Excavacion de zapatas y muros m3 14.70 23.90 351.33 298.63 52.70 ###
05.01.03.07.02 Excavacion de cimientos m3 5.64 48.17 271.68 230.93 40.75 ###
05.01.03.07.03 Relleno con material propio m3 10.50 15.31 160.76 136.65 24.11 ###
05.01.03.07.04 Eliminacion de material excedente con Equipo (d=1 km) m3 12.80 21.03 269.18 269.18 ###
05.01.03.07.05 Solado - Concreto C:H 1:10, e=10CM m2 10.89 37.55 408.92 408.92 ###
05.01.03.07.06 Zapatas - Concreto f'c=210 kg/cm2 m3 4.36 511.09 2,228.35 2,228.35 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.01.03.07.07 Zapatas - Acero f'y=4200 kg/cm2 kg 52.20 4.95 258.39 258.39 ###
05.01.03.07.08 Cimiento Corrido - Concreto Ciclopeo C:H 1:10 + 30% PG m3 4.32 462.27 1,997.01 1,997.01 ###
05.01.03.07.09 Sobrecimiento-Concreto C:H 1:8+25%PM m3 1.87 365.57 683.62 68.36 615.26 ###
05.01.03.07.10 Sobrecimientos - Encofrado y Desencofrado m2 14.94 45.97 686.79 68.68 618.11 ###
05.01.03.07.11 Muro de Ladrillo de CABEZA 9x13x24 cm m2 45.91 99.97 4,589.62 458.96 4,130.66 ###
05.01.03.07.12 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm m2 22.28 72.20 1,608.62 160.86 1,447.76 ###
05.01.03.07.13 Columnas - Concreto f'c=210 kg/cm2 m3 0.90 502.41 452.17 452.17 ###
05.01.03.07.14 Columnas - Encofrado y Desencofrado m2 20.56 71.29 1,465.72 1,465.72 ###
05.01.03.07.15 Columnas - Acero f'y=4200 kg/cm2 kg 224.25 4.92 1,103.31 1,103.31 ###
05.01.03.07.16 Vigas - Concreto f'c= 210 Kg/Cm2 m3 1.20 462.27 554.72 554.72 ###
05.01.03.07.17 Vigas - Encofrado y Desencofrado m2 16.77 48.73 817.20 817.20 ###
05.01.03.07.18 Vigas - Acero fy=4200 kg/cm2 kg 194.59 4.92 957.38 957.38 ###
05.01.03.07.19 RAMPA - Concreto f'c= 210 kg/cm2 m3 4.39 502.58 2,206.33 2,206.33 ###
05.01.03.07.20 RAMPA - Encofrado y Desencofrado m2 53.83 40.02 2,154.28 2,154.28 ###
05.01.03.07.21 Rampa - Acero f'y= 4200 kg/cm2 kg 113.36 4.95 561.13 561.13 ###
05.01.03.07.22 Tarrajeo en Columnas C:A - 1:5 m2 37.33 38.80 1,448.40 1,448.40 ###
05.01.03.07.23 Tarrajeo en exteriores mezcla C:A - 1:5 m2 136.38 37.41 5,101.98 5,101.98 ###
05.01.03.07.24 Pintura Latex en Muros Exteriores 2 manos m2 156.94 11.00 1,726.34 1,726.34 ###
05.01.03.07.25 Correas metalicas en pasadizo m 52.20 48.62 2,537.96 2,537.96 ###
05.01.03.07.26 Cobertura de policarbonato 5.80 x 1.05 m2 36.58 48.71 1,781.81 1,781.81 ###
05.01.03.08 MUROS DE CONTENCIÓN INTERNOS ###
05.01.03.08.01 Solado - Concreto C:H 1:10, e=10CM m2 115.51 37.55 4,337.40 4,337.40 ###
05.01.03.08.02 Muros de Contención - Concreto f'c=210 kg/cm2 m3 131.82 502.41 66,227.69 66,227.69 ###
05.01.03.08.03 Muros de Contención - Encofrado y Desencofrado m2 553.02 71.29 39,424.80 39,424.80 ###
05.01.03.08.04 Muros de Contención - Acero f'y=4200 kg/cm2 kg 7,191.00 4.92 35,379.72 35,379.72 ###
05.01.03.08.05 Juntas de dilatacion de c/tecknoport m 75.60 7.54 570.02 570.02 ###
05.02 ARQUITECTURA ###
05.02.01 MUROS, TABIQUES DE ABAÑILERIA ###
05.02.01.01 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm m2 649.05 72.20 46,861.41 46,861.41 ###
05.02.01.02 Muro de Ladrillo caravista 9x13x24 cm m2 178.77 89.55 16,008.85 16,008.85 ###
05.02.01.03 Muro de Ladrillo de CABEZA 9x13x24 cm m2 195.92 99.97 19,586.12 19,586.12 ###
05.02.02 REVOQUES Y REVESTIMIENTOS ###
05.02.02.01 Tarrajeo en interiores mezcla C:A - 1:5 m2 1,332.27 29.96 39,914.81 39,914.81 ###
05.02.02.02 Tarrajeo en exteriores mezcla C:A - 1:5 m2 682.75 37.41 25,541.68 25,541.68 ###
05.02.02.03 Tarrajeo en Columnas C:A - 1:5 m2 624.64 38.80 24,236.03 24,236.03 ###
05.02.02.04 Tarrajeo en Vigas, mezcla C:A - 1:5 m2 588.03 35.72 21,004.43 21,004.43 ###
05.02.02.05 Bruñas de 1/2" m 1,464.98 4.68 6,856.11 6,856.11 ###
05.02.02.06 Vestiduras de Derrames en Vanos mezcla 1:5 ML 691.18 19.47 13,457.27 13,457.27 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.02.03 CIELORRASOS ###
05.02.03.01 Cielorrasos con Tarrajeo con Mezcla de Cemento sobre Losa Aligerada m2 842.84 34.49 29,069.55 29,069.55 ###
05.02.04 PISOS Y PAVIMENTOS ###
05.02.04.01 FALSO PISO ###
05.02.04.01.01 Contrapiso de concreto f'c= 175kg/cm2 de 40 mm m2 844.65 30.58 25,829.40 25,829.40 ###
05.02.04.02 PISOS Y VEREDAS ###
05.02.04.02.01 Piso Ceramico de 30x30 antideslizante m2 65.68 53.32 3,502.06 3,151.85 350.21 ###
05.02.04.02.02 Piso porcelanato de 60 x 60 m m2 187.62 55.31 10,377.26 9,339.53 1,037.73 ###
05.02.04.02.03 Piso Madera Machihembrada m2 494.61 93.59 46,290.55 41,661.50 4,629.06 ###
05.02.04.02.04 Piso de cemento pulido m2 926.28 37.39 34,633.61 34,633.61 ###
05.02.04.03 ZOCALOS Y CONTRAZOCALOS ###
05.02.04.03.01 Zocalo de cerámico m2 111.89 26.31 2,943.83 2,943.83 ###
05.02.04.03.02 Contrazocalo de porcelanato m 133.42 51.17 6,827.10 6,827.10 ###
05.02.04.03.03 Contrazocalo de madera aguano 3/4"x4" y rodon 3/4" m 341.49 36.01 12,297.05 12,297.05 ###
05.02.04.03.04 Zocalo de pintura exterior m2 237.16 26.31 6,239.68 6,239.68 ###
05.02.05 CARPINTERIA DE MADERA ###
05.02.05.01 Puerta contraplacada de 01 hoja m2 44.48 234.01 10,408.76 10,408.76
05.02.05.02 Puerta de madera cedro nacional de 01 hoja m2 53.32 369.72 19,713.47 19,713.47
05.02.06 CARPINTERIA METALICA ###
05.02.06.01 Ventana de aluminio y accesorios m2 158.51 108.06 17,128.59 15,415.73 1,712.86
05.02.06.02 Varilla de seguridad con fierro liso 1/2" para Ventana m 190.80 64.99 12,400.09 11,160.08 1,240.01
05.02.06.03 Puerta metalica - Ingreso principal, Inc. Accesorios y colocación m2 14.85 656.80 9,753.48 8,778.13 975.35
05.02.06.04 Pintura en Puerta metalica - Ingreso principal m2 14.85 16.99 252.30 227.07 25.23
05.02.06.05 Escalera Metalica c/ Tubo de FºGº de 2" p/ Tanque Elevado Inc. pintado m 3.00 340.04 1,020.12 1,020.12
05.02.06.06 Baranda de TUBO DE ALUM de 2" para rampas m 80.87 210.07 16,988.36 16,988.36
05.02.07 CERRAJERIA ###
05.02.07.01 BISAGRAS ###
05.02.07.01.01 Bisagra aluminizada capuchina pesada de 4" x 4" pza 94.00 16.11 1,514.34 1,514.34
05.02.07.01.02 Bisagra Aluminizada capuchina pesada de 2" x 2" pza 123.00 17.96 2,209.08 2,209.08
05.02.07.02 CERRADURAS ###
05.02.07.02.01 Cerradura tipo forte de 2 golpes pza 42.00 60.91 2,558.22 2,558.22
05.02.07.03 ACCESORIOS DE CIERRE ###
05.02.07.03.01 Manija de bronce p/puertas de Ventanas c/picaporte de 2 1/2" und 48.00 26.91 1,291.68 1,291.68
05.02.07.04 VIDRIOS, CRISTALES Y SIMILARES ###
05.02.07.04.01 Vidrio templado mas lamina de seguridad en carpinteria de aluminio p2 156.06 14.43 2,251.95 2,251.95
05.02.07.04.02 Espejo Biselado (1.20mx0.60m) und 8.00 83.65 669.20 669.20
05.02.08 PINTURA ###
05.02.08.01 PINTURA EN MUROS ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.02.08.01.01 Pintura base con imprimante 2 manos m2 2,015.02 11.51 23,192.88 23,192.88
05.02.08.01.02 Pintura Latex en Muros Interiores 2 manos m2 1,332.27 11.00 14,654.97 14,654.97
05.02.08.01.03 Pintura Latex en Muros Exteriores 2 manos m2 682.75 11.00 7,510.25 7,510.25
05.02.08.01.04 Pintura Latex en columnas, vigas y derrames 2 manos m2 1,212.67 11.00 13,339.37 13,339.37
05.02.08.01.05 Vestiduras de Derrames en Vanos mezcla 1:5 m 691.18 19.47 13,457.27 13,457.27
05.02.08.02 PINTURA DE CIELOS RASOS ###
05.02.08.02.01 Pintura base con imprimante en cielorraso 02 manos m2 842.84 11.72 9,878.08 9,878.08
05.02.08.02.02 Pintura Latex en Cielorraso 02 manos m2 842.84 11.13 9,380.81 9,380.81
05.02.09 COBERTURA ###
05.02.09.01 TIJERALES METALICOS EN PASADIZOS und 34.00 603.08 20,504.72 20,504.72 ###
05.02.09.02 Correas metalicas en pasadizo m 662.36 48.62 32,203.94 32,203.94 ###
05.02.09.03 Correas de madera en techos m 2,569.35 12.57 32,296.73 32,296.73 ###
05.02.09.04 Cobertura de policarbonato 5.80 x 1.05 m2 219.76 48.71 10,704.51 10,704.51 ###
05.02.09.05 Cobertura de Techo Trapezoidal PV4 1.05 m x 3.60m 0.30 mm m2 968.67 31.53 30,542.17 30,542.17 ###
05.03 INSTALACIONES SANITARIAS ###
05.03.01 APARATOS SANITARIOS Y ACCESORIOS ###
05.03.01.01 LAVATORIOS ###
05.03.01.01.01 Lavatorio de ceramico vitrificado de 20" x 18" con pedestal Inc. Instalación und 10.00 185.28 1,852.80 1,852.80 ###
05.03.01.01.02 Lavadero de acero Inox. de 80X50CM de una poza c/escurridero und 3.00 135.00 405.00 405.00 ###
05.03.01.02 INODOROS ###
05.03.01.02.01 Inodoro Estandar de Loza Inc. Instalación und 10.00 240.11 2,401.10 2,401.10 ###
05.03.01.02.02 Baranda de apoyo plegable und 4.00 144.90 579.60 579.60 ###
05.03.01.03 URINARIOS ###
05.03.01.03.01 Urinario de loza Inc. Instalación und 3.00 97.82 293.46 293.46 ###
05.03.01.04 GRIFERIA ###
05.03.01.04.01 Grifo Cromado tipo cuello de ganso de 2 llaves und 3.00 42.00 126.00 126.00 ###
05.03.01.04.02 Grifo para lavatorio de 2 llaves und 10.00 32.00 320.00 320.00 ###
05.03.01.04.03 Grifo para ducha de dos llaves Inc. Instalación und 2.00 55.64 111.28 111.28 ###
05.03.02 SISTEMA DE DESAGUE Y VENTILACION ###
05.03.02.01 SISTEMA DE DESAGUE ###
05.03.02.01.01 Salida de Desagüe Inodoros 4" pto 10.00 59.52 595.20 595.20 ###
05.03.02.01.02 Salida de desague urinarios 2" pto 3.00 47.10 141.30 141.30 ###
05.03.02.01.03 Salida de Desagüe Lavatorios 2" pto 13.00 48.46 629.98 629.98 ###
05.03.02.01.04 Salida de Desagüe Sumideros 2" pto 15.00 55.15 827.25 827.25 ###
05.03.02.01.05 Salida de Desagüe para Registro Roscado 4" pto 8.00 54.55 436.40 436.40 ###
05.03.02.02 SISTEMA DE REDES DE DESAGUE ###
05.03.02.02.01 Red colectora PVC para Desague de 4" m 87.88 20.31 1,784.84 1,784.84 ###
05.03.02.02.02 Red colectora PVC para Desague de 2" m 24.74 30.59 756.80 756.80 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.03.02.03 ACCESORIOS VARIOS ###
05.03.02.03.01 Sumidero Cromado de 2" und 15.00 24.09 361.35 361.35 ###
05.03.02.03.02 Registro Roscado Ø 4" und 8.00 50.70 405.60 405.60 ###
05.03.02.03.03 Uniones Yee PVC SAL Ø 2" x 2" und 16.00 28.39 454.24 454.24 ###
05.03.02.03.04 Uniones Yee PVC SAL Ø 4" x 2" und 10.00 34.49 344.90 344.90 ###
05.03.02.03.05 Codo PVC SAL Ø 4" x 4" a 90º und 17.00 18.37 312.29 312.29 ###
05.03.02.03.06 Codo PVC SAL Ø 2*2" a 90º und 4.00 18.37 73.48 40.41 33.07 ###
05.03.02.03.07 Reduccion PVC SAL Ø 4" a 2" und 5.00 17.96 89.80 89.80 ###
05.03.02.04 CAJAS DE INSPECCION Y CONEXIONES ###
05.03.02.04.01 Caja de Registro de Desagüe de 10"x20" und 3.00 147.05 441.15 441.15 ###
05.03.02.05 VENTILACIÓN ###
05.03.02.05.01 Sombrero de Ventilación PVC SAL Ø 2" pto 17.00 11.42 194.14 194.14 ###
05.03.02.05.02 Salida PVC SAL para Ventilación Ø 2" h=2.60m pto 17.00 79.41 1,349.97 1,349.97 ###
05.03.02.06 PRUEBAS HIDRAULICAS ###
05.03.02.06.01 Prueba hidráulica en Red de Desague y Desinfeccion m 106.22 3.33 353.71 353.71 ###
05.03.03 SISTEMA DE AGUA FRIA ###
05.03.03.01 SALIDA PARA PUNTOS DE AGUA FRIA ###
05.03.03.01.01 Salida de agua para Inodoros Tanque Bajo pto 10.00 47.65 476.50 476.50 ###
05.03.03.01.02 Salida de agua en Urinarios pto 3.00 44.74 134.22 134.22 ###
05.03.03.01.03 Salida de agua en Lavatorios pto 13.00 44.74 581.62 581.62 ###
05.03.03.02 REDES DE DISTRIBUCION Y MONTAJE ###
05.03.03.02.01 Tuberia PVC SAP Ø 1/2" m 150.46 14.59 2,195.21 2,195.21 ###
05.03.03.03 ACCESORIOS VARIOS ###
05.03.03.03.01 Tee PVC SAP de 1/2" und 10.00 30.17 301.70 301.70 ###
05.03.03.03.02 Codo PVC SAP Ø 1/2" x 90º und 27.00 22.40 604.80 604.80 ###
05.03.03.04 LLAVES Y VALVULAS ###
05.03.03.04.01 Valvula de Globo de 1/2", incl. accesorios und 4.00 55.57 222.28 222.28 ###
05.03.03.04.02 Caja de Valvula con Tapa F°G° und 11.00 144.66 1,591.26 1,591.26 ###
05.03.03.05 PRUEBAS HIDRAULICAS ###
Prueba hidráulicaen red de agua y desinfeccion
05.03.03.05.01 m 150.46 3.06 460.41 460.41 ###
05.03.03.06 INSTALACIONES ESPECIALES ###
05.03.03.06.01 Instalacion de accesorios de Tanque Elevado und 1.00 1,622.10 1,622.10 1,622.10 ###
05.03.03.06.02 Instalacion de tanque cisterna und 1.00 3,622.10 3,622.10 3,622.10 ###
05.03.03.06.03 suministro e instalacion de electrobomba 1hp und 1.00 522.10 522.10 522.10 ###
05.03.04 SISTEMA DE DRENAJE PLUVIAL ###
CANALETA SEMICIRC. GALVANIZ. D=4 DESAGUE PLUVIAL
05.03.04.01 m 270.93 23.58 6,388.53 6,388.53 ###
Tuberia PVC 3" de bajada de drenaje pluvial
05.03.04.02 m 41.00 68.20 2,796.20 2,796.20 ###
05.03.05 SISTEMA DE AGUA CALIENTE ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.03.05.01 SALIDA PARA PUNTOS DE AGUA CALIENTE ###
05.03.05.01.01 Salida de agua en Lavatorios pto 15.00 44.74 671.10 671.10 ###
05.03.05.02 REDES DE DISTRIBUCION ###
05.03.05.02.01 Tuberia PVC SAP Ø 1/2" m 67.71 14.59 987.89 987.89 ###
05.03.05.03 ACCESORIOS VARIOS ###
05.03.05.03.01 Tee PVC SAP de 1/2" und 8.00 30.17 241.36 241.36 ###
05.03.05.03.02 Codo PVC SAP Ø 1/2" x 90º und 12.00 22.40 268.80 268.80 ###
05.03.05.03.03 Valvula de Globo de 1/2", incl accesorios und 11.00 55.57 611.27 611.27 ###
05.03.05.03.04 Terma Electrica und 1.00 2,612.09 2,612.09 2,612.09 ###
05.03.05.04 PRUEBAS HIDRAULICAS ###
05.03.05.04.01 Prueba hidráulicaen red de agua y desinfeccion m 67.71 3.06 207.19 207.19 ###
05.04 INSTALACIONES ELECTRICAS ###
05.04.01 SALIDA PARA INSTALACIONES ELÉCTRICAS ###
05.04.01.01 Salida para Centro de Luz Techo y Pared pto 118.00 93.19 10,996.42 10,996.42 ###
05.04.01.02 Salida tomacorriente doble con tierra en Piso con caja Hermetica pto 13.00 104.84 1,362.92 1,362.92 ###
05.04.01.03 TOMACORRIENTE MONOFASICO DOBLE,SUELO / TECHO pto 1.00 104.84 104.84 104.84 ###
05.04.01.04 Salida tomacorriente doble con tierra en Piso con caja Hermetica pto 71.00 104.84 7,443.64 7,443.64 ###
05.04.01.05 Interruptor unipolar simple con placa de acero inoxidable pto 21.00 61.71 1,295.91 1,295.91 ###
05.04.01.06 Interruptor unipolar doble con placa de acero inoxidable pto 14.00 43.71 611.94 611.94 ###
05.04.01.07 Interruptor de conmutación con placa de acero inoxidable pto 4.00 64.71 258.84 258.84 ###
05.04.01.08 Salida Luz Emergencia de Bateria pto 10.00 35.88 358.80 358.80 ###
05.04.01.09 Salida para Pulsador de Timbre pto 2.00 53.32 106.64 63.98 42.66 ###
05.04.01.10 salida de telefono-internet pto 4.00 75.11 300.44 300.44 ###
05.04.01.11 Salida doble de video hdmi y audio rca conexión a equipo sonido pto 8.00 115.98 927.84 927.84 ###
05.04.01.12 Salida de parlantes pto 16.00 73.65 1,178.40 1,178.40 ###
05.04.02 CANALIZACIONES, CONDUCTOS O TUBERÍAS ###
05.04.02.01 Tubería Empotrada Alumbrado y Tomacorrientes PVC SAP NTP 399.006 DE 20 mm m 938.42 15.44 14,489.20 14,489.20 ###
05.04.02.02 Tubería Empotrada DE linea telefonica internet m 86.12 15.44 1,329.69 1,329.69 ###
05.04.02.03 tuberia empotrada para timbre m 18.06 15.44 278.85 278.85 ###
05.04.02.04 Curva PVC SAP NTP 399.006 DE 50 mm und 472.00 6.52 3,077.44 3,077.44 ###
05.04.03 CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS ###
05.04.03.01 Cable NH-80 DE 6 mm2 ALIMENTADORES m 1,079.18 6.98 7,532.68 7,532.68 ###
05.04.03.02 Cable NH-80 DE 4 mm2 ALIMENTADORES m 94.51 5.98 565.17 565.17 ###
05.04.03.03 Cable N2XOH de 1 x 6 mm2 m 62.13 6.98 433.67 433.67 ###
05.04.03.04 Cable para internet RJ45 8P8C m 86.12 6.98 601.12 601.12 ###
05.04.03.05 Cable de Audio Apantallado para parlantes m 27.66 3.52 97.36 97.36 ###
05.04.04 SISTEMA DE CONDUCTOS ###
05.04.04.01 Canaleta para conductor enterrado m 94.51 53.72 5,077.08 5,077.08 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
05.04.05 TABLEROS DE DISTRIBUCION ###
05.04.05.01 TABLERO GENERAL DE F°G° TRIFASICO 380/220 PARA EMPOTRAR CON BASE 20 POLOS pza 1.00 479.82 479.82 479.82 ###
05.04.05.02 TABLERO DE F°G° TRIFASICO 380/220 PARA EMPOTRAR CON BASE 10 POLOS INTERR. pza 5.00 428.07 2,140.35 2,140.35 ###
05.04.06 DISPOSITIVOS DE MANIOBRA Y PROTECCION ###
05.04.06.01 Interruptor simple con placa de acero inoxidable pza 21.00 23.26 488.46 488.46 ###
05.04.06.02 Interruptor doble con placa de acero inoxidable pza 14.00 41.61 582.54 582.54 ###
05.04.06.03 Interruptor de conmutación con placa de acero inoxidable pza 4.00 59.61 238.44 238.44 ###
05.04.07 ARTEFACTOS ###
05.04.07.01 Luminaria con Dos Lámparas Fluorescentes T8 de 36W, Rejilla Aluminizada P/Adosar al techo. (ElemeEQP 61.00 132.27 8,068.47 8,068.47 ###
05.04.07.02 Luminaria de Sección Circular P/Adosar Con Dos Lámparas Ahorradoras De 1x14 W, E - 27 Sistem und 28.00 175.67 4,918.76 4,918.76 ###
05.04.07.03 Luminaria tipo braquet termoformado con una lampara fluorescente de 50 W, E - 27 con difusor acrilico EQP 42.00 152.79 6,417.18 6,417.18 ###
05.04.07.04 Equipo de luz de emergencia portatil con lampara de halogeno 2x8watt und 10.00 117.17 1,171.70 1,171.70 ###
05.04.08 EQUIPOS ELECTRICOS, MECANICOS Y ESPECIALES ###
05.04.08.01 Pozo de puesta a tierra EQP 5.00 1,331.91 6,659.55 6,659.55 ###
05.04.08.02 Acometida de Energia Electrica, Incluye red de baja tension independiente glb 1.00 350.00 350.00 350.00 ###
05.04.08.03 CAJA DE PASO jgo 6.00 0.00 0.00 - ###
05.04.08.04 Timbre de 8" CON IP 66 jgo 2.00 88.67 177.34 177.34 ###
05.04.08.05 Pruebas Electricas (Aislamiento y Continuidad) glb 1.00 1,254.24 1,254.24 1,254.24 ###
05.04.08.06 Pruebas Electricas (Resistencia de Puesta a tierra) und 5.00 169.49 847.45 847.45 ###
06 LOSA DEPORTIVA ###
06.01 LOSA ###
06.01.01 Excavacion de losa m3 193.92 41.28 8,005.02 8,005.02 ###
06.01.02 Nivelacion Interior y Apisonado m2 646.40 1.35 872.64 872.64 ###
06.01.03 Base granular compactado e= 0.15 cm m3 96.96 21.60 2,094.34 2,094.34 ###
06.01.04 Concreto f'c= 210 Kg/Cm2 m3 96.96 520.01 50,420.17 50,420.17 ###
06.01.05 Encofrado y desencofrado m2 56.07 57.34 3,215.05 3,215.05 ###
06.01.06 Junta de construccion m 269.40 5.88 1,584.07 1,584.07 ###
06.01.07 Pintura de marcas en Losa m 321.00 7.58 2,433.18 2,433.18 ###
06.01.08 Piso de cemento pulido m2 640.00 37.39 23,929.60 23,929.60 ###
06.01.09 Arco multifuncional+tablero de basquetbol und 2.00 1,864.41 3,728.82 3,728.82 ###
06.01.10 Postes para net und 1.00 254.24 254.24 254.24 ###
REFLECTORES HALOGENURO DE 400 W
06.01.11 EQP 4.00 412.22 1,648.88 1,648.88 ###
06.01.12 Salida para reflectores pto 4.00 88.48 353.92 353.92 ###
06.01.13 Salida tomacorriente doble con tierra en Piso con caja Hermetica pto 2.00 104.84 209.68 209.68 ###
06.01.14 Interruptor unipolar simple con placa de acero inoxidable pto 1.00 61.71 61.71 61.71 ###
06.01.15 Tubería Empotrada para alumbrado exterior PVC SAP NTP 399.006 DE 40 mm m 82.35 17.94 1,477.36 1,477.36 ###
06.01.16 Cable NH-80 de 1 x 6 mm2 m 82.35 6.98 574.80 574.80 ###
06.01.17 Interruptor simple con placa de acero inoxidable pza 2.00 23.26 46.52 46.52 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
06.01.18 Interruptor doble con placa de acero inoxidable pza 1.00 49.76 49.76 49.76 ###
06.01.19 Cable N2XOH de 1 x 6 mm2 m 20.18 6.98 140.86 140.86 ###
06.02 COBERTURA METALICA ###
06.02.01 Excavacion zapatas para cobertura m3 104.54 48.17 5,035.69 5,035.69 ###
06.02.02 Relleno con material propio m3 27.10 15.31 414.90 414.90 ###
06.02.03 Solado - Concreto C:H 1:10, e=10CM m2 5.81 37.55 218.17 218.17 ###
06.02.04 Zapatas - Concreto f'c=210 kg/cm2 m3 34.85 511.09 17,811.49 17,811.49 ###
06.02.05 Zapatas - Acero f'y=4200 kg/cm2 kg 1,193.19 4.95 5,906.29 5,906.29 ###
06.02.06 Columnas - Concreto f'c=210 kg/cm2 m3 19.15 502.41 9,621.15 9,621.15 ###
06.02.07 Columnas - Encofrado y Desencofrado m2 159.60 71.29 11,377.88 11,377.88 ###
06.02.08 Columnas - Acero f'y=4200 kg/cm2 kg 4,236.18 4.92 20,842.01 20,842.01 ###
06.02.09 Vigas - Concreto f'c= 210 Kg/Cm2 m3 25.06 462.27 11,584.49 11,584.49 ###
06.02.10 Vigas - Encofrado y Desencofrado m2 161.28 48.73 7,859.17 7,859.17 ###
06.02.11 Vigas - Acero fy=4200 kg/cm2 kg 1,905.66 4.92 9,375.85 9,375.85 ###
06.02.12 Tarrajeo en Columnas C:A - 1:5 m2 387.08 38.80 15,018.70 15,018.70 ###
06.02.13 Pintura Latex en columnas, vigas y derrames 2 manos m2 387.08 11.00 4,257.88 4,257.88 ###
06.02.14 Tijerales metalicos und 6.00 8,465.15 50,790.90 50,790.90 ###
06.02.15 Correas metalicas en techo m 627.00 48.62 30,484.74 30,484.74 ###
06.02.16 Cobertura de policarbonato 5.90x2.10 m2 201.50 48.71 9,815.07 9,815.07 ###
06.02.17 Cobertura techo UPVC 1.07x3.60 m2 675.64 48.71 32,910.42 32,910.42 ###
06.02.18 Izaje de tijerales de estrutura metalica und 6.00 334.37 2,006.22 2,006.22 ###
06.02.19 Habilitado y Doblado de acero m 416.00 1.48 615.68 615.68 ###
06.02.20 Encuentro de viga de acero y columna de concreto und 12.00 201.83 2,421.96 2,421.96 ###
06.02.21 Cobertura Vertical de policarbonato m2 157.52 150.20 23,659.50 23,659.50 ###
07 OBRAS EXTERIORES ###
07.01 CERCO PERIMETRICO ###
07.01.01 Excavacion de zanja para cimiento de cerco m3 7.25 48.17 349.23 349.23 ###
07.01.02 Eliminacion de material excedente con Equipo (d=1 km) m3 9.43 21.03 198.31 198.31 ###
07.01.03 Cimiento Concreto simple F´c=175 kg/cm2 m3 4.58 462.27 2,117.20 2,117.20 ###
07.01.04 Cerco Perimetrico con Malla Olimpica Galvanizada m2 146.89 169.21 24,855.26 24,855.26 ###
07.01.05 TUBO DE CERCO INCL PINTURA und 53.00 174.82 9,265.46 9,265.46 ###
07.01.06 Sobrecimiento-Concreto C:H 1:8+25%PM m3 1.49 365.57 544.70 544.70 ###
07.01.07 Sobrecimientos - Encofrado y Desencofrado m2 11.92 45.97 547.96 547.96 ###
07.01.08 Columnas - Concreto f'c=210 kg/cm2 m3 1.13 502.41 567.72 567.72 ###
07.01.09 Columnas - Encofrado y Desencofrado m2 18.15 71.29 1,293.91 1,293.91 ###
07.01.10 Columnas - Acero f'y=4200 kg/cm2 kg 104.88 4.92 516.01 516.01 ###
07.01.11 Muro de Ladrillo KK de Soga C:A 1:4 de 24 X 13 X 9 cm m2 34.05 72.20 2,458.41 2,458.41 ###
07.01.12 Vigas - Concreto f'c= 210 Kg/Cm2 m3 0.56 462.27 258.87 258.87 ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
07.01.13 Vigas - Encofrado y Desencofrado m2 9.68 48.73 471.71 471.71 ###
07.01.14 Vigas - Acero fy=4200 kg/cm2 kg 88.45 4.92 435.17 435.17 ###
07.01.15 Tarrajeo en Columnas C:A - 1:5 m2 18.15 38.80 704.22 704.22
07.01.16 Tarrajeo en vigas C:A - 1:5 m2 9.68 61.66 596.87 596.87
07.01.17 Tarrajeo en muros m2 68.10 37.41 2,547.62 2,547.62
07.02 MUROS DE CONTENCION ###
07.02.01 Excavacion para muro de contención con maquinaria m3 262.82 48.17 12,660.04 12,660.04 ###
07.02.02 Relleno con material de propio - manual m3 78.63 15.31 1,203.83 1,203.83 ###
07.02.03 Eliminacion de material excedente con Equipo (d=1 km) m3 186.53 21.03 3,922.73 3,922.73 ###
07.02.04 Solado - Concreto C:H 1:10, e=10CM m2 107.18 37.55 4,024.61 4,024.61 ###
07.02.05 Encofrado y desencofrado m2 307.35 57.34 17,623.45 17,623.45 ###
07.02.06 Muro de gravedad - Concreto Ciclopeo C:H 1:10 + 30% PG m3 44.38 462.27 20,515.54 20,515.54 ###
07.02.07 Muros de Contención - Concreto f'c=210 kg/cm2 m3 112.47 502.41 56,506.05 56,506.05 ###
07.02.08 Muros - Acero f'y= 4200 kg/cm2 kg 5,055.76 4.95 25,026.01 25,026.01 ###
07.02.09 Juntas de dilatacion de c/tecknoport m 34.20 7.54 257.87 257.87 ###
07.03 CERCO EN LOSA DEPORTIVA ###
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
07.03.01 Columna - Concreto f'c= 175 kg/cm2 m3 5.12 462.27 2,366.82 2,366.82
07.03.02 Columna - Encofrado y desencofrado m2 81.90 57.34 4,696.15 4,696.15
07.03.03 Columna - Acero fy=4200 kg/cm2 kg 655.69 4.95 3,245.67 3,245.67
07.03.04 Muro de Ladrillo caravista 9x13x24 cm m2 539.76 89.55 48,335.51 48,335.51
07.03.05 Vigas - Concreto f'c= 175 Kg/Cm2 m3 2.10 462.27 970.77 970.77
07.03.06 Vigas - Encofrado y Desencofrado m2 36.40 48.73 1,773.77 1,773.77
07.03.07 Vigas - Acero fy=4200 kg/cm2 kg 447.60 4.92 2,202.19 2,202.19
07.03.08 Tarrajeo en Columnas C:A - 1:5 m2 66.15 38.80 2,566.62 2,566.62
07.03.09 Tarrajeo en vigas C:A - 1:5 m2 36.40 61.66 2,244.42 2,244.42
07.03.10 Tarrajeo en muros DE CERCO DE LOSA m2 251.90 37.41 9,423.58 9,423.58
07.05 ASTA DE BANDERA CON BASE CIRCULAR ###
07.05.01 Concreto f'c= 175 kg/cm2 m3 2.69 462.27 1,243.51 1,243.51 ###
07.05.02 Encofrado y desencofrado m2 3.98 57.34 228.21 228.21 ###
07.05.03 Acero fy=4200 kg/cm2 kg 4.23 4.95 20.94 20.94 ###
07.05.04 Asta de bandera und 1.00 1,385.99 1,385.99 1,385.99 ###
08 FLETE TERRESTRE ###
08.01 Flete terreste glb 1.00 330,495.25 330,495.25 66,099.05 66,099.05 66,099.05 66,099.05 66,099.05 ###

### ### ### ### ### ###

MES 01 MES 02 MES 03 MES 04 MES 05 MES 06


COSTO DIRECTO S/. 2,949,331.12 S/. 312,738.84 S/. 523,906.01 S/. 553,329.05 S/. 722,413.33 S/. 599,228.24 S/. 237,715.65
GASTOS GENERALES (10%) 10.00% S/. 294,933.11 S/. 31,273.88 S/. 52,390.60 S/. 55,332.91 S/. 72,241.33 S/. 59,922.82 S/. 23,771.57
UTILIDAD (8%) 8.00% S/. 235,946.49 S/. 25,019.11 S/. 41,912.48 S/. 44,266.32 S/. 57,793.07 S/. 47,938.26 S/. 19,017.25
SUB TOTAL S/. 3,480,210.72 S/. 369,031.83 S/. 618,209.09 S/. 652,928.28 S/. 852,447.73 S/. 707,089.32 S/. 280,504.47
I.G.V. (18%) 18.00% S/. 626,437.93 S/. 66,425.73 S/. 111,277.64 S/. 117,527.09 S/. 153,440.59 S/. 127,276.08 S/. 50,490.80
COSTO DE EJECUCION DE OBRA S/. 4,106,648.65 S/. 435,457.56 S/. 729,486.73 S/. 770,455.37 S/. 1,005,888.32 S/. 834,365.40 S/. 330,995.27
PLAN DE CONTINGENCIA S/. 20,000.00 S/. 3,333.33 S/. 3,333.33 S/. 3,333.33 S/. 3,333.33 S/. 3,333.34 S/. 3,333.34
MOBILIARIO Y EQUIPAMIENTO S/. 201,150.23 S/. 33,525.04 S/. 33,525.04 S/. 33,525.04 S/. 33,525.04 S/. 33,525.04 S/. 33,525.03
VALOR REFERENCIAL S/. 4,327,798.88 S/. 472,315.93 S/. 766,345.10 S/. 807,313.74 S/. 1,042,746.69 S/. 871,223.78 S/. 367,853.64
SUPERVISION (5%) CD 5.00% S/. 147,466.56 S/. 15,636.94 S/. 26,195.30 S/. 27,666.45 S/. 36,120.67 S/. 29,961.41 S/. 11,885.79
VALOR DE FINANCIAMIENTO S/. 4,475,265.44 S/. 487,952.87 S/. 792,540.40 S/. 834,980.19 S/. 1,078,867.36 S/. 901,185.19 S/. 379,739.43
%AVANCE 10.60 % 17.76 % 18.76 % 24.49 % 20.32 % 8.06 %
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

Proyecto “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”

Cliente:MUNICIPALIDAD DISTRITAL DE SURCUBAMBA

Lugar: HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE

CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
%ACUMULADO 10.60 % 28.37 % 47.13 % 71.62 % 91.94 % 100.00 %
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
01 OBRAS PROVISIONALES
01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 Alquiler de almacen de obra mes 6.00 423.73 2,542.38 363.20 363.20 363.20 363.20 363.20 363.20 363.20
01.01.02 Cartel de Identificacion de Obra und 1.00 1,695.93 1,695.93 1,695.93
01.01.03 Servicios higienicos durante la ej mes 6.00 254.24 1,525.44 1,525.44
01.01.04 Cerco Provisional de Calamina m 205.27 49.65 10,191.66 10,191.66
01.02 INSTALACIONES PROVISIONALES
01.02.01 Agua para la construcción glb 1.00 500.00 500.00 500.00
01.02.02 Energia electrica para la construc glb 1.00 2,000.00 2,000.00 2,000.00
02 TRABAJOS PRELIMINARES
02.01 Limpieza de Terreno Manual m2 2,895.00 0.68 1,968.60 1,968.60
02.02 Trazo, Niveles y Replanteo Prelimin m2 2,551.89 3.22 8,217.09 2,054.27 6,162.82
02.03 Movilizacion y desmovilizacion de glb 1.00 33,118.64 33,118.64 8,279.66 8,279.66 16,559.32
02.04 DEMOLICIONES
02.04.01 Demolicion de muros de adobe m3 615.10 25.00 15,377.50 15,377.50
02.04.02 Demolicion de falso piso de conc m3 120.14 91.92 11,043.27 11,043.27
02.04.03 Demolicion de cimentacion m3 90.01 216.08 19,449.36 19,449.36
02.04.04 Desmontaje de puertas und 26.00 16.21 421.46 421.46
02.04.05 Desmontaje de ventanas und 35.00 12.96 453.60 453.60
02.04.06 Desmontaje de paredes prefabric und 8.00 42.05 336.40 336.40
02.04.07 Desmontaje de barandas m2 17.00 28.03 476.51 476.51
02.04.08 Desmontaje de aparatos sanitario und 6.00 40.52 243.12 243.12
02.04.09 Desmontaje de tijetales de mader und 72.00 45.92 3,306.24 3,306.24
02.04.10 Desmontaje de coberturas m2 1,201.36 18.23 21,900.79 21,900.79
02.04.11 Eliminacion de material excedent m3 1,072.82 21.03 22,561.40 6,768.42 15,792.98
02.05 MOVIMIENTO DE TIERRAS
02.05.01 CORTES
02.05.01.01 Corte masivo de terreno narutal m3 1,820.52 11.78 21,445.73 6,433.72 15,012.01
02.05.02 NIVELACION INTERIOR Y APISONADO
02.05.02.01 Nivelacion Interior y Apisonado m2 2,345.00 1.35 3,165.75 3,165.75
02.05.03 RELLENO CON MATERIAL PROPIO
02.05.03.01 Relleno con material propio m3 650.23 15.31 9,955.02 9,955.02
02.05.03.02 Eliminacion de material exced m3 1,521.46 21.03 31,996.30 31,996.30
03 SISTEMA DE DRENAJE
03.01 SISTEMA DE DRENAJE PLUVIAL SUPERFICIAL
03.01.01 Excavacion de zanja para drenaje m3p 34.08 41.28 1,406.82 1,406.82
03.01.02 Eliminacion de material excedent m3 44.30 21.03 931.63 931.63
03.01.03 Concreto f'c= 210 Kg/Cm2 m3 17.48 520.01 9,089.77 9,089.77
03.01.04 Encofrado y desencofrado m2 131.06 57.34 7,514.98 7,514.98
03.01.05 Acabado y Revestimiento en drenm2 174.75 37.39 6,533.90 6,533.90
03.01.06 Rejilla Metalica p/Canal Evac. Agum 218.44 101.59 22,191.32 22,191.32
03.01.07 Caja de Registro de Drenaje pluvi und 3.00 152.05 456.15 456.15
04 SEGURIDAD Y SALUD
04.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO
04.01.01 Elaboracion, Implementacion y ad glb 1.00 847.45 847.45 847.45
04.01.02 Equipos de Proteccion Individual und 30.00 299.20 8,976.00 1,795.20 7,180.80
04.01.03 Equipos de Proteccion Colectiva glb 1.00 2,800.00 2,800.00 1,120.00 1,680.00
04.01.04 Señalizacion Temporal de Seguridglb 1.00 654.81 654.81 654.81
04.01.05 Capacitacion en Seguridad y Salu und 1.00 1,400.00 1,400.00 1,400.00
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
04.01.06 Recursos para Respuestas ante glb 1.00 700.00 700.00 700.00
04.02 CURADO Y PROTECCION DEL CONCRETO
04.02.01 Curado y proteccion del concreto m2 4,200.00 2.87 12,054.00 3,977.82 2,049.18 2,049.18 1,928.64 2,049.18
05 MODULO EDUCATIVO
05.01 ESTRUCTURAS
05.01.01 MOVIMIENTO DE TIERRAS
05.01.01.01 EXCAVACIONES
05.01.01.01.01 Excavacion de zapatas y murom3 323.70 23.90 7,736.43 5,802.32 1,934.11
05.01.01.01.02 Excavacion de cimientos m3 221.59 48.17 10,673.99 8,005.49 2,668.50
05.01.01.02 RELLENO CON MATERIAL PROPIO
05.01.01.02.01 Relleno con material propio m3 210.50 15.31 3,222.76 1,772.52 1,450.24
05.01.01.02.02 Eliminacion de material exc m3 435.23 21.03 9,152.89 5,034.09 4,118.80
05.01.01.03 NIVELACION DE TERRENO
05.01.01.03.01 Nivelacion Interior y Apisonad m2 728.78 1.35 983.85 983.85
05.01.02 OBRAS DE CONCRETO SIMPLE
05.01.02.01 ZAPATAS
05.01.02.01.01 Solado - Concreto C:H 1:10, m2 256.14 37.55 9,618.06 6,732.64 2,885.42
05.01.02.01.02 falsa zapata - Concreto , e=3 m3 45.74 298.32 13,645.16 13,645.16
05.01.02.02 CIMIENTO CORRIDO
05.01.02.02.01 Cimiento Corrido - Concret m3 65.85 462.27 30,440.48 19,786.31 10,654.17
05.01.02.02.02 Sobrecimiento-Concreto C: m3 29.10 365.57 10,638.09 6,914.76 3,723.33
05.01.02.02.03 Sobrecimientos - Encofrado m2 299.72 45.97 13,778.13 8,955.78 4,822.35
05.01.02.03 PISO DE CONCRETO Y VEREDAS
05.01.02.03.01 PISOS INTERIORES
05.01.02.03.01.01 Falso piso en interiores-C m2 663.28 45.96 30,484.35 30,484.35
05.01.02.03.02 PISOS EXTERIORES
05.01.02.03.02.01 Piso de patio de formacio m2 715.28 45.96 32,874.27 16,437.14 16,437.13
05.01.02.03.02.02 pisos exteriores-Concreto m2 354.36 45.96 16,286.39 8,143.20 8,143.19
05.01.02.03.02.03 veredas-Concreto F'c 175 m2 443.50 45.96 20,383.26 10,191.63 10,191.63
05.01.02.03.02.04 Encofrado y desencofrado m2 69.45 57.34 3,982.26 1,991.13 1,991.13
05.01.02.03.02.05 juntas con asfalto exterior m 463.03 14.67 6,792.65 6,792.65
05.01.03 OBRAS DE CONCRETO ARMADO
05.01.03.01 ZAPATAS
05.01.03.01.01 Zapatas - Concreto f'c=210 k m3 88.58 511.09 45,272.35 38,481.50 6,790.85
05.01.03.01.02 Zapatas - Acero f'y=4200 kg/ kg 1,832.79 4.95 9,072.31 7,711.46 1,360.85
05.01.03.02 VIGAS DE CIMENTACION
05.01.03.02.01 VIGAS DE CIMENTACION - Cm3 19.03 511.09 9,726.04 9,726.04
05.01.03.02.02 VIGAS DE CIMENTACION - A kg 2,159.08 4.95 10,687.45 10,687.45
05.01.03.03 COLUMNAS
05.01.03.03.01 Columnas - Concreto f'c=210 m3 52.31 502.41 26,281.07 7,884.32 13,140.54 5,256.21
05.01.03.03.02 Columnas - Encofrado y Dese m2 529.26 71.29 37,730.95 11,319.29 18,865.48 7,546.18
05.01.03.03.03 Columnas - Acero f'y=4200 k kg 7,020.08 4.92 34,538.79 10,361.64 17,269.40 6,907.75
05.01.03.03.04 Columnetas de Concreto f'c= m3 8.78 473.74 4,159.44 3,327.55 831.89
05.01.03.03.05 Columnetas - Encofrado y De m2 116.48 50.65 5,899.71 4,719.77 1,179.94
05.01.03.03.06 Columnetas - Acero f'y=4200 kg 1,163.57 4.92 5,724.76 1,717.43 2,862.38 1,144.95
05.01.03.04 VIGAS
05.01.03.04.01 Vigas - Concreto f'c= 210 Kg m3 76.97 462.27 35,580.92 19,569.51 16,011.41
05.01.03.04.02 Vigas - Encofrado y Desencof m2 675.03 48.73 32,894.21 18,091.82 14,802.39
05.01.03.04.03 Vigas - Acero fy=4200 kg/cm2 kg 8,535.91 4.92 41,996.68 23,098.17 18,898.51
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
05.01.03.05 LOSA ALIGERADA
05.01.03.05.01 Losa Aligerada - Concreto f' m3 79.05 502.58 39,728.95 13,905.13 25,823.82
05.01.03.05.02 Losa Aligerada - Encofrado m2 1,044.85 40.02 41,814.90 14,635.22 27,179.68
05.01.03.05.03 Losa Aligerada - Acero f'y= kg 3,633.03 4.95 17,983.50 6,294.23 11,689.27
05.01.03.05.04 Losa Aligerada - Ladrillo H und 8,475.86 3.24 27,461.79 9,611.63 17,850.16
05.01.03.06 ESCALERA
05.01.03.06.01 ESCALERA - Concreto f'c= m3 5.65 502.58 2,839.58 2,839.58
05.01.03.06.02 ESCALERA - Encofrado y De m2 23.11 40.02 924.86 924.86
05.01.03.06.03 Escalera - Acero f'y= 4200 kg kg 94.05 4.95 465.55 465.55
05.01.03.07 RAMPA
05.01.03.07.01 Excavacion de zapatas y murom3 14.70 23.90 351.33 351.33
05.01.03.07.02 Excavacion de cimientos m3 5.64 48.17 271.68 271.68
05.01.03.07.03 Relleno con material propio m3 10.50 15.31 160.76 160.76
05.01.03.07.04 Eliminacion de material exc m3 12.80 21.03 269.18 269.18
05.01.03.07.05 Solado - Concreto C:H 1:10, m2 10.89 37.55 408.92 408.92
05.01.03.07.06 Zapatas - Concreto f'c=210 k m3 4.36 511.09 2,228.35 2,228.35
05.01.03.07.07 Zapatas - Acero f'y=4200 kg/ kg 52.20 4.95 258.39 258.39
05.01.03.07.08 Cimiento Corrido - Concret m3 4.32 462.27 1,997.01 1,997.01
05.01.03.07.09 Sobrecimiento-Concreto C: m3 1.87 365.57 683.62 683.62
05.01.03.07.10 Sobrecimientos - Encofrado m2 14.94 45.97 686.79 686.79
05.01.03.07.11 Muro de Ladrillo de CABEZA m2 45.91 99.97 4,589.62 4,589.62
05.01.03.07.12 Muro de Ladrillo KK de Soga m2 22.28 72.20 1,608.62 1,608.62
05.01.03.07.13 Columnas - Concreto f'c=210 m3 0.90 502.41 452.17 452.17
05.01.03.07.14 Columnas - Encofrado y Dese m2 20.56 71.29 1,465.72 1,465.72
05.01.03.07.15 Columnas - Acero f'y=4200 k kg 224.25 4.92 1,103.31 1,103.31
05.01.03.07.16 Vigas - Concreto f'c= 210 Kg m3 1.20 462.27 554.72 554.72
05.01.03.07.17 Vigas - Encofrado y Desencof m2 16.77 48.73 817.20 817.20
05.01.03.07.18 Vigas - Acero fy=4200 kg/cm2 kg 194.59 4.92 957.38 957.38
05.01.03.07.19 RAMPA - Concreto f'c= 210 m3 4.39 502.58 2,206.33 2,206.33
05.01.03.07.20 RAMPA - Encofrado y Desenc m2 53.83 40.02 2,154.28 2,154.28
05.01.03.07.21 Rampa - Acero f'y= 4200 kg/c kg 113.36 4.95 561.13 561.13
05.01.03.07.22 Tarrajeo en Columnas C:A - m2 37.33 38.80 1,448.40 1,448.40
05.01.03.07.23 Tarrajeo en exteriores mezcla m2 136.38 37.41 5,101.98 5,101.98
05.01.03.07.24 Pintura Latex en Muros Exter m2 156.94 11.00 1,726.34 1,726.34
05.01.03.07.25 Correas metalicas en pasadizom 52.20 48.62 2,537.96 2,537.96
05.01.03.07.26 Cobertura de policarbonato 5. m2 36.58 48.71 1,781.81 1,781.81
05.01.03.08 MUROS DE CONTENCIÓN INTERNOS
05.01.03.08.01 Solado - Concreto C:H 1:10, m2 115.51 37.55 4,337.40 4,337.40
05.01.03.08.02 Muros de Contención - Concr m3 131.82 502.41 66,227.69 46,359.38 19,868.31
05.01.03.08.03 Muros de Contención - Enco m2 553.02 71.29 39,424.80 27,597.36 11,827.44
05.01.03.08.04 Muros de Contención - Acero kg 7,191.00 4.92 35,379.72 24,765.80 10,613.92
05.01.03.08.05 Juntas de dilatacion de c/teck m 75.60 7.54 570.02 570.02
05.02 ARQUITECTURA
05.02.01 MUROS, TABIQUES DE ABAÑILERIA
05.02.01.01 Muro de Ladrillo KK de Soga C m2 649.05 72.20 46,861.41 46,861.41
05.02.01.02 Muro de Ladrillo caravista 9x1 m2 178.77 89.55 16,008.85 16,008.85
05.02.01.03 Muro de Ladrillo de CABEZA 9 m2 195.92 99.97 19,586.12 19,586.12
05.02.02 REVOQUES Y REVESTIMIENTOS
05.02.02.01 Tarrajeo en interiores mezcla C: m2 1,332.27 29.96 39,914.81 17,961.66 21,953.15
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
05.02.02.02 Tarrajeo en exteriores mezcla C:m2 682.75 37.41 25,541.68 11,493.76 14,047.92
05.02.02.03 Tarrajeo en Columnas C:A - 1: m2 624.64 38.80 24,236.03 10,906.21 13,329.82
05.02.02.04 Tarrajeo en Vigas, mezcla C:A - m2 588.03 35.72 21,004.43 21,004.43
05.02.02.05 Bruñas de 1/2" m 1,464.98 4.68 6,856.11 6,856.11
05.02.02.06 Vestiduras de Derrames en Van ML 691.18 19.47 13,457.27 13,457.27
05.02.03 CIELORRASOS
05.02.03.01 Cielorrasos con Tarrajeo con m2 842.84 34.49 29,069.55 29,069.55
05.02.04 PISOS Y PAVIMENTOS
05.02.04.01 FALSO PISO
05.02.04.01.01 Contrapiso de concreto f'c= m2 844.65 30.58 25,829.40 15,497.64 10,331.76
05.02.04.02 PISOS Y VEREDAS
05.02.04.02.01 Piso Ceramico de 30x30 antid m2 65.68 53.32 3,502.06 3,151.85 350.21
05.02.04.02.02 Piso porcelanato de 60 x 60 m m2 187.62 55.31 10,377.26 9,339.53 1,037.73
05.02.04.02.03 Piso Madera Machihembrada m2 494.61 93.59 46,290.55 41,661.50 4,629.05
05.02.04.02.04 Piso de cemento pulido m2 926.28 37.39 34,633.61 34,633.61
05.02.04.03 ZOCALOS Y CONTRAZOCALOS
05.02.04.03.01 Zocalo de cerámico m2 111.89 26.31 2,943.83 2,943.83
05.02.04.03.02 Contrazocalo de porcelanato m 133.42 51.17 6,827.10 6,827.10
05.02.04.03.03 Contrazocalo de madera agua m 341.49 36.01 12,297.05 12,297.05
05.02.04.03.04 Zocalo de pintura exterior m2 237.16 26.31 6,239.68 6,239.68
05.02.05 CARPINTERIA DE MADERA
05.02.05.01 Puerta contraplacada de 01 hojam2 44.48 234.01 10,408.76 10,408.76
05.02.05.02 Puerta de madera cedro nacionam2 53.32 369.72 19,713.47 19,713.47
05.02.06 CARPINTERIA METALICA
05.02.06.01 Ventana de aluminio y accesoriom2 158.51 108.06 17,128.59 15,415.73 1,712.86
05.02.06.02 Varilla de seguridad con fierro m 190.80 64.99 12,400.09 11,160.08 1,240.01
05.02.06.03 Puerta metalica - Ingreso princ m2 14.85 656.80 9,753.48 8,778.13 975.35
05.02.06.04 Pintura en Puerta metalica - Ing m2 14.85 16.99 252.30 227.07 25.23
05.02.06.05 Escalera Metalica c/ Tubo de F m 3.00 340.04 1,020.12 1,020.12
05.02.06.06 Baranda de TUBO DE ALUM de m 80.87 210.07 16,988.36 16,988.36
05.02.07 CERRAJERIA
05.02.07.01 BISAGRAS
05.02.07.01.01 Bisagra aluminizada capuchin pza 94.00 16.11 1,514.34 1,514.34
05.02.07.01.02 Bisagra Aluminizada capuchi pza 123.00 17.96 2,209.08 2,209.08
05.02.07.02 CERRADURAS
05.02.07.02.01 Cerradura tipo forte de 2 golpepza 42.00 60.91 2,558.22 2,558.22
05.02.07.03 ACCESORIOS DE CIERRE
05.02.07.03.01 Manija de bronce p/puertas und 48.00 26.91 1,291.68 1,291.68
05.02.07.04 VIDRIOS, CRISTALES Y SIMILARES
05.02.07.04.01 Vidrio templado mas lamina p2 156.06 14.43 2,251.95 2,251.95
05.02.07.04.02 Espejo Biselado (1.20mx0.60mund 8.00 83.65 669.20 669.20
05.02.08 PINTURA
05.02.08.01 PINTURA EN MUROS
05.02.08.01.01 Pintura base con imprimante m2 2,015.02 11.51 23,192.88 23,192.88
05.02.08.01.02 Pintura Latex en Muros Inter m2 1,332.27 11.00 14,654.97 14,654.97
05.02.08.01.03 Pintura Latex en Muros Exter m2 682.75 11.00 7,510.25 7,510.25
05.02.08.01.04 Pintura Latex en columnas, m2 1,212.67 11.00 13,339.37 13,339.37
05.02.08.01.05 Vestiduras de Derrames en m 691.18 19.47 13,457.27 13,457.27
05.02.08.02 PINTURA DE CIELOS RASOS
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
05.02.08.02.01 Pintura base con imprimante m2 842.84 11.72 9,878.08 9,878.08
05.02.08.02.02 Pintura Latex en Cielorraso m2 842.84 11.13 9,380.81 9,380.81
05.02.09 COBERTURA
05.02.09.01 TIJERALES METALICOS EN und 34.00 603.08 20,504.72 20,504.72
05.02.09.02 Correas metalicas en pasadizo m 662.36 48.62 32,203.94 32,203.94
05.02.09.03 Correas de madera en techos m 2,569.35 12.57 32,296.73 32,296.73
05.02.09.04 Cobertura de policarbonato 5.80m2 219.76 48.71 10,704.51 10,704.51
05.02.09.05 Cobertura de Techo Trapezoid m2 968.67 31.53 30,542.17 30,542.17
05.03 INSTALACIONES SANITARIAS
05.03.01 APARATOS SANITARIOS Y ACCESORIOS
05.03.01.01 LAVATORIOS
05.03.01.01.01 Lavatorio de ceramico vitrifi und 10.00 185.28 1,852.80 1,852.80
05.03.01.01.02 Lavadero de acero Inox. de und 3.00 135.00 405.00 405.00
05.03.01.02 INODOROS
05.03.01.02.01 Inodoro Estandar de Loza Inc. und 10.00 240.11 2,401.10 2,401.10
05.03.01.02.02 Baranda de apoyo plegable und 4.00 144.90 579.60 579.60
05.03.01.03 URINARIOS
05.03.01.03.01 Urinario de loza Inc. Instalació und 3.00 97.82 293.46 293.46
05.03.01.04 GRIFERIA
05.03.01.04.01 Grifo Cromado tipo cuello de und 3.00 42.00 126.00 126.00
05.03.01.04.02 Grifo para lavatorio de 2 llavesund 10.00 32.00 320.00 320.00
05.03.01.04.03 Grifo para ducha de dos llavesund 2.00 55.64 111.28 111.28
05.03.02 SISTEMA DE DESAGUE Y VENTILACION
05.03.02.01 SISTEMA DE DESAGUE
05.03.02.01.01 Salida de Desagüe Inodoros 4 pto 10.00 59.52 595.20 595.20
05.03.02.01.02 Salida de desague urinarios 2"pto 3.00 47.10 141.30 141.30
05.03.02.01.03 Salida de Desagüe Lavatorios pto 13.00 48.46 629.98 629.98
05.03.02.01.04 Salida de Desagüe Sumideros pto 15.00 55.15 827.25 827.25
05.03.02.01.05 Salida de Desagüe para Regi pto 8.00 54.55 436.40 436.40
05.03.02.02 SISTEMA DE REDES DE DESAGUE
05.03.02.02.01 Red colectora PVC para Desa m 87.88 20.31 1,784.84 1,784.84
05.03.02.02.02 Red colectora PVC para Desa m 24.74 30.59 756.80 756.80
05.03.02.03 ACCESORIOS VARIOS
05.03.02.03.01 Sumidero Cromado de 2" und 15.00 24.09 361.35 361.35
05.03.02.03.02 Registro Roscado Ø 4" und 8.00 50.70 405.60 405.60
05.03.02.03.03 Uniones Yee PVC SAL Ø 2" x und 16.00 28.39 454.24 454.24
05.03.02.03.04 Uniones Yee PVC SAL Ø 4" x und 10.00 34.49 344.90 344.90
05.03.02.03.05 Codo PVC SAL Ø 4" x 4" a 90ºund 17.00 18.37 312.29 312.29
05.03.02.03.06 Codo PVC SAL Ø 2*2" a 90º und 4.00 18.37 73.48 73.48
05.03.02.03.07 Reduccion PVC SAL Ø 4" a 2" und 5.00 17.96 89.80 89.80
05.03.02.04 CAJAS DE INSPECCION Y CONEXIONES
05.03.02.04.01 Caja de Registro de Desagüe und 3.00 147.05 441.15 441.15
05.03.02.05 VENTILACIÓN
05.03.02.05.01 Sombrero de Ventilación PVC pto 17.00 11.42 194.14 194.14
05.03.02.05.02 Salida PVC SAL para Ventila pto 17.00 79.41 1,349.97 1,349.97
05.03.02.06 PRUEBAS HIDRAULICAS
05.03.02.06.01 Prueba hidráulica en Red de m 106.22 3.33 353.71 117.90 117.90 117.91
05.03.03 SISTEMA DE AGUA FRIA
05.03.03.01 SALIDA PARA PUNTOS DE AGUA FRIA
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
05.03.03.01.01 Salida de agua para Inodoro pto 10.00 47.65 476.50 476.50
05.03.03.01.02 Salida de agua en Urinarios pto 3.00 44.74 134.22 134.22
05.03.03.01.03 Salida de agua en Lavatorios pto 13.00 44.74 581.62 581.62
05.03.03.02 REDES DE DISTRIBUCION Y MONTAJE
05.03.03.02.01 Tuberia PVC SAP Ø 1/2" m 150.46 14.59 2,195.21 2,195.21
05.03.03.03 ACCESORIOS VARIOS
05.03.03.03.01 Tee PVC SAP de 1/2" und 10.00 30.17 301.70 301.70
05.03.03.03.02 Codo PVC SAP Ø 1/2" x 90º und 27.00 22.40 604.80 604.80
05.03.03.04 LLAVES Y VALVULAS
05.03.03.04.01 Valvula de Globo de 1/2", incl und 4.00 55.57 222.28 222.28
05.03.03.04.02 Caja de Valvula con Tapa F°G und 11.00 144.66 1,591.26 1,591.26
05.03.03.05 PRUEBAS HIDRAULICAS
Prueba hidráulicaen red de agua y desinfeccion
05.03.03.05.01 m 150.46 3.06 460.41 153.47 153.47 153.47
05.03.03.06 INSTALACIONES ESPECIALES
05.03.03.06.01 Instalacion de accesorios d und 1.00 1,622.10 1,622.10 1,622.10
05.03.03.06.02 Instalacion de tanque cisterna und 1.00 3,622.10 3,622.10 3,622.10
05.03.03.06.03 suministro e instalacion de und 1.00 522.10 522.10 522.10
05.03.04 SISTEMA DE DRENAJE PLUVIAL
CANALETA SEMICIRC. GALVANIZ. D=4 DESAGUE PLUVIAL
05.03.04.01 m 270.93 23.58 6,388.53 6,388.53
Tuberia PVC 3" de bajada de drenaje pluvial
05.03.04.02 m 41.00 68.20 2,796.20 2,796.20
05.03.05 SISTEMA DE AGUA CALIENTE
05.03.05.01 SALIDA PARA PUNTOS DE AGUA CALIENTE
05.03.05.01.01 Salida de agua en Lavatorios pto 15.00 44.74 671.10 671.10
05.03.05.02 REDES DE DISTRIBUCION
05.03.05.02.01 Tuberia PVC SAP Ø 1/2" m 67.71 14.59 987.89 987.89
05.03.05.03 ACCESORIOS VARIOS
05.03.05.03.01 Tee PVC SAP de 1/2" und 8.00 30.17 241.36 241.36
05.03.05.03.02 Codo PVC SAP Ø 1/2" x 90º und 12.00 22.40 268.80 268.80
05.03.05.03.03 Valvula de Globo de 1/2", incl und 11.00 55.57 611.27 611.27
05.03.05.03.04 Terma Electrica und 1.00 2,612.09 2,612.09 2,612.09
05.03.05.04 PRUEBAS HIDRAULICAS
05.03.05.04.01 Prueba hidráulicaen red de m 67.71 3.06 207.19 207.19
05.04 INSTALACIONES ELECTRICAS
05.04.01 SALIDA PARA INSTALACIONES ELÉCTRICAS
05.04.01.01 Salida para Centro de Luz Tech pto 118.00 93.19 10,996.42 10,996.42
05.04.01.02 Salida tomacorriente doble con pto 13.00 104.84 1,362.92 1,362.92
05.04.01.03 TOMACORRIENTE MONOFAS pto 1.00 104.84 104.84 104.84
05.04.01.04 Salida tomacorriente doble con pto 71.00 104.84 7,443.64 7,443.64
05.04.01.05 Interruptor unipolar simple con pto 21.00 61.71 1,295.91 1,295.91
05.04.01.06 Interruptor unipolar doble con pto 14.00 43.71 611.94 611.94
05.04.01.07 Interruptor de conmutación con pto 4.00 64.71 258.84 258.84
05.04.01.08 Salida Luz Emergencia de Bater pto 10.00 35.88 358.80 358.80
05.04.01.09 Salida para Pulsador de Timbre pto 2.00 53.32 106.64 106.64
05.04.01.10 salida de telefono-internet pto 4.00 75.11 300.44 300.44
05.04.01.11 Salida doble de video hdmi y a pto 8.00 115.98 927.84 927.84
05.04.01.12 Salida de parlantes pto 16.00 73.65 1,178.40 1,178.40
05.04.02 CANALIZACIONES, CONDUCTOS O TUBERÍAS
05.04.02.01 Tubería Empotrada Alumbrad m 938.42 15.44 14,489.20 14,489.20
05.04.02.02 Tubería Empotrada DE linea telem 86.12 15.44 1,329.69 1,329.69
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
05.04.02.03 tuberia empotrada para timbre m 18.06 15.44 278.85 278.85
05.04.02.04 Curva PVC SAP NTP 399.006 und 472.00 6.52 3,077.44 3,077.44
05.04.03 CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS
05.04.03.01 Cable NH-80 DE 6 mm2 AL m 1,079.18 6.98 7,532.68 7,532.68
05.04.03.02 Cable NH-80 DE 4 mm2 AL m 94.51 5.98 565.17 565.17
05.04.03.03 Cable N2XOH de 1 x 6 mm2 m 62.13 6.98 433.67 433.67
05.04.03.04 Cable para internet RJ45 8P8C m 86.12 6.98 601.12 601.12
05.04.03.05 Cable de Audio Apantallado par m 27.66 3.52 97.36 97.36
05.04.04 SISTEMA DE CONDUCTOS
05.04.04.01 Canaleta para conductor enterr m 94.51 53.72 5,077.08 5,077.08
05.04.05 TABLEROS DE DISTRIBUCION
05.04.05.01 TABLERO GENERAL DE F pza 1.00 479.82 479.82 479.82
05.04.05.02 TABLERO DE F°G° TRIF pza 5.00 428.07 2,140.35 2,140.35
05.04.06 DISPOSITIVOS DE MANIOBRA Y PROTECCION
05.04.06.01 Interruptor simple con placa de pza 21.00 23.26 488.46 488.46
05.04.06.02 Interruptor doble con placa de pza 14.00 41.61 582.54 582.54
05.04.06.03 Interruptor de conmutación con pza 4.00 59.61 238.44 238.44
05.04.07 ARTEFACTOS
05.04.07.01 Luminaria con Dos Lámparas F EQP 61.00 132.27 8,068.47 8,068.47
05.04.07.02 Luminaria de Sección Circul und 28.00 175.67 4,918.76 4,918.76
05.04.07.03 Luminaria tipo braquet termofo EQP 42.00 152.79 6,417.18 6,417.18
05.04.07.04 Equipo de luz de emergencia p und 10.00 117.17 1,171.70 1,171.70
05.04.08 EQUIPOS ELECTRICOS, MECANICOS Y ESPECIALES
05.04.08.01 Pozo de puesta a tierra EQP 5.00 1,331.91 6,659.55 6,659.55
05.04.08.02 Acometida de Energia Electrica glb 1.00 350.00 350.00 350.00
05.04.08.03 CAJA DE PASO jgo 6.00 0.00 0.00 -
05.04.08.04 Timbre de 8" CON IP 66 jgo 2.00 88.67 177.34 177.34
05.04.08.05 Pruebas Electricas (Aislamiento glb 1.00 1,254.24 1,254.24 1,254.24
05.04.08.06 Pruebas Electricas (Resistencia und 5.00 169.49 847.45 847.45
06 LOSA DEPORTIVA
06.01 LOSA
06.01.01 Excavacion de losa m3 193.92 41.28 8,005.02 8,005.02
06.01.02 Nivelacion Interior y Apisonado m2 646.40 1.35 872.64 872.64
06.01.03 Base granular compactado e= 0.1 m3 96.96 21.60 2,094.34 2,094.34
06.01.04 Concreto f'c= 210 Kg/Cm2 m3 96.96 520.01 50,420.17 12,605.04 37,815.13
06.01.05 Encofrado y desencofrado m2 56.07 57.34 3,215.05 3,215.05
06.01.06 Junta de construccion m 269.40 5.88 1,584.07 1,584.07
06.01.07 Pintura de marcas en Losa m 321.00 7.58 2,433.18 2,433.18
06.01.08 Piso de cemento pulido m2 640.00 37.39 23,929.60 23,929.60
06.01.09 Arco multifuncional+tablero de ba und 2.00 1,864.41 3,728.82 3,728.82
06.01.10 Postes para net und 1.00 254.24 254.24 254.24
REFLECTORES HALOGENURO DE 400 W
06.01.11 EQP 4.00 412.22 1,648.88 1,648.88
06.01.12 Salida para reflectores pto 4.00 88.48 353.92 353.92
06.01.13 Salida tomacorriente doble con ti pto 2.00 104.84 209.68 209.68
06.01.14 Interruptor unipolar simple con pl pto 1.00 61.71 61.71 61.71
06.01.15 Tubería Empotrada para alumbr m 82.35 17.94 1,477.36 1,477.36
06.01.16 Cable NH-80 de 1 x 6 mm2 m 82.35 6.98 574.80 574.80
06.01.17 Interruptor simple con placa de ac pza 2.00 23.26 46.52 46.52
06.01.18 Interruptor doble con placa de acepza 1.00 49.76 49.76 49.76
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
06.01.19 Cable N2XOH de 1 x 6 mm2 m 20.18 6.98 140.86 140.86
06.02 COBERTURA METALICA
06.02.01 Excavacion zapatas para coberturm3 104.54 48.17 5,035.69 5,035.69
06.02.02 Relleno con material propio m3 27.10 15.31 414.90 414.90
06.02.03 Solado - Concreto C:H 1:10, e=1 m2 5.81 37.55 218.17 218.17
06.02.04 Zapatas - Concreto f'c=210 kg/cm m3 34.85 511.09 17,811.49 17,811.49
06.02.05 Zapatas - Acero f'y=4200 kg/cm2 kg 1,193.19 4.95 5,906.29 5,906.29
06.02.06 Columnas - Concreto f'c=210 kg/ m3 19.15 502.41 9,621.15 9,621.15
06.02.07 Columnas - Encofrado y Desencofm2 159.60 71.29 11,377.88 11,377.88
06.02.08 Columnas - Acero f'y=4200 kg/cm kg 4,236.18 4.92 20,842.01 20,842.01
06.02.09 Vigas - Concreto f'c= 210 Kg/Cm2m3 25.06 462.27 11,584.49 11,584.49
06.02.10 Vigas - Encofrado y Desencofradom2 161.28 48.73 7,859.17 7,859.17
06.02.11 Vigas - Acero fy=4200 kg/cm2 kg 1,905.66 4.92 9,375.85 9,375.85
06.02.12 Tarrajeo en Columnas C:A - 1:5 m2 387.08 38.80 15,018.70 15,018.70
06.02.13 Pintura Latex en columnas, viga m2 387.08 11.00 4,257.88 4,257.88
06.02.14 Tijerales metalicos und 6.00 8,465.15 50,790.90 50,790.90
06.02.15 Correas metalicas en techo m 627.00 48.62 30,484.74 30,484.74
06.02.16 Cobertura de policarbonato 5.90x m2 201.50 48.71 9,815.07 9,815.07
06.02.17 Cobertura techo UPVC 1.07x3.60 m2 675.64 48.71 32,910.42 6,582.08 26,328.34
06.02.18 Izaje de tijerales de estrutura metaund 6.00 334.37 2,006.22 2,006.22
06.02.19 Habilitado y Doblado de acero m 416.00 1.48 615.68 615.68
06.02.20 Encuentro de viga de acero y col und 12.00 201.83 2,421.96 2,421.96
06.02.21 Cobertura Vertical de policarbonatm2 157.52 150.20 23,659.50 23,659.50
07 OBRAS EXTERIORES
07.01 CERCO PERIMETRICO
07.01.01 Excavacion de zanja para cimien m3 7.25 48.17 349.23 349.23
07.01.02 Eliminacion de material excedent m3 9.43 21.03 198.31 198.31
07.01.03 Cimiento Concreto simple F´c=17 m3 4.58 462.27 2,117.20 2,117.20
07.01.04 Cerco Perimetrico con Malla Olim m2 146.89 169.21 24,855.26 9,942.10 14,913.16
07.01.05 TUBO DE CERCO INCL PINTUR und 53.00 174.82 9,265.46 9,265.46
07.01.06 Sobrecimiento-Concreto C:H 1: m3 1.49 365.57 544.70 544.70
07.01.07 Sobrecimientos - Encofrado y De m2 11.92 45.97 547.96 547.96
07.01.08 Columnas - Concreto f'c=210 kg/ m3 1.13 502.41 567.72 567.72
07.01.09 Columnas - Encofrado y Desencofm2 18.15 71.29 1,293.91 1,293.91
07.01.10 Columnas - Acero f'y=4200 kg/cm kg 104.88 4.92 516.01 516.01
07.01.11 Muro de Ladrillo KK de Soga C:A m2 34.05 72.20 2,458.41 2,458.41
07.01.12 Vigas - Concreto f'c= 210 Kg/Cm2m3 0.56 462.27 258.87 258.87
07.01.13 Vigas - Encofrado y Desencofradom2 9.68 48.73 471.71 471.71
07.01.14 Vigas - Acero fy=4200 kg/cm2 kg 88.45 4.92 435.17 435.17
07.01.15 Tarrajeo en Columnas C:A - 1:5 m2 18.15 38.80 704.22 704.22
07.01.16 Tarrajeo en vigas C:A - 1:5 m2 9.68 61.66 596.87 596.87
07.01.17 Tarrajeo en muros m2 68.10 37.41 2,547.62 2,547.62
07.02 MUROS DE CONTENCION
07.02.01 Excavacion para muro de conten m3 262.82 48.17 12,660.04 12,660.04
07.02.02 Relleno con material de propio - m3 78.63 15.31 1,203.83 1,203.83
07.02.03 Eliminacion de material excedent m3 186.53 21.03 3,922.73 3,922.73
07.02.04 Solado - Concreto C:H 1:10, e=1 m2 107.18 37.55 4,024.61 4,024.61
07.02.05 Encofrado y desencofrado m2 307.35 57.34 17,623.45 17,623.45
07.02.06 Muro de gravedad - Concreto C m3 44.38 462.27 20,515.54 20,515.54
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO : “RECUPERACION DEL LOCAL ESCOLAR N° 31115 DE LA LOCALIDAD VISTA ALEGRE, DISTRITO DE SURCUBAMBA - PROVINCIA TAYACAJA - DEPARTAMENTO HUANCAVELICA”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE SURCUBAMBA
CONTRATISTA : CONSORCIO VISTA ALEGRE
SUPERVISIÓN : CONSORCIO SUPERVISIÓN ESCORPION
LUGAR : HUANCAVELICA - TAYACAJA - SURCUBAMBA - LOCALIDAD VISTA ALEGRE
CRONOGRAMA VALORIZADO
Item Descripción Und Metrado Precio Parcial MES 01 (25 al 30 MES 02 (01 al 31 MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al 31 MES 06 (01 al 28 MES 07 (01 al 23
SET.) OCT.) NOV.) DIC.) ENE.) FEB.) MAR.)
07.02.07 Muros de Contención - Concreto m3 112.47 502.41 56,506.05 56,506.05
07.02.08 Muros - Acero f'y= 4200 kg/cm2 kg 5,055.76 4.95 25,026.01 25,026.01
07.02.09 Juntas de dilatacion de c/tecknopom 34.20 7.54 257.87 257.87
07.03 CERCO EN LOSA DEPORTIVA
07.03.01 Columna - Concreto f'c= 175 kg/c m3 5.12 462.27 2,366.82 2,366.82
07.03.02 Columna - Encofrado y desencofr m2 81.90 57.34 4,696.15 4,696.15
07.03.03 Columna - Acero fy=4200 kg/cm2 kg 655.69 4.95 3,245.67 3,245.67
07.03.04 Muro de Ladrillo caravista 9x13x2 m2 539.76 89.55 48,335.51 48,335.51
07.03.05 Vigas - Concreto f'c= 175 Kg/Cm2m3 2.10 462.27 970.77 970.77
07.03.06 Vigas - Encofrado y Desencofradom2 36.40 48.73 1,773.77 1,773.77
07.03.07 Vigas - Acero fy=4200 kg/cm2 kg 447.60 4.92 2,202.19 2,202.19
07.03.08 Tarrajeo en Columnas C:A - 1:5 m2 66.15 38.80 2,566.62 2,566.62
07.03.09 Tarrajeo en vigas C:A - 1:5 m2 36.40 61.66 2,244.42 2,244.42
07.03.10 Tarrajeo en muros DE CERCO D m2 251.90 37.41 9,423.58 9,423.58
07.05 ASTA DE BANDERA CON BASE CIRCULAR
07.05.01 Concreto f'c= 175 kg/cm2 m3 2.69 462.27 1,243.51 1,243.51
07.05.02 Encofrado y desencofrado m2 3.98 57.34 228.21 228.21
07.05.03 Acero fy=4200 kg/cm2 kg 4.23 4.95 20.94 20.94
07.05.04 Asta de bandera und 1.00 1,385.99 1,385.99 1,385.99
08 FLETE TERRESTRE
08.01 Flete terreste glb 1.00 330,495.25 330,495.25 66,099.05 66,099.05 66,099.05 66,099.05 66,099.05

S/. 86,240.15 S/. 481,344.89 S/. 532,249.19 S/. 503,434.09 S/. 554,215.50 S/. 486,071.49 S/. 305,775.81

MES 01 (25 al MES 02 (01 al MES 03 (01 al 30 MES 04 (01 al 31 MES 05 (01 al MES 06 (01 al MES 07 (01 al
30 SET.) 31 OCT.) NOV.) DIC.) 31 ENE.) 28 FEB.) 23 MAR.)
COSTO DIRECTO S/. 2,949,331.12 S/. 86,240.15 S/. 481,344.89 S/. 532,249.19 S/. 503,434.09 S/. 554,215.50 S/. 486,071.49 S/. 305,775.81
GASTOS GENERALES (10%) 10.00% S/. 294,933.11 S/. 8,624.02 S/. 48,134.49 S/. 53,224.92 S/. 50,343.41 S/. 55,421.55 S/. 48,607.15 S/. 30,577.58
UTILIDAD (8%) 8.00% S/. 235,946.49 S/. 6,899.21 S/. 38,507.59 S/. 42,579.94 S/. 40,274.73 S/. 44,337.24 S/. 38,885.72 S/. 24,462.06
SUB TOTAL S/. 3,480,210.72 S/. 101,763.38 S/. 567,986.97 S/. 628,054.05 S/. 594,052.23 S/. 653,974.29 S/. 573,564.36 S/. 360,815.45
I.G.V. (18%) 18.00% S/. 626,437.93 S/. 18,317.41 S/. 102,237.65 S/. 113,049.73 S/. 106,929.40 S/. 117,715.37 S/. 103,241.58 S/. 64,946.78
COSTO DE EJECUCION DE OBRA S/. 4,106,648.65 S/. 120,080.79 S/. 670,224.62 S/. 741,103.78 S/. 700,981.63 S/. 771,689.66 S/. 676,805.94 S/. 425,762.23
PLAN DE CONTINGENCIA S/. 20,000.00 S/. 2,857.14 S/. 2,857.14 S/. 2,857.14 S/. 2,857.14 S/. 2,857.14 S/. 2,857.14 S/. 2,857.16
MOBILIARIO Y EQUIPAMIENTO S/. 201,150.23 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 50,287.56 S/. 150,862.67
PLAN DE VIGILANCIA, CONTROL Y PREVENCIÓN S/. 10,000.00 S/. 1,428.57 S/. 1,428.57 S/. 1,428.57 S/. 1,428.57 S/. 1,428.57 S/. 1,428.57 S/. 1,428.58
VALOR REFERENCIAL S/. 4,337,798.88 S/. 124,366.50 S/. 674,510.33 S/. 745,389.49 S/. 705,267.34 S/. 775,975.37 S/. 731,379.21 S/. 580,910.64
%AVANCE 2.92 % 16.32 % 18.05 % 17.07 % 18.79 % 16.48 % 10.37 %
%ACUMULADO 2.92 % 19.24 % 37.29 % 54.36 % 73.15 % 89.63 % 100.00 %