Está en la página 1de 29

METRADO DE CONCRETO EN ZAPATAS

ITEM DESCRIPCIÓN
N°VECES AREA ALTURA VOL.CONCRET. SUBTOTAL TOTAL
01.00.00 OBRAS DE CONCRETO CICLOPEO (MODULO A)
01.01.00 OBRAS DE CONCRETO SIMPLE 1:10. 30% P.G. MAX. 8" 49.998
01.01.01 CIMIENTOS CORRIDOS 17.76
CIM.CORRIDO ENTRE LOS EJES E' Y G - 8 Y 8' - 9 Y 8 1 3.36 0.6 2.02
CIM.CORRIDO EN EL EJE 8-8 1 1.35 0.6 0.81
CIM.CORRIDO EN EL EJE E' ENTRE 7 Y 8 1 1.31 0.6 0.79
CIM.CORRIDO EN EL EJE F ENTRE 7 Y 8 1 1.31 0.6 0.79
CIM.CORRIDO EN EL EJE G ENTRE 7 Y 9 1 1.32 0.6 0.79
CIM.CORRIDO EN EL EJE 7 ENTRE F Y G 1 1.35 0.6 0.81
CIM.CORRIDO EN EL EJE E' ENTRE 7 Y 6 1 0.79 0.6 0.47
CIM.CORRIDO EN EL EJE F ENTRE 7 Y 6 1 0.79 0.6 0.47
CIM.CORRIDO EN EL EJE G ENTRE 7 Y 6 1 0.79 0.6 0.47
CIM.CORRIDO EN EL EJE 6 ENTRE F Y G 1 1.35 0.6 0.81
CIM.CORRIDO EN EL EJE G ENTRE 5 Y 6 1 1.02 0.6 0.61
CIM.CORRIDO EN EL EJE F ENTRE 5 Y 6 1 1.03 0.6 0.62
CIM.CORRIDO EN EL EJE F ENTRE 5 Y 7 1 1.03 0.6 0.62
CIM.CORRIDO EN EL EJE G ENTRE 5 Y 7 1 1.03 0.6 0.62
CIM.CORRIDO EN EL EJE 5 ENTRE F Y G 1 1.35 0.6 0.81
CIM.CORRIDO EN EL EJE E ENTRE 4 Y 5 1 0.98 0.6 0.59
CIM.CORRIDO EN EL EJE F ENTRE 4 Y 5 1 1.02 0.6 0.61
CIM.CORRIDO EN EL EJE G ENTRE 4 Y 5 1 0.98 0.6 0.59
CIM.CORRIDO EN EL EJE 4 ENTRE E Y F 1 0.23 0.6 0.14
CIM.CORRIDO EN EL EJE 4 ENTRE F Y G 1 0.99 0.6 0.59
CIM.CORRIDO EN EL EJE E ENTRE 4 Y 3' 1 1.03 0.6 0.62
CIM.CORRIDO EN EL EJE F ENTRE 4 Y 3' 1 0.78 0.6 0.47
CIM.CORRIDO EN EL EJE G ENTRE 4 Y 3' 1 0.78 0.6 0.47
CIM.CORRIDO EN EL EJE 3' ENTRE E Y F 1 0.57 0.6 0.34
CIM.CORRIDO EN EL EJE 3' ENTRE F Y G 1 0.99 0.6 0.59
CIM.CORRIDO EN EL EJE F ENTRE 1' Y 3 1 0.91 0.6 0.55
CIM.CORRIDO EN EL EJE G ENTRE 1' Y 3' 1 0.6 0.6 0.36
CIM.CORRIDO EN EL EJE 1 'ENTRE F Y G 1 0.55 0.6 0.33
01.01.02 ZAPATAS 20.7
ZAPATA T-4 4 2.15 1 8.6
ZAPATA T-3 10 1.21 1 12.1
02.00.00 OBRAS DE CONCRETO ARMADO MODULO A N°VECES AREA ALTURA VOL.CONCRET. SUBTOTAL TOTAL
02.01.00 OBRAS DE CONCRETO ARMADO F'C=140KG/CM2 10.491
02.01.01 VIGAS DE CIMENTACION F'C=140KG/CM2 4.71
VIGA.CIMEN.T1 EN EL EJE 8 ENTRE E - G 1 1.34 0.25 0.34
VIGA.CIMEN. T1 EN EL EJE 7 ENTRE E - G 1 1.34 0.25 0.34
VIGA.CIMEN.T1 EN EL EJE 6 ENTRE E - G 1 1.34 0.25 0.34
VIGA.CIMEN.T1 EN EL EJE 5 ENTRE E - G 1 1.34 0.25 0.34
VIGA.CIMEN.T1 EN EL EJE 4 ENTRE E - G 1 1.34 0.25 0.34
VIGA.CIMEN.T1 EN EL EJE 3' ENTRE E - G 1 1.42 0.25 0.36
VIGA.CIMEN.T2 EN EL EJE E ENTRE 8 Y 3' 1 2.3 0.25 0.58
VIGA.CIMEN.T1 EN EL EJE F ENTRE 8 Y 1' 1 4.4 0.25 1.1
VIGA.CIMEN.T2 EN EL EJE G ENTRE 8 Y 3' 1 3.88 0.25 0.97
02.01.02 SOBRECIMIENTOS F'C=140KG/CM2 3.36
SOBRECIMIENTOS EN EL EJE 8, 7 ,6 Y 5 ENTRE E-F 4 0.15 0.3 0.18
SOBRECIMIENTOS EN EL EJE 8, 7 ,6 Y 5 ENTRE F-G 4 0.62 0.3 0.74
SOBRECIMIENTOS EN EL EJE 4 ENTRE E-F 1 0.28 0.3 0.08
SOBRECIMIENTOS EN EL EJE 4 ENTRE F-G 1 0.49 0.3 0.15
SOBRECIMIENTOS EN EL EJE 3' ENTRE E-F 1 0.27 0.3 0.08
SOBRECIMIENTOS EN EL EJE 3' ENTRE F-G 1 0.49 0.3 0.15
SOBRECIMIENTOS EN EL EJE E' ENTRE 8-3' 1 2.04 0.3 0.61
SOBRECIMIENTOS EN EL EJE F ENTRE 8-3' 1 2.46 0.3 0.74
SOBRECIMIENTOS EN EL EJE G ENTRE 8-3' 1 2.1 0.3 0.63
02.02.00 OBRAS DE CONCRETO ARMADO F'C=210KG/CM2 19.28615
02.02.01 COLUMNAS F'C=210KG/CM2 4.55
COLUMNAS T-3 14 0.063 3.45 3.04
COLUMNAS T-2 5 0.053 3.45 0.91
COLUMNAS T-5' 1 0.0375 3.45 0.13
COLUMNAS T-5 1 0.072 3.45 0.25
COLUMNAS T-6 1 0.064 3.45 0.22
02.02.02 LOSA ALIGERADA 6.21
LOSA ALIGERADA "H" 1 8.77 0.05 0.44
LOSA ALIGERADA "I" 1 29.1 0.05 1.46
LOSA ALIGERADA "F" 1 4 0.05 0.2
LOSA ALIGERADA "G" 1 10.29 0.05 0.51
LOSA ALIGERADA "D" 1 4.63 0.05 0.23
LOSA ALIGERADA "E" 1 7.79 0.05 0.39
LOSA ALIGERADA "C" 1 2.65 0.05 0.13
VIGUETAS EN LA LOSA "H" 3 0.88 0.15 0.4
VIGUETAS EN LA LOSA "I" 11 0.59 0.15 0.97
VIGUETAS EN LA LOSA "I'" 5 0.29 0.15 0.22
VIGUETAS EN LA LOSA "F'" 5 0.28 0.15 0.21
VIGUETAS EN LA LOSA "G'" 11 0.28 0.15 0.46
VIGUETAS EN LA LOSA "D'" 5 0.25 0.15 0.19
VIGUETAS EN LA LOSA "E'" 8 0.25 0.15 0.3
VIGUETAS EN LA LOSA "C'" 5 0.09 0.15 0.07
VIGUETAS EN LA LOSA "C'" 2 0.1 0.15 0.03
02.02.03 VIGAS F'C=210KG/CM2 4.0755
EJE 8-8 VIGA- 04(0.25X0.25) 1 1.27 0.25 0.3175
EJE 7-7 VIGA- 04(0.25X0.30) 1 1.27 0.30 0.381
EJE 6-6 VIGA- 04(0.25X0.25) 1 1.27 0.25 0.3175
EJE 5-5 VIGA- 04(0.25X0.25) 1 1.27 0.25 0.3175
EJE 4-4 VIGA- 04(0.25X0.25) 1 1.27 0.20 0.254
EJE 3'-3'VIGA- 04(0.25X0.25) 1 1.27 0.20 0.254
EJE E' ENTRE 7 Y 8 VIGA- 04(0.15X0.20) 1 0.5 0.20 0.10
EJE F' ENTRE 7 Y 8 VIGA- 04(0.25X0.20) 1 0.87 0.20 0.174
EJE G ENTRE 7 Y 8 VIGA- 04(0.25X0.20) 1 0.87 0.20 0.174
EJE ENTRE 7 Y 8 VIGA BORDE- 04(0.15X0.20) 1 0.26 0.20 0.052
EJE E' ENTRE 7 Y 6 VIGA AMARRE (0.15X0.20) 1 0.35 0.20 0.07
EJE F' ENTRE 7 Y 6 VIGA AMARRE (0.25X0.20) 1 0.61 0.20 0.122
EJE G ENTRE 7 Y 6 VIGA AMARRE (0.25X0.20) 1 0.61 0.20 0.122
EJE E' ENTRE 5 Y 6 VIGA AMARRE (0.15X0.20) 1 0.43 0.2 0.086
EJE F' ENTRE 5 Y 6 VIGA AMARRE (0.25X0.20) 1 0.73 0.2 0.146
EJE ENTRE 5 Y 6 VIGA BORDE (0.15X0.20) 1 0.44 0.2 0.088
EJE G ENTRE 5 Y 6 VIGA AMARRE(0.25X0.20) 1 0.73 0.2 0.146
EJE E' ENTRE 5 Y 4 VIGA AMARRE (0.15X0.20) 1 0.41 0.2 0.082
EJE F' ENTRE 5 Y 4 VIGA AMARRE (0.25X0.20) 1 0.7 0.2 0.14
EJE G ENTRE 5 Y 4 VIGA AMARRE (0.25X0.20) 1 0.7 0.2 0.14
EJE E' ENTRE 5 Y 4 VIGA AMARRE (0.15X0.20) 1 0.38 0.2 0.076
EJE F' ENTRE 5 Y 4 VIGA AMARRE (0.25X0.20) 1 0.6 0.2 0.12
EJE G ENTRE 5 Y 4 VIGA AMARRE (0.25X0.20) 1 0.6 0.2 0.12
EJE 3' ENTRE E Y F VIGA AMARRE (0.15X0.20) 1 0.28 0.2 0.056
ENTRE EJES 3' Y 2 VIGA AMARRE (0.15X0.20) 1 0.45 0.2 0.09
EJE 2 ENTRE E Y F VIGA AMARRE (0.15X0.20) 1 0.3 0.2 0.06
EJE F ENTRE 3' Y 2 VIGA AMARRE (0.15X0.20) 1 0.35 0.2 0.07
02.02.04 LADRILLO KING KONG. 560.02
LOSA ALIGERADA "H" LADRILLO 0.30X0.30X0.15 1 8.77 1 73.05
LOSA ALIGERADA "I" LADRILLO 0.30X0.30X0.16 1 29.1 1 242.4
LOSA ALIGERADA "F" LADRILLO 0.30X0.30X0.17 1 4.00 1 33.32
LOSA ALIGERADA "G" LADRILLO 0.30X0.30X0.18 1 10.29 1 85.72
LOSA ALIGERADA "D" LADRILLO 0.30X0.30X0.19 1 4.63 1 38.57
LOSA ALIGERADA "E" LADRILLO 0.30X0.30X0.20 1 7.79 1 64.89
LOSA ALIGERADA "C" LADRILLO 0.30X0.30X0.21 1 2.65 1 22.07

03.00.00 OBRAS DE CONCRETO CICLOPEO MODULO B N°VECES AREA ALTURA VOL.CONCRET. SUBTOTAL TOTAL
03.01.00 OBRAS DE CONCRETO SIMPLE 1:10. 30% P.G. MAX. 8" 18.46
03.01.01 CIMIENTOS CORRIDOS CORRIDOS 5.96
CIM.CORRIDO EN EL EJE 3 ENTRE A Y C 1 0.43 0.6 0.26
CIM.CORRIDO EN EL EJE 3 ENTRE C Y D 1 1.38 0.6 0.83
CIM.CORRIDO EN EL EJE 3 ENTRE D Y E 1 1.25 0.6 0.75
CIM.CORRIDO EN EL EJE A ENTRE 1 Y 2 1 0.62 0.6 0.37
CIM.CORRIDO EN EL EJE 2 ENTRE A Y C 1 0.35 0.6 0.21
CIM.CORRIDO EN EL EJE B ENTRE 2 Y 1 1 1 0.6 0.6
CIM.CORRIDO EN EL EJE C ENTRE 2 Y 1 1 0.62 0.6 0.37
CIM.CORRIDO EN EL EJE D ENTRE 1 Y 2 1 0.84 0.6 0.5
CIM.CORRIDO EN EL EJE E ENTRE 1 Y 2 1 0.62 0.6 0.37
CIM.CORRIDO EN EL EJE 1 ENTRE A Y C 1 0.44 0.6 0.26
CIM.CORRIDO EN EL EJE 1 ENTRE C Y D 1 1.37 0.6 0.82
CIM.CORRIDO EN EL EJE 1 ENTRE D Y E 1 1.04 0.6 0.62
03.01.02 ZAPATAS 12.5
ZAPATA T-4 3 2.15 1 6.45
ZAPATA T-3 5 1.21 1 6.05
04.00.00 OBRAS DE CONCRETO ARMADO MODULO B
04.01.00 OBRAS DE CONCRETO ARMADO F'C=140KG/CM2 3.68
04.01.01 VIGAS DE CIMENTACION F'V=140KG/CM2 2.26
VIGA.CIMEN.T1 EN EL EJE 3 ENTRE A-E 1 2.4 0.25 0.6
VIGA.CIMEN.T1 EN EL EJE 2 ENTRE A-C 1 0.6 0.25 0.15
VIGA.CIMEN.T1 EN EL EJE 1 ENTRE A-E 1 2.5 0.25 0.63
VIGA.CIMEN.T1 EN EL EJE A ENTRE 1-3 1 0.6 0.25 0.15
VIGA.CIMEN.T1 EN EL EJE C ENTRE 1-3 1 0.98 0.25 0.25
VIGA.CIMEN.T1 EN EL EJE D ENTRE 1-3 1 0.95 0.25 0.24
VIGA.CIMEN.T1 EN EL EJE E ENTRE 1-3 1 0.97 0.25 0.24
04.01.02 SOBRECIMIENTOS F'C=140KG/CM2 1.42
SOBRECIMIENTOS EN EL EJE 3 ENTRE A-E 1 1.263 0.3 0.38
SOBRECIMIENTOS EN EL EJE 3 ENTRE A-E 1 0.3225 0.3 0.1
SOBRECIMIENTOS EN EL EJE 1 ENTRE A-E 1 1.3275 0.3 0.4
SOBRECIMIENTOS EN EL EJE A ENTRE 1-3 1 0.555 0.3 0.17
SOBRECIMIENTOS EN EL EJE C ENTRE 1-3 1 0.5475 0.3 0.16
SOBRECIMIENTOS EN EL EJE D ENTRE 1-3 1 0.4425 0.3 0.13
SOBRECIMIENTOS EN EL EJE D ENTRE 1-3 1 0.27 0.3 0.08
04.02.00 OBRAS DE CONCRETO ARMADO F'C=210KG/CM2 7.03
04.02.01 COLUMNAS F'C=210KG/CM2 2.88
COLUMNAS T-3 6 0.063 3.45 1.3
COLUMNAS T-1 6 0.06 3.45 1.24
COLUMNAS T-4 1 0.098 3.45 0.34
04.02.02 LOSA ALIGERADA 2.64
LOSA ALIGERADA "A" 1 2.69 0.05 0.13
LOSA ALIGERADA "B" 1 27.11 0.05 1.36
VIGUETAS EN LA LOSA "A" 3 0.22 0.15 0.1
VIGUETAS EN LA LOSA "B" 10 0.70 0.15 1.05
02.02.03 VIGAS F'C=210KG/CM2 1.51
EJE A ENTRE 1-3 VIGA- 01(0.15X0.20) 1 0.46 0.2 0.09
EJE C ENTRE 1-3 VIGA- 01(0.25X0.20) 1 0.91 0.2 0.18
EJE D ENTRE 1-3 VIGA- 01(0.25X0.20) 1 0.95 0.3 0.29
EJE E ENTRE 1-3 VIGA- 01(0.25X0.20) 1 0.91 0.2 0.18
EJE 3 ENTRE A-E VIGA AMARRE- 01(0.25X0.20) 1 1.33 0.2 0.27
EJE 2 ENTRE A-C VIGA AMARRE- 01(0.25X0.20) 1 0.54 0.2 0.11
EJE 1 ENTRE A-C VIGA AMARRE- 01(0.25X0.20) 1 1.94 0.2 0.39
04.02.04 LADRILLO KING KONG. 248.24 249
LOSA ALIGERADA "A" LADRILLO 0.30X0.30X0.15 1 2.69 1 22.41
LOSA ALIGERADA "B" LADRILLO 0.30X0.30X0.16 1 27.11 1 225.83
LONGITUD PARCIAL(m)-DIAMTERO
ITEM DESCRIPCION UND Nº veses Nº elem. Long. (m)
1/4" 3/8" 1/2" 5/8" 3/4"

04.01.00 ACERO F'Y=4200 KG/CM2(MODULO A) KG


04.01.01.00 ZAPATAS ACERO fy=4200kg/cm2 M
04.01.01.01 ZATAPAS (1.95X1.10)
MALLA EJE Y: 1.8
6 7 1.8 75.6

MALLA EJE X:
0.95
6 12 0.95 68.4

04.01.01.01 ZATAPAS (1.95X1.10) M


MALLA EJE Y: 0.95

8 7 0.95 53.2

MALLA EJE X:
0.95

8 7 0.95 53.2

04.01.02.00. COLUMNAS ACERO fy=4200kg/cm2 M


04.01.02.01.00 COLUMNAS TIPO 1(0.15X0.40)
5.25
0.25
1 4 5.5 22.0

5.25
0.25
1 2 5.5 11.0

04.01.02.01.01 ESTRIBOS 1(0.15X0.40) ∅1/4",2@0.05,4@0.10, 3@0.15, resto@0.20

0.065 hasta sobrecimi.: 1.6 1 10 1.03 10.3


0.10

columna neta: 2.95 1 22 1.03 22.66


0.35
04.01.02.02.00 COLUMNAS TIPO 2(0.15X0.35)
5.25
0.25
5 6 5.5 165

04.01.02.02.01 ESTRIBOS 1(0.15X0.35) ∅1/4",2@0.05,4@0.10, 3@0.15, resto@0.20

0.065 hasta sobrecimi.: 1.6 5 10 0.93 9.3


0.10

columna neta: 2.95 5 22 0.93 20.46


0.3
04.01.02.03.00 COLUMNAS TIPO 3( 0.25X0.25)
5.25
0.25
15 4 5.5 330.0

04.01.02.03.01 ESTRIBOS 1(0.25X0.25) ∅3/8",2@0.05,4@0.10, 3@0.15, resto@0.20

0.125 hasta sobrecimi.: 1.6 14 10 1.05 147


0.20

columna neta: 2.95 14 22 1.05 323.4


0.20
04.01.02.04.00 COLUMNAS PERIMETRICA( 0.15X0.40)
3.75
0.25
2 4 4 32.0

04.01.02.04.01 ESTRIBOS 1(0.15X0.40) ∅1/4",2@0.05,4@0.10, 3@0.15, resto@0.20

0.065 hasta sobrecimi.: 1.05 2 7 0.93 6.51


0.20

columna neta: 2.8 2 20 0.93 18.6


0.20
04.01.02.05.00 COLUMNAS TIPO 5( 0.15X0.40)
3.85
0.25
2 6 4.1 49.2

04.01.02.05.01 ESTRIBOS 1(0.15X0.40) ∅1/4",2@0.05,4@0.10, 3@0.15, resto@0.20


0.28 0.065
015
0.10 hasta sobrecimi.: 1.6 2 10 0.83 16.6
0.17
0.28
0.065 0.17 columna neta: 2.95 2 20 0.83 33.2
0.20
0.10
04.01.03.00. VIGAS DE CIMENTACION M
04.01.03.01.00 VIGAS ( 0.25X0.25) ENTRE EJE E Y G EN LOS EJES 5-6-7-8
A 1.1
0.15 0.15
4 4 1.4 22.4

4.1
0.15 0.15
4 4 4.4 70.4

04.01.03.01.01 ESTRIBOS 1(0.25X0.25) ∅1/4"resto@0.20

0.065 4 6 0.93 5.58


0.20

4 8 0.93 7.44
0.20
04.01.03.02.00 VIGAS ( 0.25X0.25) ENTRE EJE E Y G EN LOS EJES 4
A 1.85

1 4 2.15 8.6
0.15 0.15
1 4 2.15 8.6

3.25
0.15 0.15
1 4 3.55 14.2
04.01.03.01.01 ESTRIBOS 1(0.25X0.25) ∅1/4" resto@0.20

0.065 1 9 0.93 8.37


0.20

1 17 0.93 15.81
0.20
04.01.03.02.00 VIGAS ( 0.25X0.25) ENTRE EJE E Y G EN LOS EJES E
A 2
0.15 0.15
1 4 2.3 9.2

3.25
0.15 0.15
1 4 3.55 14.2

04.01.03.02.01 ESTRIBOS 1(0.25X0.25) ∅1/4" resto@0.20

0.065 1 10 0.93 9.3


0.20

1 17 0.93 15.81
0.20
04.01.03.03.00 VIGAS ( 0.25X0.25) ENTRE EJE E Y F EN LOS EJES 2
A 2
0.15 0.15
1 4 2.3 9.2
15.24

04.01.03.03.01 ESTRIBOS 1(0.25X0.25) ∅1/4" resto@0.20

0.065
0.20 1 10 0.93 9.3

0.20
04.01.03.04.00 VIGAS ( 0.25X0.25) EN EJE F
A 16.04
0.15 0.15
1 4 16.34 65.4

04.01.03.04.01 ESTRIBOS 1(0.25X0.25) ∅1/4" resto@0.20

0.065
0.20 1 80 0.93 74.4

0.20
04.01.03.05.00 VIGAS ( 0.25X0.25) EN EJE F
A 5.7
0.15 0.15
1 4 6 24.0
15.24

04.01.03.05.01 ESTRIBOS 1(0.25X0.25) ∅1/4" resto@0.20

0.065
0.20 1 68 0.73 49.64

0.10
04.01.04.00. VIGAS PRINCIPALES LOSA M
04.01.04.01.00 VIGAS 04 ( 0.25X0.25) EN EJE 8
A 5.75
0.2 0.2
1 6 6.15 36.9

04.01.04.01.01 ESTRIBOS 1(0.25X0.25) resto@0.20

0.125
0.20 1 38 1.05 39.9

0.20
04.01.04.02.00 VIGAS 03 ( 0.25X0.30) EN EJE 7
A 5.75
0.2 0.2
1 6 6.15 36.9

04.01.04.02.01 ESTRIBOS 1(0.25X0.30) resto@0.20

0.125
0.25 1 38 1.15 43.7

0.20
04.01.04.03.00 VIGAS 034( 0.25X0.25) EN EJE 6
A 5.75
0.2 0.2
1 6 6.15 36.9

04.01.04.03.01 ESTRIBOS 1(0.25X0.25) resto@0.20

0.125
0.20 1 38 1.05 39.9

0.20
04.01.04.04.00 VIGAS 04 ( 0.25X0.25) EN EJE 5
A 5.75
0.2 0.2
1 6 6.15 36.9

04.01.04.04.01 ESTRIBOS 1(0.25X0.30) resto@0.20

0.125
0.20 1 38 1.05 39.9

0.20
04.01.04.05.00 VIGAS 02 ( 0.25X0.20) EN EJE 4
A 5.75
0.2 0.2
1 5 6.15 30.8

04.01.04.05.01 ESTRIBOS 1(0.25X0.20) resto@0.20

0.125
0.15 1 39 0.95 37.05

0.20
04.01.04.06.00 VIGAS 02( 0.25X0.20) EN EJE 3'
A 3.7
0.2 0.2
1 5 4.1 20.5
04.01.04.06.01 ESTRIBOS 1(0.25X0.30) resto@0.20

0.125
0.15 1 23 0.95 21.85

0.20
04.01.04.06.00 VIGAS 02( 0.25X0.20) EN EJE 2
A 3.45
0.2 0.2
1 5 3.85 19.3

04.01.04.06.01 ESTRIBOS 1(0.25X0.30) resto@0.20

0.125
0.15 1 17 0.95 16.15

0.20
04.01.05.00. VIGAS DE AMARRE M
04.01.05.01.00 VIGAS A ( 0.15X0.20) EN EJE E'
A 16.05
0.2 0.2
1 4 16.45 65.8

04.01.05.01.01 ESTRIBOS 1(0.15X0.20) resto@0.20

0.125
0.15 1 103 0.75 77.25

0.10
04.01.05.02.00 VIGAS A ( 0.25X0.20) EN EJE F'
A 17.83
0.2 0.2
1 4 18.23 72.9

04.01.05.02.01 ESTRIBOS 1(0.25X0.20) resto@0.20

0.125
0.15 1 116 0.95 110.2

0.20
04.01.05.03.00 VIGAS A ( 0.25X0.20) EN EJE G'
A 16.05
0.2 0.2
1 4 16.45 65.8

04.01.05.03.01 ESTRIBOS 1(0.25X0.20) resto@0.20

0.125
0.15 1 103 0.95 97.85

0.20
04.01.05.04.00 VIGAS A ( 0.25X0.20) EN EJE E
A 4.25
0.2 0.2
1 4 4.65 18.6

04.01.05.04.01 ESTRIBOS 1(0.25X0.20) resto@0.20

0.125
0.15 1 32 0.95 30.4

0.20
04.01.06.00. ACERO EN LOSA ALIGERADA M
04.01.06.01.00 LOSA H
BASTONES 1.52
0.15
1 3 1.67 5.0

BALANCIN 6.4
0.15
1 3 6.55 19.7

BALANCIN 1.25

1 3 1.25 3.8

BALANCIN 2.35

1 3 2.35 7.1

BASTONES 1.08
0.15
1 3 1.23 3.7

BASTONES 1.08
0.15
1 3 1.23 3.7

BALANCIN 2.98

1 3 2.98 8.9

BASTONES 1.05
0.15
2 3 1.2 7.2

BALANCIN 3

1 4 3 12.0

BASTONES 0.95
0.15
1 4 1.1 4.4

04.01.06.01.00 LOSA I
BASTONES 1.37
0.15
1 11 1.52 16.7
BALANCIN 6.4

1 11 6.4 70.4

BALANCIN 1.25

1 11 1.25 13.8
BALANCIN 2.35

1 11 2.35 25.9

BASTONES 1.13
0.15
1 11 1.28 14.1

04.01.06.01.00 LOSA I'


BALANCIN 3.35

1 5 3.35 16.8

BASTONES 0.975
0.15
2 5 1.125 11.3

04.01.06.01.00 LOSA G Y E
BALANCIN 5.9

1 9 5.9 53.1

BALANCIN 2.2

1 8 2.2 17.6

BASTONES 1.125
0.15
2 8 1.275 20.4

BASTONES 1.025
0.15
2 8 1.175 18.8

04.01.06.01.00 LOSA D
BALANCIN 2.85

1 5 2.85 14.3

BASTONES 0.9
0.15
1 5 1.05 5.3

BASTONES 1
0.15
1 5 1.15 5.8

04.01.06.01.00 LOSA C
BALANCIN 2.3

1 5 2.3 11.5

BASTONES 0.8
0.15
1 5 0.95 4.8

BASTONES 0.7
0.15
1 5 0.85 4.3

04.01.06.01.00 LOSA C'


BALANCIN 1.35

1 2 1.35 2.7

04.01.06.00. ACERO EN ESCALERA (4 PASOS) M


BALANCIN 2.87

1 7 2.87 20.1

BALANCIN 1.1

1 18 1.1 19.8

BALANCIN 1.96

1 7 1.96 13.7
06.01.00 SISTEMA DE AGUA FRIA MODULO A
06.01.01 RED DE DISTRIBUCION TUBERIA PVC SAP 1/2'' M 60.83
RED DISTRIBUCION PLANTA 1 47.63 47.63
RED DISTRIBUCION ELEVACION 1 13.20 13.20

06.01.02 CODO 90°PVC Ø 1/2'' UND 44.00


BAÑOS + GENERAL 44 44.00

06.01.03 TEE PVC Ø 1/2" UND 24.00


1/2 BAÑO +SALA+COCINA 12 2.00 24.00

06.01.04 VALVULA DE CONTROL ESFERICA Ø 1/2" UND 7.00


BAÑOS+ GENERAL 7 7.00

06.01.05 GRISFOS Ø 1/2" UND 2.00


LAVATORIO Y JARDIN 2 2.00
LAVAMANOS 3 3.00 3.00

06.02.00 SISTEMA DE DESAGUE MODULO A


06.02.01 RED DE DISTRIBUCION TUBERIA PVC SAP 2'' M 7.52
GENERAL PLANTA 1 7.52 7.52
GENERAL ELEVACION 2 11.00 22.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.02 CODO PVC Ø 2" x 90º UND 7.00
GENERAL 7 7.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.03 TEE PVC Ø 2"COLECTOR PRINCIPAL UND 1.00
Colector principal 1°piso 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.04 YEE PVC Ø 2"COLECTOR PRINCIPAL UND 4.00
Colector principal 1°piso 4 4.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.05 reduccion de Ø 4" a 2"COLECTOR PRINCIPAL UND 4.00
Colector principal 1°piso 4 4.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.06 CODO 45° PVC Ø 2"COLECTOR PRINCIPAL UND 1.00
Colector principal 1°piso 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.07 YEE PVC Ø 4" A 2" COLECTOR PRINCIPAL UND 2.00
Colector principal 1°piso 2 2.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.08 TRAMPA PVC Ø 2"COLECTOR PRINCIPAL UND 7.00
TRAMPA NORMAL PARA BAÑO 6 6.00
TRAMPA DE GRASAS 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.09 SUMIDERO Ø 2" UND 7.00
BAÑOS 7 7.00

06.02.10 RED DE DISTRIBUCION TUBERIA PVC SAP 4'' M 48.83


GENERAL PLANTA 1 30.23 30.23
GENERAL ELEVACION 2 9.30 18.60

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.11 Codo PVC Desagüe 4" x 90º SP UND 5.00
GENERAL 5 5.00
Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.12 YEE PVC Ø 4"COLECTOR PRINCIPAL UND 1.00
Colector principal 1°piso 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.13 TEE PVC Ø 4"COLECTOR PRINCIPAL UND 7.00
Colector principal 1°piso 7 7.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.14 REGISTRO ROSCADO Ø 4"COLECTOR PRINCIPAL UND 3.00
BAÑO 3 3.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.02.15 CODO 45° PVC Ø 4"COLECTOR PRINCIPAL UND 4.00
Colector principal 1°piso 4 4.00

06.03.00 SISTEMA DE AGUA FRIA MODULO B


06.03.01 RED DE DISTRIBUCION TUBERIA PVC SAP 1/2'' M 19.69
RED DISTRIBUCION PLANTA 1 17.85 17.85
RED DISTRIBUCION ELEVACION 1 1.84 1.84

06.03.02 CODO 90°PVC Ø 1/2'' UND 16.00


1/2 BAÑO +SALA+COCINA 16 16.00

06.03.03 TEE PVC Ø 1/2" UND 8.00


1/2 BAÑO +SALA+COCINA 4 2.00 8.00

06.03.04 VALVULA DE CONTROL ESFERICA Ø 1/2" UND 3.00


1/2 BAÑO 2 2.00
INICIO DE LA MATRIZ 1 1.00

06.03.05 GRISFOS Ø 1/2" UND 2.00


1/2 BAÑO 1 1.00
COCINA 1 1.00

06.04.00 SISTEMA DE DESAGUE MODULO B


06.04.01 RED DE DISTRIBUCION TUBERIA PVC SAP 2'' M 3.58
1/2 BAÑO + COCINA 1 3.58 3.58

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.02 CODO PVC Ø 2" x 90º UND 3.00
1/2 BAÑO + COCINA 3 3.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.03 TEE PVC Ø 2"COLECTOR PRINCIPAL UND 1.00
Colector principal 1°piso 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.04 TRAMPA PVC Ø 2"COLECTOR PRINCIPAL UND 2.00
TRAMPA NORMAL PARA BAÑO 1 1.00
TRAMPA DE GRASAS 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.05 SUMIDERO Ø 2" UND 1.00
1/2 BAÑO 1 1.00

06.04.06 RED DE DISTRIBUCION TUBERIA PVC SAP 4'' M 16.17


1/2 BAÑO + COCINA 1 16.17 16.17

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.07 CODO PVC Ø 4" x 90º UND 2.00
1/2 BAÑO + COCINA 2 2.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.08 YEE PVC Ø 4"COLECTOR PRINCIPAL UND 3.00
Colector principal 1°piso 3 3.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.09 TEE PVC Ø 4"COLECTOR PRINCIPAL UND 2.00
Colector principal 1°piso 2 2.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.10 REGISTRO ROSCADO Ø 4"COLECTOR PRINCIPAL UND 1.00
BAÑO 1 1.00

Dimenciones Area/

ITEM DESCRIPCION UND Long. Anc. Alto sección Parcial TOTAL
veses
(m) (m) (m) (m2)
06.04.11 CAJA DE REGISTRO DE DESAGUE PZA 2.00
COLECTOR PRINCIPAL 2 2.00
ITEM DESCRIPCION UND Nº veses Long. (m) Parcial TOTAL

06.05.00 INSTALACIONES ELECTRICAS

05.05.01.00 INSTALACIONES ELECTRICAS INTERCOMUNICADOR /TELEFONO

LINEA DE INTERCOMUNICADOR / DUCTO CON TUBERIA PVC-SEL (15


05.05.01.01 M 36.96
mm)-5/8"-3m.
INTERCOMUNICADOR-SALA 1 9.80 9.80
SALA -ESTUDIO 1 13.50 13.50
ESTUDIO -DORMITORIO PRINCIPAL 1 4.66 4.66
MONTANTES 3 3.00 9.00

05.05.01.02 CURVAS PVC-SEL (15 mm)-5/8"-3m. UND 6.00

INTERCOMUNICADOR-SALA 3
SALA -ESTUDIO 1
ESTUDIO -DORMITORIO PRINCIPAL 2

05.05.01.03 CAJAS OCTOGONALES UND 2.00

INTERCOMUNICADOR-SALA 2

05.05.01.04 Caja de Paso Rectangular 100x55 mm UND 2.00

INTERCOMUNICADOR-SALA 2
Cable TW 14 AWG Verde 100 m
05.05.01.05 M 39.96
Indeco
INTERCOMUNICADOR-SALA 1 12.80 12.80
SALA -ESTUDIO 1 13.50 13.50
ESTUDIO -DORMITORIO PRINCIPAL 1 4.66 4.66
MONTANTES 3 3.00 9.00

ITEM DESCRIPCION UND Nº veses Long. (m) Parcial TOTAL

05.05.02.00 INSTALACIONES ELECTRICAS INTERRUPTORES

05.05.02.01 INTERRUPTORES / DUCTO CON TUBERIA PVC-SEL (15 mm)-5/8"-3m. M 84.33

TABLERO-SALA -COCINA -ESTUDIO 1 37.73 37.73


ESTUDIO-PASADIZO-DORMITORIO 1 8.87 8.87
DORMITORIO -PASADICO 1 13.19 13.19
DORMITORIO -PASADICO 3 8.18 24.54

05.05.02.02 CURVAS PVC-SEL (15 mm)-5/8"-3m. UND 1.00


GENERAL 22

05.05.02.03 CAJAS OCTOGONALES UND 1.00


INTERCOMUNICADOR-SALA 1

05.05.02.04 TOMACORRIENTE DOBLE OVAL BATICINO UND 15.00


INTERCOMUNICADOR-SALA 15

05.05.02.05 TOMACORRIENTE+ PUERTOS USB UND 2.00


INTERCOMUNICADOR-SALA 2

Cable TW 14 AWG Verde 100 m


05.05.02.06 M 84.33
Indeco
TABLERO-SALA -COCINA -ESTUDIO 1 37.73 37.73
ESTUDIO-PASADIZO-DORMITORIO 1 8.87 8.87
DORMITORIO -PASADICO 1 13.19 13.19
DORMITORIO -PASADICO 3 8.18 24.54
05.05.03.00 POZO A TIERRA
LINEA DE INTERCOMUNICADOR / DUCTO CON TUBERIA PVC-SEL (15
05.05.03.01 M 14.45
mm)-5/8"-3m.
TABLERO-SALA -COCINA -ESTUDIO 1 14.45 14.45

05.05.03.02 CAJAS OCTOGONALES UND 1.00


INTERCOMUNICADOR-SALA 1

Cable TW 14 AWG Verde 100 m


05.05.03.03 M 16.25
Indeco
TABLERO-SALA -COCINA -ESTUDIO 1 16.25 16.25

05.05.03.04 CURVAS PVC-SEL (15 mm)-5/8"-3m. UND 3.00


GENERAL 3

05.05.04.00 BOMBA DE CISTERNA


LINEA DE INTERCOMUNICADOR / DUCTO CON TUBERIA PVC-SEL (15
05.05.04.01 M 28.98
mm)-5/8"-3m.
TABLERO-SALA -COCINA -ESTUDIO 1 28.98 28.98

05.05.04.02 CAJAS OCTOGONALES UND 1.00


INTERCOMUNICADOR-SALA 1
05.05.04.03 CURVAS PVC-SEL (15 mm)-5/8"-3m. UND 10.00
GENERAL 10

Cable TW 14 AWG Verde 100 m


05.05.04.04 M 31.98
Indeco
TABLERO-SALA -COCINA -ESTUDIO 1 31.98 31.98

05.05.05.00 INSTALACIONES ELECTRICAS LUMINARIAS

05.05.05.01 LINEA DELUMINARIAS / DUCTO CON TUBERIA PVC-SEL (15 mm)-5/8"-3m. M 223.74

SALA+CONINA+1/2 BAÑO (PLANTA) 1 31.06 31.06


SALA+CONINA+1/2 BAÑO (ELEVACION) 1 88.20 88.20
DORMITORIOS + BAÑOS +PASADIZO(PLANTA) 1 79.88 79.88
DORMITORIOS + BAÑOS +PASADIZO(ELEVACION) 1 24.60 24.60

05.05.05.02 CURVAS PVC-SEL (15 mm)-5/8"-3m. UND 24.00


GENERAL 29

05.05.05.03 CAJAS OCTOGONALES UND 24.00


INTERCOMUNICADORES GENERALES 24

05.05.05.04 INTERRUPTOR SIMPLE OVAL BATICINO UND 11.00


SALA+COCINA 2
DORMITORIOS + BAÑOS +PASADIZO(PLANTA) 9

05.05.05.05 UND 4.00


Interruptor Conmutador Simple S Placa
DORMITORIOS + BAÑOS +PASADIZO(PLANTA) 4

05.05.05.06 INTERRUPTOR COMMUTADOR OVAL BATICINO UND 4.00


SALA + COCINA +GRADAS 4

05.05.05.07 Caja de Paso Rectangular 100x55 mm UND 2.00

PUNTOS DE TV 2

Tapa ciega Redonda


05.05.05.08 Tapa ciega Redonda UND 5.00
PUNTOS DE TV 5

Cable TW 14 AWG Verde 100 m


05.05.05.09 M 225.60
Indeco
SALA+CONINA+1/2 BAÑO (PLANTA) 1 31.06 31.06
SALA+CONINA+1/2 BAÑO (ELEVACION) 1 89.10 89.10
DORMITORIOS + BAÑOS +PASADIZO(PLANTA) 1 79.88 79.88
DORMITORIOS + BAÑOS +PASADIZO(ELEVACION) 1 25.56 25.56

05.05.06.00 INSTALACION DE TABLEROS DE CONTROL ELECTRICO


Tablero Empotrable Tapa Fume 8 Puertos
05.05.06.01 UND 1.00
Schneider Electric
Tablero general 1 1.00

05.05.07.00 SUMINISTRO E INSTALACION DE LAMPARAS


Foco ahorrador espiral 23W E27 luz blanca
05.05.07.01 UND 21.00
Philips
General 21 21.00
05.05.07.02 SOCKET UND 21.00
General 21 21.00
Cinta aislante 1700 negro
05.05.07.03 UND 7.00
3M( 18 metros)
General 7 7.00
MURO VANOS
ITEM DESCRIPCION
AREA TOTAL
05.01.00 ARQUITECTURA MODULO A UND M2 Nº Rep. Area (m2) Nº Rep. Area (m2)
Long. (m) Alto (m) Long. (m) Alto (m)
MUROS DE LADRILLO KK DE ARCILLA DE SOGA
05.01.01.00 184.65
MODULA "A"
Primer Nivel

EJE 8 ENTRE E'-G 1 5.22 2.8 14.62 - - - 0.00

EJE E' ENTRE 8'-8 1 1.58 2.8 4.42 - - - 0.00

EJE G ENTRE 9-8 1 0.7 2.8 1.96 - - - 0.00


EJE 8 ENTRE F'-G 1 4.1 2.6 10.66 1 2.25 1.6 3.60
EJE E'ENTRE 7- 8 1 3.33 2.6 8.66 - - - 0.00
EJE F' ENTRE 7-8 1 2.57 2.6 6.68 - - - 0.00
EJE 7 ENTRE F'-G 1 4.45 2.6 11.57 - - - 0.00
EJE G' ENTRE 7-8 1 2.4 2.6 6.24 - - - 0.00
EJE G ENTRE 7-8 1 3.1 2.6 8.06 - - - 0.00
EJE E' ENTRE 6-7 1 2.33 2.6 6.06 - - - 0.00
EJE F' ENTRE 6-7 1 1.53 2.6 3.98 - - - 0.00
EJE G' ENTRE 6-7 1 2.2 2.6 5.72 - - - 0.00
EJE G ENTRE 6-7 1 2.65 2.6 6.89 - - - 0.00
EJE E ENTRE 5-6 1 2.8 2.6 7.28 - - - 0.00
EJE 6 ENTRE F'-G 1 4.1 2.6 10.66 1 2.25 1.6 3.60
EJE G' ENTRE F'-G 1 3.05 2.6 7.93 1 1.1 0.4 0.44
EJE 5 ENTRE F'-G 1 2.25 2.6 5.85 1 2.25 1.6 3.60
EJE 5 ENTRE F'-G 1 0.9 2.6 2.34 - - - 0.00
EJE G ENTRE 5-6 1 2.9 2.6 7.54 - - - 0.00
EJE E' ENTRE 4-5 1 2.7 2.6 7.02 - - - 0.00
EJE F' ENTRE 4-5 1 2.5 2.6 6.50 - - - 0.00
EJE 4' ENTRE 4-5 1 3.25 2.6 8.45 - - - 0.00
EJE G ENTRE 4-5 1 2.8 2.6 7.28 - - - 0.00
EJE E' ENTRE 4-3' 1 1.55 2.6 4.03 - - - 0.00
EJE F' ENTRE 4-3' 1 1.5 2.6 3.90 - - - 0.00
EJE 3' ENTRE F-G 1 3.25 2.6 8.45 1 2.35 1.6 3.76
EJE G ENTRE 3-4 1 2.4 2.6 6.24 - - - 0.00
EJE G ENTRE 1'-3' 1 2.83 2.8 7.92 - - - 0.00
EJE 1' ENTRE F-G 1 0.98 2.8 2.74 - - - 0.00

05.01.02.00 REVOQUES Y ENLUCIDOSMODULA "A"

MURO NO INCLUIDO
ITEM DESCRIPCION UND Nº Rep. Area (m2) Nº Rep. Area (m2) TOTAL 330.41
Long. (m) Alto (m) Long. (m) Alto (m)
05.01.02.01 TARRAJEO EN MURO INTERIOR C:A : 1:5 M2 255.71
SS.HH. 1 ENTRE LOS EJE 7-7 Y 8-8 1 8.11 2.6 21.09 - - - 0.00
SS.HH. 1 ENTRE LOS EJE 7-7 Y 6-6 1 7.86 2.6 20.44 - - - 0.00
SS.HH. 1 ENTRE LOS EJE 5-5 Y 6-6 1 8.91 2.1 18.71 1 1.1 0.4 0.44
MURO - EJE 8 ENTRE F' -G 1 4.7 2.6 12.22 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 8 Y 7 1 11.09 2.6 28.83 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 6 Y 7 1 10.9 2.6 28.34 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 4 Y 5 1 12.87 2.6 33.46 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 3' Y 4 1 11.3 2.6 29.38 1 2.35 1.6 3.76
PASADIZO ENTRE LOS EJES 3', 4, 5, 6,7 Y 8 1 23.2 2.6 60.32 - - - 0.00
TRAGALUZ ENTRE LOSEJES 5-6 1 8.4 2.6 21.84 1 4.5 1.6 7.20
LAVANDERIA SOLO EJE 3' 1 3.6 2.6 9.36 1 1.55 1.6 2.48

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL
(m2)

03.01.02.02 CIELORRASO MORTERO C:A 1:5 M2 74.70

DORMITOIO + BAÑO(ENTRE LOS EJES 7 Y 8) 1 13.52


DORMITOIO + BAÑO(ENTRE LOS EJES 6 Y 7) 1 12.97
DORMITOIO + BAÑO(ENTRE LOS EJES 4 Y 6) 1 18.38
DORMITOIO + BAÑO(ENTRE LOS EJES 3' Y 4) 1 9.09
PASADIZO 1 20.74
05.01.03.00 PISOS Y PAVIMENTOS

Area/ sección FACTORES/M2


ITEM DESCRIPCION UND Nº veses Parcial TOTAL
(m2)
BOL.CEMENTO AGR.FINO M3
05.01.03.01 FALSO PISO, CONCRETO C:H, 1:12, E=4” M2 96.12 0.35 0.13
DORMITOIO + BAÑO(ENTRE LOS EJES 7 Y 8) 1 13.52 33.64 12.50
DORMITOIO + BAÑO(ENTRE LOS EJES 6 Y 7) 1 12.97
DORMITOIO + BAÑO(ENTRE LOS EJES 4 Y 6) 1 18.38
DORMITOIO + BAÑO(ENTRE LOS EJES 3' Y 4) 1 9.09
PASADIZO 1 20.74
LAVANDERIA 1 10.61
TRAGALUZ 1 10.81

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL UNID.
(m2)
PISO CERAMICO 0.45 x 0.45m. (AMBIENTES
05.01.03.02 M2 433.40
INTERIORES)
PAZADIZO + GRADAS 1 23.30 115.04
ESTUDIO 1 9.09 44.89
BAÑOS CON TINA 1 1 8.78 43.37
BAÑOS SIMPLES COMPLETOS 1 2 13.17 130.08

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL UND.
(m2)
05.01.03.03 ZOCALO INTERIOR (0.095*0.60m) M2 106.46

PAZADIZO+ ESTUDIO 4.668 81.89

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL M2
Fragua para cerámicos azul acero 1Kg (m2)
05.01.03.04 Chema M2 76.71
Chema
PAZADIZO + GRADAS 1 23.30
ESTUDIO 1 9.09
BAÑOS CON TINA 1 1 8.78
BAÑOS SIMPLES COMPLETOS 1 2 13.17
PAZADIZO+ ESTUDIO 4.67

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL M2
(m2)

05.01.03.04 PISO PARQUET (AMBIENTES INTERIORES) M2 31.84

DORMITORIO PRINCIPAL 1 12.69


DORMITORIO SIMPLE 1 9.25
DORMITORIO SIMPLE 1 1 9.90

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL M2
(m2)
05.01.03.05 ZOCALOPARQUET (0.095*0.60m) M2 3.49

DORMITORIO PRINCIPAL 1 1.287

DORMITORIO SIMPLE 1 1.09

DORMITORIO SIMPLE 1 1.111


05.01.04 PINTURA

MURO VANOS
ITEM DESCRIPCION UND Nº vec. Area (m2) Nº vec. Area (m2) Parcial TOTAL
Long. (m) Alto (m) Long. (m) Alto (m)

PINTURA LATEX EN MUROS EXTERIORES E


05.01.04.01 M2 396.49M2
NTERIORES

SS.HH. 1 ENTRE LOS EJE 7-7 Y 8-8 1 8.11 2.6 21.09 - - - 0.00
SS.HH. 1 ENTRE LOS EJE 7-7 Y 6-6 1 7.86 2.6 20.44 - - - 0.00
SS.HH. 1 ENTRE LOS EJE 5-5 Y 6-6 1 8.91 2.1 18.71 1 1.1 0.4 0.44
MURO - EJE 8 ENTRE F' -G 1 4.7 2.6 12.22 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 8 Y 7 1 11.09 2.6 28.83 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 6 Y 7 1 10.9 2.6 28.34 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 4 Y 5 1 12.87 2.6 33.46 1 2.25 1.6 3.60
DORMITORIO -ENTRE EJES 3' Y 4 1 11.3 2.6 29.38 1 2.35 1.6 3.76
PASADIZO ENTRE LOS EJES 3', 4, 5, 6,7 Y 8 1 23.2 2.6 60.32 - - - 0.00
TRAGALUZ ENTRE LOSEJES 5-6 1 8.4 2.6 21.84 1 4.5 1.6 7.20
LAVANDERIA SOLO EJE 3' 1 3.6 2.6 9.36 1 1.55 1.6 2.48
DORMITOIO + BAÑO(ENTRE LOS EJES 7 Y 8) 1 13.52
DORMITOIO + BAÑO(ENTRE LOS EJES 6 Y 7) 1 12.97
DORMITOIO + BAÑO(ENTRE LOS EJES 4 Y 6) 1 18.38
DORMITOIO + BAÑO(ENTRE LOS EJES 3' Y 4) 1 9.09
PASADIZO 1 20.74

MURO VANOS
ITEM DESCRIPCION UND Nº vec. Area (m2) Nº vec. Area (m2) Parcial TOTAL
Long. (m) Alto (m) Long. (m) Alto (m)

PINTURA BASE EN MUROS EXTERIORES E


05.01.04.01 M2 396.49M2
NTERIORES
05.01.05 CARPINTERIA DE MADERA

ITEM DESCRIPCION UND Nº veses Parcial TOTAL

SUMINISTRO E INSTALACION DE PUERTA P-1 (INC.


05.01.05.01 8.00
CERRAJERIA Y ACABADOS)

PUERTA2 0.90X2.61 1 5
5.00

PUERTA 3 0.75*2.10 1 3
3.00

ITEM DESCRIPCION UND Nº veses Parcial TOTAL

SUMINISTRO E INSTALACION DE VENTANA V-1 (INC.


05.01.05.02 UND 4.00
CERRAJERIA Y ACABADOS)

VENTANA 4 (2.25*1.60) 1 3 3.00


VENTANA 3 (2.35*1.60) 1 1 1.00
VENTANA A-1 (1.10*0.4) 1 1 1.00

05.01.06 SUMINSTRO E INSTALACION DE INTA.SANITARIAS

ITEM DESCRIPCION UND Nº veses Parcial TOTAL

SUMINISTRO E INSTALACION DE BAÑOSY MEDIO


05.01.06.01 1.00
BAÑOS

DORMITORIO PRINCIPAL MEDIO BAÑO + TINA 1 4


1.00
DORMITORIO BAÑO COMPLETO SIMPLE 1 2 1.00

MURO VANOS
ITEM DESCRIPCION
AREA TOTAL FATOR *M2
05.02.00 ARQUITECTURA MODULO B UND M2 Nº Rep. Area (m2) Nº Rep. Area (m2)
Long. (m) Alto (m) Long. (m) Alto (m)
MUROS DE LADRILLO KK DE ARCILLA DE SOGA
05.02.01.00 69.74 45.35
MODULA "B"
EJE 3 ENTRE C-D 1 3.5 2.6 9.10 1 2.15 1.6 3.44
EJE 3 ENTRE C-E 1 3.35 2.6 8.71 1 1.9 1.6 3.04
EJE 1 ENTRE A- C 1 1.9 2.6 4.94 - - - 0.00
EJE 1 ENTRE C- D 1 3.6 2.6 9.36 - - - 0.00
EJE 1 ENTRE D-E 1 3.35 2.6 8.71 - - - 0.00
EJE A ENTRE 2-3 1 0.68 2.6 1.77 - - - 0.00
EJE A ENTRE 1-2 1 2.43 2.6 6.32 - - - 0.00
EJE B ENTRE 1-3 1 2.55 2.6 6.63 - - - 0.00
EJE C ENTRE 1-2 1 2.85 2.6 7.41 - - - 0.00
EJE D' ENTRE 1-2 1 3 2.6 7.80 1 1.7 1.6 2.72
EJE E ENTRE 1-2 1 3.15 2.6 8.19 - - - 0.00

05.01.02.00 REVOQUES Y ENLUCIDOSMODULA "B"

MURO NO INCLUIDO
ITEM DESCRIPCION UND Nº Rep. Area (m2) Nº Rep. Area (m2) TOTAL
Long. (m) Alto (m) Long. (m) Alto (m)
05.01.02.01 TARRAJEO EN MURO INTERIOR C:A : 1:5 M2 123.98
SS.HH. 1 ENTRE LOS EJE B-BY C-C 1 7.39 2.6 19.21 - - - 0.00
ESACALERA 1 8.46 2.6 22.00 - - - 0.00
MURO - EXTERIOR 1 8.15 2.6 21.19 1 4.05 1.6 6.48
SALA 1 21.31 2.6 55.41 1 5.75 1.6 9.20
COCINA 1 9.45 2.6 24.57 1 1.7 1.6 2.72

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL
(m2)

05.01.02.02 CIELORRASO MORTERO C:A 1:5 M2 35.14

ESACALERA 1 1.40
MEDIO BAÑO 1 4.15
SALA 1 21.14
COCINA 1 8.45
05.01.03.00 PISOS Y PAVIMENTOS

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL
(m2)

05.01.03.01 FALSO PISO, CONCRETO C:H, 1:10, E=4” M2 35.14


ESCALERA 1 1.40
MEDIO BAÑO 1 4.15
SALA 1 21.14
COCINA 1 8.45

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL
(m2)
PISO CERAMICO 0.45 x 0.45m. (AMBIENTES
03.01.03.02 M2 254.91
INTERIORES)
Primer Nivel
SALA + COCINA + PAZADIZO 1 31.81 157.09
MEDIO BAÑO 1 11.11 54.86
ESCALERA LLEGADA A SEGUNDO NIVEL 1 8.70 42.96

Area/ sección
ITEM DESCRIPCION UND Nº veses Parcial TOTAL
(m2)
03.01.03.03 ZOCALO INTERIOR (0.095*0.60m) M2 58.91

SALA + COCINA + PAZADIZO 3.358 58.91

05.01.04 PINTURA

MURO VANOS
ITEM DESCRIPCION UND Nº vec. Area (m2) Nº vec. Area (m2) Parcial TOTAL
Long. (m) Alto (m) Long. (m) Alto (m)

05.08.01 PINTURA LATEX EN MUROS EXTERIORES M2 137.91M2

Primer Nivel

EJE 3 ENTRE C Y E EXTRENO 1 7.85 2.6 20.41 1 4.05 1.6 6.48

SS.HH. 1 ENTRE LOS EJE B-BY C-C 1 7.39 2.6 19.21 - - - 0.00
ESACALERA 1 8.46 2.6 22.00 - - - 0.00
MURO - EXTERIOR 1 8.15 2.6 21.19 1 4.05 1.6 6.48
SALA 1 21.31 2.6 55.41 1 5.75 1.6 9.20
COCINA 1 9.45 2.6 24.57 1 1.7 1.6 2.72

05.01.05 CARPINTERIA DE MADERA

ITEM DESCRIPCION UND Nº veses Parcial TOTAL

SUMINISTRO E INSTALACION DE PUERTA P-1 (INC.


05.01.05.01 4.00
CERRAJERIA Y ACABADOS)

PUERTA 1.00X2.60 1 4
4.00

PUERTA 0.90X2.61 1 0
0.00

PUERTA 0.75*2.10 1 0
0.00

ITEM DESCRIPCION UND Nº veses Parcial TOTAL

SUMINISTRO E INSTALACION DE VENTANA V-1 (INC.


05.01.05.02 UND 2.00
CERRAJERIA Y ACABADOS)

VENTANA 1 (2.15*1.60) 1 1
1.00
VENTANA 1 (1.90*1.60) 1 1 1.00

05.01.06 SUMINSTRO E INSTALACION DE INTA.SANITARIAS

ITEM DESCRIPCION UND Nº veses Parcial TOTAL

SUMINISTRO E INSTALACION DE BAÑOSY MEDIO


05.01.06.01 1.00
BAÑOS

SALA MEDIO BAÑO 1 4


1.00
PRESUPUESTO GANADOR
MODULO A 1 2 1 2
ITEM DESCRIPCIÓN PARCIAL REDONDEO sodimac costo hernandez COSTO PARCIAL COSTO PARCIAL
01.00 OBRAS DE CONCRETO
01.01 CEMENTO PACASMAYO EXTRA FORTE 411.89 412.00 22.00 21.00 9064.00 8652.00
01.02 HORMIGON 45.00 45.00 65.00 25.00 2925.00 1125.00
01.03 P.G.8" MAX 22.50 23.00 65.00 55.00 1495.00 1265.00
01.04 ARENA GRUESA 14.89 15.00 65.00 55.00 975.00 825.00
01.05 PIEDRA 1/2" 23.82 24.00 65.00 55.00 1560.00 1320.00
01.06 LADRILLO KING KONG 0.30X0.30X0.15 0.56 1.00 1200.00 1200.00 1200.00 1200.00
02.00 Barras de Acero 1/4" ACERO
02.01 Aceros de
Barras Arequipa
Acero 3/8" 80.68 81.00 7.00 6.50 567.00 526.50
02.02 Aceros de
Barras Arequipa
Acero 1/2" 71.36 72.00 15.70 15.50 1130.40 1116.00
02.03 Aceros de
Barras Arequipa
Acero 5/8" 163.41 164.00 27.80 27.00 4559.20 4428.00
02.04 Aceros Arequipa 39.11 40.00 42.80 42.00 1712.00 1680.00
03.00 AGUA FRIA 0.00
03.01 Tubo Agua Simple Presión 1/2" 15.21 16.00 6.90 7.50 110.40 120.00
03.02 CODO 90°PVC Ø 1/2'' 44.00 44.00 0.50 1.00 22.00 44.00
03.03 TEE PVC Ø 1/2"
Sanking 24.00 24.00 1.50 2.00 36.00 48.00
03.04 Karson
Karson 7.00 10.00 6.50 18.00 65.00 180.00
03.05 Karson
Llave para Lavatorio Baja Málaga FF8253D 2.00 2.00 11.90 25.00 23.80 50.00
03.06 Karson
Pegamento PVC 16 Oz Negro Mediano 3.00 3.00 8.80 25.00 26.40 75.00
03.07 4.00 4.00 25.90 16.00 103.60 64.00
03.08 CINTA TEFLON 5.00 5.00 1.20 1.00 6.00 5.00
04.00 Pavco DESAGUE 0.00
04.01 Pavco
Codo Desagüe PVC 2" x 90° 2.51 3.00 29.80 12.00 89.40 36.00
04.02 Pavco 7.00 7.00 1.60 2.00 11.20 14.00
04.03 Tee Desagüe PVC Ø 2" 1.00 1.00 1.80 3.50 1.80 3.50
04.04 YEE desague PVC Ø 2" 4.00 4.00 2.30 3.50 9.20 14.00
04.05 Reduccion 4x2 desague 4.00 4.00 4.90 4.00 19.60 16.00
04.06 CODO 45° PVC Ø 2" 1.00 1.00 1.70 1.80 1.70 1.80
04.07 YEE PVC desagüe
Trampa Ø 4" A 2 2" premium 2.00 2.00 8.50 7.00 17.00 14.00
04.08 Pavco
Trampa desagüe 2" premium 6.00 6.00 4.20 12.00 25.20 72.00
04.09 Pavco (grasas)
Sumidero 2" bronce pesado 1.00 1.00 6.20 7.00 6.20 7.00
04.10 Duragrif
Tubo PVC SAP 4'' de 3m 7.00 7.00 8.70 3.00 60.90 21.00
04.11 Pavco
Codo PVC Desagüe 4" X 90º SP 16.28 17.00 81.50 24.00 1385.50 408.00
04.12 Matusita 5.00 5.00 6.80 6.00 34.00 30.00
04.13 YEE PVC Ø 4" 1.00 1.00 8.55 9.00 8.55 9.00
04.14 Tee Desagüe
Registro PVC4"Ø 4"
dorado 7.00 7.00 8.10 9.00 56.70 63.00
04.15 Galusa 3.00 3.00 19.90 12.00 59.70 36.00
04.16 CODO 45° PVC Ø 4 4.00 4.00 5.40 6.00 21.60 24.00
05.00 Tubo PVC SEL 5/8'' 3m ELECTRICAS 1808.25 769.30
05.01 Pavco
Curva PVC SEL 90º 5/8'' 129.49 130.00 2.90 3.50 377.00 455.00
05.02 Pavco 44.00 44.00 0.46 0.50 20.24 22.00
05.03 CAJAS OCTOGONALES 29.00 29.00 1.25 1.00 36.25 29.00
05.04 Caja de Paso Rectangular 100x55 mm 2.00 2.00 0.90 0.90 1.80 1.80
05.05 Cable TW 14 AWG Verde 100 m 3.98 4.00 107.30 105.00 429.20 420.00
05.06 TOMACORRIENTE DOBLE OVAL BATICINO 15.00 15.00 14.20 8.00 213.00 120.00
05.07 TOMACORRIENTE+
Conmutador SimplePUERTOS
PrimmusUSBBlanco 2.00 2.00 74.90 74.90 149.80 149.80
05.08 Karson
Interruptor Triple Clio Blanco 11.00 11.00 9.20 9.00 101.20 99.00
05.09 Halux 4.00 4.00 22.90 12.00 91.60 48.00
05.10 Interruptor Conmutador Simple S Placa 4.00 4.00 6.90 10.00 27.60 40.00
05.11 Caja de Paso Rectangular 100x55 mm 2.00 2.00 0.90 0.90 1.80 1.80
05.12 Tapa ciega Redonda 5.00 5.00 1.70 1.00 8.50 5.00
05.13 Tablero Empotrable Tapa Fume 8 Puertos 1.00 1.00 29.90 29.90 29.90 29.90
05.14 Foco ahorrador espiral 23W E27 luz blanca 21.00 21.00 14.90 14.90 312.90 312.90
05.15 WALL SOCKET 21.00 21.00 2.50 6.00 52.50 126.00
05.16 Cinta aislante 1700 negro 7.00 7.00 6.50 3.50 45.50 24.50
05.17 LLAVES TERMICAS 25A 4.00 4.00 7.50 35.00 30.00 140.00
1928.79
06.00 AQUITECTURA 0.00
06.01 LADRILLOS 8.79 9.00 370.00 370.00 3330.00 3330.00
06.02 CEMENTO PACASMAYO EXTRAFORTE 106.66 107.00 22.00 21.00 2354.00 2247.00
06.03 AGREGADO FINO M3 29.27 30.00 60.00 55.00 1800.00 1650.00
06.04 PISO CERAMICO 0.45 x 0.45m. (PROMEDIO) 48.16 49.00 41.61 41.61 2038.89 2038.89
06.05 ZOCALOpara
Fragua INTERIOR (0.095*0.60m)(PROMEDIO)
cerámicos azul acero 1Kg 106.46 107.00 6.50 6.50 695.50 695.50
06.06 Chema 25.57 26.00 7.40 7.40 192.40 192.40
06.07 PISO PARQUET (AMBIENTES INTERIORES) 38.21 39.00 70.00 70.00 2730.00 2730.00
06.08 PISO PARQUET (AMBIENTES INTERIORES) 3.49 4.00 14.00 14.00 56.00 56.00
06.09 PINTURA BASE 9.91 10.00 21.00 3.50 210.00 35.00
06.10 PINTURA LATEX EN MUROS EXTERIORES E INTERIORES 6.61 7.00 21.00 21.00 147.00 147.00
06.11 PUERTA2 0.90X2.61 5.00 5.00 160.00 160.00 800.00 800.00
06.12 PUERTA 3 0.75*2.10 3.00 3.00 130.00 130.00 390.00 390.00
06.13 Kit de Accesorios para Baños Adhesivos Color Bone 3.00 3.00 65.00 18.00 195.00 54.00
06.14 TANQUE + TAZA + LAVATORIO + PEDESTAL MANANTIAL 3.00 3.00 287.60 287.60 862.80 862.80
TOTAL MATERIALES 48856.47 41515.39
MANO DE OBRA S/. 17500.00
PREUPUESTO TOTAL 59015.39
PRESUPUESTO GANADOR
MODULO A 1 2 A B C D E F G
ITEM DESCRIPCIÓN PARCIAL REDONDEO sodimac costo hernandez COSTO
01.00 OBRAS DE CONCRETO
01.01 CEMENTO PACASMAYO EXTRA FORTE 411.89 412.00 22 21 8652
01.02 HORMIGON 45.00 45 65 25 1125
01.03 P.G.8" MAX 22.50 23 65 55 1265
01.04 ARENA GRUESA 14.89 15 65 55 825
01.05 PIEDRA 1/2" 23.82 24 65 55 1320
01.06 LADRILLO KING KONG 0.30X0.30X0.15 0.56 1 1200 1200 1200
02.00 Barras de Acero 1/4" ACERO 0
02.01 Aceros Arequipa
Barras de Acero 3/8" 80.68 81 7 6.5 526.5
02.02 Aceros Arequipa
Barras de Acero 1/2" 71.36 72 15.7 15.5 1116
02.03 Aceros de
Barras Arequipa
Acero 5/8" 163.41 164 27.8 27 4428
02.04 Aceros Arequipa 39.11 40 42.8 42 1680
03.00 AGUA FRIA 0
03.01 Tubo Agua Simple Presión 1/2" 15.21 16.00 6.9 7.5 120
03.02 CODO 90°PVC Ø 1/2'' 44.00 44 0.5 1 44
03.03 TEE PVC Ø 1/2"
Sanking 24.00 24 1.5 2 48
03.04 Karson
Karson 7.00 10 6.5 18 180
03.05 Karson
Llave para Lavatorio Baja Málaga FF8253D 2.00 2 11.9 25 50
03.06 Karson
Pegamento PVC 16 Oz Negro Mediano 3 3 8.8 25 75
03.07 4 4 25.9 16 64
03.08 CINTA TEFLON 5 5 1.2 1 5
04.00 Pavco DESAGUE 0
04.01 Pavco
Codo Desagüe PVC 2" x 90° 2.51 3 29.8 12 36
04.02 Pavco 7.00 7 1.6 2 14
04.03 Tee Desagüe PVC Ø 2" 1.00 1 1.8 3.5 3.5
04.04 YEE desague PVC Ø 2" 4.00 4 2.3 3.5 14
04.05 Reduccion 4x2 desague 4.00 4 4.9 4 16
04.06 CODO 45° PVC Ø 2" 1.00 1 1.7 1.8 1.8
04.07 YEE PVC desagüe
Trampa Ø 4" A 2 2" premium 2.00 2 8.5 7 14
04.08 Pavco
Trampa desagüe 2" premium 6 6 4.2 12 72
04.09 Pavco (grasas)
Sumidero 2" bronce pesado 1 1 6.2 7 7
04.10 Duragrif
Tubo PVC SAP 4'' de 3m 7.00 7 8.7 3 21
04.11 Pavco
Codo PVC Desagüe 4" X 90º SP 16.28 17 81.5 24 408
04.12 Matusita 5.00 5 6.8 6 30
04.13 YEE PVC Ø 4" 1.00 1 8.55 9 9
04.14 Tee Desagüe
Registro PVC4"Ø 4"
dorado 7.00 7 8.1 9 63
04.15 Galusa 3.00 3 19.9 12 36
04.16 CODO 45° PVC Ø 4 4 4 5.4 6 24
05.00 Tubo PVC SEL 5/8'' 3m ELECTRICAS 0
05.01 Pavco
Curva PVC SEL 90º 5/8'' 129.49 130 2.9 3.5 455
05.02 Pavco 44.00 44 0.46 0.5 22
05.03 CAJAS OCTOGONALES 29.00 29 1.25 1 29
05.04 Caja de Paso Rectangular 100x55 mm 2.00 2 0.9 0.9 1.8
05.05 Cable TW 14 AWG Verde 100 m 3.98 4 107.3 105 420
05.06 TOMACORRIENTE DOBLE OVAL BATICINO 15.00 15 14.2 8 120
05.07 TOMACORRIENTE+
Conmutador SimplePUERTOS
PrimmusUSB
Blanco 2.00 2 74.9 74.9 149.8
05.08 Karson 11.00 11 9.2 9 99
Interruptor Triple Clio Blanco
05.09 Halux 4.00 4 22.9 12 48
05.10 Interruptor Conmutador Simple S Placa 4.00 4 6.9 10 40
05.11 Caja de Paso Rectangular 100x55 mm 2.00 2 0.9 0.9 1.8
05.12 Tapa ciega Redonda 5.00 5 1.7 1 5
05.13 Tablero Empotrable Tapa Fume 8 Puertos 1.00 1 29.9 29.9 29.9
05.14 Foco ahorrador espiral 23W E27 luz blanca 21.00 21 14.9 14.9 312.9
05.15 WALL SOCKET 21.00 21 2.5 6 126
05.16 Cinta aislante 1700 negro 7.00 7 6.5 3.5 24.5
05.17 LLAVES TERMICAS 25A 4.00 4 7.5 35 140
06.00 AQUITECTURA 0
06.01 LADRILLOS 8.79 9 370 370 3330
06.02 CEMENTO PACASMAYO EXTRAFORTE 106.66 107 22 21 2247
06.03 AGREGADO FINO M3 29.27 30 60 55 1650
06.04 PISO CERAMICO 0.45 x 0.45m. (PROMEDIO) 48.16 49 41.61 41.61 2038.89
06.05 ZOCALOpara
Fragua INTERIOR (0.095*0.60m)(PROMEDIO)
cerámicos azul acero 1Kg 106.46 107 6.5 6.5 695.5
06.06 Chema 25.57 26 7.4 7.4 192.4
06.07 PISO PARQUET (AMBIENTES INTERIORES) 38.21 39 70 70 2730
06.08 PISO PARQUET (AMBIENTES INTERIORES) 3.49 4 14 14 56
06.09 PINTURA BASE 9.91 10 21 3.5 35
06.10 PINTURA LATEX EN MUROS EXTERIORES E INTERIORES 6.61 7 21 21 147
06.11 PUERTA2 0.90X2.61 5.00 5 160 160 800
06.12 PUERTA 3 0.75*2.10 3.00 3 130 130 390
06.13 Kit de Accesorios para Baños Adhesivos Color Bone 3 3 65 65 195
06.14 TANQUE + TAZA + LAVATORIO + PEDESTAL MANANTIAL 3 3 287.6 287.6 862.8
TOTAL MATERIALES 40887.09
MANO DE OBRA 17500
58387.09
CALCULO DE MATERIALES EN COLUMNAS0.25X0.25
H L1 L2
COLUMNAS 2.8 0.25 0.25
VOLUM. 0.175

cantidad de materiales para 210kg/cm2


factores/m3 cant.material
cemento 8.5 1.49bols
arena 0.5 0.09m3
piedra 1/2 0.8 0.14m3

cantidad de materiales por numero de columnas


para columnas: 1
cemento 1.49bols
arena 0.09m3
piedra 1/2 0.14m3

numero de Baldes para cada agregado


H d D
balde 0.35 0.28 0.28
VOLUM. 0.022m3
CANT.FINAL
cemento 1.49bols 2.00bols
arena 4.09balde 5.0balde
piedra 1/2 6.36balde 7.0balde

CALCULO DE MATERIALES EN COLUMNAS 0.35*0.15


H L1 L2
COLUMNAS 2.8 0.15 0.35
VOLUM. 0.147

cantidad de materiales para 210kg/cm2


factores/m3 cant.material
cemento 8.5 1.25bols
arena 0.5 0.07m3
piedra 1/2 0.8 0.12m3

cantidad de materiales por numero de columnas


para columnas: 1
cemento 1.25bols
arena 0.07m3
piedra 1/2 0.12m3

numero de Baldes para cada agregado


H d D
balde 0.35 0.28 0.28
VOLUM. 0.022m3
CANT.FINAL
cemento 1.25bols 2.00bols
arena 3.18balde 4.0balde
piedra 1/2 5.45balde 6.0balde
CUADRO RESUMEN
TIPOS DE COLUMNA MATERIAL
MATERALES TOTAL
COL.25*25 COL.15*35 SUBTOTAL
cemento 1.49bols 1.25bols 2.74bols 2.80bols
arena 4.09m3 3.18m3 7.27m3 7.30m3
piedra 1/2 6.36m3 5.45m3 11.82m3 11.90m3
CALCULO DE MATERIALES POR METRO CUBICO DE CONCRETO SIMPLE (CEMENTO+HORMIGON+PIERA
MEDIANA+AGUA)
PROPORCIONES
PARA CIEMIENTOS: 1: 10+ 30%PM FACTO (A/C) 0.8
DENSIDAD CEMEN 3.15
CALCULO PREVIO DE PESOS SECOS AIRE: 1

cemento: 1p3 = 42.50kg


hormigon: (8P3*1800kg/m3)/35.315p3 = 407.80kg
agua: (42.5*0.8) = 34.00kg
484.30kg
RENDIMIENTO DE LA MEZCLA (vólumenes absolutos)

cemento: 1p3 = 0.0135m3


hormigon: = 0.1510m3
agua: = 0.0340m3
0.1985m3
Como en 1m3 de mezcla debe haber 25% P.M. Y aproximadamente 1% de aire atrapado, entonces el volumen
absoluto de 1 m3 de mezcla sin considerar P.M. y aire atrapado es de:

V(1m3)= 0.69m3
Factor cemento = 3.48bolsas
3.4760705289673
CANTIDAD DE MATERIALES

Cemento: 3.48bolsas
Hormigon: 0.985m3
Agua: 0.118m3
Piedra: 0.476m3

El cuadro adjunto muestra las proporciones que se obtienen sin considerar desperdicios y relación a/c = 0.80

CEMENTO PIEDRA AGUA


PROPORCIONES A/C (BOLSAS) (M3)
HORMIGON MEDIANA
(M3) (M3)

1: 10+ I 0.8 3.5bolsas 0.99m3 0.48m3 0.12m3


VALORES A INGRESAR VALORES TRANSPORTADOS VLORES CALCULADOS

Ingrese las dimensiones del ladrillo (Recuadros de color amarillo) teniendo en cuenta que el largo es la dimensión más grande, e alto la más pequeña y el espesor la intermedia.

Largo L(cm) Altto H(cm) Espesor e(cm) Vol (cm^3)


23 7.5 13 2242.5

Dimenciones del Ladrillo muro en Tizón Dimenciones del Ladrillo muro en Soga Dimenciones del Ladrillo muro en Papelillo

H (cm)= 7.5

e (cm)= 23 H (cm)= e (cm)= H (cm)= e (cm)=


7.5 13 13 7.5
L (cm)= 13 L (cm)= 23 L (cm)= 23

Largo L(cm) Altto H(cm) Espesor e(cm) Vol (cm^3) Largo L(cm) Altto H(cm) Espesor e(cm) Vol (cm^3) Largo L(cm) Altto H(cm) Espesor e(cm) Vol (cm^3)
13 7.5 23 2242.5 23 7.5 13 2242.5 23 13 7.5 2242.5

El espesor del mortero entre ladrillos es de 1 a 1,2 cm. Sim embargo, el espesor también depende de la perfección del ladrillo, la trabajabilidad del mortero y de una buena mano de obra. 1.5 cm máximo

espesro mortero largo (cm) espesro mortero alto (cm)


𝐽_ℎ 1.5 𝐽_𝑣 1.5
Formula para calculo de numero de ladrillos

Cantidad de Ladrillos, muro en Tizón por m^2 Cantidad de Ladrillos, muro en Soga por m^2 Cantidad de Ladrillos, muro en Papelillo por m^2
77 45 28

Defina el porcentaje de desperdicio


% de desperdicio 5

Cantidad de Ladrillos total, muro en Tizón por m^2 Cantidad de Ladrillos total, muro en Soga por m^2 Cantidad de Ladrillos total, muro en Papelillo por m^2
80 48 30

Cantidad de mortero de pega m^3 / m^2 muro

𝐶𝑎𝑛𝑡𝑖𝑑𝑎𝑑 𝑑𝑒 𝑚𝑜𝑟𝑡𝑒𝑟𝑜 𝑚^3⁄𝑚^2 𝑚𝑢𝑟𝑜= [100∗100−𝐿∗𝐻∗((# 𝑑𝑒 𝑙𝑎𝑑𝑟𝑖𝑙𝑙𝑜𝑠)⁄𝑚^2 )∗𝑒⁄ 〖 10 〗 ^6 ]

Cantidad de mortero, muro en Tizón Cantidad de mortero, muro en Soga Cantidad de mortero, muro en Papelillo
0.058 0.028 0.012

Defina el porcentaje de desperdicio


% de desperdicio 5

Cantidad de mortero total, muro en Tizón Cantidad de mortero, muro en Soga Cantidad de mortero, muro en Papelillo
0.061 0.030 0.012

Cantidad de cemento por m^2 muro esto depende de la proporcion en volumen a utilizar

TABLA. 1. Se presentan las cantidades de material por m^3 de mortero para las proporciones en volumen suelto más usadas y la estimación de la resistencia a la compresión a los 28 días, se recomienda
establecer los propios valores de resistencia para los materiales de la región

Mezcla Rango Resistencia


Prop. En CEMENTO Agragado Agua Probable a la
Fino Compresión 28 días
Vol. Lt.
m^3
C:F
𝐾_𝑔⁄ 〖𝑐𝑚〗 ^2
Kg Sacos P.S.I.
1 |1 900 18.00 0.72 405 230-280 3300-4000
1 |2 600 12.00 0.96 300 190-240 2700-3450
1 |2.5 515 10.25 1.03 280 160-210 2300-3000
1 |3 450 9.00 1.08 260 140-190 2000-2700
1 |3.5 400 8.00 1.12 250 125-175 1800-2500
1 |4 360 7.20 1.15 240 110-160 1600-2300
1 |5 300 6.00 1.20 225 100-150 1500-2200
1 |6 260 5.25 1.23 210 85-135 1200-1900
1 |7 225 4.50 1.26 195 75-125 1100-1600
1 |8 200 4.00 1.28 185 65-115 900-1600
1 |9 180 3.75 1.30 175 55-100 800-1500
1 |10 165 3.25 1.31 165 45-95 650-1350

Determine la proporcion del mortero para pega a utilizar y utilice los valores de cemento en Kg y agregado fino en m^3 de la tabla anterior si no conoce los de la zona o región

Cemento Agr. Fino


Proporcion
Kg m^3
1 |8 200 1.25

Cantidad de cemento y agre. fino, muro en Tizón por m^2 Cantidad de cemento y agre. fino, muro en Soga por m^2 Cantidad de cemento y agre. fino, muro en Papelillo por m^2

Cemento Kg 11.6 Cemento Kg 5.7 Cemento Kg 2.4


Agre. Fino m^3 0.073 Agre. Fino m^3 0.035 Agre. Fino m^3 0.015

Defina el porcentaje de desperdicio


% de desperdicio 5

Cantidad de cemento y agre. fino, muro en Tizón por m^2 Cantidad de cemento y agre. fino, muro en Soga por m^2 Cantidad de cemento y agre. fino, muro en Papelillo por m^2

Cemento Kg 12.2 Cemento Kg 5.9 Cemento Kg 2.5


Agre. Fino m^3 0.076 Agre. Fino m^3 0.037 Agre. Fino m^3 0.016

Cantidad de mortero para repello m^3 / m^2 muro

Determino la proporcion a utilizar 1 : A

A 𝐶_𝐵= 36⁄((1+𝐴) ) 𝐶_(𝐵 (𝑠𝑎𝑐𝑜𝑠)) 〖𝐴𝑔𝑟𝑒 . 〗 _𝐹𝑖𝑛𝑜


〖𝐴𝑔𝑟𝑒 . 〗 _(𝐹𝑖𝑛𝑜 ) ((𝑚^3 𝑑𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙)⁄(𝑚^3 𝑑𝑒 𝑚𝑜𝑟𝑡𝑒𝑟𝑜))
4 〖𝐴𝑔𝑟𝑒 . 〗 _𝐹𝑖𝑛𝑜=0.04∗𝐶_𝐵∗𝐴
7.2 1.15

Determino el espesor del repello

e (cm) Agr. Fino m^3 Cemento Kg/m^3 7.2


2 1.15 Agre. Fino m^3 0.023
valor tomado de
la tabla 1 según
la proporcinon

Defina el porcentaje de desperdicio


% de desperdicio 10

Cantidad de mortero de prepello, muro en Tizón Cantidad de mortero de prepello, muro en Soga Cantidad de mortero de prepello, muro en Papelillo
Cemento Kg/m^3 7.9 Cemento Kg/m^3 7.9 Cemento Kg/m^3 7.9
Agre. Fino m^3 0.025 Agre. Fino m^3 0.025 Agre. Fino m^3 0.025

RESUMEN CANTIDADES POR m^2 DE MURO

Muro en Tizón Muro en Soga Muro en Papelillo


Cantidad de ladrillos por m^2 80 Cantidad de ladrillos por m^2 48 Cantidad de ladrillos por m^2 30
Cantidad de mortero de pega m^3 / m^2 muro 0.061 Cantidad de mortero de pega m^3 / m^2 muro 0.030 Cantidad de mortero de pega m^3 / m^2 muro 0.012
Cemento Kg 12.2 Cemento Kg 5.9 Cemento Kg 2.5
Agre. Fino m^3 0.076 Agre. Fino m^3 0.037 Agre. Fino m^3 0.016
Cantidad de mortero de prepello, muro en Tizón Cantidad de mortero de prepello, muro en Tizón Cantidad de mortero de prepello, muro en Tizón
Cemento Kg/m^3 7.9 Cemento Kg/m^3 7.9 Cemento Kg/m^3 7.9
Agre. Fino m^3 0.025 Agre. Fino m^3 0.025 Agre. Fino m^3 0.025

Si conoce las dimensiones totales del muro

Largo L(m) Altto H(m) Area A(m^2)


10 15 150

Muro en Tizón Muro en Soga Muro en Papelillo


Cantidad de Ladrillos, muro en Tizón 12069 Cantidad de Ladrillos, muro en Soga 7143 Cantidad de Ladrillos, muro en Papelillo 4433
Cantidad de mortero de pega, muro en Tizón Cantidad de mortero de pega, muro en Soga Cantidad de mortero de pega, muro en Papelillo
Cemento Kg 1832 37 bultos Cemento Kg 891 18 bultos Cemento Kg 374 7 bultos
Agre. Fino m^3 11 Agre. Fino m^3 6 Agre. Fino m^3 2

Si conoce las dimensiones totales del muro a repellar

Largo L(m) Altto H(m) Area A(m^2)


10 15 150

Muro en Tizón Muro en Soga Muro en Papelillo


Cantidad de mortero de prepello, muro en Tizón Cantidad de mortero de prepello, muro en Soga Cantidad de mortero de prepello, muro en Papelillo
Cemento Kg/m^3 1188 24 bultos Cemento Kg/m^3 1188 23.76 bultos Cemento Kg/m^3 1188 23.76 bultos
Agre. Fino m^3 4 Agre. Fino m^3 4 Agre. Fino m^3 4