Está en la página 1de 10

ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL

OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
KM. 134+778 - KM. 181+000
SUPERVISOR : CONSORCIO SUPERVISOR OYON
CONTRATISTA : CONSORCIO VIAL AMBO

RESUMEN GENERAL DE METRADOS


CONTRATO PRINCIPAL
VALORIZACION Nº 024 - DICIEMBRE 2020

Item Descripción Unidad Metrado

100.0 TRABAJOS PRELIMINARES


101.A MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb -
102.A TOPOGRAFIA Y GEOREFERENCIACION km 1.68
103.A MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL glb 0.00606
107.A ACCESOS A CANTERAS, DME, PLANTAS Y FUENTES DE AGUA km -
200.0 MOVIMIENTO DE TIERRAS -
201.A DESBROCE Y LIMPIEZA EN ZONA NO BOSCOSAS ha -
205.A EXCAVACION EN EXPLANACIONES EN MATERIAL COMUN m3 1,330.58
205.B EXCAVACION EN EXPLANACIONES EN ROCA SUELTA m3 608.72
205.C EXCAVACION EN EXPLANACIONES EN ROCA FIJA m3 4,170.94
206.A REMOCION DE DERRUMBES m3 -
207.A PERFILADO Y COMPACTADO EN ZONAS DE CORTE m2 1,176.90
210.A CONFORMACION DE TERRAPLENES m3 969.86
210.B RELLENO EN LATERAL EN BERMAS m3 -
220.B MEJORAMIENTO DE SUBRASANTE CON MATERIAL DE CANTERA m3 1,922.97
220.C MEJORAMIENTO DE SUBRASANTE CON MATERIAL DE CANTERA, SOLUCION ESPE m3 -
230.A MATERIAL DE PRESTAMO PARA RELLENOS m3 2,892.83
300 SUB BASES Y BASE -
303.A SUB-BASE GRANULAR m3 683.66
303.B BASE DE CONCRETO HIDRAULICO F'C 85 KG/CM2 m3 -
500 PAVIMENTO DE CONCRETO HIDRAULICO -
501.A PAVIMIENTO DE CONCRETO HIDRAULICO S'c: 45 kg/cm2 (PAVIMENTADORA) m3 1,230.64
501.B PAVIMIENTO DE CONCRETO HIDRAULICO S'c: 45 kg/cm2 (MANUAL) m3 39.26
502.A ACERO LONGITUDINAL (BARRA DE AMARRE) kg 1,631.08
502.B ACERO TRANSVERSAL (PASA JUNTA) kg 18,086.63
502.C CANASTILLAS kg 142.67
503.A JUNTAS DE CONSTRUCCION DE CONCRETO HIDRAULICO m -
503.B JUNTAS DE CONTRACCION DE CONCRETO HIDRAULICO m 2.52
503.C JUNTAS DE EXPANSION m -
504.A SONIZADORES und 419.75
612.C ENCOFRADO Y DESENCOFRADO PARA PAVIMENTOS m2 -
600.0 OBRAS DE ARTE Y DRENAJE -
202.E DEMOLICION DE ESTRUCTURAS EXISTENTES m3 -
220.C PEDRAPLENES PARA MEJORAMIENTO m3 -
601.A EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 691.50
603.A ELIMINACION DE ALCANTARILLAS EXISTENTES m -
605.A RELLENO PARA ESTRUCTURAS m3 336.07
605.A1 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 -
605.B MATERIAL FILTRANTE m3 57.89
605.C MATERIAL IMPERMEABLE m3 11.20
610.C CONCRETO CLASE C (Fc= 280 kg/cm2) m3 8.72
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
KM. 134+778 - KM. 181+000
SUPERVISOR : CONSORCIO SUPERVISOR OYON
CONTRATISTA : CONSORCIO VIAL AMBO

RESUMEN GENERAL DE METRADOS


CONTRATO PRINCIPAL
VALORIZACION Nº 024 - DICIEMBRE 2020

Item Descripción Unidad Metrado

610.D CONCRETO CLASE D (Fc= 210 kg/cm2) m3 171.26


610.E CONCRETO CLASE E (Fc= 175 kg/cm2) m3 0.09
610.E1 CONCRETO CICLOPEO (Fc= 175 kg/cm2 + 30%P.M.) m3 117.92
610.H CONCRETO CLASE H (Fc= 100 kg/cm2) m3 14.68
612.A ENCOFRADO Y DESENCOFRADO PARA OBRAS DE ARTE m2 1,739.52
615.A ACERO DE REFUERZO Fy= 4200 kg/cm2 kg 12,003.92
622.B TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE Ø= 0.90 m m 8.10
622.C TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE Ø= 1.20 m m -
622.D TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE Ø= 1.50 m m -
622.E TUBERIA CORRUGADA DE ACERO GALVANIZADO MULTIPLE ABOVEDADA (4.04x2.8 m -
625.A SUBDREN TIPO 1 m 60.14
625.B DESCARGA DE SUBDREN TIPO 1 m 13.00
626.A TRINCHERA DRENANTE m -
626.B DESCARGA DE TRINCHERA DRENANTE m -
635.A CUNETA REVESTIDA TIPO I (TRIANGULAR) m -
635.B CUNETA REVESTIDA TIPO II (RECTANGULAR URBANA) m -
635.C CUNETA DE CORONACION REVESTIDA (ZANJA) m -
635.D CUNETA DE BANQUETA REVESTIDA m -
635.E CUNETA REVESTIDA TIPO BATEA m -
637.A BORDILLOS m -
640.A EMBOQUILLADO DE PIEDRA e=0.15m m2 -
640.B EMBOQUILLADO DE PIEDRA e=0.20m m2 -
640.C EMBOQUILLADO DE PIEDRA e=0.35m m2 -
649.A TUBO DE PVC-SAP CLASE 10, D= 1" m -
649.B TUBO DE PVC-SAP CLASE 10, D= 2" m 47.71
649.E TUBERIA REGIDA PERFORADA (6") m 234.83
649.E1 TUBERIA REGIDA NO PERFORADA (6") m 243.80
649.F TUBO DE PVC-SAP CLASE 10, D= 4" c/perforacion m -
649.F1 TUBO DE PVC-SAP CLASE 10, D= 4" s/perforacion m 6.80
650.H GEOTEXTIL NO TEJIDO CLASE 2 m2 237.68
650.I GEOCOMPUESTO DE DRENAJE m2 25.90
650.N GEOMALLA UNIAXIAL 120 kN/M m2 5,184.00
655.A JUNTA DE CONSTRUCCION m -
655.C JUNTA TIPO 1 PARA MUROS m2 42.80
655.D JUNTA TIPO 2 PARA MUROS m2 -
655.G JUNTA CON EL PAVIMENTO RIGIDO m 95.00
655.I JUNTA DE CONSTRUCCION WATER STOP m 226.50
658.A ZANJA DE DRENAJE REVESTIDA m -
658.B ZANJA DE DRENAJE SIN REVESTIR m -
665.A GAVION TIPO CAJA DE 2.7mm 5.0x1.0x0.5m m3 -
665.B GAVION TIPO CAJA DE 2.7mm 5.0x1.0x1.0m m3 -
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
KM. 134+778 - KM. 181+000
SUPERVISOR : CONSORCIO SUPERVISOR OYON
CONTRATISTA : CONSORCIO VIAL AMBO

RESUMEN GENERAL DE METRADOS


CONTRATO PRINCIPAL
VALORIZACION Nº 024 - DICIEMBRE 2020

Item Descripción Unidad Metrado

665.C GAVION TIPO CAJA DE 2.7mm 5.0x1.5x1.0m m3 -


665.E GAVION TIPO CAJA DE 2.7mm 5.0x1.5x0.5m m3 -
665.H GAVION TIPO CAJA DE 2.7mm 1.0x1.0x4.0 m m3 -
665.I GAVION TIPO CAJA DE 2.7mm 0.5x1.0x4.0 m m3 486.00
670.A ENCUAZAMIENTO RIOS Y QUEBARADAS m3 -
670.B CONSTRUCCION DE DIQUES PROVISIONALES m3 -
695.A COMPUERTA DE RIEGO (TIPO TARJETA) kg -
700.0 TRANSPORTE -
700.A TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D<= 1 km m3k 6,465.70
700.B TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D> 1 km m3k 17,604.74
700.C TRANSPORTE DE CONCRETO HIDRAULICO (CON VOLQUETE) D<= 1 km m3k 1,450.35
700.D TRANSPORTE DE CONCRETO HIDRAULICO (CON VOLQUETE) D> 1 km m3k 7,651.29
700.E TRANSPORTE DE CONCRETO HIDRAULICO (CON MIXER) D<= 1 km m3k 358.86
700.F TRANSPORTE DE CONCRETO HIDRAULICO (CON MIXER) D> 1 km m3k 6,692.81
700.G TRANSPORTE DE ELIMINACION DE MATERIAL A DME PARA D<= 1 km m3k 2,197.07
700.H TRANSPORTE DE ELIMINACION DE MATERIAL A DME PARA D> 1 km m3k 34,077.92
800.0 SEÑALIZACION Y SEGURIDAD VIAL -
801.E SEÑALES PREVENTIVAS (0.75X0.75) und -
801.E2 RETIRO DE SEÑALES TEMPORALES und -
801.F SEÑALES PREVENTIVA REGULAR P-61 (0.60m x 0.40m) und -
802.J SEÑAL REGLAMENTARIA OCTOGONAL R-1 (0.60m x 0.60m) und -
802.I SEÑAL REGLAMENTARIA RECTANGULAR (0.80m x 1.20m) und -
803.C SEÑALES INFORMATIVAS m2 -
804.A POSTES DE SOPORTES DE SEÑALES und -
804.B ESTRUCTURA DE SOPORTE DE SEÑALES E-1 und -
804.C ESTRUCTURA DE SOPORTE DE SEÑALES E-2 und -
805 POSTE DELINEADOR und -
810 MARCAS EN EL PAVIMENTO m2 -
815 TACHA BIDIRECCIONALES RETROREFLECTANTES und -
820.A BARRERAS DE SEGURIDAD BORDE LATERAL m2 -
820.B TRANSICION Y CONEXION DE BARRERA METALICA A BARRERA DE CONCRETO und -
821.A BARRERA DE SEGURIDAD DE CONCRETO m -
825.A CAPTAFAROS und -
830.A POSTE DE KILOMETRAJE und -
840.A PINTADO DE PARAPETOS DE MUROS Y ALCANTARILLAS m2 -
850.A GIBAS O RESALTO LOMO DE TORO m -
900.0 PROGRAMA AMBIENTAL -
907 PROGRAMA DE CIERRE DE OBRA -
901.A1 RETIRO Y ALMACENAMIENTO DE TOP SOIL m2 -
901.A2 REPOSICION DE TOP SOIL m2 -
907.A READECUAION AMBIENTAL DE CANTERAS DE CERRO m2 -
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
KM. 134+778 - KM. 181+000
SUPERVISOR : CONSORCIO SUPERVISOR OYON
CONTRATISTA : CONSORCIO VIAL AMBO

RESUMEN GENERAL DE METRADOS


CONTRATO PRINCIPAL
VALORIZACION Nº 024 - DICIEMBRE 2020

Item Descripción Unidad Metrado

907.B READECUAION AMBIENTAL DE CANTERAS DE RIO m2 -


907.C ACONDICIONAMIENTO DE DESECHOS Y MATERIAL EXCEDENTE m3 7,741.39
907.D READECUACION AMBIENTAL DEL POLVORIN m2 -
907.E READECUACION AMBIENTAL DE PLANTAS DE CHANCADO m2 -
907.F READECUACION AMBIENTAL DE PLANTAS DE CONCRETO m2 -
907.G READECUACION AMBIENTAL DE PATIO DE MAQUINAS m2 -
907.H REVEGETACION DE (INSTALACIONES AUXILIARES) m2 -
908 PROGRAMA DE MONITOREO AMBIENTAL -
908.A MONITOREO DE CALIDAD DE AIRE Cpña -
908.B MONITOREO DE CALIDAD DE AGUA Cpña -
908.C MONITOREO DE EFLUENTES Cpña -
908.D MONITOREO DE CALIDAD DE RUIDO Cpña -
908.E MONITOREO DE FLORA Y FAUNA Cpña -
908.F MONITOREO HIDROBIOLOGICO Cpña -
909 SUBPROGRAMA DE SEÑALIZACION Y SEGURIDAD VIAL -
909.A1 SEÑALES INFORMATIVAS AMBIENTAL PERMANENTE m2 -
804.B ESTRUCTURA DE SOPORTE DE SEÑALES E-1 und -
910 PAGO POR EXTRACCION DE MATERIAL DE CANTERAS DE RIO -
910.A PAGO POR DERECHO DE EXTRACCION DE MATERIALES DE CANTERAS DE RIO m3 -
2000 PEAJES -
2002 PEAJES glb -
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
VALOR REFERENCIA : S/. 356'519,801.08 inc. IGV
MONTO CONTRATO : S/. 356'480,311.71 inc. IGV

PLANILLA DE VALORIZACIÓN Nº 24
December 2020

ACUMULADO ANTERIOR VALORIZACIÓN ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR


Ítem Descripción Und. Metrado Precio Parcial
S/. S/. Metrado S/. % Metrado S/. % Metrado S/. % Metrado S/. %

100.0 TRABAJOS PRELIMINARES 7,145,737.91 3,296,162.69 46.13% 26,778.49 0.37% 3,322,941.18 46.50% 3,822,796.74 53.50%
101.A MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 1,117,962.00 1,117,962.00 0.40 452,451.20 40.47% - 0.00% 0.40 452,451.20 40.47% 0.59529 665,510.80 59.53%
102.A TOPOGRAFIA Y GEOREFERENCIACION km 48.94 5,873.47 287,447.62 46.29 271,859.43 94.58% 1.68 9,867.43 3.43% 47.97 281,726.86 98.01% 0.97 5,720.76 1.99%
103.A MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL glb 1.00 2,790,603.50 2,790,603.50 0.29751 830,231.94 29.75% 0.006060 16,911.06 0.61% 0.30357 847,143.00 30.36% 0.69643 1,943,460.50 69.64%
107.A ACCESOS A CANTERAS, DME, PLANTAS Y FUENTES DE AGUA km 9.20 320,622.26 2,949,724.79 5.43 1,741,620.12 59.04% - 0.00% 5.43 1,741,620.12 59.04% 3.77 1,208,104.68 40.96%
200.0 MOVIMIENTO DE TIERRAS 46,676,652.25 27,692,263.23 59.33% 364,808.18 0.78% 28,057,071.41 60.11% 18,619,580.84 39.89%
201.A DESBROCE Y LIMPIEZA EN ZONA NO BOSCOSAS ha 14.06 4,541.90 63,859.11 14.06 63,859.11 100.00% - 0.00% 14.06 63,859.11 100.00% 0.00 - 0.00%
205.A EXCAVACION EN EXPLANACIONES EN MATERIAL COMUN m3 650,749.71 6.34 4,125,753.16 597,844.83 3,790,336.23 91.87% 1,330.58 8,435.88 0.20% 599,175.41 3,798,772.11 92.07% 51,574.30 326,981.06 7.93%
205.B EXCAVACION EN EXPLANACIONES EN ROCA SUELTA m3 274,968.41 15.59 4,286,757.51 188,272.09 2,935,161.88 68.47% 608.72 9,489.94 0.22% 188,880.81 2,944,651.82 68.69% 86,087.60 1,342,105.68 31.31%
205.C EXCAVACION EN EXPLANACIONES EN ROCA FIJA m3 761,115.79 27.62 21,022,018.12 522,100.37 14,420,412.30 68.60% 4,170.94 115,201.36 0.55% 526,271.31 14,535,613.66 69.14% 234,844.48 6,486,404.45 30.86%
206.A REMOCION DE DERRUMBES m3 64,544.39 3.01 194,278.61 43,992.78 132,418.27 68.16% 0.00 - 0.00% 43,992.78 132,418.27 68.16% 20,551.61 61,860.35 31.84%
207.A PERFILADO Y COMPACTADO EN ZONAS DE CORTE m2 453,673.04 1.85 839,295.12 47,740.20 88,319.37 10.52% 1,176.90 2,177.27 0.26% 48,917.10 90,496.64 10.78% 404,755.94 748,798.49 89.22%
210.A CONFORMACION DE TERRAPLENES m3 142,401.88 8.92 1,270,224.77 52,119.07 464,902.10 36.60% 969.86 8,651.15 0.68% 53,088.93 473,553.25 37.28% 89,312.95 796,671.51 62.72%
210.B RELLENO EN LATERAL EN BERMAS m3 16,092.43 45.86 737,998.84 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 16,092.43 737,998.84 100.00%
220.B MEJORAMIENTO DE SUBRASANTE CON MATERIAL DE CANTERA m3 75,858.02 45.86 3,478,848.80 37,142.10 1,703,336.71 48.96% 1,922.97 88,187.40 2.53% 39,065.07 1,791,524.11 51.50% 36,792.95 1,687,324.69 48.50%
220.C MEJORAMIENTO DE SUBRASANTE CON MATERIAL DE CANTERA, SOLUCION ESPECIAL m3 12,670.43 51.16 648,219.20 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 12,670.43 648,219.20 100.00%
230.A MATERIAL DE PRESTAMO PARA RELLENOS m3 218,259.90 45.86 10,009,399.01 89,261.17 4,093,517.26 40.90% 2,892.83 132,665.18 1.33% 92,154.00 4,226,182.44 42.22% 126,105.90 5,783,216.57 57.78%
300 SUB BASES Y BASE 13,639,938.46 572,654.25 4.20% 40,479.51 0.30% 613,133.76 4.50% 13,026,804.70 95.50%
303.A SUB-BASE GRANULAR m3 49,150.99 59.21 2,910,230.12 9,671.58 572,654.25 19.68% 683.66 40,479.51 1.39% 10,355.24 613,133.76 21.07% 38,795.75 2,297,096.36 78.93%
303.B BASE DE CONCRETO HIDRAULICO F'C 85 KG/CM2 m3 36,193.99 296.45 10,729,708.34 0.00 - 0.00% - 0.00% 0.00 - 0.00% 36,193.99 10,729,708.34 100.00%
500 PAVIMENTO DE CONCRETO HIDRAULICO 81,255,913.91 4,811,518.96 5.92% 923,731.97 1.14% 5,735,250.93 7.06% 75,520,662.97 92.94%
501.A PAVIMIENTO DE CONCRETO HIDRAULICO S'c: 45 kg/cm2 (PAVIMENTADORA) m3 106,767.37 515.70 55,059,932.71 6,501.99 3,353,076.24 6.09% 1,230.64 634,641.05 1.15% 7,732.63 3,987,717.29 7.24% 99,034.74 51,072,215.42 92.76%
501.B PAVIMIENTO DE CONCRETO HIDRAULICO S'c: 45 kg/cm2 (MANUAL) m3 8,552.73 595.09 5,089,644.10 290.23 172,712.97 3.39% 39.26 23,363.23 0.46% 329.49 196,076.20 3.85% 8,223.24 4,893,567.89 96.15%
502.A ACERO LONGITUDINAL (BARRA DE AMARRE) kg 136,972.20 13.54 1,854,603.59 10,106.10 136,836.59 7.38% 1,631.08 22,084.82 1.19% 11,737.18 158,921.41 8.57% 125,235.02 1,695,682.17 91.43%
502.B ACERO TRANSVERSAL (PASA JUNTA) kg 1,262,314.15 13.37 16,877,140.19 83,603.24 1,117,775.32 6.62% 18,086.63 241,818.24 1.43% 101,689.87 1,359,593.56 8.06% 1,160,624.28 15,517,546.62 91.94%
502.C CANASTILLAS kg 223,040.13 7.10 1,583,584.92 821.17 5,830.31 0.37% 142.67 1,012.96 0.06% 963.84 6,843.27 0.43% 222,076.29 1,576,741.66 99.57%
503.A JUNTAS DE CONSTRUCCION DE CONCRETO HIDRAULICO m 49,668.85 2.28 113,244.98 1,777.36 4,052.38 3.58% 0.00 - 0.00% 1,777.36 4,052.38 3.58% 47,891.49 109,192.60 96.42%
503.B JUNTAS DE CONTRACCION DE CONCRETO HIDRAULICO m 247,953.26 2.28 565,333.43 2,837.57 6,469.66 1.14% 2.52 5.75 0.00% 2,840.09 6,475.41 1.15% 245,113.17 558,858.03 98.85%
503.C JUNTAS DE EXPANSION m 103.62 2.28 236.25 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 103.62 236.25 100.00%
504.A SONIZADORES und 32,059.00 1.92 61,553.28 2,158.30 4,143.94 6.73% 419.75 805.92 1.31% 2,578.05 4,949.86 8.04% 29,480.95 56,603.42 91.96%
612.C ENCOFRADO Y DESENCOFRADO PARA PAVIMENTOS m2 1,191.26 42.51 50,640.46 249.86 10,621.55 20.97% 0.00 - 0.00% 249.86 10,621.55 20.97% 941.40 40,018.91 79.03%
600.0 OBRAS DE ARTE Y DRENAJE 41,251,340.40 0.00 9,411,248.01 22.81% 664,822.43 1.61% 0.00 10,076,070.44 24.43% 0.00 31,175,269.97 75.57%
202.E DEMOLICION DE ESTRUCTURAS EXISTENTES m3 1,975.41 120.90 238,827.07 302.53 36,575.88 15.31% 0.00 - 0.00% 302.53 36,575.88 15.31% 1,672.88 202,251.19 84.69%
220.C PEDRAPLENES PARA MEJORAMIENTO m3 635.79 75.63 48,084.80 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 635.79 48,084.80 100.00%
601.A EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 103,539.21 8.60 890,437.21 31,696.86 272,593.00 30.61% 691.50 5,946.90 0.67% 32,388.36 278,539.90 31.28% 71,150.85 611,897.31 68.72%
603.A ELIMINACION DE ALCANTARILLAS EXISTENTES m 370.70 25.27 9,367.59 256.55 6,483.02 69.21% 0.00 - 0.00% 256.55 6,483.02 69.21% 114.15 2,884.57 30.79%
605.A RELLENO PARA ESTRUCTURAS m3 33,747.38 67.07 2,263,436.78 8,846.25 593,317.99 26.21% 336.07 22,540.21 1.00% 9,182.32 615,858.20 27.21% 24,565.06 1,647,578.57 72.79%
605.A1 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 1,836.00 26.02 47,772.72 926.00 24,094.52 50.44% 0.00 - 0.00% 926.00 24,094.52 50.44% 910.00 23,678.20 49.56%
605.B MATERIAL FILTRANTE m3 2,687.80 116.38 312,806.16 330.30 38,440.31 12.29% 57.89 6,737.24 2.15% 388.19 45,177.55 14.44% 2,299.61 267,628.61 85.56%
605.C MATERIAL IMPERMEABLE m3 447.60 92.87 41,568.61 57.40 5,330.74 12.82% 11.20 1,040.14 2.50% 68.60 6,370.88 15.33% 379.00 35,197.73 84.67%
610.C CONCRETO CLASE C (Fc= 280 kg/cm2) m3 1,160.46 623.17 723,163.86 672.65 419,175.30 57.96% 8.72 5,434.04 0.75% 681.37 424,609.34 58.72% 479.09 298,554.52 41.28%
610.D CONCRETO CLASE D (Fc= 210 kg/cm2) m3 7,854.55 592.62 4,654,763.42 1,951.34 1,156,403.11 24.84% 171.26 101,492.10 2.18% 2,122.60 1,257,895.21 27.02% 5,731.95 3,396,868.21 72.98%
610.E CONCRETO CLASE E (Fc= 175 kg/cm2) m3 1,365.47 546.75 746,570.72 665.66 363,949.61 48.75% 0.09 49.21 0.01% 665.75 363,998.82 48.76% 699.72 382,571.91 51.24%
610.E1 CONCRETO CICLOPEO (Fc= 175 kg/cm2 + 30%P.M.) m3 7,864.35 440.46 3,463,931.60 1,679.20 739,620.44 21.35% 117.92 51,939.04 1.50% 1,797.12 791,559.48 22.85% 6,067.23 2,672,372.13 77.15%
610.H CONCRETO CLASE H (Fc= 100 kg/cm2) m3 722.93 470.36 340,037.35 299.21 140,736.42 41.39% 14.68 6,904.88 2.03% 313.89 147,641.30 43.42% 409.04 192,396.05 56.58%
612.A ENCOFRADO Y DESENCOFRADO PARA OBRAS DE ARTE m2 58,304.47 68.27 3,980,446.17 22,024.60 1,503,619.45 37.78% 1,739.52 118,757.03 2.98% 23,764.12 1,622,376.48 40.76% 34,540.35 2,358,069.69 59.24%
615.A ACERO DE REFUERZO Fy= 4200 kg/cm2 kg 506,913.62 7.65 3,877,889.19 166,045.59 1,270,248.76 32.76% 12,003.92 91,829.99 2.37% 178,049.51 1,362,078.75 35.12% 328,864.11 2,515,810.44 64.88%
622.B TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE Ø= 0.90 m m 1,035.18 368.88 381,857.20 757.81 279,540.95 73.21% 8.10 2,987.93 0.78% 765.91 282,528.88 73.99% 269.27 99,328.32 26.01%
622.C TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE Ø= 1.20 m m 486.81 520.01 253,146.07 416.34 216,500.96 85.52% 0.00 - 0.00% 416.34 216,500.96 85.52% 70.47 36,645.10 14.48%
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
VALOR REFERENCIA : S/. 356'519,801.08 inc. IGV
MONTO CONTRATO : S/. 356'480,311.71 inc. IGV

PLANILLA DE VALORIZACIÓN Nº 24
December 2020

ACUMULADO ANTERIOR VALORIZACIÓN ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR


Ítem Descripción Und. Metrado Precio Parcial
S/. S/. Metrado S/. % Metrado S/. % Metrado S/. % Metrado S/. %

622.D TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE Ø= 1.50 m m 24.30 699.16 16,989.59 24.30 16,989.59 100.00% 0.00 - 0.00% 24.30 16,989.59 100.00% 0.00 - 0.00%
622.E TUBERIA CORRUGADA DE ACERO GALVANIZADO MULTIPLE ABOVEDADA (4.04x2.84m) m 21.06 3,891.21 81,948.88 20.73 80,664.78 98.43% 0.00 - 0.00% 20.73 80,664.78 98.43% 0.33 1,284.10 1.57%
625.A SUBDREN TIPO 1 m 11,172.00 197.99 2,211,944.28 3,637.30 720,149.03 32.56% 60.14 11,907.12 0.54% 3,697.44 732,056.15 33.10% 7,474.56 1,479,888.13 66.90%
625.B DESCARGA DE SUBDREN TIPO 1 m 2,250.00 156.25 351,562.50 522.03 81,567.19 23.20% 13.00 2,031.25 0.58% 535.03 83,598.44 23.78% 1,714.97 267,964.06 76.22%
626.A TRINCHERA DRENANTE m 913.00 102.70 93,765.10 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 913.00 93,765.10 100.00%
626.B DESCARGA DE TRINCHERA DRENANTE m 150.00 89.96 13,494.00 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 150.00 13,494.00 100.00%
635.A CUNETA REVESTIDA TIPO I (TRIANGULAR) m 46,979.53 105.68 4,964,796.73 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 46,979.53 4,964,796.73 100.00%
635.B CUNETA REVESTIDA TIPO II (RECTANGULAR URBANA) m 145.00 456.14 66,140.30 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 145.00 66,140.30 100.00%
635.C CUNETA DE CORONACION REVESTIDA (ZANJA) m 1,918.00 67.41 129,292.38 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 1,918.00 129,292.38 100.00%
635.D CUNETA DE BANQUETA REVESTIDA m 16,130.98 74.69 1,204,822.90 85.00 6,348.65 0.53% 0.00 - 0.00% 85.00 6,348.65 0.53% 16,045.98 1,198,474.25 99.47%
635.E CUNETA REVESTIDA TIPO BATEA m 58.00 273.86 15,883.88 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 58.00 15,883.88 100.00%
637.A BORDILLOS m 4,940.00 93.99 464,310.60 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 4,940.00 464,310.60 100.00%
640.A EMBOQUILLADO DE PIEDRA e=0.15m m2 13,082.37 68.58 897,188.93 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 13,082.37 897,188.93 100.00%
640.B EMBOQUILLADO DE PIEDRA e=0.20m m2 8,681.97 102.34 888,512.81 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 8,681.97 888,512.81 100.00%
640.C EMBOQUILLADO DE PIEDRA e=0.35m m2 46.79 140.32 6,565.57 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 46.79 6,565.57 100.00%
649.A TUBO DE PVC-SAP CLASE 10, D= 1" m 36.75 13.55 497.96 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 36.75 497.96 100.00%
649.B TUBO DE PVC-SAP CLASE 10, D= 2" m 2,080.55 19.22 39,988.17 369.92 7,109.85 17.78% 47.71 916.99 2.29% 417.63 8,026.84 20.07% 1,662.92 31,961.32 79.93%
649.E TUBERIA REGIDA PERFORADA (6") m 1,058.85 40.75 43,148.14 340.25 13,865.19 32.13% 234.83 9,569.32 22.18% 575.08 23,434.51 54.31% 483.77 19,713.63 45.69%
649.E1 TUBERIA REGIDA NO PERFORADA (6") m 1,731.60 36.19 62,666.60 410.70 14,863.23 23.72% 243.80 8,823.12 14.08% 654.50 23,686.35 37.80% 1,077.10 38,980.25 62.20%
649.F TUBO DE PVC-SAP CLASE 10, D= 4" c/perforacion m 3,227.70 34.63 111,775.25 490.00 16,968.70 15.18% 0.00 - 0.00% 490.00 16,968.70 15.18% 2,737.70 94,806.55 84.82%
649.F1 TUBO DE PVC-SAP CLASE 10, D= 4" s/perforacion m 591.94 34.63 20,498.88 85.64 2,965.71 14.47% 6.80 235.48 1.15% 92.44 3,201.19 15.62% 499.50 17,297.69 84.38%
650.H GEOTEXTIL NO TEJIDO CLASE 2 m2 37,527.79 13.45 504,748.78 10,772.14 144,885.29 28.70% 237.68 3,196.80 0.63% 11,009.82 148,082.09 29.34% 26,517.97 356,666.70 70.66%
650.I GEOCOMPUESTO DE DRENAJE m2 12,120.00 31.11 377,053.20 2,334.60 72,629.40 19.26% 25.90 805.75 0.21% 2,360.50 73,435.15 19.48% 9,759.50 303,618.05 80.52%
650.N GEOMALLA UNIAXIAL 120 kN/M m2 116,805.00 11.64 1,359,610.20 33,482.00 389,730.48 28.66% 5,184.00 60,341.76 4.44% 38,666.00 450,072.24 33.10% 78,139.00 909,537.96 66.90%
655.A JUNTA DE CONSTRUCCION m 383.90 35.80 13,743.62 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 383.90 13,743.62 100.00%
655.C JUNTA TIPO 1 PARA MUROS m2 1,804.79 54.20 97,819.62 208.92 11,323.46 11.58% 42.80 2,319.76 2.37% 251.72 13,643.22 13.95% 1,553.07 84,176.39 86.05%
655.D JUNTA TIPO 2 PARA MUROS m2 22.12 63.73 1,409.71 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 22.12 1,409.71 100.00%
655.G JUNTA CON EL PAVIMENTO RIGIDO m 61,197.99 23.30 1,425,913.17 0.00 - 0.00% 95.00 2,213.50 0.16% 95.00 2,213.50 0.16% 61,102.99 1,423,699.67 99.84%
655.I JUNTA DE CONSTRUCCION WATER STOP m 2,583.80 33.18 85,730.48 1,645.75 54,606.00 63.69% 226.50 7,515.27 8.77% 1,872.25 62,121.27 72.46% 711.55 23,609.23 27.54%
658.A ZANJA DE DRENAJE REVESTIDA m 2,310.00 113.84 262,970.40 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 2,310.00 262,970.40 100.00%
658.B ZANJA DE DRENAJE SIN REVESTIR m 1,509.00 37.03 55,878.27 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 1,509.00 55,878.27 100.00%
665.A GAVION TIPO CAJA DE 2.7mm 5.0x1.0x0.5m m3 44.50 276.25 12,293.13 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 44.50 12,293.13 100.00%
665.B GAVION TIPO CAJA DE 2.7mm 5.0x1.0x1.0m m3 806.00 276.07 222,512.42 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 806.00 222,512.42 100.00%
665.C GAVION TIPO CAJA DE 2.7mm 5.0x1.5x1.0m m3 364.50 264.73 96,494.09 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 364.50 96,494.09 100.00%
665.E GAVION TIPO CAJA DE 2.7mm 5.0x1.5x0.5m m3 66.75 308.93 20,621.08 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 66.75 20,621.08 100.00%
665.H GAVION TIPO CAJA DE 2.7mm 1.0x1.0x4.0 m m3 6,912.00 248.60 1,718,323.20 2,171.00 539,710.60 31.41% 0.00 - 0.00% 2,171.00 539,710.60 31.41% 4,741.00 1,178,612.60 68.59%
665.I GAVION TIPO CAJA DE 2.7mm 0.5x1.0x4.0 m m3 2,876.00 286.60 824,261.60 594.00 170,240.40 20.65% 486.00 139,287.60 16.90% 1,080.00 309,528.00 37.55% 1,796.00 514,733.60 62.45%
670.A ENCUAZAMIENTO RIOS Y QUEBARADAS m3 11,476.17 17.89 205,308.68 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 11,476.17 205,308.68 100.00%
670.B CONSTRUCCION DE DIQUES PROVISIONALES m3 31.01 26.84 832.31 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 31.01 832.31 100.00%
695.A COMPUERTA DE RIEGO (TIPO TARJETA) kg 449.58 13.16 5,916.47 0.00 - 0.00% 0.00 - 0.00% 0.00 - 0.00% 449.58 5,916.47 100.00%
700.0 TRANSPORTE 35,718,196.98 22,058,445.17 61.76% 117,763.30 0.33% 22,176,208.47 62.09% 13,541,988.51 37.91%
700.A TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D<= 1 km m3k 576,635.10 3.79 2,185,447.03 111,334.35 421,957.19 19.31% 6,465.70 24,505.00 1.12% 117,800.05 446,462.19 20.43% 458,835.05 1,738,984.84 79.57%
700.B TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D> 1 km m3k 6,099,338.67 0.79 4,818,477.55 1,129,256.55 892,112.67 18.51% 17,604.74 13,907.74 0.29% 1,146,861.29 906,020.41 18.80% 4,952,477.38 3,912,457.13 81.20%
700.C TRANSPORTE DE CONCRETO HIDRAULICO (CON VOLQUETE) D<= 1 km m3k 106,019.60 5.69 603,251.52 7,005.18 39,859.47 6.61% 1,450.35 8,252.49 1.37% 8,455.53 48,111.96 7.98% 97,564.07 555,139.56 92.02%
700.D TRANSPORTE DE CONCRETO HIDRAULICO (CON VOLQUETE) D> 1 km m3k 1,221,254.29 1.31 1,599,843.12 63,738.64 83,497.62 5.22% 7,651.29 10,023.19 0.63% 71,389.93 93,520.81 5.85% 1,149,864.36 1,506,322.31 94.15%
700.E TRANSPORTE DE CONCRETO HIDRAULICO (CON MIXER) D<= 1 km m3k 62,559.22 4.51 282,142.08 5,580.19 25,166.66 8.92% 358.86 1,618.46 0.57% 5,939.05 26,785.12 9.49% 56,620.17 255,356.97 90.51%
700.F TRANSPORTE DE CONCRETO HIDRAULICO (CON MIXER) D> 1 km m3k 809,951.57 1.04 842,349.63 128,333.82 133,467.17 15.84% 6,692.81 6,960.52 0.83% 135,026.63 140,427.69 16.67% 674,924.94 701,921.94 83.33%
700.G TRANSPORTE DE ELIMINACION DE MATERIAL A DME PARA D<= 1 km m3k 1,618,098.54 4.04 6,537,118.10 1,288,632.23 5,206,074.21 79.64% 2,197.07 8,876.16 0.14% 1,290,829.30 5,214,950.37 79.77% 327,269.24 1,322,167.72 20.23%
700.H TRANSPORTE DE ELIMINACION DE MATERIAL A DME PARA D> 1 km m3k 14,726,224.96 1.28 18,849,567.95 11,918,992.32 15,256,310.18 80.94% 34,077.92 43,619.74 0.23% ### 15,299,929.92 81.17% 2,773,154.72 3,549,638.04 18.83%
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
VALOR REFERENCIA : S/. 356'519,801.08 inc. IGV
MONTO CONTRATO : S/. 356'480,311.71 inc. IGV

PLANILLA DE VALORIZACIÓN Nº 24
December 2020

ACUMULADO ANTERIOR VALORIZACIÓN ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR


Ítem Descripción Und. Metrado Precio Parcial
S/. S/. Metrado S/. % Metrado S/. % Metrado S/. % Metrado S/. %

800.0 SEÑALIZACION Y SEGURIDAD VIAL 3,285,634.09 - 0.00% - 0.00% - 0.00% 3,285,634.09 100.00%
801.E SEÑALES PREVENTIVAS (0.75X0.75) und 363.00 476.97 173,140.11 0.00 - 0.00% - 0.00% 0.00 - 0.00% 363.00 173,140.11 100.00%
801.E2 RETIRO DE SEÑALES TEMPORALES und 44.00 99.04 4,357.76 0.00 - 0.00% - 0.00% 0.00 - 0.00% 44.00 4,357.76 100.00%
801.F SEÑALES PREVENTIVA REGULAR P-61 (0.60m x 0.40m) und 279.00 344.02 95,981.58 0.00 - 0.00% - 0.00% 0.00 - 0.00% 279.00 95,981.58 100.00%
802.J SEÑAL REGLAMENTARIA OCTOGONAL R-1 (0.60m x 0.60m) und 3.00 354.79 1,064.37 0.00 - 0.00% - 0.00% 0.00 - 0.00% 3.00 1,064.37 100.00%
802.I SEÑAL REGLAMENTARIA RECTANGULAR (0.80m x 1.20m) und 112.00 589.28 65,999.36 0.00 - 0.00% - 0.00% 0.00 - 0.00% 112.00 65,999.36 100.00%
803.C SEÑALES INFORMATIVAS m2 30.78 614.76 18,922.31 0.00 - 0.00% - 0.00% 0.00 - 0.00% 30.78 18,922.31 100.00%
804.A POSTES DE SOPORTES DE SEÑALES und 757.00 256.03 193,814.71 0.00 - 0.00% - 0.00% 0.00 - 0.00% 757.00 193,814.71 100.00%
804.B ESTRUCTURA DE SOPORTE DE SEÑALES E-1 und 13.00 2,057.92 26,752.96 0.00 - 0.00% - 0.00% 0.00 - 0.00% 13.00 26,752.96 100.00%
804.C ESTRUCTURA DE SOPORTE DE SEÑALES E-2 und 6.00 1,085.38 6,512.28 0.00 - 0.00% - 0.00% 0.00 - 0.00% 6.00 6,512.28 100.00%
805 POSTE DELINEADOR und 4,543.00 157.06 713,523.58 0.00 - 0.00% - 0.00% 0.00 - 0.00% 4,543.00 713,523.58 100.00%
810 MARCAS EN EL PAVIMENTO m2 15,300.74 10.61 162,340.85 0.00 - 0.00% - 0.00% 0.00 - 0.00% 15,300.74 162,340.85 100.00%
815 TACHA BIDIRECCIONALES RETROREFLECTANTES und 7,278.00 16.56 120,523.68 0.00 - 0.00% - 0.00% 0.00 - 0.00% 7,278.00 120,523.68 100.00%
820.A BARRERAS DE SEGURIDAD BORDE LATERAL m2 4,284.00 332.79 1,425,672.36 0.00 - 0.00% - 0.00% 0.00 - 0.00% 4,284.00 1,425,672.36 100.00%
820.B TRANSICION Y CONEXION DE BARRERA METALICA A BARRERA DE CONCRETO und 3.00 1,971.51 5,914.53 0.00 - 0.00% - 0.00% 0.00 - 0.00% 3.00 5,914.53 100.00%
821.A BARRERA DE SEGURIDAD DE CONCRETO m 105.00 1,295.84 136,063.20 0.00 - 0.00% - 0.00% 0.00 - 0.00% 105.00 136,063.20 100.00%
825.A CAPTAFAROS und 1,311.00 34.19 44,823.09 0.00 - 0.00% - 0.00% 0.00 - 0.00% 1,311.00 44,823.09 100.00%
830.A POSTE DE KILOMETRAJE und 50.00 172.47 8,623.50 0.00 - 0.00% - 0.00% 0.00 - 0.00% 50.00 8,623.50 100.00%
840.A PINTADO DE PARAPETOS DE MUROS Y ALCANTARILLAS m2 2,384.30 29.35 69,979.21 0.00 - 0.00% - 0.00% 0.00 - 0.00% 2,384.30 69,979.21 100.00%
850.A GIBAS O RESALTO LOMO DE TORO m 26.70 435.38 11,624.65 0.00 - 0.00% - 0.00% 0.00 - 0.00% 26.70 11,624.65 100.00%
900.0 PROGRAMA AMBIENTAL 7,564,647.67 4,217,566.06 55.75% 15,869.85 0.21% 4,233,435.91 55.96% 3,331,211.76 44.04%
907 PROGRAMA DE CIERRE DE OBRA 6,766,548.89 3,520,999.81 52.04% 15,869.85 0.23% 3,536,869.66 52.27% 3,229,679.23 47.73%
901.A1 RETIRO Y ALMACENAMIENTO DE TOP SOIL m2 424,410.34 2.27 963,411.47 164,104.51 372,517.24 38.67% - 0.00% 164,104.51 372,517.24 38.67% 260,305.83 590,894.23 61.33%
901.A2 REPOSICION DE TOP SOIL m2 424,410.34 1.89 802,135.54 0.00 - 0.00% - 0.00% 0.00 - 0.00% 424,410.34 802,135.54 100.00%
907.A READECUAION AMBIENTAL DE CANTERAS DE CERRO m2 213,165.35 1.39 296,299.84 0.00 - 0.00% - 0.00% 0.00 - 0.00% 213,165.35 296,299.84 100.00%
907.B READECUAION AMBIENTAL DE CANTERAS DE RIO m2 134,431.22 1.28 172,071.96 0.00 - 0.00% - 0.00% 0.00 - 0.00% 134,431.22 172,071.96 100.00%
907.C ACONDICIONAMIENTO DE DESECHOS Y MATERIAL EXCEDENTE m3 1,976,961.68 2.05 4,052,771.44 1,535,845.16 3,148,482.57 77.69% 7,741.39 15,869.85 0.39% 1,543,586.55 3,164,352.42 78.08% 433,375.13 888,419.02 21.92%
907.D READECUACION AMBIENTAL DEL POLVORIN m2 3,029.03 1.89 5,724.87 0.00 - 0.00% - 0.00% 0.00 - 0.00% 3,029.03 5,724.87 100.00%
907.E READECUACION AMBIENTAL DE PLANTAS DE CHANCADO m2 12,324.34 1.89 23,293.00 0.00 - 0.00% - 0.00% 0.00 - 0.00% 12,324.34 23,293.00 100.00%
907.F READECUACION AMBIENTAL DE PLANTAS DE CONCRETO m2 10,940.24 1.89 20,677.05 0.00 - 0.00% - 0.00% 0.00 - 0.00% 10,940.24 20,677.05 100.00%
907.G READECUACION AMBIENTAL DE PATIO DE MAQUINAS m2 27,922.91 1.27 35,462.10 0.00 - 0.00% - 0.00% 0.00 - 0.00% 27,922.91 35,462.10 100.00%
907.H REVEGETACION DE (INSTALACIONES AUXILIARES) m2 424,410.34 0.93 394,701.62 0.00 - 0.00% - 0.00% 0.00 - 0.00% 424,410.34 394,701.62 100.00%
908 PROGRAMA DE MONITOREO AMBIENTAL 308,280.24 0.00 260,659.68 84.55% 0.00 0.00% 260,659.68 84.55% 47,620.56 15.45%
908.A MONITOREO DE CALIDAD DE AIRE Cpña 8.00 17,085.64 136,685.12 7.00 119,599.48 87.50% - 0.00% 7.00 119,599.48 87.50% 1.00 17,085.64 12.50%
908.B MONITOREO DE CALIDAD DE AGUA Cpña 8.00 3,701.51 29,612.08 7.00 25,910.57 87.50% - 0.00% 7.00 25,910.57 87.50% 1.00 3,701.51 12.50%
908.C MONITOREO DE EFLUENTES Cpña 8.00 2,146.47 17,171.76 5.00 10,732.35 62.50% - 0.00% 5.00 10,732.35 62.50% 3.00 6,439.41 37.50%
908.D MONITOREO DE CALIDAD DE RUIDO Cpña 8.00 1,223.64 9,789.12 7.00 8,565.48 87.50% - 0.00% 7.00 8,565.48 87.50% 1.00 1,223.64 12.50%
908.E MONITOREO DE FLORA Y FAUNA Cpña 6.00 16,995.00 101,970.00 5.00 84,975.00 83.33% - 0.00% 5.00 84,975.00 83.33% 1.00 16,995.00 16.67%
908.F MONITOREO HIDROBIOLOGICO Cpña 6.00 2,175.36 13,052.16 5.00 10,876.80 83.33% - 0.00% 5.00 10,876.80 83.33% 1.00 2,175.36 16.67%
909 SUBPROGRAMA DE SEÑALIZACION Y SEGURIDAD VIAL 53,911.97 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 53,911.97 100.00%
909.A1 SEÑALES INFORMATIVAS AMBIENTAL PERMANENTE m2 38.88 605.12 23,527.07 0.00 - 0.00% - 0.00% 0.00 - 0.00% 38.88 23,527.07 100.00%
804.B ESTRUCTURA DE SOPORTE DE SEÑALES E-1 und 15.00 2,025.66 30,384.90 0.00 - 0.00% - 0.00% 0.00 - 0.00% 15.00 30,384.90 100.00%
910 PAGO POR EXTRACCION DE MATERIAL DE CANTERAS DE RIO 435,906.57 0.00 435,906.57 100.00% 0.00 0.00% 0.00 435,906.57 100.00% 0.00 0.00 0.00%
910.A PAGO POR DERECHO DE EXTRACCION DE MATERIALES DE CANTERAS DE RIO m3 129,349.13 3.37 435,906.57 129,349.13 435,906.57 100.00% - 0.00% 129,349.13 435,906.57 100.00% 0.00 - 0.00%
2000 PEAJES 2,717,549.41 - 0.00% - 0.00% - 0.00% 2,717,549.41 100.00%
2002 PEAJES glb 1.00 2,717,549.41 2,717,549.41 0.00 - 0.00% - 0.00% 0.00 - 0.00% 1.00 2,717,549.41 100.00%

COSTO DIRECTO S/. 239,255,611.08 72,059,858.37 2,154,253.73 74,214,112.10 165,041,498.99


GASTOS GENERALES FIJOS 0.876% S/. 2,095,385.58 631,095.70 18,866.82 649,962.52 1,445,423.06
OBRA : MEJORAMIENTO DE LA CARRETERA ÓYON - AMBO, TRAMO I: ÓYON - DESVÍO CERRO DE PASCO
ENTIDAD : MINISTERIO DE TRANSPORTES Y COMUNICACIONES - MTC- PROVIAS NACIONAL
VALOR REFERENCIA : S/. 356'519,801.08 inc. IGV
MONTO CONTRATO : S/. 356'480,311.71 inc. IGV

PLANILLA DE VALORIZACIÓN Nº 24
December 2020

ACUMULADO ANTERIOR VALORIZACIÓN ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR


Ítem Descripción Und. Metrado Precio Parcial
S/. S/. Metrado S/. % Metrado S/. % Metrado S/. % Metrado S/. %

GASTOS GENERALES VARIABLES 15.392% S/. 36,825,401.31 11,091,205.72 331,575.33 11,422,781.05 25,402,620.26
UTILIDAD (10.00%) 10.00% S/. 23,925,561.11 7,205,985.84 215,425.37 7,421,411.21 16,504,149.90
SUBTOTAL S/. 302,101,959.08 90,988,145.63 2,720,121.25 93,708,266.88 208,393,692.21
Porcentaje de avance 100.00% 30.12% 0.90% 31.02% 68.98%
OBRA : MEJORAMIENTO DE LA CARRETERA OYON - AMBO, TRAMO I: OYON - DESVÍO CERRO DE PASCO - KM. 134+778 - KM. 181+000
CONTRATO : 073-2018-MTC/20
PROPIETARIO : MTC - PROYECTO ESPECIAL DE INFRAESTRUCTURA DE TRANSPORTE NACIONAL - PROVIAS NACIONAL

CONTRATISTA : CONSORCIO VIAL AMBO


SUPERVISION : CONSORCIO SUPERVISOR OYON

AVANCE DE OBRA CON RELACIÓN AL C.A.O. VIGENTE


VALORIZACIONES DE OBRA PROGRAMADAS - MONTO SIN I.G.V. (S/.) VALORIZACIONES DE OBRA EJECUTADAS - MONTO SIN I.G.V. (S/.) SITUACION DE LA OBRA
ADICIONALES ADICIONAL ADELANTADO ATRASADO
VAL. Nº PERIODO CONTRATO
% CONTRATO
PRINCIPAL + TOTAL ACUMULADO % ACUM TOTAL % PARCIAL ACUMULADO % ACUM.
DEDUCTIVOS Nº 01 Nº 02 Nº 04 Nº 05 PARCIAL PRINCIPAL Nº 01 Nº 02 Nº 04 Nº 05 (%) (%)

1 Sep-18
### 377,798.25 377,798.25 0.13 377,798.25 0.13 311,292.89 311,292.89 0.10 311,292.89 0.10 0.00% -17.60%

2 Oct-18### 639,949.53 639,949.53 0.21 1,017,747.78 0.34 1,352,046.83 1,352,046.83 0.45 1,663,339.72 0.55 63.43%

3 Nov-18
### 1,815,160.90 1,815,160.90 0.60 2,832,908.68 0.94 812,437.11 812,437.11 0.27 2,475,776.83 0.82 - 12.61%

4 Dec-18
Set-97 5,443,704.94 5,443,704.94 1.80 8,276,613.62 2.74 1,940,006.00 1,940,006.00 0.64 4,415,782.83 1.46 - 46.65%

5 Jan-19
### 7,044,086.22 7,044,086.22 2.33 15,320,699.84 5.07 1,254,706.74 1,254,706.74 0.42 5,670,489.57 1.88 - 62.99%

6 Feb-19
### 7,966,101.46 7,966,101.46 2.64 23,286,801.29 7.71 2,154,854.78 2,154,854.78 0.71 7,825,344.35 2.59 - 66.40%

7 Mar-19
### 8,367,800.84 8,367,800.84 2.77 31,654,602.13 10.48 2,802,911.64 2,802,911.64 0.93 10,628,255.99 3.52 - 66.42%

8 Apr-19### 8,690,488.09 8,690,488.09 2.88 40,345,090.22 13.35 3,446,771.83 3,446,771.83 1.14 14,075,027.82 4.66 - 65.11%

9 May-19
### 18,389,789.25 18,389,789.25 6.09 58,734,879.47 19.44 4,453,139.56 4,453,139.56 1.47 18,528,167.38 6.13 - 68.45%

10 Jun-19 23,059,364.52 23,059,364.52 7.63 81,794,244.00 27.08 4,012,538.59 4,012,538.59 1.33 22,540,705.97 7.46 - 72.44%

11 Jul-19 25,559,542.74 25,559,542.74 8.46 107,353,786.74 35.54 5,728,833.14 5,728,833.14 1.90 28,269,539.11 9.36 - 73.67%

12 Aug-19 25,478,872.71 25,478,872.71 8.43 132,832,659.45 43.97 4,898,447.31 4,898,447.31 1.62 33,167,986.42 10.98 - 75.03%

13 Sep-19 24,906,728.04 24,906,728.04 8.24 157,739,387.49 52.21 6,049,871.77 6,049,871.77 2.00 39,217,858.19 12.98 - 75.14%

14 Oct-19 23,847,571.78 23,847,571.78 7.89 181,586,959.27 60.11 8,850,910.93 8,850,910.93 2.93 48,068,769.12 15.91 - 73.53%

15 Nov-19
### 17,435,078.42 17,435,078.42 5.77 199,022,037.69 65.88 7,519,246.82 7,519,246.82 2.49 55,588,015.94 18.40 - 72.07%

16 Dec-19 16,371,088.25 16,371,088.25 5.42 215,393,125.94 71.30 6,291,894.42 6,291,894.42 2.08 61,879,910.36 20.48 - 71.27%

17 Jan-20 14,469,911.50 14,469,911.50 4.79 229,863,037.44 76.09 3,502,051.15 3,502,051.15 1.16 65,381,961.51 21.64 - 71.56%

18 Feb-20 14,316,060.04 14,316,060.04 4.74 244,179,097.48 80.83 3,009,577.77 3,009,577.77 1.00 68,391,539.28 22.64 - 71.99%

19 Mar-20 5,287,543.47 5,287,543.47 1.75 249,466,640.95 82.58 3,968,012.22 3,968,012.22 1.31 72,359,551.50 23.95 - 70.99%

20 Apr-20 0.00 0.00 249,466,640.95 82.58 0.00 0.00 0.00 72,359,551.50 23.95

21 May-20
### 0.00 0.00 249,466,640.95 82.58 0.00 0.00 0.00 72,359,551.50 23.95

22 Jun-20 0.00 0.00 249,466,640.95 82.58 0.00 0.00 0.00 72,359,551.50 23.95

23 Jul-20 10,369,838.94 10,369,838.94 3.43 259,836,479.89 86.01 0.00 0.00 72,359,551.50 23.95

24 Aug-20 12,938,672.22 12,938,672.22 4.28 272,775,152.10 90.29 2,328,937.68 2,328,937.68 0.77 74,688,489.18 24.72 - 72.62%

25 Sep-20 11,389,022.92 11,389,022.92 3.77 284,164,175.02 94.06 5,897,281.48 5,897,281.48 1.95 80,585,770.66 26.68 - 71.64%

26 Oct-20 10,298,067.16 10,298,067.16 3.41 294,462,242.18 97.47 3,851,032.69 3,851,032.69 1.27 84,436,803.35 27.95 - 71.33%

27 Nov-20 6,503,264.61 6,503,264.61 2.15 300,965,506.79 99.62 6,574,844.95 6,574,844.95 2.18 91,011,648.30 30.13 - 69.76%

28 Dec-20 1,136,452.29 1,136,452.29 0.38 302,101,959.08 100.00 2,720,121.25 2,720,121.25 0.90


0.00 0.00 0.00 91,011,648.30 30.13

302,101,959.08 0.00 0.00 0.00 0.00 302,101,959.08 100.00 93,731,769.55 0.00 0.00 0.00 0.00 93,731,769.55 31.03
CAO - Calendario de Avance de Obra N° 12, presentado a la Entidad mediante Carta N° 238-2018/SV-1602-H/JS

20 GRÁFICO COMPARATIVO ACUMULADO


100

90

80

70

60

50

40

30 30.13
27.95
26.68
23.95 23.95 23.95 23.95 23.95 24.72
22.64
21.64
20 20.48
18.40
15.91
12.98
10.98
10 9.36
7.46
6.13
4.66
3.52
1.88 2.59
0.82 1.46
0 0.10 0.55
Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20

PROGRAMADO EJECUTADO

GRÁFICO COMPARATIVO MENSUAL

27,500,000

25,000,000

22,500,000

20,000,000

17,500,000

15,000,000

12,500,000

10,000,000

7,500,000

5,000,000

2,500,000

0
Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20

PROGRAMADO EJECUTADO
GRÁFICO COMPARATIVO MENSUAL
27,500,000

25,000,000

22,500,000

20,000,000

17,500,000

15,000,000

12,500,000

10,000,000

7,500,000

5,000,000

2,500,000

0
Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20

PROGRAMADO EJECUTADO

Nota: El Control de los avances ejecutados en el mes, se realiza con el CAO vigente aprobado por la Entidad mediante Oficio N° xxxxx

También podría gustarte